SlideShare a Scribd company logo
1 of 10
BIG Structural Engineering Corporation
The "BIG" engineering project
Bigger is better, because it reflects our profit motives“
By: Mark Blum
University of British Columbia
Project Management
PM TOOL KIT ASSIGNMENT: Course IL821W14A
Executive Summary & Background
This presentation is with regards to, the current
budget and schedule overruns in, “The BIG
Engineering project” utilizing Earned Value
Analysis.
Earned Value Analysis (EVA); has been used by the U.S. Defence Department since the 1960s and
they have found it to be an accurate forecasting tool. Their statistical analysis has shown that
once a project is 10% complete, the overrun at completion will not be less than the current
overrun.
They also found that once a project is 20% complete, the (CPI) Cost Performance Index does not vary
from its current value by more than 10%*.
* QUOTE: UBC Project Management Course Manual
This project is currently over budget regarding it’s, C.P.I
and other key indicators.
- Something needs to be done to change this course …
Section I
This project is behind schedule and over budget as of the end of 1Q10.
The project is 25% complete, this means we need to achieve overall savings
during the remaining 75% of the project. -How do we do this?
This meeting is to review options
Actual and projected cost comparisons
@
24%completion of Project
V.A.C (Current
"Variance at
completion" -
$168,618.40
A.C (Actual cost to
date) 629522
(Schedual Variance)
-Over budget. -
248660
E.A.C (Estimated
Cost @ completion)
1988478.4
AC (Actual cost to
date)
SV (Schedual
Variance) -Over
budget.
EAC (Estimated
Cost @ completion)
VAC (Current
"Varance at
completion"
Making Sense of Dollars and Cents
$0.00
$100,000.00
$200,000.00
$300,000.00
$400,000.00
$500,000.00
$600,000.00
$700,000.00
$800,000.00
$900,000.00
PlannedValue-PV(BCWS) EarnedValue-EV(BCWP) AC(ACWP)
Series1
Column #1
Planned Value PV (BCWS)
Cumulative, budgeted cost of work scheduled
(How much money we budgeted)
which is: $824,800.00
Column #2
Earned Value - EV (BCWP )
Cumulative budgeted cost of work
performed or Earned Value.
(This is what is paid for and completed).
which is: $576,140.00
Column #3
Actual Cost (ACWP)
Cumulative actual cost of work
performed or (What we paid for so far)
which is $629,522.00
Current Project Status
I have conducted an analysis of the projects progress to date,
to determine the reason, costs and the schedule are
exceeding expectations and underperforming.
1. The Schedule Performance Index is 0.7, and there is a cost Variance of 0.92.
( anything less than 1 is over budget)
2. The schedule variance is $248, 660.00 Dollars over budgeted allocations.
3. The cost Variance is $53,382.00 Dollars over budgeted allocations.
WHY ?
Earned Value Analysis tracks money expended
compares it to budgeted allocations for actual
performance.
E.V.A. is a very good way to monitor progress; - and to be proactive.
When resource allocations have not been fulfilled, as planned or budgeted for:
• This unfulfilled work, causes budgetary deficiencies and cost overruns.
• In this project, the categories of Design / Planning / Control and Scope are not in compliance with the plan.
• In this project “TASKS” are showing very low resource utilization compliance, with planned results and
particularly scheduled results pointing towards exceeding both the scheduled and budget projections.
• When “Planned value” and “Actual cost” are not equal, this creates budgeted cost overruns.
• This is due to non performance as per my analysis caused by the under performance of resources.
• In a domino effect; This affects both earned value, and critical schedules to complete the project.
• You can see from the Ms. Project budget cost over runs are due largely do to scheduling issues, or in simpler
terms;
-Work is not being performed as schedule by resources.
Summary of Calculations
Note: *These values have been rounded off.
Earned Value Calculations*
PV = Planned Value $825,000
AC = Actual Cost to date $630,000
EV = Earned Value
– What is completed
$576,000
SV = Schedule Variance ($249,000)
CV = Cost Variance ($53,000)
SPI = Schedule Performance Index .70
CPI = Cost Performance Index .92
EAC = Estimate at completion $2,000,000
VAC = Variance at completion ($169,000)
BAC = Budget at completion $1,819,000
ETC = Estimate at completion $1,676,000
Section II
Specific Solutions
What is the essence
of the issue?
It appears we have an issue with resource
non-performance causing budget
overruns.
Delays in getting work (tasks), done on
time as scheduled, are going to
result cost increases given current
projections, if corrective action is
not taken as soon as possible.
Resources not availing themselves to the
project, are therefore causing
delays and increased costs.
How do we rectify
this problem?
It is critical that all departments :
implement the resources necessary for the
project tasks suffering from non
conformity in order to succeed
according to our plan, to bring the
project back on track, so that we can
achieve project completion both;
On Time & On Budget.
Specific Solutions
How should we proceed proactively /
concretely and prevent the
projected cost over runs?
After this meeting, I will supply a list of resources that are
under performing to each department by email.
1. I will be sending an excel spread sheet by email
after this meeting to each affected senior manager
explaining these areas are under performing. The
yellow highlighted areas are an itemized list for each
task/resource that is non conforming.
1. You can forward this to each of the affected
department managers, and determine the reason
for non performance, and how this can be overcome
and to allocate the specified non-performing
resources on a priority bases.
2. This list will enable you to address the problems
with resources that are causing these budgetary
overruns due to non performance, so that we can
bring the project back on track.
What are the
costs of these
recommendations ?
These recommendations will not
change the projects
scope, but rather bring the
budgets and time
schedule back in line with
the allocations.
It is critical that the change
control committee
approve the requirement
that resources be
allocated without further
delay to bring the project
back on track with the
allocated budgets and
expedite the performance
of all resources towards
their fulfillment.
Section III
Decisions - management needs to make
Actions needed
I am confident that each department will make the adjustments necessary
to allocate resources once I provide this listing and you have seen the listing of non
performers. You can now pin point where you need to take action and where
are the compliance issues, provide motivation, to either meet or exceed
the expectations of our plan in the spirit of true team work.
Thank you!
Mark Blum
© 2014 Mark Blum ALL RIGHTS RESERVED

More Related Content

What's hot

Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction projectIAEME Publication
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis trainingPaul King
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-controleidalin95
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management EssentialsGlen Alleman
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)Harshit Mahajan
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners Shenin Hassan
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7Muzette Charles, PMP
 
Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examManish Purwar
 
Earned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsEarned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsIftikhar Anjum
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMatt Stehling
 

What's hot (18)

Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction project
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis training
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management Essentials
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Project Control Process
Project Control ProcessProject Control Process
Project Control Process
 
Project cost control
Project cost controlProject cost control
Project cost control
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
 
Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp exam
 
Earned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsEarned Value Management (EVM) Limitations
Earned Value Management (EVM) Limitations
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 

Similar to Mark blum ubc tool box execution - powerpoint presentation

Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneWaleed Hamdy Albana
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Develop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docxDevelop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docxkhenry4
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project managementselinasimpson1601
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxsagarlesley
 
Highlights on Earned Value Management Elements
Highlights on Earned Value Management ElementsHighlights on Earned Value Management Elements
Highlights on Earned Value Management ElementsYahya Khatib
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.pptProfDrAnbalaganChinn
 
Basic Concepts of Earned Value Management.pdf
Basic Concepts of Earned Value Management.pdfBasic Concepts of Earned Value Management.pdf
Basic Concepts of Earned Value Management.pdfElyes ELEBRI
 
INFORMATION SYTEMS .docx
INFORMATION SYTEMS                                                .docxINFORMATION SYTEMS                                                .docx
INFORMATION SYTEMS .docxpauline234567
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureJohn Carter
 
PM Session 7
PM Session 7PM Session 7
PM Session 7dmdk12
 
03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdfzohir khellouf
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementHayat Denzi
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
PM_Assignment3_Group1 (2).pptx
PM_Assignment3_Group1 (2).pptxPM_Assignment3_Group1 (2).pptx
PM_Assignment3_Group1 (2).pptxvanna37
 

Similar to Mark blum ubc tool box execution - powerpoint presentation (20)

EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Develop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docxDevelop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docx
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Highlights on Earned Value Management Elements
Highlights on Earned Value Management ElementsHighlights on Earned Value Management Elements
Highlights on Earned Value Management Elements
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Basic Concepts of Earned Value Management.pdf
Basic Concepts of Earned Value Management.pdfBasic Concepts of Earned Value Management.pdf
Basic Concepts of Earned Value Management.pdf
 
INFORMATION SYTEMS .docx
INFORMATION SYTEMS                                                .docxINFORMATION SYTEMS                                                .docx
INFORMATION SYTEMS .docx
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown Structure
 
PM Session 7
PM Session 7PM Session 7
PM Session 7
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
PM_Assignment3_Group1 (2).pptx
PM_Assignment3_Group1 (2).pptxPM_Assignment3_Group1 (2).pptx
PM_Assignment3_Group1 (2).pptx
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 

Recently uploaded

Full night 🥵 Call Girls Delhi New Friends Colony {9711199171} Sanya Reddy ✌️o...
Full night 🥵 Call Girls Delhi New Friends Colony {9711199171} Sanya Reddy ✌️o...Full night 🥵 Call Girls Delhi New Friends Colony {9711199171} Sanya Reddy ✌️o...
Full night 🥵 Call Girls Delhi New Friends Colony {9711199171} Sanya Reddy ✌️o...shivangimorya083
 
Brighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingBrighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingNeil Barnes
 
dokumen.tips_chapter-4-transient-heat-conduction-mehmet-kanoglu.ppt
dokumen.tips_chapter-4-transient-heat-conduction-mehmet-kanoglu.pptdokumen.tips_chapter-4-transient-heat-conduction-mehmet-kanoglu.ppt
dokumen.tips_chapter-4-transient-heat-conduction-mehmet-kanoglu.pptSonatrach
 
Saket, (-DELHI )+91-9654467111-(=)CHEAP Call Girls in Escorts Service Saket C...
Saket, (-DELHI )+91-9654467111-(=)CHEAP Call Girls in Escorts Service Saket C...Saket, (-DELHI )+91-9654467111-(=)CHEAP Call Girls in Escorts Service Saket C...
Saket, (-DELHI )+91-9654467111-(=)CHEAP Call Girls in Escorts Service Saket C...Sapana Sha
 
定制英国白金汉大学毕业证(UCB毕业证书) 成绩单原版一比一
定制英国白金汉大学毕业证(UCB毕业证书)																			成绩单原版一比一定制英国白金汉大学毕业证(UCB毕业证书)																			成绩单原版一比一
定制英国白金汉大学毕业证(UCB毕业证书) 成绩单原版一比一ffjhghh
 
Schema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfSchema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfLars Albertsson
 
B2 Creative Industry Response Evaluation.docx
B2 Creative Industry Response Evaluation.docxB2 Creative Industry Response Evaluation.docx
B2 Creative Industry Response Evaluation.docxStephen266013
 
Predicting Employee Churn: A Data-Driven Approach Project Presentation
Predicting Employee Churn: A Data-Driven Approach Project PresentationPredicting Employee Churn: A Data-Driven Approach Project Presentation
Predicting Employee Churn: A Data-Driven Approach Project PresentationBoston Institute of Analytics
 
VIP High Class Call Girls Bikaner Anushka 8250192130 Independent Escort Servi...
VIP High Class Call Girls Bikaner Anushka 8250192130 Independent Escort Servi...VIP High Class Call Girls Bikaner Anushka 8250192130 Independent Escort Servi...
VIP High Class Call Girls Bikaner Anushka 8250192130 Independent Escort Servi...Suhani Kapoor
 
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Callshivangimorya083
 
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Callshivangimorya083
 
Digi Khata Problem along complete plan.pptx
Digi Khata Problem along complete plan.pptxDigi Khata Problem along complete plan.pptx
Digi Khata Problem along complete plan.pptxTanveerAhmed817946
 
From idea to production in a day – Leveraging Azure ML and Streamlit to build...
From idea to production in a day – Leveraging Azure ML and Streamlit to build...From idea to production in a day – Leveraging Azure ML and Streamlit to build...
From idea to production in a day – Leveraging Azure ML and Streamlit to build...Florian Roscheck
 
High Class Call Girls Noida Sector 39 Aarushi 🔝8264348440🔝 Independent Escort...
High Class Call Girls Noida Sector 39 Aarushi 🔝8264348440🔝 Independent Escort...High Class Call Girls Noida Sector 39 Aarushi 🔝8264348440🔝 Independent Escort...
High Class Call Girls Noida Sector 39 Aarushi 🔝8264348440🔝 Independent Escort...soniya singh
 
Call Girls In Mahipalpur O9654467111 Escorts Service
Call Girls In Mahipalpur O9654467111  Escorts ServiceCall Girls In Mahipalpur O9654467111  Escorts Service
Call Girls In Mahipalpur O9654467111 Escorts ServiceSapana Sha
 
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改atducpo
 
Kantar AI Summit- Under Embargo till Wednesday, 24th April 2024, 4 PM, IST.pdf
Kantar AI Summit- Under Embargo till Wednesday, 24th April 2024, 4 PM, IST.pdfKantar AI Summit- Under Embargo till Wednesday, 24th April 2024, 4 PM, IST.pdf
Kantar AI Summit- Under Embargo till Wednesday, 24th April 2024, 4 PM, IST.pdfSocial Samosa
 

Recently uploaded (20)

Full night 🥵 Call Girls Delhi New Friends Colony {9711199171} Sanya Reddy ✌️o...
Full night 🥵 Call Girls Delhi New Friends Colony {9711199171} Sanya Reddy ✌️o...Full night 🥵 Call Girls Delhi New Friends Colony {9711199171} Sanya Reddy ✌️o...
Full night 🥵 Call Girls Delhi New Friends Colony {9711199171} Sanya Reddy ✌️o...
 
VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...
VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...
VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...
 
Brighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data StorytellingBrighton SEO | April 2024 | Data Storytelling
Brighton SEO | April 2024 | Data Storytelling
 
dokumen.tips_chapter-4-transient-heat-conduction-mehmet-kanoglu.ppt
dokumen.tips_chapter-4-transient-heat-conduction-mehmet-kanoglu.pptdokumen.tips_chapter-4-transient-heat-conduction-mehmet-kanoglu.ppt
dokumen.tips_chapter-4-transient-heat-conduction-mehmet-kanoglu.ppt
 
Saket, (-DELHI )+91-9654467111-(=)CHEAP Call Girls in Escorts Service Saket C...
Saket, (-DELHI )+91-9654467111-(=)CHEAP Call Girls in Escorts Service Saket C...Saket, (-DELHI )+91-9654467111-(=)CHEAP Call Girls in Escorts Service Saket C...
Saket, (-DELHI )+91-9654467111-(=)CHEAP Call Girls in Escorts Service Saket C...
 
定制英国白金汉大学毕业证(UCB毕业证书) 成绩单原版一比一
定制英国白金汉大学毕业证(UCB毕业证书)																			成绩单原版一比一定制英国白金汉大学毕业证(UCB毕业证书)																			成绩单原版一比一
定制英国白金汉大学毕业证(UCB毕业证书) 成绩单原版一比一
 
Schema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfSchema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdf
 
B2 Creative Industry Response Evaluation.docx
B2 Creative Industry Response Evaluation.docxB2 Creative Industry Response Evaluation.docx
B2 Creative Industry Response Evaluation.docx
 
Predicting Employee Churn: A Data-Driven Approach Project Presentation
Predicting Employee Churn: A Data-Driven Approach Project PresentationPredicting Employee Churn: A Data-Driven Approach Project Presentation
Predicting Employee Churn: A Data-Driven Approach Project Presentation
 
VIP High Class Call Girls Bikaner Anushka 8250192130 Independent Escort Servi...
VIP High Class Call Girls Bikaner Anushka 8250192130 Independent Escort Servi...VIP High Class Call Girls Bikaner Anushka 8250192130 Independent Escort Servi...
VIP High Class Call Girls Bikaner Anushka 8250192130 Independent Escort Servi...
 
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call
꧁❤ Greater Noida Call Girls Delhi ❤꧂ 9711199171 ☎️ Hard And Sexy Vip Call
 
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls CP 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
 
Digi Khata Problem along complete plan.pptx
Digi Khata Problem along complete plan.pptxDigi Khata Problem along complete plan.pptx
Digi Khata Problem along complete plan.pptx
 
From idea to production in a day – Leveraging Azure ML and Streamlit to build...
From idea to production in a day – Leveraging Azure ML and Streamlit to build...From idea to production in a day – Leveraging Azure ML and Streamlit to build...
From idea to production in a day – Leveraging Azure ML and Streamlit to build...
 
High Class Call Girls Noida Sector 39 Aarushi 🔝8264348440🔝 Independent Escort...
High Class Call Girls Noida Sector 39 Aarushi 🔝8264348440🔝 Independent Escort...High Class Call Girls Noida Sector 39 Aarushi 🔝8264348440🔝 Independent Escort...
High Class Call Girls Noida Sector 39 Aarushi 🔝8264348440🔝 Independent Escort...
 
Call Girls In Mahipalpur O9654467111 Escorts Service
Call Girls In Mahipalpur O9654467111  Escorts ServiceCall Girls In Mahipalpur O9654467111  Escorts Service
Call Girls In Mahipalpur O9654467111 Escorts Service
 
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service
(PARI) Call Girls Wanowrie ( 7001035870 ) HI-Fi Pune Escorts Service
 
Delhi 99530 vip 56974 Genuine Escort Service Call Girls in Kishangarh
Delhi 99530 vip 56974 Genuine Escort Service Call Girls in  KishangarhDelhi 99530 vip 56974 Genuine Escort Service Call Girls in  Kishangarh
Delhi 99530 vip 56974 Genuine Escort Service Call Girls in Kishangarh
 
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
代办国外大学文凭《原版美国UCLA文凭证书》加州大学洛杉矶分校毕业证制作成绩单修改
 
Kantar AI Summit- Under Embargo till Wednesday, 24th April 2024, 4 PM, IST.pdf
Kantar AI Summit- Under Embargo till Wednesday, 24th April 2024, 4 PM, IST.pdfKantar AI Summit- Under Embargo till Wednesday, 24th April 2024, 4 PM, IST.pdf
Kantar AI Summit- Under Embargo till Wednesday, 24th April 2024, 4 PM, IST.pdf
 

Mark blum ubc tool box execution - powerpoint presentation

  • 1. BIG Structural Engineering Corporation The "BIG" engineering project Bigger is better, because it reflects our profit motives“ By: Mark Blum University of British Columbia Project Management PM TOOL KIT ASSIGNMENT: Course IL821W14A
  • 2. Executive Summary & Background This presentation is with regards to, the current budget and schedule overruns in, “The BIG Engineering project” utilizing Earned Value Analysis. Earned Value Analysis (EVA); has been used by the U.S. Defence Department since the 1960s and they have found it to be an accurate forecasting tool. Their statistical analysis has shown that once a project is 10% complete, the overrun at completion will not be less than the current overrun. They also found that once a project is 20% complete, the (CPI) Cost Performance Index does not vary from its current value by more than 10%*. * QUOTE: UBC Project Management Course Manual This project is currently over budget regarding it’s, C.P.I and other key indicators. - Something needs to be done to change this course …
  • 3. Section I This project is behind schedule and over budget as of the end of 1Q10. The project is 25% complete, this means we need to achieve overall savings during the remaining 75% of the project. -How do we do this? This meeting is to review options Actual and projected cost comparisons @ 24%completion of Project V.A.C (Current "Variance at completion" - $168,618.40 A.C (Actual cost to date) 629522 (Schedual Variance) -Over budget. - 248660 E.A.C (Estimated Cost @ completion) 1988478.4 AC (Actual cost to date) SV (Schedual Variance) -Over budget. EAC (Estimated Cost @ completion) VAC (Current "Varance at completion"
  • 4. Making Sense of Dollars and Cents $0.00 $100,000.00 $200,000.00 $300,000.00 $400,000.00 $500,000.00 $600,000.00 $700,000.00 $800,000.00 $900,000.00 PlannedValue-PV(BCWS) EarnedValue-EV(BCWP) AC(ACWP) Series1 Column #1 Planned Value PV (BCWS) Cumulative, budgeted cost of work scheduled (How much money we budgeted) which is: $824,800.00 Column #2 Earned Value - EV (BCWP ) Cumulative budgeted cost of work performed or Earned Value. (This is what is paid for and completed). which is: $576,140.00 Column #3 Actual Cost (ACWP) Cumulative actual cost of work performed or (What we paid for so far) which is $629,522.00
  • 5. Current Project Status I have conducted an analysis of the projects progress to date, to determine the reason, costs and the schedule are exceeding expectations and underperforming. 1. The Schedule Performance Index is 0.7, and there is a cost Variance of 0.92. ( anything less than 1 is over budget) 2. The schedule variance is $248, 660.00 Dollars over budgeted allocations. 3. The cost Variance is $53,382.00 Dollars over budgeted allocations. WHY ?
  • 6. Earned Value Analysis tracks money expended compares it to budgeted allocations for actual performance. E.V.A. is a very good way to monitor progress; - and to be proactive. When resource allocations have not been fulfilled, as planned or budgeted for: • This unfulfilled work, causes budgetary deficiencies and cost overruns. • In this project, the categories of Design / Planning / Control and Scope are not in compliance with the plan. • In this project “TASKS” are showing very low resource utilization compliance, with planned results and particularly scheduled results pointing towards exceeding both the scheduled and budget projections. • When “Planned value” and “Actual cost” are not equal, this creates budgeted cost overruns. • This is due to non performance as per my analysis caused by the under performance of resources. • In a domino effect; This affects both earned value, and critical schedules to complete the project. • You can see from the Ms. Project budget cost over runs are due largely do to scheduling issues, or in simpler terms; -Work is not being performed as schedule by resources.
  • 7. Summary of Calculations Note: *These values have been rounded off. Earned Value Calculations* PV = Planned Value $825,000 AC = Actual Cost to date $630,000 EV = Earned Value – What is completed $576,000 SV = Schedule Variance ($249,000) CV = Cost Variance ($53,000) SPI = Schedule Performance Index .70 CPI = Cost Performance Index .92 EAC = Estimate at completion $2,000,000 VAC = Variance at completion ($169,000) BAC = Budget at completion $1,819,000 ETC = Estimate at completion $1,676,000
  • 8. Section II Specific Solutions What is the essence of the issue? It appears we have an issue with resource non-performance causing budget overruns. Delays in getting work (tasks), done on time as scheduled, are going to result cost increases given current projections, if corrective action is not taken as soon as possible. Resources not availing themselves to the project, are therefore causing delays and increased costs. How do we rectify this problem? It is critical that all departments : implement the resources necessary for the project tasks suffering from non conformity in order to succeed according to our plan, to bring the project back on track, so that we can achieve project completion both; On Time & On Budget.
  • 9. Specific Solutions How should we proceed proactively / concretely and prevent the projected cost over runs? After this meeting, I will supply a list of resources that are under performing to each department by email. 1. I will be sending an excel spread sheet by email after this meeting to each affected senior manager explaining these areas are under performing. The yellow highlighted areas are an itemized list for each task/resource that is non conforming. 1. You can forward this to each of the affected department managers, and determine the reason for non performance, and how this can be overcome and to allocate the specified non-performing resources on a priority bases. 2. This list will enable you to address the problems with resources that are causing these budgetary overruns due to non performance, so that we can bring the project back on track. What are the costs of these recommendations ? These recommendations will not change the projects scope, but rather bring the budgets and time schedule back in line with the allocations. It is critical that the change control committee approve the requirement that resources be allocated without further delay to bring the project back on track with the allocated budgets and expedite the performance of all resources towards their fulfillment.
  • 10. Section III Decisions - management needs to make Actions needed I am confident that each department will make the adjustments necessary to allocate resources once I provide this listing and you have seen the listing of non performers. You can now pin point where you need to take action and where are the compliance issues, provide motivation, to either meet or exceed the expectations of our plan in the spirit of true team work. Thank you! Mark Blum © 2014 Mark Blum ALL RIGHTS RESERVED