Institut Supérieur d'Informatique
Program: IT Project management
Course: Project Management Planning
Professor: Rachid Baida
1. Context and Objective
2. Constraints and Assumption
3. In Scope/Out of scope
4. WBS
5. PBS
6. Gantt Chart
7. Pert Chart
8. Resource plan
9. Risk Plan
10. Communication Plan
11. Conclusion
 Context: Global Solutions, one of the most reputed companies in Montreal. In order to
facilitate the employee’s payment, the organization needs to implement cloud-based
payroll system.
 Objective: To purchase and implement cloud-based payroll system in order to process
the employee's payment accurately and on time.
Constraints:
 Time constraint of 6 months to complete the project.
 Cloud solution is another constraint which bound us to not use any other platform.
Assumption:
Compatibility.
The server is already installed.
Infrastructure is already built.
 Finding the best cloud-based payroll solution from the market.
 Explore different cloud-based payroll solution and test the prototypes.
 Evaluate the software’s.
 Choose the best software.
 Purchase the solution.
 Integrate the software with the cloud solution.
 Configure the firewall.
 Test and confirm the software.
 Go Live.
 No need to buy infrastructure.
 No need to buy hardware’s.
 No maintenance cost.
 No need to spend money on security.
Project start Date: 20/January/2020
Project end Date: 08/June/2020
Cost: 12732.5 CAD
Total Duration: 100 Days
ID Resource Name Role Rate Duration (Days) Cost ($)
1 Ashu Project Manager 50$ 100 6800
2 Manan Project Control Officer 50$ 100 (5%
Availability)
425
2 Rahul Procurement 50$ 49 2450
3 Smith System Admin 50$ 42 2100
5 Alex Software Tester 50$ 30 1500
6 Jasmin Network Admin 50$ 15 750
Type of Risk Category Probability Prioritize Response
Software Delay Technical Low 4 We can sign the
agreement with the
vendor.
Installation Technical Medium 3 We will have a backup
data in case of any
issue during
installation.
Security Technical High 1 Signing the contract
with the vendor in case
of any conflict or data
leakage.
Server Issue Technical Medium 2 We will have a backup
server in case of any
failure.
Communication Method(Way) Frequency Objective People Involved
Project Status Face to face Meeting Every week Demonstrate project
status
Stakeholders, Project
Manager
Vendor Choice Group Meeting Identify the vendor Identify benefits Stakeholders and
project manager and
team
 In the end, it is concluded that the project will be completed within the given time and budget.
 The project will be based on cloud-based solution as given by our stakeholder.
Lessons Learned:
 WBS
 PBS
 Gantt Chart
 PERT Chart
 Resource Plan
 Risk Plan
 Communication Plan
• https://www.integrity-data.com/how-to-implement-a-cloud-based-payroll-system/
• https://www.cloudpay.net/resources/global-payroll-implementation-stage-1-the-first-step-in-global-payroll-implementation-phase-1-
of-global-payroll-implementation
• https://www.pmi.org/learning/library/risk-analysis-project-management-7070
• https://immedis.com/set-payroll-implementation-success/
• https://solutiondots.com/blog/payroll-process-and-the-risks-to-be-avoided/
• http://www.payrolllab.com/cloud-payroll-data-security.php
• https://www.softwareadvice.com/hr/industryview/cloud-payroll-report-2015/
• https://www.hrpayrollsystems.net/saas/
• https://opentextbc.ca/projectmanagement/chapter/chapter-8-overview-of-project-planning-project-management/
• https://www.hpe.com/us/en/insights/articles/understanding-cloud-based-firewalls-1702.html
Planning Payclo (Project management)

More Related Content

Similar to Planning Payclo (Project management)

Week Four JournalObjectiveYou will identify key ethical proble.docx
Week Four JournalObjectiveYou will identify key ethical proble.docxWeek Four JournalObjectiveYou will identify key ethical proble.docx
Week Four JournalObjectiveYou will identify key ethical proble.docx
alanfhall8953
 
James dimas it infrastructure approach
James dimas it infrastructure approachJames dimas it infrastructure approach
James dimas it infrastructure approach
James (JD) Dimas
 
Project charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeProject charter and plan document for millennium upgrade
Project charter and plan document for millennium upgrade
Theodore Van Patten, Jr.
 
Lead Allocation System - Attribute Driven Design (ADD)
Lead Allocation System - Attribute Driven Design (ADD)Lead Allocation System - Attribute Driven Design (ADD)
Lead Allocation System - Attribute Driven Design (ADD)
Amin Bandeali
 
CPIN 269 Final Documentation
CPIN 269 Final DocumentationCPIN 269 Final Documentation
CPIN 269 Final Documentation
Jennifer Cordes
 
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docxITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
priestmanmable
 
Scope Scope StatementProject TitleProject SponserObjectiveMobile t.docx
Scope Scope StatementProject TitleProject SponserObjectiveMobile t.docxScope Scope StatementProject TitleProject SponserObjectiveMobile t.docx
Scope Scope StatementProject TitleProject SponserObjectiveMobile t.docx
kenjordan97598
 

Similar to Planning Payclo (Project management) (20)

Lecture6
Lecture6Lecture6
Lecture6
 
Software Project Proposal- Result Analysis Tool
Software Project Proposal- Result Analysis ToolSoftware Project Proposal- Result Analysis Tool
Software Project Proposal- Result Analysis Tool
 
Online Exam Management System(OEMS)
Online Exam Management System(OEMS)Online Exam Management System(OEMS)
Online Exam Management System(OEMS)
 
Online cinematicketingdocx
Online cinematicketingdocxOnline cinematicketingdocx
Online cinematicketingdocx
 
Spm project planning
Spm project planning Spm project planning
Spm project planning
 
Near east university
Near east universityNear east university
Near east university
 
Project Management Sample
Project Management SampleProject Management Sample
Project Management Sample
 
Software engineering project(srs)!!
Software engineering project(srs)!!Software engineering project(srs)!!
Software engineering project(srs)!!
 
Week Four JournalObjectiveYou will identify key ethical proble.docx
Week Four JournalObjectiveYou will identify key ethical proble.docxWeek Four JournalObjectiveYou will identify key ethical proble.docx
Week Four JournalObjectiveYou will identify key ethical proble.docx
 
Business Proposal for Project
Business Proposal for ProjectBusiness Proposal for Project
Business Proposal for Project
 
James dimas it infrastructure approach
James dimas it infrastructure approachJames dimas it infrastructure approach
James dimas it infrastructure approach
 
Pm soln9416141129710
Pm soln9416141129710Pm soln9416141129710
Pm soln9416141129710
 
Project charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeProject charter and plan document for millennium upgrade
Project charter and plan document for millennium upgrade
 
ERP/SAP Project Charter
ERP/SAP Project CharterERP/SAP Project Charter
ERP/SAP Project Charter
 
Lead Allocation System - Attribute Driven Design (ADD)
Lead Allocation System - Attribute Driven Design (ADD)Lead Allocation System - Attribute Driven Design (ADD)
Lead Allocation System - Attribute Driven Design (ADD)
 
CPIN 269 Final Documentation
CPIN 269 Final DocumentationCPIN 269 Final Documentation
CPIN 269 Final Documentation
 
(Fall2016)Lecture1.pptx
(Fall2016)Lecture1.pptx(Fall2016)Lecture1.pptx
(Fall2016)Lecture1.pptx
 
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docxITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Scope Scope StatementProject TitleProject SponserObjectiveMobile t.docx
Scope Scope StatementProject TitleProject SponserObjectiveMobile t.docxScope Scope StatementProject TitleProject SponserObjectiveMobile t.docx
Scope Scope StatementProject TitleProject SponserObjectiveMobile t.docx
 

Recently uploaded

TrustArc Webinar - Unified Trust Center for Privacy, Security, Compliance, an...
TrustArc Webinar - Unified Trust Center for Privacy, Security, Compliance, an...TrustArc Webinar - Unified Trust Center for Privacy, Security, Compliance, an...
TrustArc Webinar - Unified Trust Center for Privacy, Security, Compliance, an...
TrustArc
 

Recently uploaded (20)

TrustArc Webinar - Unified Trust Center for Privacy, Security, Compliance, an...
TrustArc Webinar - Unified Trust Center for Privacy, Security, Compliance, an...TrustArc Webinar - Unified Trust Center for Privacy, Security, Compliance, an...
TrustArc Webinar - Unified Trust Center for Privacy, Security, Compliance, an...
 
Simplifying Mobile A11y Presentation.pptx
Simplifying Mobile A11y Presentation.pptxSimplifying Mobile A11y Presentation.pptx
Simplifying Mobile A11y Presentation.pptx
 
Vector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxVector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptx
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
 
Decarbonising Commercial Real Estate: The Role of Operational Performance
Decarbonising Commercial Real Estate: The Role of Operational PerformanceDecarbonising Commercial Real Estate: The Role of Operational Performance
Decarbonising Commercial Real Estate: The Role of Operational Performance
 
API Governance and Monetization - The evolution of API governance
API Governance and Monetization -  The evolution of API governanceAPI Governance and Monetization -  The evolution of API governance
API Governance and Monetization - The evolution of API governance
 
WSO2 Micro Integrator for Enterprise Integration in a Decentralized, Microser...
WSO2 Micro Integrator for Enterprise Integration in a Decentralized, Microser...WSO2 Micro Integrator for Enterprise Integration in a Decentralized, Microser...
WSO2 Micro Integrator for Enterprise Integration in a Decentralized, Microser...
 
Navigating Identity and Access Management in the Modern Enterprise
Navigating Identity and Access Management in the Modern EnterpriseNavigating Identity and Access Management in the Modern Enterprise
Navigating Identity and Access Management in the Modern Enterprise
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
الأمن السيبراني - ما لا يسع للمستخدم جهله
الأمن السيبراني - ما لا يسع للمستخدم جهلهالأمن السيبراني - ما لا يسع للمستخدم جهله
الأمن السيبراني - ما لا يسع للمستخدم جهله
 
ADP Passwordless Journey Case Study.pptx
ADP Passwordless Journey Case Study.pptxADP Passwordless Journey Case Study.pptx
ADP Passwordless Journey Case Study.pptx
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
Quantum Leap in Next-Generation Computing
Quantum Leap in Next-Generation ComputingQuantum Leap in Next-Generation Computing
Quantum Leap in Next-Generation Computing
 
Top 10 CodeIgniter Development Companies
Top 10 CodeIgniter Development CompaniesTop 10 CodeIgniter Development Companies
Top 10 CodeIgniter Development Companies
 
Stronger Together: Developing an Organizational Strategy for Accessible Desig...
Stronger Together: Developing an Organizational Strategy for Accessible Desig...Stronger Together: Developing an Organizational Strategy for Accessible Desig...
Stronger Together: Developing an Organizational Strategy for Accessible Desig...
 
The Zero-ETL Approach: Enhancing Data Agility and Insight
The Zero-ETL Approach: Enhancing Data Agility and InsightThe Zero-ETL Approach: Enhancing Data Agility and Insight
The Zero-ETL Approach: Enhancing Data Agility and Insight
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
ChatGPT and Beyond - Elevating DevOps Productivity
ChatGPT and Beyond - Elevating DevOps ProductivityChatGPT and Beyond - Elevating DevOps Productivity
ChatGPT and Beyond - Elevating DevOps Productivity
 
JavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate GuideJavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate Guide
 

Planning Payclo (Project management)

  • 1. Institut Supérieur d'Informatique Program: IT Project management Course: Project Management Planning Professor: Rachid Baida
  • 2. 1. Context and Objective 2. Constraints and Assumption 3. In Scope/Out of scope 4. WBS 5. PBS 6. Gantt Chart 7. Pert Chart 8. Resource plan 9. Risk Plan 10. Communication Plan 11. Conclusion
  • 3.  Context: Global Solutions, one of the most reputed companies in Montreal. In order to facilitate the employee’s payment, the organization needs to implement cloud-based payroll system.  Objective: To purchase and implement cloud-based payroll system in order to process the employee's payment accurately and on time.
  • 4. Constraints:  Time constraint of 6 months to complete the project.  Cloud solution is another constraint which bound us to not use any other platform. Assumption: Compatibility. The server is already installed. Infrastructure is already built.
  • 5.  Finding the best cloud-based payroll solution from the market.  Explore different cloud-based payroll solution and test the prototypes.  Evaluate the software’s.  Choose the best software.  Purchase the solution.  Integrate the software with the cloud solution.  Configure the firewall.  Test and confirm the software.  Go Live.
  • 6.  No need to buy infrastructure.  No need to buy hardware’s.  No maintenance cost.  No need to spend money on security.
  • 7.
  • 8.
  • 9. Project start Date: 20/January/2020 Project end Date: 08/June/2020 Cost: 12732.5 CAD Total Duration: 100 Days
  • 10.
  • 11.
  • 12.
  • 13.
  • 14. ID Resource Name Role Rate Duration (Days) Cost ($) 1 Ashu Project Manager 50$ 100 6800 2 Manan Project Control Officer 50$ 100 (5% Availability) 425 2 Rahul Procurement 50$ 49 2450 3 Smith System Admin 50$ 42 2100 5 Alex Software Tester 50$ 30 1500 6 Jasmin Network Admin 50$ 15 750
  • 15. Type of Risk Category Probability Prioritize Response Software Delay Technical Low 4 We can sign the agreement with the vendor. Installation Technical Medium 3 We will have a backup data in case of any issue during installation. Security Technical High 1 Signing the contract with the vendor in case of any conflict or data leakage. Server Issue Technical Medium 2 We will have a backup server in case of any failure.
  • 16. Communication Method(Way) Frequency Objective People Involved Project Status Face to face Meeting Every week Demonstrate project status Stakeholders, Project Manager Vendor Choice Group Meeting Identify the vendor Identify benefits Stakeholders and project manager and team
  • 17.  In the end, it is concluded that the project will be completed within the given time and budget.  The project will be based on cloud-based solution as given by our stakeholder. Lessons Learned:  WBS  PBS  Gantt Chart  PERT Chart  Resource Plan  Risk Plan  Communication Plan
  • 18. • https://www.integrity-data.com/how-to-implement-a-cloud-based-payroll-system/ • https://www.cloudpay.net/resources/global-payroll-implementation-stage-1-the-first-step-in-global-payroll-implementation-phase-1- of-global-payroll-implementation • https://www.pmi.org/learning/library/risk-analysis-project-management-7070 • https://immedis.com/set-payroll-implementation-success/ • https://solutiondots.com/blog/payroll-process-and-the-risks-to-be-avoided/ • http://www.payrolllab.com/cloud-payroll-data-security.php • https://www.softwareadvice.com/hr/industryview/cloud-payroll-report-2015/ • https://www.hrpayrollsystems.net/saas/ • https://opentextbc.ca/projectmanagement/chapter/chapter-8-overview-of-project-planning-project-management/ • https://www.hpe.com/us/en/insights/articles/understanding-cloud-based-firewalls-1702.html