SlideShare a Scribd company logo
Project - CP- SEZ
Client - CaterPillar Signs Pvt Ltd
PMC - Sakshaam Consultancy
Architect & Structure - VMS Engineering & Design Services (P) Ltd
Project By - Alok Infracon Pvt Ltd
Sr No Activity Target Target Date
1 Back Filling @ Plinth Level From Grid C/M To 1/8 Will Be Done 09-06-2021
2 GSB Lying From Grid F-M To 1-8 Will Be Done (Part 1 To Part 4 ) 09-06-2021
3 Floor PCC From Grid F-M To 1-8 Will Be Done (Part 1 To Part 4 ) 09-06-2021
4 Shuttering Work
Part - 1 Slab Part -1 From Grid J/M - 1/4.5 09-06-2021
Part -2 From Grid J/M - 4.5/8 Running
Column Up Tp GF Slab 1st Flight Of All Will Be Done & 2nd Flight From C To M 09-06-2021
5 Reinforcement Work
Part -1 Slab It Will Be Start 09-06-2021
Column Up Tp GF Slab It Will Be Done From A To M & 1 To 8 09-06-2021
6 Concrete Work
Column Up Tp GF Slab 1st Flight Of All Will Be Done & 2nd Flight From C To M 09-06-2021
7 Anti Termite Treatment From Grid F-A To 1-8 Will Be Done (Part 1 To Part 4 ) 09-06-2021
8 Brick Work Outer Side Brick Work Will Be Done 10-06-2021
ALOK INFRACON PVT LTD
NEXT WEEK SCHEDULE FROM 03-06-2021 TO 09-06-2021

More Related Content

What's hot

Faisalaiah project (english) 3 REV.03
Faisalaiah project (english) 3 REV.03Faisalaiah project (english) 3 REV.03
Faisalaiah project (english) 3 REV.03
Wael Nafad
 
summer internship
summer internshipsummer internship
summer internship
Rahul Singh Dhanik
 
CV-Atif_Ashraf-4
CV-Atif_Ashraf-4CV-Atif_Ashraf-4
CV-Atif_Ashraf-4
Atif Ashraf
 
jyotithakurkumar@gmail.com
jyotithakurkumar@gmail.comjyotithakurkumar@gmail.com
jyotithakurkumar@gmail.com
jyoti thakur
 
SwartJ-cv (Jan 2016)
SwartJ-cv (Jan 2016)SwartJ-cv (Jan 2016)
SwartJ-cv (Jan 2016)
Johan Swart
 
CV WAQAR.
CV WAQAR.CV WAQAR.
CV WAQAR.
Malik Waqar
 
Updated CV of Satheeshkumar
Updated CV of SatheeshkumarUpdated CV of Satheeshkumar
Updated CV of Satheeshkumar
satheeshkumar rajamanickam
 
GIRIRAJAN
GIRIRAJANGIRIRAJAN
GlennN Resume
GlennN ResumeGlennN Resume
GlennN Resume
Nicholas Glenn
 
L&T Portfolio
L&T PortfolioL&T Portfolio
L&T Portfolio
Arjun Ramesh
 
LAND SURVEYOR Resume 2013 legat
LAND SURVEYOR Resume 2013 legatLAND SURVEYOR Resume 2013 legat
LAND SURVEYOR Resume 2013 legat
Sylvain Legat
 
RESUME RAJBIR SINGH (1)
RESUME RAJBIR SINGH (1)RESUME RAJBIR SINGH (1)
RESUME RAJBIR SINGH (1)
Rajbir Singh
 
Amos_Kivelowitz_Resume
Amos_Kivelowitz_ResumeAmos_Kivelowitz_Resume
Amos_Kivelowitz_Resume
Amos Kivelowitz
 
Senior surveyor ragab atta c.v
Senior surveyor ragab atta c.vSenior surveyor ragab atta c.v
Senior surveyor ragab atta c.v
ragabata
 
Project Controller
Project ControllerProject Controller
Project Controller
Shenoy Vinayak
 
Steve Miller CV 2017
Steve Miller CV 2017Steve Miller CV 2017
Steve Miller CV 2017
Steven Miller
 
Construction Outlook 2011 - Ernie Swickard (Office of Court Construction Mgmt)
Construction Outlook 2011 - Ernie Swickard (Office of Court Construction Mgmt)Construction Outlook 2011 - Ernie Swickard (Office of Court Construction Mgmt)
Construction Outlook 2011 - Ernie Swickard (Office of Court Construction Mgmt)
AGC of California
 
Narrow Pavement Widening - San Angelo District
Narrow Pavement Widening - San Angelo DistrictNarrow Pavement Widening - San Angelo District
Narrow Pavement Widening - San Angelo District
Center for Transportation Research - UT Austin
 
57 MAIN ROAD WEST (2)
57 MAIN ROAD WEST (2)57 MAIN ROAD WEST (2)
57 MAIN ROAD WEST (2)
Ar.Harry Sachdeva
 
M Halsey CV
M Halsey CVM Halsey CV
M Halsey CV
Mike Halsey
 

What's hot (20)

Faisalaiah project (english) 3 REV.03
Faisalaiah project (english) 3 REV.03Faisalaiah project (english) 3 REV.03
Faisalaiah project (english) 3 REV.03
 
summer internship
summer internshipsummer internship
summer internship
 
CV-Atif_Ashraf-4
CV-Atif_Ashraf-4CV-Atif_Ashraf-4
CV-Atif_Ashraf-4
 
jyotithakurkumar@gmail.com
jyotithakurkumar@gmail.comjyotithakurkumar@gmail.com
jyotithakurkumar@gmail.com
 
SwartJ-cv (Jan 2016)
SwartJ-cv (Jan 2016)SwartJ-cv (Jan 2016)
SwartJ-cv (Jan 2016)
 
CV WAQAR.
CV WAQAR.CV WAQAR.
CV WAQAR.
 
Updated CV of Satheeshkumar
Updated CV of SatheeshkumarUpdated CV of Satheeshkumar
Updated CV of Satheeshkumar
 
GIRIRAJAN
GIRIRAJANGIRIRAJAN
GIRIRAJAN
 
GlennN Resume
GlennN ResumeGlennN Resume
GlennN Resume
 
L&T Portfolio
L&T PortfolioL&T Portfolio
L&T Portfolio
 
LAND SURVEYOR Resume 2013 legat
LAND SURVEYOR Resume 2013 legatLAND SURVEYOR Resume 2013 legat
LAND SURVEYOR Resume 2013 legat
 
RESUME RAJBIR SINGH (1)
RESUME RAJBIR SINGH (1)RESUME RAJBIR SINGH (1)
RESUME RAJBIR SINGH (1)
 
Amos_Kivelowitz_Resume
Amos_Kivelowitz_ResumeAmos_Kivelowitz_Resume
Amos_Kivelowitz_Resume
 
Senior surveyor ragab atta c.v
Senior surveyor ragab atta c.vSenior surveyor ragab atta c.v
Senior surveyor ragab atta c.v
 
Project Controller
Project ControllerProject Controller
Project Controller
 
Steve Miller CV 2017
Steve Miller CV 2017Steve Miller CV 2017
Steve Miller CV 2017
 
Construction Outlook 2011 - Ernie Swickard (Office of Court Construction Mgmt)
Construction Outlook 2011 - Ernie Swickard (Office of Court Construction Mgmt)Construction Outlook 2011 - Ernie Swickard (Office of Court Construction Mgmt)
Construction Outlook 2011 - Ernie Swickard (Office of Court Construction Mgmt)
 
Narrow Pavement Widening - San Angelo District
Narrow Pavement Widening - San Angelo DistrictNarrow Pavement Widening - San Angelo District
Narrow Pavement Widening - San Angelo District
 
57 MAIN ROAD WEST (2)
57 MAIN ROAD WEST (2)57 MAIN ROAD WEST (2)
57 MAIN ROAD WEST (2)
 
M Halsey CV
M Halsey CVM Halsey CV
M Halsey CV
 

Similar to 03 06-2021

Review of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptxReview of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptx
MayankGandhi51
 
Project Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.pptProject Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.ppt
AkdDeshmukh
 
General Project report standing abrevation stock fy mou rt if olc hgf hhb h ...
General Project report standing abrevation stock fy mou rt if olc hgf  hhb h ...General Project report standing abrevation stock fy mou rt if olc hgf  hhb h ...
General Project report standing abrevation stock fy mou rt if olc hgf hhb h ...
r66025007
 
MCV
MCVMCV
Ahmed el gohary cv
Ahmed el gohary cvAhmed el gohary cv
Ahmed el gohary cv
Ahmed El gohary
 
cv بدون
cv بدونcv بدون
cv بدون
????? ??? ????
 
Bill ure cv 31 08-16
Bill ure cv 31 08-16Bill ure cv 31 08-16
Bill ure cv 31 08-16
bill ure
 
NIZAM ENTERPRISE profile (1)
NIZAM ENTERPRISE profile (1)NIZAM ENTERPRISE profile (1)
NIZAM ENTERPRISE profile (1)
hassand bindin
 
Project management report of stadium
Project management report of stadiumProject management report of stadium
Project management report of stadium
SLIIT, Sri Lanka
 
ayman y7ia
ayman y7iaayman y7ia
ayman y7ia
ayman yehia
 
CONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATIONCONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATION
cyberyogi07
 
Buildings so r 14 15
Buildings so r 14 15Buildings so r 14 15
Buildings so r 14 15
Ptpg Stuc
 
CV _Abdullah_Highway Design Engineer
CV _Abdullah_Highway Design EngineerCV _Abdullah_Highway Design Engineer
CV _Abdullah_Highway Design Engineer
Engr Abdullah
 
status report.pdf
status report.pdfstatus report.pdf
status report.pdf
AnupKumarPathak4
 
CV-Priono_Update
CV-Priono_UpdateCV-Priono_Update
CV-Priono_Update
Priono Abadi))
 
ANPARA D FGD PPT 07.06.2023-M (2).pptx
ANPARA D FGD PPT 07.06.2023-M (2).pptxANPARA D FGD PPT 07.06.2023-M (2).pptx
ANPARA D FGD PPT 07.06.2023-M (2).pptx
ssuser3797b9
 
GOPAL
GOPALGOPAL
elsayed cv last
elsayed cv lastelsayed cv last
elsayed cv last
elsayed hegazy
 
Rajib Ali CV (Final)
Rajib Ali CV (Final)Rajib Ali CV (Final)
Rajib Ali CV (Final)
Rajib Ali
 
NEMER- CV - 16
NEMER- CV - 16NEMER- CV - 16
NEMER- CV - 16
Nemer Abuhajar
 

Similar to 03 06-2021 (20)

Review of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptxReview of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptx
 
Project Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.pptProject Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.ppt
 
General Project report standing abrevation stock fy mou rt if olc hgf hhb h ...
General Project report standing abrevation stock fy mou rt if olc hgf  hhb h ...General Project report standing abrevation stock fy mou rt if olc hgf  hhb h ...
General Project report standing abrevation stock fy mou rt if olc hgf hhb h ...
 
MCV
MCVMCV
MCV
 
Ahmed el gohary cv
Ahmed el gohary cvAhmed el gohary cv
Ahmed el gohary cv
 
cv بدون
cv بدونcv بدون
cv بدون
 
Bill ure cv 31 08-16
Bill ure cv 31 08-16Bill ure cv 31 08-16
Bill ure cv 31 08-16
 
NIZAM ENTERPRISE profile (1)
NIZAM ENTERPRISE profile (1)NIZAM ENTERPRISE profile (1)
NIZAM ENTERPRISE profile (1)
 
Project management report of stadium
Project management report of stadiumProject management report of stadium
Project management report of stadium
 
ayman y7ia
ayman y7iaayman y7ia
ayman y7ia
 
CONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATIONCONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATION
 
Buildings so r 14 15
Buildings so r 14 15Buildings so r 14 15
Buildings so r 14 15
 
CV _Abdullah_Highway Design Engineer
CV _Abdullah_Highway Design EngineerCV _Abdullah_Highway Design Engineer
CV _Abdullah_Highway Design Engineer
 
status report.pdf
status report.pdfstatus report.pdf
status report.pdf
 
CV-Priono_Update
CV-Priono_UpdateCV-Priono_Update
CV-Priono_Update
 
ANPARA D FGD PPT 07.06.2023-M (2).pptx
ANPARA D FGD PPT 07.06.2023-M (2).pptxANPARA D FGD PPT 07.06.2023-M (2).pptx
ANPARA D FGD PPT 07.06.2023-M (2).pptx
 
GOPAL
GOPALGOPAL
GOPAL
 
elsayed cv last
elsayed cv lastelsayed cv last
elsayed cv last
 
Rajib Ali CV (Final)
Rajib Ali CV (Final)Rajib Ali CV (Final)
Rajib Ali CV (Final)
 
NEMER- CV - 16
NEMER- CV - 16NEMER- CV - 16
NEMER- CV - 16
 

Recently uploaded

一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
amsjournal
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
sachin chaurasia
 
john krisinger-the science and history of the alcoholic beverage.pptx
john krisinger-the science and history of the alcoholic beverage.pptxjohn krisinger-the science and history of the alcoholic beverage.pptx
john krisinger-the science and history of the alcoholic beverage.pptx
Madan Karki
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
Roger Rozario
 
gray level transformation unit 3(image processing))
gray level transformation unit 3(image processing))gray level transformation unit 3(image processing))
gray level transformation unit 3(image processing))
shivani5543
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
zubairahmad848137
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
Mahmoud Morsy
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
Anant Corporation
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 

Recently uploaded (20)

一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
 
john krisinger-the science and history of the alcoholic beverage.pptx
john krisinger-the science and history of the alcoholic beverage.pptxjohn krisinger-the science and history of the alcoholic beverage.pptx
john krisinger-the science and history of the alcoholic beverage.pptx
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
 
gray level transformation unit 3(image processing))
gray level transformation unit 3(image processing))gray level transformation unit 3(image processing))
gray level transformation unit 3(image processing))
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 

03 06-2021

  • 1. Project - CP- SEZ Client - CaterPillar Signs Pvt Ltd PMC - Sakshaam Consultancy Architect & Structure - VMS Engineering & Design Services (P) Ltd Project By - Alok Infracon Pvt Ltd Sr No Activity Target Target Date 1 Back Filling @ Plinth Level From Grid C/M To 1/8 Will Be Done 09-06-2021 2 GSB Lying From Grid F-M To 1-8 Will Be Done (Part 1 To Part 4 ) 09-06-2021 3 Floor PCC From Grid F-M To 1-8 Will Be Done (Part 1 To Part 4 ) 09-06-2021 4 Shuttering Work Part - 1 Slab Part -1 From Grid J/M - 1/4.5 09-06-2021 Part -2 From Grid J/M - 4.5/8 Running Column Up Tp GF Slab 1st Flight Of All Will Be Done & 2nd Flight From C To M 09-06-2021 5 Reinforcement Work Part -1 Slab It Will Be Start 09-06-2021 Column Up Tp GF Slab It Will Be Done From A To M & 1 To 8 09-06-2021 6 Concrete Work Column Up Tp GF Slab 1st Flight Of All Will Be Done & 2nd Flight From C To M 09-06-2021 7 Anti Termite Treatment From Grid F-A To 1-8 Will Be Done (Part 1 To Part 4 ) 09-06-2021 8 Brick Work Outer Side Brick Work Will Be Done 10-06-2021 ALOK INFRACON PVT LTD NEXT WEEK SCHEDULE FROM 03-06-2021 TO 09-06-2021