Improve Your
Library
Using The 5 Phases of Project Management
Today We Will...
• Get comfortable with “Project Management”
• All 5 phases
• Focus on planning
• Learn how to construct a Charter that prevents scope creep while identifying risks
and satisfying stakeholders
• And maybe identify what all these jargon-y words really mean
• Brainstorm our way into an excellent WBS
• Then use that to create a killer Gantt Chart
• Be comfortable with planning. And planning to plan.
Project Management
The art and science of managing people, money and time to produce a specific service or
product.
Basic, common sense “best practices” for getting stuff done that is all wrapped up in
specialized jargon and specific tools.
The best way to make sure you produce something that makes everyone happy - but not
a guarantee that this will happen.
Project Management
Phases
"Project Management (phases)" by Alphamu57 - Own work. Licensed under GFDL via Commons -
https://commons.wikimedia.org/wiki/File:Project_Management_(phases).png#/media/File:Project_Management_(phases).png
Jargon
Project
Scope
Scope creep
Stakeholders
Milestone
Risk
Issue
Deliverable
Dependencies
Constraints
PERT
Gantt
Project: Activities with defined outcome
and resources, more than 50 or so hours
(official PM definition)
Scope: The size of the project, what is
applicable and what isn’tScope Creep: The addition of activities
to the project that are out of scope
Stakeholders: People affected by
the project
Milestone: A deliverable that helps
to show that schedules are
being kept - hit milestones,
make the project
Risk: Something that could happen
to the project and should be
mitigatedIssue: Something that has
happened and needs to be dealt
with
Deliverable: Something that has
been created/altered as a result
of project processes -
documents, websites, reports,
etc.
Constraints: A limit that you need to
keep in mind - time, money,
people are most common, with
rules/regs of industry also being
popular (library privacy rules,
etc.)
PERT: Program Evaluation Review
Technique - helps to schedule
activities in a project
(mathematically)
Gantt: Helps to schedule activities
in a project (visually)
Brainstorming
Rules:
• No judgement zone
• Everyone gets a voice
• Have a recorder
• Make sure all ideas are visible
• Distribute ideas as soon as possible
• Take time between brainstorming and idea
deciding
Techniques:
• Mind mapping techniques
• Start with a few “starter” ideas
• Build on associations
• Butcher block paper and/or post its
• Lots and lots of people in a room doing this all at
once!
Project Management - Planning
• First 2 phases
• Initiation
• Plan to plan
• Planning and Design
• Document the plan
• The rest of the phases execute, monitor and close out the plan
Initiation - Planning to Plan
• Gather needs/assess current environment
• Determine total budget
• Determine total human resources
• Determine time available
• Identify Stakeholders
• Run through project initiation checklist
• https://www.dropbox.com/s/5d11kruoiazl05d/Project%20Initiation%20Checklist%20Template.dot?d
l=0
• Create Project Charter (output)
Environmental Scan
• What problem is the project solving?
• What options are available as solutions?
• What resources are available to help solve the problem?
• Time, People, Money
• What constraints are in place?
• Where is the library *now* - how far do you have to go to get to “done”?
Constraints
• Budget
• How much money will each solution require?
• How much money is available?
• Will fundraising need to happen?
• What stakeholders can you approach to get funding increases?
• People
• What staff skills are in place right now?
• What skills are needed?
• How many people are available for the work?
• Time
• What deadlines are externally imposed?
• How long will each solution take to put into place?
Stakeholders
• Who is affected by the project?
• Affected by the work being done?
• Affected by the solution chosen?
• Affected by the budget, time, people requirements?
• Affected by the end result?
• Sponsors
• Workers/Project Team
• Final users
image credit: https://openclipart.org/detail/35563/abstract-people
The Charter - Requirements
• Whatever you need to make your project a success…
• Scope statement
• Statement of Conditions
• Assumptions, Risks, Constraints, etc.
• Project Structure
• Waterfall? Agile? begin thinking about how to plan
• Communication plan
• Team Organization
• Who’s on the project team
• Who are the project’s sponsors?
• Who are the stakeholders that need to be considered during the work?
The Charter - Resources
Simple Charter - One Page
https://www.dropbox.com/s/fw4jruu6eqlrgbd/Project-Charter-Simple.doc?dl=0
Full Charter - with Table of Contents and more than you probably need
https://www.dropbox.com/s/qa37ylgt1hbkuwa/ProjectCharter.docx?dl=0
Planning/Design
• Figure out planning method
• Waterfall? Agile?
• Get planning team together
• Figure out scope of project
• Work out deliverables needed for project
• Create WBS from deliverables list
• Project estimates
• Budget, people, time
• PM estimating tricks
• Risk identification
• Get approval of plans to start work
Planning Method
• Waterfall
• Plan at the beginning through to the end (traditional)
• Agile
• Plan for 2 weeks, meet again at the end of those weeks to reassess and plan for next two weeks
• Rinse, repeat
• Agile software development
• Rolling Wave
• Cross between Waterfall and Agile
• Plan to end, but revisit occasionally to assess and change as needed
Planning Team
• More brains is more better
• Get as wide a cross-section of the organization as possible
• Have a defined goal for each meeting
• “Run an effective meeting”
• Agenda!
• Action Items!
• Use brainstorming techniques as well as discussions
Scope
• What *isn’t* appropriate for this project?
• What *exactly* are we doing here?
• Scope change forms - keep them handy for use during the execution stage
• Be ruthless!
Deliverables
• What will be produced as a result of this project?
• Not just end-stage results - internal project docs, too
• Plan ahead for what needs to be produced before other project activities can go
ahead
• Know what dependencies are in your project
• Critical Path Planning (helpful in project time estimates)
• Match skills to required deliverables
• People management - the hardest part of project management
WBS?
https://upload.wikimedia.org/wikipedia/commons/e/e0/WBS_Painting_Exampl.png - By
Arithmandar (Own work) [Public domain], via Wikimedia Commons
Project Estimation
• General Estimation Tips
• Figure the resource needed, double it
• With more experience, that formula can be tweaked
• Estimating people needed
• Estimating time needed
• That Critical Path Planning thing again
• Estimating money needed
Gantt Chart Fever
https://www.flickr.com/photos/perhapstoopink/467087455
Risk identification
• Project Assumptions
• What if you are wrong?
• Past projects
• Documentation is vital here
• Experienced staff
• Pick their brains!
• Brainstorming
Approvals
• Sponsor feedback
• Administration’s signatures
• Project team’s buy-in
• Start work!
The rest of the process
• Execution
• Do the work laid out in the WBS/Gantt Chart
• Monitoring and Controlling
• Use the charter and other planning documents to make sure you are on time, budget and schedule
• Close Out
• Finalize documentation and file it for use in future projects (reinventing the wheel is time-
consuming!!)
• Have a party!
Questions?
Image Credit:
https://openclipart.org/detail/231627/prismatic-3d-
question-mark
Thank You!
Robin Hastings
Director of Technology Services and Technology Consultant
Northeast Kansas Library System
robin.hastings@gmail.com

More Related Content

What's hot

STUDENT RECORD MANAGEMENT SYSTEM (1)
STUDENT RECORD MANAGEMENT SYSTEM (1)STUDENT RECORD MANAGEMENT SYSTEM (1)
STUDENT RECORD MANAGEMENT SYSTEM (1)
Juliet Nandutu
 
Capstone Project Student Management System
Capstone Project Student Management SystemCapstone Project Student Management System
Capstone Project Student Management System
Donna Muller
 
BASIC CONCEPTS OF COMPUTER NETWORKS
BASIC CONCEPTS OF COMPUTER NETWORKS BASIC CONCEPTS OF COMPUTER NETWORKS
BASIC CONCEPTS OF COMPUTER NETWORKS
Kak Yong
 

What's hot (20)

STUDENT RECORD MANAGEMENT SYSTEM (1)
STUDENT RECORD MANAGEMENT SYSTEM (1)STUDENT RECORD MANAGEMENT SYSTEM (1)
STUDENT RECORD MANAGEMENT SYSTEM (1)
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)
 
Computer networks
Computer networks   Computer networks
Computer networks
 
Programming notations
Programming notationsProgramming notations
Programming notations
 
Online library management system
Online library management systemOnline library management system
Online library management system
 
Integrating project life cycle with process groups
Integrating project life cycle with process groupsIntegrating project life cycle with process groups
Integrating project life cycle with process groups
 
Network Troubleshooting
Network TroubleshootingNetwork Troubleshooting
Network Troubleshooting
 
Intelligent Heuristics for the Game Isolation
Intelligent Heuristics  for the Game IsolationIntelligent Heuristics  for the Game Isolation
Intelligent Heuristics for the Game Isolation
 
What Is Project Portfolio Management
What Is Project Portfolio ManagementWhat Is Project Portfolio Management
What Is Project Portfolio Management
 
Feasibility report for library management system
Feasibility report for library management systemFeasibility report for library management system
Feasibility report for library management system
 
Capstone Project Student Management System
Capstone Project Student Management SystemCapstone Project Student Management System
Capstone Project Student Management System
 
Software requirement specification(SRS)
Software requirement specification(SRS)Software requirement specification(SRS)
Software requirement specification(SRS)
 
Project Management Plan for a Bookstore opening. Case: Uzbekistan
Project Management Plan for a Bookstore opening. Case: UzbekistanProject Management Plan for a Bookstore opening. Case: Uzbekistan
Project Management Plan for a Bookstore opening. Case: Uzbekistan
 
Project Management Tools
Project Management ToolsProject Management Tools
Project Management Tools
 
80 best sample system proposal title for research - computer technology compu...
80 best sample system proposal title for research - computer technology compu...80 best sample system proposal title for research - computer technology compu...
80 best sample system proposal title for research - computer technology compu...
 
BASIC CONCEPTS OF COMPUTER NETWORKS
BASIC CONCEPTS OF COMPUTER NETWORKS BASIC CONCEPTS OF COMPUTER NETWORKS
BASIC CONCEPTS OF COMPUTER NETWORKS
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project Management
 
Network
NetworkNetwork
Network
 
Example for ER diagram part11
Example for ER diagram part11Example for ER diagram part11
Example for ER diagram part11
 
Ms Project 2010
Ms Project 2010Ms Project 2010
Ms Project 2010
 

Similar to Improve your library: Using the 5 Phases of Project Management

Digital Project Management UCC Nov 2013
Digital Project Management UCC Nov 2013Digital Project Management UCC Nov 2013
Digital Project Management UCC Nov 2013
Shawn Day
 
OIT Project Management - Day 1
OIT Project Management - Day 1OIT Project Management - Day 1
OIT Project Management - Day 1
Kevin Thomas
 

Similar to Improve your library: Using the 5 Phases of Project Management (20)

Improve Your Library: Using the 5 Phases of Project Management (February 2017)
Improve Your Library: Using the 5 Phases of Project Management (February 2017)Improve Your Library: Using the 5 Phases of Project Management (February 2017)
Improve Your Library: Using the 5 Phases of Project Management (February 2017)
 
Project management
Project managementProject management
Project management
 
Project Management Basics
Project Management BasicsProject Management Basics
Project Management Basics
 
Project Management
Project ManagementProject Management
Project Management
 
Digital Project Management UCC Nov 2013
Digital Project Management UCC Nov 2013Digital Project Management UCC Nov 2013
Digital Project Management UCC Nov 2013
 
Elements of Project Management
Elements of Project ManagementElements of Project Management
Elements of Project Management
 
Elements of Project Management
Elements of Project ManagementElements of Project Management
Elements of Project Management
 
Everyone is a project manager. You can too!
Everyone is a project manager. You can too!Everyone is a project manager. You can too!
Everyone is a project manager. You can too!
 
Interactive activity I
Interactive activity IInteractive activity I
Interactive activity I
 
Project Management Base Camp
Project Management Base CampProject Management Base Camp
Project Management Base Camp
 
Project management - a practical overview Sue Greener
Project management - a practical overview Sue GreenerProject management - a practical overview Sue Greener
Project management - a practical overview Sue Greener
 
Project Management as an Art Form (DrupalCon Chicago 2011)
Project Management as an Art Form (DrupalCon Chicago 2011)Project Management as an Art Form (DrupalCon Chicago 2011)
Project Management as an Art Form (DrupalCon Chicago 2011)
 
Scrum, Kanban, and Gantt scheduling in one project – nonsense or necessity? -...
Scrum, Kanban, and Gantt scheduling in one project – nonsense or necessity? -...Scrum, Kanban, and Gantt scheduling in one project – nonsense or necessity? -...
Scrum, Kanban, and Gantt scheduling in one project – nonsense or necessity? -...
 
Session 2-Introduction to PPM -b.pdf
Session 2-Introduction to PPM -b.pdfSession 2-Introduction to PPM -b.pdf
Session 2-Introduction to PPM -b.pdf
 
Introduction to Tech Communication & Project Management
Introduction toTech Communication &Project ManagementIntroduction toTech Communication &Project Management
Introduction to Tech Communication & Project Management
 
Project Management
Project ManagementProject Management
Project Management
 
Chapter-4.pptx
Chapter-4.pptxChapter-4.pptx
Chapter-4.pptx
 
OIT Project Management - Day 1
OIT Project Management - Day 1OIT Project Management - Day 1
OIT Project Management - Day 1
 
OIT Project Management - Day 1
OIT Project Management - Day 1OIT Project Management - Day 1
OIT Project Management - Day 1
 
Project management
Project management Project management
Project management
 

More from ALATechSource

More from ALATechSource (20)

Liven Up Baby and Toddler Storytimes with Sign Language (March 2019)
Liven Up Baby and Toddler Storytimes with Sign Language (March 2019)Liven Up Baby and Toddler Storytimes with Sign Language (March 2019)
Liven Up Baby and Toddler Storytimes with Sign Language (March 2019)
 
Dealing with Mental Health on the Front Lines: Part 1
Dealing with Mental Health on the Front Lines: Part 1Dealing with Mental Health on the Front Lines: Part 1
Dealing with Mental Health on the Front Lines: Part 1
 
Serving Children with Autism Spectrum Disorder: Part 2 (Feb. 2019)
Serving Children with Autism Spectrum Disorder: Part 2 (Feb. 2019)Serving Children with Autism Spectrum Disorder: Part 2 (Feb. 2019)
Serving Children with Autism Spectrum Disorder: Part 2 (Feb. 2019)
 
Using Visual Arts in Early Childhood Programming
Using Visual Arts in Early Childhood ProgrammingUsing Visual Arts in Early Childhood Programming
Using Visual Arts in Early Childhood Programming
 
Serving Children with Autism Spectrum Disorder (Feb. 2019)
Serving Children with Autism Spectrum Disorder (Feb. 2019)Serving Children with Autism Spectrum Disorder (Feb. 2019)
Serving Children with Autism Spectrum Disorder (Feb. 2019)
 
Library Website Rehab: Promotional Webinar
Library Website Rehab: Promotional WebinarLibrary Website Rehab: Promotional Webinar
Library Website Rehab: Promotional Webinar
 
Taking STEAM Programs to the Next Level
Taking STEAM Programs to the Next LevelTaking STEAM Programs to the Next Level
Taking STEAM Programs to the Next Level
 
Creating a Digital Media Space for Today's Teens: Part 2 (Jan. 2019)
Creating a Digital Media Space for Today's Teens: Part 2 (Jan. 2019)Creating a Digital Media Space for Today's Teens: Part 2 (Jan. 2019)
Creating a Digital Media Space for Today's Teens: Part 2 (Jan. 2019)
 
Creating a Social Media Policy for Your Library (January 2019)
Creating a Social Media Policy for Your Library (January 2019)Creating a Social Media Policy for Your Library (January 2019)
Creating a Social Media Policy for Your Library (January 2019)
 
Creating a Digital Media Space for Today's Teens: Part 1 (Jan. 2019)
Creating a Digital Media Space for Today's Teens: Part 1 (Jan. 2019)Creating a Digital Media Space for Today's Teens: Part 1 (Jan. 2019)
Creating a Digital Media Space for Today's Teens: Part 1 (Jan. 2019)
 
Working with Individuals Affected by Homelessness: An Empathy-Driven Approach...
Working with Individuals Affected by Homelessness: An Empathy-Driven Approach...Working with Individuals Affected by Homelessness: An Empathy-Driven Approach...
Working with Individuals Affected by Homelessness: An Empathy-Driven Approach...
 
Fake News, Real Concerns: Developing Information-Literate Students (December ...
Fake News, Real Concerns: Developing Information-Literate Students (December ...Fake News, Real Concerns: Developing Information-Literate Students (December ...
Fake News, Real Concerns: Developing Information-Literate Students (December ...
 
Offering Service and Support to the LGBTQIA Community and Allies (Nov. 2018)
Offering Service and Support to the LGBTQIA Community and Allies (Nov. 2018)Offering Service and Support to the LGBTQIA Community and Allies (Nov. 2018)
Offering Service and Support to the LGBTQIA Community and Allies (Nov. 2018)
 
Library Director Bootcamp: Getting the Skills You Need, Part 3 (Nov. 2018)
Library Director Bootcamp: Getting the Skills You Need, Part 3 (Nov. 2018)Library Director Bootcamp: Getting the Skills You Need, Part 3 (Nov. 2018)
Library Director Bootcamp: Getting the Skills You Need, Part 3 (Nov. 2018)
 
Engaging Learners through Active Instruction and Assessment
Engaging Learners through Active Instruction and AssessmentEngaging Learners through Active Instruction and Assessment
Engaging Learners through Active Instruction and Assessment
 
Library Director Bootcamp: Getting the Skills You Need, Part 2 (Nov. 2018)
Library Director Bootcamp: Getting the Skills You Need, Part 2 (Nov. 2018)Library Director Bootcamp: Getting the Skills You Need, Part 2 (Nov. 2018)
Library Director Bootcamp: Getting the Skills You Need, Part 2 (Nov. 2018)
 
AL Live: What Do the Midterms Mean for Your Library? (November 2018)
AL Live: What Do the Midterms Mean for Your Library? (November 2018)AL Live: What Do the Midterms Mean for Your Library? (November 2018)
AL Live: What Do the Midterms Mean for Your Library? (November 2018)
 
Library Director Bootcamp: Getting the Skills You Need, Part 1 (Nov. 2018)
Library Director Bootcamp: Getting the Skills You Need, Part 1 (Nov. 2018)Library Director Bootcamp: Getting the Skills You Need, Part 1 (Nov. 2018)
Library Director Bootcamp: Getting the Skills You Need, Part 1 (Nov. 2018)
 
Prepare for the Future: Tech Strategies You Need to Know (November 2018)
Prepare for the Future: Tech Strategies You Need to Know (November 2018)Prepare for the Future: Tech Strategies You Need to Know (November 2018)
Prepare for the Future: Tech Strategies You Need to Know (November 2018)
 
Write and Cite “Chicago Style”: Helping Students and Patrons Understand The C...
Write and Cite “Chicago Style”: Helping Students and Patrons Understand The C...Write and Cite “Chicago Style”: Helping Students and Patrons Understand The C...
Write and Cite “Chicago Style”: Helping Students and Patrons Understand The C...
 

Recently uploaded

Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Krashi Coaching
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
fonyou31
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
QucHHunhnh
 

Recently uploaded (20)

Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 

Improve your library: Using the 5 Phases of Project Management

  • 1. Improve Your Library Using The 5 Phases of Project Management
  • 2. Today We Will... • Get comfortable with “Project Management” • All 5 phases • Focus on planning • Learn how to construct a Charter that prevents scope creep while identifying risks and satisfying stakeholders • And maybe identify what all these jargon-y words really mean • Brainstorm our way into an excellent WBS • Then use that to create a killer Gantt Chart • Be comfortable with planning. And planning to plan.
  • 3. Project Management The art and science of managing people, money and time to produce a specific service or product. Basic, common sense “best practices” for getting stuff done that is all wrapped up in specialized jargon and specific tools. The best way to make sure you produce something that makes everyone happy - but not a guarantee that this will happen.
  • 4. Project Management Phases "Project Management (phases)" by Alphamu57 - Own work. Licensed under GFDL via Commons - https://commons.wikimedia.org/wiki/File:Project_Management_(phases).png#/media/File:Project_Management_(phases).png
  • 5. Jargon Project Scope Scope creep Stakeholders Milestone Risk Issue Deliverable Dependencies Constraints PERT Gantt Project: Activities with defined outcome and resources, more than 50 or so hours (official PM definition) Scope: The size of the project, what is applicable and what isn’tScope Creep: The addition of activities to the project that are out of scope Stakeholders: People affected by the project Milestone: A deliverable that helps to show that schedules are being kept - hit milestones, make the project Risk: Something that could happen to the project and should be mitigatedIssue: Something that has happened and needs to be dealt with Deliverable: Something that has been created/altered as a result of project processes - documents, websites, reports, etc. Constraints: A limit that you need to keep in mind - time, money, people are most common, with rules/regs of industry also being popular (library privacy rules, etc.) PERT: Program Evaluation Review Technique - helps to schedule activities in a project (mathematically) Gantt: Helps to schedule activities in a project (visually)
  • 6. Brainstorming Rules: • No judgement zone • Everyone gets a voice • Have a recorder • Make sure all ideas are visible • Distribute ideas as soon as possible • Take time between brainstorming and idea deciding Techniques: • Mind mapping techniques • Start with a few “starter” ideas • Build on associations • Butcher block paper and/or post its • Lots and lots of people in a room doing this all at once!
  • 7. Project Management - Planning • First 2 phases • Initiation • Plan to plan • Planning and Design • Document the plan • The rest of the phases execute, monitor and close out the plan
  • 8. Initiation - Planning to Plan • Gather needs/assess current environment • Determine total budget • Determine total human resources • Determine time available • Identify Stakeholders • Run through project initiation checklist • https://www.dropbox.com/s/5d11kruoiazl05d/Project%20Initiation%20Checklist%20Template.dot?d l=0 • Create Project Charter (output)
  • 9. Environmental Scan • What problem is the project solving? • What options are available as solutions? • What resources are available to help solve the problem? • Time, People, Money • What constraints are in place? • Where is the library *now* - how far do you have to go to get to “done”?
  • 10. Constraints • Budget • How much money will each solution require? • How much money is available? • Will fundraising need to happen? • What stakeholders can you approach to get funding increases? • People • What staff skills are in place right now? • What skills are needed? • How many people are available for the work? • Time • What deadlines are externally imposed? • How long will each solution take to put into place?
  • 11. Stakeholders • Who is affected by the project? • Affected by the work being done? • Affected by the solution chosen? • Affected by the budget, time, people requirements? • Affected by the end result? • Sponsors • Workers/Project Team • Final users image credit: https://openclipart.org/detail/35563/abstract-people
  • 12. The Charter - Requirements • Whatever you need to make your project a success… • Scope statement • Statement of Conditions • Assumptions, Risks, Constraints, etc. • Project Structure • Waterfall? Agile? begin thinking about how to plan • Communication plan • Team Organization • Who’s on the project team • Who are the project’s sponsors? • Who are the stakeholders that need to be considered during the work?
  • 13. The Charter - Resources Simple Charter - One Page https://www.dropbox.com/s/fw4jruu6eqlrgbd/Project-Charter-Simple.doc?dl=0 Full Charter - with Table of Contents and more than you probably need https://www.dropbox.com/s/qa37ylgt1hbkuwa/ProjectCharter.docx?dl=0
  • 14. Planning/Design • Figure out planning method • Waterfall? Agile? • Get planning team together • Figure out scope of project • Work out deliverables needed for project • Create WBS from deliverables list • Project estimates • Budget, people, time • PM estimating tricks • Risk identification • Get approval of plans to start work
  • 15. Planning Method • Waterfall • Plan at the beginning through to the end (traditional) • Agile • Plan for 2 weeks, meet again at the end of those weeks to reassess and plan for next two weeks • Rinse, repeat • Agile software development • Rolling Wave • Cross between Waterfall and Agile • Plan to end, but revisit occasionally to assess and change as needed
  • 16. Planning Team • More brains is more better • Get as wide a cross-section of the organization as possible • Have a defined goal for each meeting • “Run an effective meeting” • Agenda! • Action Items! • Use brainstorming techniques as well as discussions
  • 17. Scope • What *isn’t* appropriate for this project? • What *exactly* are we doing here? • Scope change forms - keep them handy for use during the execution stage • Be ruthless!
  • 18. Deliverables • What will be produced as a result of this project? • Not just end-stage results - internal project docs, too • Plan ahead for what needs to be produced before other project activities can go ahead • Know what dependencies are in your project • Critical Path Planning (helpful in project time estimates) • Match skills to required deliverables • People management - the hardest part of project management
  • 20. Project Estimation • General Estimation Tips • Figure the resource needed, double it • With more experience, that formula can be tweaked • Estimating people needed • Estimating time needed • That Critical Path Planning thing again • Estimating money needed
  • 22. Risk identification • Project Assumptions • What if you are wrong? • Past projects • Documentation is vital here • Experienced staff • Pick their brains! • Brainstorming
  • 23. Approvals • Sponsor feedback • Administration’s signatures • Project team’s buy-in • Start work!
  • 24. The rest of the process • Execution • Do the work laid out in the WBS/Gantt Chart • Monitoring and Controlling • Use the charter and other planning documents to make sure you are on time, budget and schedule • Close Out • Finalize documentation and file it for use in future projects (reinventing the wheel is time- consuming!!) • Have a party!
  • 26. Thank You! Robin Hastings Director of Technology Services and Technology Consultant Northeast Kansas Library System robin.hastings@gmail.com

Editor's Notes

  1. Introduction Experience with PM in my work Goals for today: Identify the 5 phases of project management Use brainstorming techniques to break down a large project into smaller components and using those to create a master plan Understand and use basic planning documentation from project management toolkits Articulate why planning is so important for successful projects
  2. Wikipedia's definition of PM My definition of PM The odds will ever be in your favor should you choose to use the tools/techniques of project management in your future projects.
  3. Project Management Institute produces the PMBOK (bible!). This is traditional, also have Agile PM just released a few years ago.
  4. Activities with defined outcome and resources, more than 50 or so hours (official PM definition) The size of the project, what is applicable and what isn’t The addition of activities to the project that are out of scope People affected by the project Something that has to be done before other activities can be done A deliverable that helps to show that schedules are being kept - hit milestones, make the project Something that could happen to the project and should be mitigated Something that has happened and needs to be dealt with Something that has been created/altered as a result of project processes - documents, websites, reports, etc. Something that must be done before other project activities can be started A limit that you need to keep in mind - time, money, people are most common, with rules/regs of industry also being popular (library privacy rules, etc.) Program Evaluation Review Technique - helps to schedule activities in a project (mathematically) Helps to schedule activities in a project (visually)
  5. Some people aren’t comfortable yelling out ideas, give out post-its so they can write down their thoughts and post them on the paper
  6. Inputs and outputs - the Charter is both an input to the Planning and Design phase (you start it in the Initiation phase) and an output to the Execute phase which helps you do the work you've spent so much time planning.
  7. There is no way to create a route to get somewhere if you don't know where you are to begin with!
  8. Use Project Charter information as input into this phase - you will continue to fill it out and expand on the project plans. The finished, signed charter will be the output of this phase and the document you use to move into the Execution phase.
  9. Another use for scope change forms - Project #2 - they can be put off. Sometimes political issues make saying no impossible - make sure the person asking understands how they will be affecting the project via the change form.
  10. Super task-chart. For larger projects, each “activity” in the box should be about 8 hours of work. For smaller projects, those activities can be broken down more, into smaller chunks.
  11. Visual way to identify who does what and when it’s supposed to be done. X-Axis - Each line is an activity (from WBS) Each color is a resource (person, department, outside vendor, etc.) Y-Axis – timeline – lets you know when the resource should be working on the activity Visualize dependencies, constraints, resource allocation, schedule and milestone achievements