SlideShare a Scribd company logo
1 of 7
Download to read offline
1 M11 STABILISATION WORKS GEOBEAR
The project involved emergency remedial works at junction 14 of the A14 Cambridge to
Huntingdon Major Improvement scheme. The junction comprises a two-lane slip road section
of motorway with cloverleaf junction that links the M11 to the A428 and A14. This section of the
northbound M11 carries around 40,000 vehicles a day and forms part of the strategic highway
network which also serves Stansted Airport and provides access to strategic ferry ports.
Issues with the embankments to the bridge abutments on the M11 overbridge at Jct 14 had
been identified by Highways England as part of routine maintenance inspections. Further
investigation through visual and ground penetrating surveys and dynamic probing identified
the presence of voids beneath the carriageway close to the abutments which, if left, could
have resulted in significant risk of settlement or collapse of the carriageway.
An urgent solution was needed that would meet both technical and programme requirements
without compromising safety. The solution required the improvement of the foundation strata
compressive strength to 4MPa, implemented with minimal disruption to road users and the
wider improvement scheme. Geobear were consulted by WSP and subsequently designed
an innovative and time efficient solution that could be implemented from the carriageway
surface with minimal disturbance to the carriageway surface, and minimal reinstatement
works.Karl Brooks, Highways England
M11 Stabilisation
Geobear’s solution to the essential
embankment repair at M11 Girton
interchange has been a highlight of this
year’s 2018/19 programme of works.
2 M11 STABILISATION WORKS GEOBEAR
Four Geobear crews worked through the
night over a three week period to deliver
the emergency works.
Specialist two-component geopolymer
material was used to fill the voiding
beneath the M11 and stabilise the area.
The material is mixed on site and pumped
into the void through steel tubes.
3 M11 STABILISATION WORKS GEOBEAR
A drilling rig was used to core 50mm holes
into the road surface and through the
slab. The holes would accomodate the
steel tubes and also be used for a cctv
monitoring.
With the drilling completed the
programme of injection works could be
agreed. Sequences of material placement
were designed by the Geobear engineering
team.
4 M11 STABILISATION WORKS GEOBEAR
Laser monitoring is used while material
is injected into the ground to ensure no
vertical movement of the slab.
Steel tubes
are positioned
through the slab
to place material.
5 M11 STABILISATION WORKS GEOBEAR
Geopolymer injection
Material is pumped
directly from the self
contained Geobear
units through a hose
and controlled with an
injection mechanism .
6 M11 STABILISATION WORKS GEOBEAR
The material injections are sequentially
planned, but engineering teams on-site
make variations as required.
Technical teams keep a record of the
quantity of material injected through each
steel tube into the void. This, together with
visual surveys ensures the voids are filled.
7 M11 STABILISATION WORKS GEOBEAR
The methodology allows for teams to work
in localised areas ensuring crucial routes
can be kept open.
Once a voided area has been filled and stabilised,
the steel tubes are cut and the holes in the road
surface filled.
Project was completed on time and and within
budget. The scheme of works was recognised as a
finanlist at the 2019 Ground Engineering Awards.

More Related Content

Similar to M11 stabilisation by Geobear

ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptxAmirShafiq25
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15ADAM DUKE
 
Presentation on Millau viaduct
Presentation on Millau viaductPresentation on Millau viaduct
Presentation on Millau viaductJayanta Sen
 
329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.pptMuhammed Sulfeek
 
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...IJERA Editor
 
Austroads Bridge Conference 2017
Austroads Bridge Conference 2017Austroads Bridge Conference 2017
Austroads Bridge Conference 2017Eric Boothman
 
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013Jacobs Engineering
 
GW Amec Foster Wheeler
GW Amec Foster WheelerGW Amec Foster Wheeler
GW Amec Foster WheelerGareth White
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxAGNIVORAY1
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen PowerpointMay Begum
 
931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01
931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01
931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01Pavitter Virdi
 

Similar to M11 stabilisation by Geobear (20)

ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx
 
CV_Emanuil Videnov
CV_Emanuil VidenovCV_Emanuil Videnov
CV_Emanuil Videnov
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15
 
Presentation on Millau viaduct
Presentation on Millau viaductPresentation on Millau viaduct
Presentation on Millau viaduct
 
Construction Forensic
Construction ForensicConstruction Forensic
Construction Forensic
 
329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt
 
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
 
Austroads Bridge Conference 2017
Austroads Bridge Conference 2017Austroads Bridge Conference 2017
Austroads Bridge Conference 2017
 
Cheyenne Landfill Project
Cheyenne Landfill ProjectCheyenne Landfill Project
Cheyenne Landfill Project
 
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
 
GW Amec Foster Wheeler
GW Amec Foster WheelerGW Amec Foster Wheeler
GW Amec Foster Wheeler
 
South Jetty
South JettySouth Jetty
South Jetty
 
Tunneling (2).ppt
Tunneling (2).pptTunneling (2).ppt
Tunneling (2).ppt
 
Case study - Kettering train station
Case study - Kettering train stationCase study - Kettering train station
Case study - Kettering train station
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
 
About Waterman Aspen Powerpoint
About Waterman Aspen PowerpointAbout Waterman Aspen Powerpoint
About Waterman Aspen Powerpoint
 
931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01
931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01
931b50e6-4a9d-4b54-8552-683e3282e2a5-150409034912-conversion-gate01
 

Recently uploaded

Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 

Recently uploaded (20)

Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 

M11 stabilisation by Geobear

  • 1. 1 M11 STABILISATION WORKS GEOBEAR The project involved emergency remedial works at junction 14 of the A14 Cambridge to Huntingdon Major Improvement scheme. The junction comprises a two-lane slip road section of motorway with cloverleaf junction that links the M11 to the A428 and A14. This section of the northbound M11 carries around 40,000 vehicles a day and forms part of the strategic highway network which also serves Stansted Airport and provides access to strategic ferry ports. Issues with the embankments to the bridge abutments on the M11 overbridge at Jct 14 had been identified by Highways England as part of routine maintenance inspections. Further investigation through visual and ground penetrating surveys and dynamic probing identified the presence of voids beneath the carriageway close to the abutments which, if left, could have resulted in significant risk of settlement or collapse of the carriageway. An urgent solution was needed that would meet both technical and programme requirements without compromising safety. The solution required the improvement of the foundation strata compressive strength to 4MPa, implemented with minimal disruption to road users and the wider improvement scheme. Geobear were consulted by WSP and subsequently designed an innovative and time efficient solution that could be implemented from the carriageway surface with minimal disturbance to the carriageway surface, and minimal reinstatement works.Karl Brooks, Highways England M11 Stabilisation Geobear’s solution to the essential embankment repair at M11 Girton interchange has been a highlight of this year’s 2018/19 programme of works.
  • 2. 2 M11 STABILISATION WORKS GEOBEAR Four Geobear crews worked through the night over a three week period to deliver the emergency works. Specialist two-component geopolymer material was used to fill the voiding beneath the M11 and stabilise the area. The material is mixed on site and pumped into the void through steel tubes.
  • 3. 3 M11 STABILISATION WORKS GEOBEAR A drilling rig was used to core 50mm holes into the road surface and through the slab. The holes would accomodate the steel tubes and also be used for a cctv monitoring. With the drilling completed the programme of injection works could be agreed. Sequences of material placement were designed by the Geobear engineering team.
  • 4. 4 M11 STABILISATION WORKS GEOBEAR Laser monitoring is used while material is injected into the ground to ensure no vertical movement of the slab. Steel tubes are positioned through the slab to place material.
  • 5. 5 M11 STABILISATION WORKS GEOBEAR Geopolymer injection Material is pumped directly from the self contained Geobear units through a hose and controlled with an injection mechanism .
  • 6. 6 M11 STABILISATION WORKS GEOBEAR The material injections are sequentially planned, but engineering teams on-site make variations as required. Technical teams keep a record of the quantity of material injected through each steel tube into the void. This, together with visual surveys ensures the voids are filled.
  • 7. 7 M11 STABILISATION WORKS GEOBEAR The methodology allows for teams to work in localised areas ensuring crucial routes can be kept open. Once a voided area has been filled and stabilised, the steel tubes are cut and the holes in the road surface filled. Project was completed on time and and within budget. The scheme of works was recognised as a finanlist at the 2019 Ground Engineering Awards.