Develop a network schedule for your project using either the arrow diagramming method or the precedence method. Also, your project schedule should illustrate float/slack for each activity.
Table 1.1. Project Tasks details
Activity
Predecessor
Anticipated Resources
Added Resources
Duration
Early start date
A (Retirement and social security benefits)
None
$126
$50
One year
1/1/2019
B (Audit & risk evaluation)
A
$118
$25
11 months
2/1/2019
C (Equipment Maintenance)
B
$121
$30
8 months
2/1/2019
D (Training & Development)
A, B
$109
$25
One year
1/2/2019
E (Logistics, appraisals & rewards)
D, C
$118
$30
One year
1/2/2019
Precedence Diagramming Method:
ES
Duration
EF
Activity Legend
LS
Float/slack
LF
LS= Late start Dependency
LF= Late Finish
ES= Early start
EF= Early finish
F= Float/Slack
08/09/2019
1 year 7 months
03/04/2021
Activity B Audit & Risk Evaluation
12/19/2020
2 months
Resources=$25
03/04/2021
07/25/2019
11 months
06/22/2020
Activity C Equipment & Maintenance
08/1/2019
4 months
Resources=$30
12/22/2020
12/27/2019
8 months
08/05//2020
Activity A Retirement & social security
Resources =$50
03/05/2020
3 days
03/8/2020
07/31/2019
2 months
09/23/2019
Activity E Logistics, Appraisals & Rewards
08/10/2019
2 days
Resources=$30
08/12/2019
03/22/2019
1 month
04/09/2019
Activity D Training & Development
03/22/19
5 days
Resources =$25
03/28/2019
5 Activities with 6 dependencies
Running head: EVM PAPER 1
EVM PAPER 1
EVM Paper
Mary Krenisky
Joe Scott
BUS 419
August 27, 2018
EVM Paper
In the current project, additional resources are added at in each work activity to complete the work packages in a quickly. The resources are added to these activities to reduce the slack that may originate if the project is accomplished based on planned resources only. An earned value analysis has to be performed to keep track of a project’s performance. This type of assessment gives a general review about the performance of a project along the chosen course. It has been noted that after adding more resources for the achievement of the ventures successfully, the slack time has been decreased and the work is going on faster than planned.
Earned value management is employed in different forms to determine the performance of the projects. By using this technique, the cost, schedule and, scope of the project are integrated that in turn aids the team of project administration to calculate and evaluate fulfillment and growth of the plan (Usmani, n.d.). The measurements of earned value are utilized by all managers of the projects. There are three main components of earned value management which are
• Actual cost
• Earned value
• Planned value
Planned value
It is the value of a task to be accomplished in a specified time. Overall planned value is known as ‘Budget at completion.’ Planned value also acts as a project’s baseline (Usmani, n.d.).
Actual cost
Actual cost denotes the quantity of money which is i.
Develop a network schedule for your project using either the arrow.docx
1. Develop a network schedule for your project using either the
arrow diagramming method or the precedence method. Also,
your project schedule should illustrate float/slack for each
activity.
Table 1.1. Project Tasks details
Activity
Predecessor
Anticipated Resources
Added Resources
Duration
Early start date
A (Retirement and social security benefits)
None
$126
$50
One year
1/1/2019
B (Audit & risk evaluation)
A
$118
$25
11 months
2/1/2019
C (Equipment Maintenance)
B
$121
$30
8 months
2/1/2019
D (Training & Development)
2. A, B
$109
$25
One year
1/2/2019
E (Logistics, appraisals & rewards)
D, C
$118
$30
One year
1/2/2019
Precedence Diagramming Method:
ES
Duration
EF
Activity Legend
LS
Float/slack
LF
LS= Late start Dependency
LF= Late Finish
ES= Early start
EF= Early finish
F= Float/Slack
08/09/2019
1 year 7 months
03/04/2021
Activity B Audit & Risk Evaluation
12/19/2020
2 months
3. Resources=$25
03/04/2021
07/25/2019
11 months
06/22/2020
Activity C Equipment & Maintenance
08/1/2019
4 months
Resources=$30
12/22/2020
12/27/2019
8 months
08/05//2020
Activity A Retirement & social security
Resources =$50
03/05/2020
3 days
03/8/2020
07/31/2019
2 months
09/23/2019
Activity E Logistics, Appraisals & Rewards
08/10/2019
2 days
Resources=$30
08/12/2019
03/22/2019
1 month
04/09/2019
Activity D Training & Development
03/22/19
5 days
Resources =$25
4. 03/28/2019
5 Activities with 6 dependencies
Running head: EVM PAPER 1
EVM PAPER 1
EVM Paper
Mary Krenisky
Joe Scott
BUS 419
August 27, 2018
EVM Paper
In the current project, additional resources are added at in
each work activity to complete the work packages in a quickly.
The resources are added to these activities to reduce the slack
that may originate if the project is accomplished based on
5. planned resources only. An earned value analysis has to be
performed to keep track of a project’s performance. This type of
assessment gives a general review about the performance of a
project along the chosen course. It has been noted that after
adding more resources for the achievement of the ventures
successfully, the slack time has been decreased and the work is
going on faster than planned.
Earned value management is employed in different forms
to determine the performance of the projects. By using this
technique, the cost, schedule and, scope of the project are
integrated that in turn aids the team of project administration to
calculate and evaluate fulfillment and growth of the plan
(Usmani, n.d.). The measurements of earned value are utilized
by all managers of the projects. There are three main
components of earned value management which are
• Actual cost
• Earned value
• Planned value
Planned value
It is the value of a task to be accomplished in a specified time.
Overall planned value is known as ‘Budget at completion.’
Planned value also acts as a project’s baseline (Usmani, n.d.).
Actual cost
Actual cost denotes the quantity of money which is invested in
the project until the present.
Earned value
Earned value is the worth of the task accomplished until
the current time. Suppose, a project is terminated in the middle,
the earned value will show the quality produced by the project
till to date. The assessment of earned value management of the
recent project indicates higher earned value and planned value.
While the actual cost spent on the project is lower. The three
cost’s that are planned value, actual cost and earned value are
mixed to achieve the information about the completion of a
6. project in a specific period.
Cost variance and schedule variance determine cost and
schedule performances of the project. Following formula
measures cost variance.
Cost variance = Earned value-actual cost (Cullen, 2016)
If cost variance is achieved in a negative value, it means that
the project is higher than the budget.
Schedule variance is computed through a specific formula, i.e.
Schedule variance = Earned value/Planned value
If schedule variance is obtained in a negative value, it denotes
the fact that the project is on the far side of the schedule
(Cullen, 2016).
In the current project, negative cost variances are obtained
for the months of January, February and, April which denotes
that the activities are higher than the planned budget and
require resources to be executed successfully. Negative
schedule variances are obtained for January and June which
shows that at these specific durations, the project is behind the
set timetable. So, there is a need for additional resources to
resolve the issue and complete the project fast.