1. NOVA DESIGN BUILD : ALL SITES STATUS REPORT
S.NO Project
Design
Procuement
Execution
T A S K S Status Action By
Initial
Committed
Date
Revised
Committed Date Remarks / Dependent Works
Sowmya Annex Reviewed on 05-09-2022
E-1 Annex C C P VYNIL FLOORING ( 25 sqmts) fixing pending Eshwar 18-07-22 open
E-2 Annex C C P Structural Glazing works One Glass Pan pending + Sealent filling Shakeel 15-07-22 open Bottom Grove cutting needed
E-3 Annex C C Fire Fighting - Hose Real Tapping in all floors Hussain informed vendor
E-4 Annex C C Pinup board for consultation rooms cleared by MD today Shakeel in process
E-5 Annex C P - Rubber Matts at panel Room Advised the Electrical Contractor Anup
E-6 Annex C Green Paint for Earthing strip at Panel room Information and NA Anup Spec request
E-7 Annex C All Bed Head Panel Internal Cu flexable pipes are requested in place of PVC pipes;
communicated to vendor accordingly to change
Anup Spec change request
E-8 Annex C Gysers - Racold Make is suggested Binu/Sudheer specs
E-9 Annex C C - Terrace Flooring : [LL Scope] due to which our false ceiling is
getting damage in 2 locations
Jay shekar
E-10 Annex C C O Terrace Masonry Works : LL Scope Jay shekar
Main & Linac Block Issues
E-1 Linac Linac - louvers to be modified with lesser opening
[but rejected by end user]
we need to explore alternate option
Anup 15-07-22 open
E-2 Linac Linac - front Alum Water Patti to have for the elevation Anup 15-07-22 open
E-3 Mainblock Bus Coupler Repair / Repacement Needed at Sowmya Main
Block Power Panel
Binu open
E-4 Mainblock Water Stagnation in toilets of RM 1,2,8,9,11 Maintainace Binu open
E-5 Linac Gas Meters needed for lines of Linac Block Trail pipe in copper only Binu open
#REF! Mainblock External Drain lines [further fastner materials indend made] Purchase open
BANNU WARANGAL
E-1 WNP staircase plastering yet to be takenup Raju
E-2 WNP west side external plastering second coat in progress will be done by 07-09 Raju
E-3 WNP p Metal doors will come by 06-09-22 anup
E-4 WNP UPVC WINDOWS WEST SIDE PENDING Raju
E-5 WNP GRANITE FLOORING IN STAIRCASE [3RD AND 4TH FLOOR] planned to complete by weekend Raju
E-6 WNP INTERNAL SS RAILING to be floated anup
E-7 WNP Lift : gova work to be takenup for painting and electrical works Raju
E-8 WNP External Painting works in progress Raju
E-9 WNP p Elevation fixed glass enquired floated anup
OMEGA KURNOOL
D-1 OK - - -
D-1 OK P DIRTY CORRIDOR PLATFORM AND STEPS JAY
E-1 OK C C P Electrical - Low Side B-1 conduit balance; B-2 linac conduit balance keethi
E-2 OK C C P Plumbing Sewer lines in 4th floor balance; Plumbing lines 3rd
and 4th flr balance
keethi
E-3 OK C C P HVAC Re work completed with cassate AC's.
copper lines to be initate.
keethi
E-4 OK C C P Fire Fire Package done; Hydrants only pending keethi
E-5 OK C C P Medical gas 4th floor only pending; Manifold area identified keethi
E-6 OK C C P Electrical - High Side Transformer [in progress] & Panels keethi
E-7 OK C C P Electrical - Captive Power DG Sets & UPS
E-6 OK C C - wooden door frames Materials to be supplied VeeraReddy
Jay Sekhar Sharma coordinated with Durga Prasad
Garu. Mr Subba Rao assured that they will
complete the works by Weekend
LL Scope
05-09-2022 1 of 2
2. NOVA DESIGN BUILD : ALL SITES STATUS REPORT
S.NO Project
Design
Procuement
Execution
T A S K S Status Action By
Initial
Committed
Date
Revised
Committed Date Remarks / Dependent Works
E-7 OK C P - Metal doors order Anup
E-8 OK C - - wood door shutters VeeraReddy
E-9 OK C C - Flooring - Tandur completed VeeraReddy
E-10 OK C - - Flooring - Granite cill work in progress VeeraReddy
E-11 OK C P - Flooring - Vitirified materials supplied VeeraReddy
E-12 OK C - - Flooring - Vynil flooring Indent to be Placed Anup
E-13 OK C C P External Plastering West side in progress [65% completed] VeeraReddy client is doing this work
Mahendra Hills
E-1 MH C C P Retaining wall works Shuttering in progress Nagaraj
E-2 MH C C P Brick Work Present kept on hold Nagaraj
MLA HOUSE
D-1 MLA P 1ST SLAB DETAIL REQUESTED ON 29/07 JAY closed
D-2 MLA P SUMP DETAIL REQUESTED ON 29/07 JAY
RAKESH VILLA
D-1 RV4 P P FLOORING STONE APPROVAL [supply of 2'x3'] REQUESTED ON 29/07 MD
D-2 RV4 P P JONARY WORKS IN PROGRESS JAY
E-1 RV4 P P P External MASONRY IN PROGRESS WILL BE COMPLETED BY WEEKEND ANUP
E-2 RV4 P P P ELECTRICAL WORKS CONDUIT WORKS DONE ANUP closed
DR KIRANS HOUSE
D-1 KH P BRICK WORK VAKDEVI
D-2 KH P PATHWAY TILES / STONE FLOORING VAKDEVI
D-3 KH P RESTORE EXISITING WOODEN ROOF AT DOOR VAKDEVI
D-4 KH P MODULAR KITCHEN VAKDEVI
D-5 KH P BED ROOM WARDROB LAMINATE TO BE REPLACED VAKDEVI
D-6 KH P ANTIQUE DOOR FIXING VAKDEVI
D-7 KH P PHE FITTINGS NEED TO BE CHANGED VAKDEVI
D-8 KH P SHOWER CUBICAL TO BE CHANGED VAKDEVI
D-9 KH P ALL DOWNLIGHTS TO BE CHANGED VAKDEVI
D-10 KH P LIGHTING FOR ENTRANCE DOOR - WIRING TO BE DONE VAKDEVI
D-11 KH P WALL PAPERS TO BE PROPOSED IF REQUIRED VAKDEVI