SlideShare a Scribd company logo
1 of 1
Earned Value on A T24 Temenos Project

The project has elected to use a method called “Earned Value” to plan and track progress. The
work stream leads are required to define a list of high level project tasks and estimate the time
that each task will require. A predicted completion date for each task can be estimated by
determining when the project will have expended the requisite effort. This is known as the
BCWS or Budgeted Cost of Work Scheduled.

The Earned Value (EV) method then assigns each task a value based upon its estimated cost /
effort. As each task progresses to completion the work stream “earns” the originally estimated
value for the task, known as the BCWP or Budgeted Cost of Work Performed.

The real cost or effort to complete the task is also tracked as the ACWP or Actual Cost of Work
Performed. The combination of these three values allows the T24 project to determine both cost
and schedule variances from the plan.

Within Share Point, performance of the two key indices is visible to all. These are CPi or Cost
Performance index and SPi or Schedule Performance index.

Guidelines for Work Stream Leads

    1. ********* is responsible for maintaining the Plan and EV schedules.
    2. Work Stream leads must provide a weekly update to the planning manager. This means
         that if you have nothing to report you provide him an email stating that; i.e. a nil
         submission. If you fail to submit a plan your Work Stream will automatically deteriorate
         one notch in its RAG status, i.e. move from Green to Amber, or Amber to Red.
    3.   The planning manager will update share point on a weekly basis, currently scheduled for
         Mondays.
    4.   As a Work Stream lead it is your responsibility to understand the implications of
         movements within your plan and the residual impact on the EV indices (CPi; SPi).
    5.   The tolerance limits are currently set at +/- 10%. The normal performance is an index of
         1.0. Below this indicates there is a negative variance from your plan, a reading above 1.0
         indicates a positive variance, and a reading of 1.0 indicates performance according to
         plan.
    6.   The Work Stream lead has the latitude to take corrective action when the performance
         sits within the tolerance limits established under point 5 above. However, should they
         exceed the tolerance limits then the management team will become involved. The Work
         Stream lead should notify the Management team as soon as they become aware that they
         will deviate beyond the established tolerance limits.
    7.   Although tracking EV occurs during project execution, it cannot be accomplished if
         appropriate planning and budget allocation has not occurred.

More Related Content

What's hot

Revised Construction Drawing Flow Chart_2016_01_11
Revised Construction Drawing Flow Chart_2016_01_11Revised Construction Drawing Flow Chart_2016_01_11
Revised Construction Drawing Flow Chart_2016_01_11
Jack Tan Kiah Kee
 
Evm Basics
Evm BasicsEvm Basics
Evm Basics
gfbreaux
 
Cert iv cost part 2
Cert iv  cost part 2Cert iv  cost part 2
Cert iv cost part 2
Skript
 
Capital Project Process Presentation
Capital Project Process PresentationCapital Project Process Presentation
Capital Project Process Presentation
Liu Qi
 

What's hot (20)

Revised Construction Drawing Flow Chart_2016_01_11
Revised Construction Drawing Flow Chart_2016_01_11Revised Construction Drawing Flow Chart_2016_01_11
Revised Construction Drawing Flow Chart_2016_01_11
 
Evm Basics
Evm BasicsEvm Basics
Evm Basics
 
EVM in MS Project
EVM in MS ProjectEVM in MS Project
EVM in MS Project
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
Project cost control
Project cost controlProject cost control
Project cost control
 
Agile metrics
Agile metricsAgile metrics
Agile metrics
 
Cert iv cost part 2
Cert iv  cost part 2Cert iv  cost part 2
Cert iv cost part 2
 
Use of forward pass and backward pass in primavera
Use of forward pass and backward pass in primaveraUse of forward pass and backward pass in primavera
Use of forward pass and backward pass in primavera
 
Capital Project Process Presentation
Capital Project Process PresentationCapital Project Process Presentation
Capital Project Process Presentation
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Earned value 01
Earned value 01Earned value 01
Earned value 01
 
21.03.2018 ARDC session #3 measuring work Progress
21.03.2018 ARDC session #3  measuring work Progress21.03.2018 ARDC session #3  measuring work Progress
21.03.2018 ARDC session #3 measuring work Progress
 
Oil and Gas Risk Analysis
Oil and Gas Risk AnalysisOil and Gas Risk Analysis
Oil and Gas Risk Analysis
 
EVMS for Commercial projects
EVMS for Commercial projectsEVMS for Commercial projects
EVMS for Commercial projects
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
CMS Capabilities
CMS CapabilitiesCMS Capabilities
CMS Capabilities
 
Whats new
Whats newWhats new
Whats new
 
Project Management-Important Equations
Project Management-Important Equations Project Management-Important Equations
Project Management-Important Equations
 
Session 10 4th edition PMP
Session   10 4th edition PMPSession   10 4th edition PMP
Session 10 4th edition PMP
 

Viewers also liked

POLS 243 INVESTIGATION PLAN
POLS 243 INVESTIGATION PLANPOLS 243 INVESTIGATION PLAN
POLS 243 INVESTIGATION PLAN
Megan James
 
Evaluación inicial
Evaluación inicialEvaluación inicial
Evaluación inicial
caro_1898
 
Operational Intelligence and Machine Data with Splunk
Operational Intelligence and Machine Data with SplunkOperational Intelligence and Machine Data with Splunk
Operational Intelligence and Machine Data with Splunk
ayman diab
 
Tarea de programacion avanzada
Tarea de programacion avanzadaTarea de programacion avanzada
Tarea de programacion avanzada
KATHYALILIBETH
 
1ro a wbqst
1ro a wbqst1ro a wbqst
1ro a wbqst
Paudcc
 
Antonya vijaya raj CV -4 Years Experiences in Senior Sustain Engineer,
Antonya vijaya raj  CV -4 Years Experiences in Senior Sustain Engineer,Antonya vijaya raj  CV -4 Years Experiences in Senior Sustain Engineer,
Antonya vijaya raj CV -4 Years Experiences in Senior Sustain Engineer,
Antonya vijaya raj s
 
Secrecion acida
Secrecion acidaSecrecion acida
Secrecion acida
moisies
 
mapa gerencia de proyectos
mapa gerencia de proyectosmapa gerencia de proyectos
mapa gerencia de proyectos
berlioz25
 

Viewers also liked (20)

POLS 243 INVESTIGATION PLAN
POLS 243 INVESTIGATION PLANPOLS 243 INVESTIGATION PLAN
POLS 243 INVESTIGATION PLAN
 
Evaluación inicial
Evaluación inicialEvaluación inicial
Evaluación inicial
 
Operational Intelligence and Machine Data with Splunk
Operational Intelligence and Machine Data with SplunkOperational Intelligence and Machine Data with Splunk
Operational Intelligence and Machine Data with Splunk
 
proyecto final
proyecto finalproyecto final
proyecto final
 
Śniadanie Daje Moc
Śniadanie Daje MocŚniadanie Daje Moc
Śniadanie Daje Moc
 
Tarea de programacion avanzada
Tarea de programacion avanzadaTarea de programacion avanzada
Tarea de programacion avanzada
 
POISSON - Estadistica
POISSON - EstadisticaPOISSON - Estadistica
POISSON - Estadistica
 
En tiempos de los romanos
En tiempos de los romanosEn tiempos de los romanos
En tiempos de los romanos
 
Lab3.15
Lab3.15Lab3.15
Lab3.15
 
Śniadanie Daje Moc
Śniadanie Daje MocŚniadanie Daje Moc
Śniadanie Daje Moc
 
1ro a wbqst
1ro a wbqst1ro a wbqst
1ro a wbqst
 
Antonya vijaya raj CV -4 Years Experiences in Senior Sustain Engineer,
Antonya vijaya raj  CV -4 Years Experiences in Senior Sustain Engineer,Antonya vijaya raj  CV -4 Years Experiences in Senior Sustain Engineer,
Antonya vijaya raj CV -4 Years Experiences in Senior Sustain Engineer,
 
Psicología organizacional laboral
Psicología organizacional laboralPsicología organizacional laboral
Psicología organizacional laboral
 
Aprendiendo de mi computadora
Aprendiendo de mi computadoraAprendiendo de mi computadora
Aprendiendo de mi computadora
 
Vp specialized2015
Vp specialized2015Vp specialized2015
Vp specialized2015
 
Secrecion acida
Secrecion acidaSecrecion acida
Secrecion acida
 
Babita dibujos
Babita dibujosBabita dibujos
Babita dibujos
 
mapa gerencia de proyectos
mapa gerencia de proyectosmapa gerencia de proyectos
mapa gerencia de proyectos
 
Projecte Museu Picasso Barcelona
Projecte Museu Picasso BarcelonaProjecte Museu Picasso Barcelona
Projecte Museu Picasso Barcelona
 
Raçadores para corte 2009 Guzerá
Raçadores para corte 2009 GuzeráRaçadores para corte 2009 Guzerá
Raçadores para corte 2009 Guzerá
 

Similar to High Level Overview Of Using The Earned Value On A T24 Project

160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
eidalin95
 
A Planning Process
A Planning ProcessA Planning Process
A Planning Process
pipmonck
 
Project Management Earned Value
Project Management Earned ValueProject Management Earned Value
Project Management Earned Value
constructioninside
 
INFORMATION SYTEMS .docx
INFORMATION SYTEMS                                                .docxINFORMATION SYTEMS                                                .docx
INFORMATION SYTEMS .docx
pauline234567
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
selinasimpson1601
 
Develop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docxDevelop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docx
khenry4
 

Similar to High Level Overview Of Using The Earned Value On A T24 Project (20)

Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 
formation.docx
formation.docxformation.docx
formation.docx
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
A Planning Process
A Planning ProcessA Planning Process
A Planning Process
 
Chap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfChap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdf
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master schedule
 
Project Management Earned Value
Project Management Earned ValueProject Management Earned Value
Project Management Earned Value
 
T24 Temenos Earned Value Management & Project Planning Presentation
T24 Temenos Earned Value Management & Project Planning PresentationT24 Temenos Earned Value Management & Project Planning Presentation
T24 Temenos Earned Value Management & Project Planning Presentation
 
INFORMATION SYTEMS .docx
INFORMATION SYTEMS                                                .docxINFORMATION SYTEMS                                                .docx
INFORMATION SYTEMS .docx
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance Analysis
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Develop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docxDevelop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docx
 
Your Projects May Be Robbing You Blind
Your Projects May Be Robbing You BlindYour Projects May Be Robbing You Blind
Your Projects May Be Robbing You Blind
 

More from Michael Gowlett PMP, Prince 2 Practitioner

More from Michael Gowlett PMP, Prince 2 Practitioner (6)

Graphical CV
Graphical CVGraphical CV
Graphical CV
 
BCBS Information Article By Mike Gowlett
BCBS Information Article By Mike GowlettBCBS Information Article By Mike Gowlett
BCBS Information Article By Mike Gowlett
 
Preparing For A Competency Interview Template
Preparing For A Competency Interview TemplatePreparing For A Competency Interview Template
Preparing For A Competency Interview Template
 
Real World Excel Formulas
Real World Excel FormulasReal World Excel Formulas
Real World Excel Formulas
 
How to setup EVM within a PMO
How to setup EVM within a PMOHow to setup EVM within a PMO
How to setup EVM within a PMO
 
T24 Temenos Methodology Overview
T24 Temenos Methodology OverviewT24 Temenos Methodology Overview
T24 Temenos Methodology Overview
 

High Level Overview Of Using The Earned Value On A T24 Project

  • 1. Earned Value on A T24 Temenos Project The project has elected to use a method called “Earned Value” to plan and track progress. The work stream leads are required to define a list of high level project tasks and estimate the time that each task will require. A predicted completion date for each task can be estimated by determining when the project will have expended the requisite effort. This is known as the BCWS or Budgeted Cost of Work Scheduled. The Earned Value (EV) method then assigns each task a value based upon its estimated cost / effort. As each task progresses to completion the work stream “earns” the originally estimated value for the task, known as the BCWP or Budgeted Cost of Work Performed. The real cost or effort to complete the task is also tracked as the ACWP or Actual Cost of Work Performed. The combination of these three values allows the T24 project to determine both cost and schedule variances from the plan. Within Share Point, performance of the two key indices is visible to all. These are CPi or Cost Performance index and SPi or Schedule Performance index. Guidelines for Work Stream Leads 1. ********* is responsible for maintaining the Plan and EV schedules. 2. Work Stream leads must provide a weekly update to the planning manager. This means that if you have nothing to report you provide him an email stating that; i.e. a nil submission. If you fail to submit a plan your Work Stream will automatically deteriorate one notch in its RAG status, i.e. move from Green to Amber, or Amber to Red. 3. The planning manager will update share point on a weekly basis, currently scheduled for Mondays. 4. As a Work Stream lead it is your responsibility to understand the implications of movements within your plan and the residual impact on the EV indices (CPi; SPi). 5. The tolerance limits are currently set at +/- 10%. The normal performance is an index of 1.0. Below this indicates there is a negative variance from your plan, a reading above 1.0 indicates a positive variance, and a reading of 1.0 indicates performance according to plan. 6. The Work Stream lead has the latitude to take corrective action when the performance sits within the tolerance limits established under point 5 above. However, should they exceed the tolerance limits then the management team will become involved. The Work Stream lead should notify the Management team as soon as they become aware that they will deviate beyond the established tolerance limits. 7. Although tracking EV occurs during project execution, it cannot be accomplished if appropriate planning and budget allocation has not occurred.