LTE ISSUE FOUND 1:
2G TRAFFIC ERLANG LOSS ON COLO
ALPHANE DHIAN & ARUM SETYO - NEXWAVE INDONESIA 2018
4
ISSUE: TRAFFIC ERLANG 2G LOSS (1)
• After GUL67 have been implemented, the network experiencing traffic 2G erlang loss.
• GUL900 rules for 2G are TRX installed for S3/3/3. This configuration will decrease TRX number from existing
2G site.
• Power rules for G900 is: 20w each TRX (60w for 3 TRX). We still found some power-config run with 10w in each
TRX. Less power means less traffic. But, this power adjustment has been done by 1-4 Nov for all GUL67. And
we have traffic increment for final result.
START STARTPWR ADJUST PWR ADJUST
5
ISSUE: TRAFFIC ERLANG 2G LOSS (2)
SOP Transmit Power GUL
G900:
20w each TRX (60w for 3 TRX).
Exception: if power before have more than 20w
in each TRX, we still have to set 20w in each
TRX, and the rest of it will be utilized to L900
(2x20w)
U900:
40w
L900:
60w (2x30w)
• Different TRX number and power setting before and after GUL implemented causing Erlang Traffic decrease
• By 1-3 Nov, power adjustment done in GSM and LTE (Value follows SOP)
Implementation Plan:
GUL POWER
ADJUSTMENT LIST
6
ISSUE: TRAFFIC ERLANG 2G LOSS (3)
Summary result after power adjustment:
• Total site experiencing traffic erlang decrement = 28 Sites;
• From those 28 sites,
• 12 sites have different antenna height more than 2m (value before and after GUL900 implementation)
• 16 sites have different Azimuth (value before and after GUL900 implementation)
• 1 site have no difference between before and after, but the antenna height is on 70m (too high)
Data Productivity
dan Physical Config GUL
7
ISSUE: TRAFFIC ERLANG 2G LOSS (4)
Summary:
1. After GUL power upgrade
(assessment result) site MGL676 CS
traffic GSM system significantly
improve +38.41%
2. Payload L900 improve +47.42%
5.85%
38.41%
38.41%
47.42%
UG Power
UG Power UG Power
UG Power UG Power
PRODUCTIVITY RESULT

More Related Content

What's hot

Mobilink Project On Site Swap SOP V2_4
Mobilink Project On Site Swap SOP V2_4Mobilink Project On Site Swap SOP V2_4
Mobilink Project On Site Swap SOP V2_4
ij qkka
 
Ap112 lcm4670 heavy lift load distribution monitoring
Ap112   lcm4670 heavy lift load distribution monitoringAp112   lcm4670 heavy lift load distribution monitoring
Ap112 lcm4670 heavy lift load distribution monitoring
Steve Sargeant - Solutions in Load Cells
 
90981041 control-system-lab-manual
90981041 control-system-lab-manual90981041 control-system-lab-manual
90981041 control-system-lab-manual
Gopinath.B.L Naidu
 
eBike Sensorless Motor Control
eBike Sensorless Motor ControleBike Sensorless Motor Control
eBike Sensorless Motor Control
alexzio
 
20100325 BDC Motor Presentation
20100325 BDC Motor Presentation20100325 BDC Motor Presentation
20100325 BDC Motor Presentation
Steven Garfinkel
 

What's hot (20)

Chichi chacha
Chichi chachaChichi chacha
Chichi chacha
 
Highly reliable & adaptive smart phased array antenna with gain adjustmen...
Highly reliable & adaptive smart phased array antenna with gain adjustmen...Highly reliable & adaptive smart phased array antenna with gain adjustmen...
Highly reliable & adaptive smart phased array antenna with gain adjustmen...
 
Iai rcp2 ba7_specsheet
Iai rcp2 ba7_specsheetIai rcp2 ba7_specsheet
Iai rcp2 ba7_specsheet
 
Iai rcp2 sa5_r_specsheet
Iai rcp2 sa5_r_specsheetIai rcp2 sa5_r_specsheet
Iai rcp2 sa5_r_specsheet
 
Mobilink Project On Site Swap SOP V2_4
Mobilink Project On Site Swap SOP V2_4Mobilink Project On Site Swap SOP V2_4
Mobilink Project On Site Swap SOP V2_4
 
PROJECT HANDLED
PROJECT HANDLEDPROJECT HANDLED
PROJECT HANDLED
 
Iai rca2 sa6_r_specsheet
Iai rca2 sa6_r_specsheetIai rca2 sa6_r_specsheet
Iai rca2 sa6_r_specsheet
 
Mini link tn-etsi_technical1
Mini link tn-etsi_technical1Mini link tn-etsi_technical1
Mini link tn-etsi_technical1
 
Servo 2.0
Servo 2.0Servo 2.0
Servo 2.0
 
Iai rcp2 ss7_r_specsheet
Iai rcp2 ss7_r_specsheetIai rcp2 ss7_r_specsheet
Iai rcp2 ss7_r_specsheet
 
Ap112 lcm4670 heavy lift load distribution monitoring
Ap112   lcm4670 heavy lift load distribution monitoringAp112   lcm4670 heavy lift load distribution monitoring
Ap112 lcm4670 heavy lift load distribution monitoring
 
[Application Case] Heavy Lift Load Distribution Monitoring
[Application Case] Heavy Lift Load Distribution Monitoring[Application Case] Heavy Lift Load Distribution Monitoring
[Application Case] Heavy Lift Load Distribution Monitoring
 
90981041 control-system-lab-manual
90981041 control-system-lab-manual90981041 control-system-lab-manual
90981041 control-system-lab-manual
 
Unicorn Wireless BTS/NodeB Installation Services
Unicorn Wireless BTS/NodeB Installation ServicesUnicorn Wireless BTS/NodeB Installation Services
Unicorn Wireless BTS/NodeB Installation Services
 
eBike Sensorless Motor Control
eBike Sensorless Motor ControleBike Sensorless Motor Control
eBike Sensorless Motor Control
 
Iai rcp2 ba6_specsheet
Iai rcp2 ba6_specsheetIai rcp2 ba6_specsheet
Iai rcp2 ba6_specsheet
 
20100325 BDC Motor Presentation
20100325 BDC Motor Presentation20100325 BDC Motor Presentation
20100325 BDC Motor Presentation
 
Keshe Magrav Power pp. 11. - Schematics Updated Oct-31-2015 v2
Keshe Magrav Power pp. 11. - Schematics Updated Oct-31-2015 v2Keshe Magrav Power pp. 11. - Schematics Updated Oct-31-2015 v2
Keshe Magrav Power pp. 11. - Schematics Updated Oct-31-2015 v2
 
Device Modeling and Simulation of DC Motor using LTspice
Device Modeling and Simulation of  DC Motor using LTspiceDevice Modeling and Simulation of  DC Motor using LTspice
Device Modeling and Simulation of DC Motor using LTspice
 
Lot 04 - AL SAAD Brackish water and reverse osmosis plant
Lot 04 - AL SAAD Brackish water and reverse osmosis plantLot 04 - AL SAAD Brackish water and reverse osmosis plant
Lot 04 - AL SAAD Brackish water and reverse osmosis plant
 

Similar to LTE ISSUE - GUL900 - 2G Traffic Loss on 4G Colo

6. itu 4 g regulation
6. itu 4 g regulation6. itu 4 g regulation
6. itu 4 g regulation
Kheng Heng
 
Irathandoverbasics 120523054755-phpapp02
Irathandoverbasics 120523054755-phpapp02Irathandoverbasics 120523054755-phpapp02
Irathandoverbasics 120523054755-phpapp02
bahareh jalali farahani
 
Irathandoverbasics 120523054755-phpapp02
Irathandoverbasics 120523054755-phpapp02Irathandoverbasics 120523054755-phpapp02
Irathandoverbasics 120523054755-phpapp02
bahareh jalali farahani
 
Design of a 400kv Transmission network
Design of a 400kv Transmission networkDesign of a 400kv Transmission network
Design of a 400kv Transmission network
Isaac Muyinza
 

Similar to LTE ISSUE - GUL900 - 2G Traffic Loss on 4G Colo (20)

Knowledge Sharing - Mobility_Strategy.pdf
Knowledge Sharing - Mobility_Strategy.pdfKnowledge Sharing - Mobility_Strategy.pdf
Knowledge Sharing - Mobility_Strategy.pdf
 
Iai scon ca_specsheet
Iai scon ca_specsheetIai scon ca_specsheet
Iai scon ca_specsheet
 
zte mobilink bts swap
zte mobilink bts swapzte mobilink bts swap
zte mobilink bts swap
 
395317358-LTE-Resource-Usage-Optimization.pptx
395317358-LTE-Resource-Usage-Optimization.pptx395317358-LTE-Resource-Usage-Optimization.pptx
395317358-LTE-Resource-Usage-Optimization.pptx
 
Gpon Network
Gpon NetworkGpon Network
Gpon Network
 
Gpon Network
Gpon NetworkGpon Network
Gpon Network
 
5G Readiness
5G Readiness5G Readiness
5G Readiness
 
6. itu 4 g regulation
6. itu 4 g regulation6. itu 4 g regulation
6. itu 4 g regulation
 
5G Demystified; the what, when and where
5G Demystified; the what, when and where5G Demystified; the what, when and where
5G Demystified; the what, when and where
 
19212757
1921275719212757
19212757
 
Ccn pv7 route_lab2-1_eigrp-load-balancing_student
Ccn pv7 route_lab2-1_eigrp-load-balancing_studentCcn pv7 route_lab2-1_eigrp-load-balancing_student
Ccn pv7 route_lab2-1_eigrp-load-balancing_student
 
Introduction To Antenna Impedance Tuner And Aperture Switch
Introduction To Antenna Impedance Tuner And Aperture SwitchIntroduction To Antenna Impedance Tuner And Aperture Switch
Introduction To Antenna Impedance Tuner And Aperture Switch
 
Irat handover basics
Irat handover basicsIrat handover basics
Irat handover basics
 
Irathandoverbasics 120523054755-phpapp02
Irathandoverbasics 120523054755-phpapp02Irathandoverbasics 120523054755-phpapp02
Irathandoverbasics 120523054755-phpapp02
 
Irathandoverbasics 120523054755-phpapp02
Irathandoverbasics 120523054755-phpapp02Irathandoverbasics 120523054755-phpapp02
Irathandoverbasics 120523054755-phpapp02
 
ga-gae system
ga-gae systemga-gae system
ga-gae system
 
Design of a 400kv Transmission network
Design of a 400kv Transmission networkDesign of a 400kv Transmission network
Design of a 400kv Transmission network
 
Introduce to DGS system
Introduce to DGS systemIntroduce to DGS system
Introduce to DGS system
 
Gtp load balancing 27.9.17
Gtp load balancing   27.9.17Gtp load balancing   27.9.17
Gtp load balancing 27.9.17
 
Intermediate: 5G Network Architecture Options (Updated)
Intermediate: 5G Network Architecture Options (Updated)Intermediate: 5G Network Architecture Options (Updated)
Intermediate: 5G Network Architecture Options (Updated)
 

Recently uploaded

Teachers record management system project report..pdf
Teachers record management system project report..pdfTeachers record management system project report..pdf
Teachers record management system project report..pdf
Kamal Acharya
 
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdfONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 

Recently uploaded (20)

Dairy management system project report..pdf
Dairy management system project report..pdfDairy management system project report..pdf
Dairy management system project report..pdf
 
Supermarket billing system project report..pdf
Supermarket billing system project report..pdfSupermarket billing system project report..pdf
Supermarket billing system project report..pdf
 
RM&IPR M5 notes.pdfResearch Methodolgy & Intellectual Property Rights Series 5
RM&IPR M5 notes.pdfResearch Methodolgy & Intellectual Property Rights Series 5RM&IPR M5 notes.pdfResearch Methodolgy & Intellectual Property Rights Series 5
RM&IPR M5 notes.pdfResearch Methodolgy & Intellectual Property Rights Series 5
 
E-Commerce Shopping using MERN Stack where different modules are present
E-Commerce Shopping using MERN Stack where different modules are presentE-Commerce Shopping using MERN Stack where different modules are present
E-Commerce Shopping using MERN Stack where different modules are present
 
Interfacing Analog to Digital Data Converters ee3404.pdf
Interfacing Analog to Digital Data Converters ee3404.pdfInterfacing Analog to Digital Data Converters ee3404.pdf
Interfacing Analog to Digital Data Converters ee3404.pdf
 
Teachers record management system project report..pdf
Teachers record management system project report..pdfTeachers record management system project report..pdf
Teachers record management system project report..pdf
 
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdfInstruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
Instruct Nirmaana 24-Smart and Lean Construction Through Technology.pdf
 
Intelligent Agents, A discovery on How A Rational Agent Acts
Intelligent Agents, A discovery on How A Rational Agent ActsIntelligent Agents, A discovery on How A Rational Agent Acts
Intelligent Agents, A discovery on How A Rational Agent Acts
 
Quiz application system project report..pdf
Quiz application system project report..pdfQuiz application system project report..pdf
Quiz application system project report..pdf
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge
 
ROAD CONSTRUCTION PRESENTATION.PPTX.pptx
ROAD CONSTRUCTION PRESENTATION.PPTX.pptxROAD CONSTRUCTION PRESENTATION.PPTX.pptx
ROAD CONSTRUCTION PRESENTATION.PPTX.pptx
 
Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1
 
Electrical shop management system project report.pdf
Electrical shop management system project report.pdfElectrical shop management system project report.pdf
Electrical shop management system project report.pdf
 
Multivibrator and its types defination and usges.pptx
Multivibrator and its types defination and usges.pptxMultivibrator and its types defination and usges.pptx
Multivibrator and its types defination and usges.pptx
 
SLIDESHARE PPT-DECISION MAKING METHODS.pptx
SLIDESHARE PPT-DECISION MAKING METHODS.pptxSLIDESHARE PPT-DECISION MAKING METHODS.pptx
SLIDESHARE PPT-DECISION MAKING METHODS.pptx
 
Linux Systems Programming: Semaphores, Shared Memory, and Message Queues
Linux Systems Programming: Semaphores, Shared Memory, and Message QueuesLinux Systems Programming: Semaphores, Shared Memory, and Message Queues
Linux Systems Programming: Semaphores, Shared Memory, and Message Queues
 
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdfONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
 
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGBRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
 
Electrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission lineElectrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission line
 
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
 

LTE ISSUE - GUL900 - 2G Traffic Loss on 4G Colo

  • 1. 3 LTE ISSUE FOUND 1: 2G TRAFFIC ERLANG LOSS ON COLO ALPHANE DHIAN & ARUM SETYO - NEXWAVE INDONESIA 2018
  • 2. 4 ISSUE: TRAFFIC ERLANG 2G LOSS (1) • After GUL67 have been implemented, the network experiencing traffic 2G erlang loss. • GUL900 rules for 2G are TRX installed for S3/3/3. This configuration will decrease TRX number from existing 2G site. • Power rules for G900 is: 20w each TRX (60w for 3 TRX). We still found some power-config run with 10w in each TRX. Less power means less traffic. But, this power adjustment has been done by 1-4 Nov for all GUL67. And we have traffic increment for final result. START STARTPWR ADJUST PWR ADJUST
  • 3. 5 ISSUE: TRAFFIC ERLANG 2G LOSS (2) SOP Transmit Power GUL G900: 20w each TRX (60w for 3 TRX). Exception: if power before have more than 20w in each TRX, we still have to set 20w in each TRX, and the rest of it will be utilized to L900 (2x20w) U900: 40w L900: 60w (2x30w) • Different TRX number and power setting before and after GUL implemented causing Erlang Traffic decrease • By 1-3 Nov, power adjustment done in GSM and LTE (Value follows SOP) Implementation Plan: GUL POWER ADJUSTMENT LIST
  • 4. 6 ISSUE: TRAFFIC ERLANG 2G LOSS (3) Summary result after power adjustment: • Total site experiencing traffic erlang decrement = 28 Sites; • From those 28 sites, • 12 sites have different antenna height more than 2m (value before and after GUL900 implementation) • 16 sites have different Azimuth (value before and after GUL900 implementation) • 1 site have no difference between before and after, but the antenna height is on 70m (too high) Data Productivity dan Physical Config GUL
  • 5. 7 ISSUE: TRAFFIC ERLANG 2G LOSS (4) Summary: 1. After GUL power upgrade (assessment result) site MGL676 CS traffic GSM system significantly improve +38.41% 2. Payload L900 improve +47.42% 5.85% 38.41% 38.41% 47.42% UG Power UG Power UG Power UG Power UG Power PRODUCTIVITY RESULT