SlideShare a Scribd company logo
1 of 1
Download to read offline
IMPLEMENTATION OF A CAPITAL PROJECT 
                                           The Office of Capital Planning & Policy (OCPP) is responsible for implementing and monitoring the County’s 
                                           Capital Program and reviewing policy as it pertains to capital construction throughout Cook County.

                         REQUESTING A PROJECT

                           • User Agencies submit requests for Capital Improvements (Projects) to OCPP once a year during the County budget year 
                           • The requests include an explanation of the need for the project; a scope of work explaining the project in detail; any consultant or other 
                             studies the User Agency commissioned to substantiate the need; copies of violation notices, and a cost estimate. 

                                                                                PROJECT APPROVAL
PROJECT DEVELOPMENT 




                                    The Office of Capital Planning & Policy: 
                                    • Reviews the request, confirms the scope of work and estimate and develops a budget for the project. 
                                    • Prioritizes the project, adds it to a 5‐year plan and submits the Capital plan to the Board for approval. 
                                    • Assigns a Project Director to the project who manages the project from beginning to end. 


                         THE PROJECT DIRECTOR                                                      FACILITIES MANAGEMENT (FM) & USER AGENCIES

                           The OCPP Project Director                                                 FM & the User Agency assign “Point People” to: 
                           • Develops the project / refines the scope of work                        • Maintain coordination and information flow within their 
                           • Administers the Contract/s                                                organization for the project 
                           • Manages and administers the approved budget and                         • Participate in various phases to provide information and 
                             schedule                                                                  input for design of the project 



                                    SELECTING A CONSULTANT

                                   • OCPP prepares a Request for a Proposal (RFP) for Consultants (Architects, Engineers, other specialists). 
                                   • Proposals are reviewed by OCPP, a Consultant is selected for the project, and an agreement is compiled. 
                                   • The County’s Agreement with the Consultant is placed on the Board Agenda for award and execution. 



                           WORKING WITH THE CONSULTANT                                          DESIGN

                           • Under the supervision of OCPP the Consultant designs the          • PROGRAM PHASE: Consultant gathers information and confirms the
                             project and prepares the Contract Documents.                        intent and scope of the work
                           • OCPP, Facilities Mgmnt. and the User Agency review the            • SCHEMATIC PHASE: Consultant prepares a preliminary design
                             documents with the Consultant at set milestones.                    concept
                           • FM and the User Agency sign off on all phases before              • DESIGN PHASE: Consultant prepares detailed design drawings and
                             OCPP gives the Consultant permission to continue to the             begins construction specifications
                             next phase.                                                       • CONTRACT DOCUMENTS: Consultant prepares the Bid Documents
 DESIGN & CONSTRUCTION




                                                                                         THE BID PHASE

                                       • The Project is placed on the Board Agenda for permission to Advertise for Bid for Construction  
                                       • The Project is Advertised and available for pick up for a minimum of 15 business days 
                                       • There is a mandatory Pre‐Bid Meeting and Site Inspection with the Bidders 
                                       • Bidders have between 12 and 30 days or more, depending on the scope of work, to prepare a Bid 
                                       • The  Lowest  Responsive  Bidder  is  Awarded  the  Contract  for  Work which  is  placed  on  the  Board  Agenda  for


                         PERMITTING & CONSTRUCTION

                          • The General Contractor applies for and obtains a permit for construction. Depending on the size and scope of the work, this can take 
                            from 30 days to 90 days or more. 
                          • The  Construction  begins  after  OCPP  receives  a  copy  of the  permit and  issues  a  ‘Notice  to  Proceed with Construction’ to the General 
                            Contractor. The Consultant performs construction observation to assure the Work is being performed per specifications. 
                          • During Construction the point person for the User Agency and Facilities Management participates in scheduled progress meetings to 
                            keep appraised of the project, address concerns, and maintain coordination and communication. 
                          • When Construction is complete a walk‐through is performed to assure that all work has been properly executed. 

                                                    ARROWS INDICATE CHRONOLOGICAL ORDER OF ACTIVITIES. PROCESSES ARE SUBJECT TO REVISION

More Related Content

What's hot

Construction Management Services
Construction Management ServicesConstruction Management Services
Construction Management ServicesDavid Rosacker
 
Construction Phase Mgmt Srvcs (2)
Construction Phase Mgmt Srvcs (2)Construction Phase Mgmt Srvcs (2)
Construction Phase Mgmt Srvcs (2)Lee Maserian R.D.I.
 
Project management in construction
Project management in constructionProject management in construction
Project management in constructionNAVNEET KUMAR JHA
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Managementjohnkirth1898
 
Project Management Project 1
Project Management Project 1Project Management Project 1
Project Management Project 1Ho Yen Liang
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycleVaibhav Sutar
 
Rev207 matrixexcelfile
Rev207 matrixexcelfileRev207 matrixexcelfile
Rev207 matrixexcelfilejbonvier
 
Project Management
Project ManagementProject Management
Project ManagementDr K M SONI
 
Lecture slides4; Construction Project Planning
Lecture slides4; Construction Project PlanningLecture slides4; Construction Project Planning
Lecture slides4; Construction Project PlanningJB Nartey
 
ENGINEERING PROJECTS 1
ENGINEERING PROJECTS 1ENGINEERING PROJECTS 1
ENGINEERING PROJECTS 1uche ibekwe
 
Project Work Breakdown Structure
Project Work Breakdown StructureProject Work Breakdown Structure
Project Work Breakdown StructureDemand Metric
 
Project Schedule Template
Project Schedule TemplateProject Schedule Template
Project Schedule TemplateDemand Metric
 
Malaysian Property Development
Malaysian Property DevelopmentMalaysian Property Development
Malaysian Property DevelopmentDebbie Loh
 
Role of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction ProjectRole of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction ProjectIOSR Journals
 
Mobile App Development Company
Mobile App Development CompanyMobile App Development Company
Mobile App Development CompanyQuytech
 
Site engineer duties
Site engineer dutiesSite engineer duties
Site engineer dutiesgetmar2
 

What's hot (20)

Construction Management Services
Construction Management ServicesConstruction Management Services
Construction Management Services
 
Construction Phase Mgmt Srvcs (2)
Construction Phase Mgmt Srvcs (2)Construction Phase Mgmt Srvcs (2)
Construction Phase Mgmt Srvcs (2)
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Project Charter
Project CharterProject Charter
Project Charter
 
RIBA plan of work
RIBA plan of workRIBA plan of work
RIBA plan of work
 
Project Management Project 1
Project Management Project 1Project Management Project 1
Project Management Project 1
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycle
 
Rev207 matrixexcelfile
Rev207 matrixexcelfileRev207 matrixexcelfile
Rev207 matrixexcelfile
 
Project Management
Project ManagementProject Management
Project Management
 
Lecture slides4; Construction Project Planning
Lecture slides4; Construction Project PlanningLecture slides4; Construction Project Planning
Lecture slides4; Construction Project Planning
 
ENGINEERING PROJECTS 1
ENGINEERING PROJECTS 1ENGINEERING PROJECTS 1
ENGINEERING PROJECTS 1
 
ICI & ITD
ICI & ITD ICI & ITD
ICI & ITD
 
Project Work Breakdown Structure
Project Work Breakdown StructureProject Work Breakdown Structure
Project Work Breakdown Structure
 
Project Schedule Template
Project Schedule TemplateProject Schedule Template
Project Schedule Template
 
Malaysian Property Development
Malaysian Property DevelopmentMalaysian Property Development
Malaysian Property Development
 
Role of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction ProjectRole of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction Project
 
Mobile App Development Company
Mobile App Development CompanyMobile App Development Company
Mobile App Development Company
 
012 bussiness planning process
012 bussiness planning process012 bussiness planning process
012 bussiness planning process
 
Site engineer duties
Site engineer dutiesSite engineer duties
Site engineer duties
 

Viewers also liked

Dave Kellogg Keynote at Host Analytics World 2013
Dave Kellogg Keynote at Host Analytics World 2013Dave Kellogg Keynote at Host Analytics World 2013
Dave Kellogg Keynote at Host Analytics World 2013Dave Kellogg
 
Infer and LeanData - Host Analytics Customer Case Study
Infer and LeanData -  Host Analytics Customer Case StudyInfer and LeanData -  Host Analytics Customer Case Study
Infer and LeanData - Host Analytics Customer Case StudyInfer
 
Planning the Shift to Office 365 - How to Get Started with Cloud Collaboratio...
Planning the Shift to Office 365 - How to Get Started with Cloud Collaboratio...Planning the Shift to Office 365 - How to Get Started with Cloud Collaboratio...
Planning the Shift to Office 365 - How to Get Started with Cloud Collaboratio...BDO IT Solutions
 
Using Dashboards & Analytics to Find Hidden Gems in Your Data
Using Dashboards & Analytics to Find Hidden Gems in Your DataUsing Dashboards & Analytics to Find Hidden Gems in Your Data
Using Dashboards & Analytics to Find Hidden Gems in Your DataAdaptive Insights
 
Demystifying Cost and Implementation Challenges with Adaptive Insights
Demystifying Cost and Implementation Challenges with Adaptive InsightsDemystifying Cost and Implementation Challenges with Adaptive Insights
Demystifying Cost and Implementation Challenges with Adaptive InsightsAdaptive Insights
 
Host Analytics Overview
Host Analytics OverviewHost Analytics Overview
Host Analytics OverviewMatt Foster
 
What Makes Great Infographics
What Makes Great InfographicsWhat Makes Great Infographics
What Makes Great InfographicsSlideShare
 
Masters of SlideShare
Masters of SlideShareMasters of SlideShare
Masters of SlideShareKapost
 
STOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
STOP! VIEW THIS! 10-Step Checklist When Uploading to SlideshareSTOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
STOP! VIEW THIS! 10-Step Checklist When Uploading to SlideshareEmpowered Presentations
 
10 Ways to Win at SlideShare SEO & Presentation Optimization
10 Ways to Win at SlideShare SEO & Presentation Optimization10 Ways to Win at SlideShare SEO & Presentation Optimization
10 Ways to Win at SlideShare SEO & Presentation OptimizationOneupweb
 
How To Get More From SlideShare - Super-Simple Tips For Content Marketing
How To Get More From SlideShare - Super-Simple Tips For Content MarketingHow To Get More From SlideShare - Super-Simple Tips For Content Marketing
How To Get More From SlideShare - Super-Simple Tips For Content MarketingContent Marketing Institute
 
How to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksHow to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksSlideShare
 

Viewers also liked (13)

Dave Kellogg Keynote at Host Analytics World 2013
Dave Kellogg Keynote at Host Analytics World 2013Dave Kellogg Keynote at Host Analytics World 2013
Dave Kellogg Keynote at Host Analytics World 2013
 
Infer and LeanData - Host Analytics Customer Case Study
Infer and LeanData -  Host Analytics Customer Case StudyInfer and LeanData -  Host Analytics Customer Case Study
Infer and LeanData - Host Analytics Customer Case Study
 
Planning the Shift to Office 365 - How to Get Started with Cloud Collaboratio...
Planning the Shift to Office 365 - How to Get Started with Cloud Collaboratio...Planning the Shift to Office 365 - How to Get Started with Cloud Collaboratio...
Planning the Shift to Office 365 - How to Get Started with Cloud Collaboratio...
 
Using Dashboards & Analytics to Find Hidden Gems in Your Data
Using Dashboards & Analytics to Find Hidden Gems in Your DataUsing Dashboards & Analytics to Find Hidden Gems in Your Data
Using Dashboards & Analytics to Find Hidden Gems in Your Data
 
Demystifying Cost and Implementation Challenges with Adaptive Insights
Demystifying Cost and Implementation Challenges with Adaptive InsightsDemystifying Cost and Implementation Challenges with Adaptive Insights
Demystifying Cost and Implementation Challenges with Adaptive Insights
 
Host Analytics Overview
Host Analytics OverviewHost Analytics Overview
Host Analytics Overview
 
What Makes Great Infographics
What Makes Great InfographicsWhat Makes Great Infographics
What Makes Great Infographics
 
Masters of SlideShare
Masters of SlideShareMasters of SlideShare
Masters of SlideShare
 
STOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
STOP! VIEW THIS! 10-Step Checklist When Uploading to SlideshareSTOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
STOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
 
You Suck At PowerPoint!
You Suck At PowerPoint!You Suck At PowerPoint!
You Suck At PowerPoint!
 
10 Ways to Win at SlideShare SEO & Presentation Optimization
10 Ways to Win at SlideShare SEO & Presentation Optimization10 Ways to Win at SlideShare SEO & Presentation Optimization
10 Ways to Win at SlideShare SEO & Presentation Optimization
 
How To Get More From SlideShare - Super-Simple Tips For Content Marketing
How To Get More From SlideShare - Super-Simple Tips For Content MarketingHow To Get More From SlideShare - Super-Simple Tips For Content Marketing
How To Get More From SlideShare - Super-Simple Tips For Content Marketing
 
How to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksHow to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & Tricks
 

Similar to Process capital project

Comfori red-sop seminar-ppt brochure-091012
Comfori red-sop seminar-ppt brochure-091012Comfori red-sop seminar-ppt brochure-091012
Comfori red-sop seminar-ppt brochure-091012REDceo.net
 
FMA - 2_CM651_Group.pptx
FMA - 2_CM651_Group.pptxFMA - 2_CM651_Group.pptx
FMA - 2_CM651_Group.pptxArJayTambaoan
 
CV Planning Manager (Sundeep Khare)
CV Planning Manager (Sundeep Khare)CV Planning Manager (Sundeep Khare)
CV Planning Manager (Sundeep Khare)sundeep khare
 
Guc arct 702 legislations lecture 4 - project delivery process and business...
Guc arct 702 legislations   lecture 4 - project delivery process and business...Guc arct 702 legislations   lecture 4 - project delivery process and business...
Guc arct 702 legislations lecture 4 - project delivery process and business...Galala University
 
Construction Stages and Construction Teams
Construction Stages and Construction TeamsConstruction Stages and Construction Teams
Construction Stages and Construction TeamsMOHDFIRRDHAUSBINMOHD
 
Updated Architecture Portfolio 2020
Updated Architecture Portfolio 2020Updated Architecture Portfolio 2020
Updated Architecture Portfolio 2020MTAF
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUPKeshav Seewraz
 
Project Phase, Project Teams & Construction Phase.pdf
Project Phase, Project Teams & Construction Phase.pdfProject Phase, Project Teams & Construction Phase.pdf
Project Phase, Project Teams & Construction Phase.pdfMOHDFIRRDHAUSBINMOHD
 
EPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group
 
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group
 
Resume for Dhanalakshmi ttt
Resume for Dhanalakshmi  tttResume for Dhanalakshmi  ttt
Resume for Dhanalakshmi tttDhana Lakshmi
 
1.Project Management in construction Industry
1.Project Management in construction Industry1.Project Management in construction Industry
1.Project Management in construction IndustryRohitKulkarni528981
 
Presentation on manual PSDP in Pakistan.pptx
Presentation on manual PSDP in Pakistan.pptxPresentation on manual PSDP in Pakistan.pptx
Presentation on manual PSDP in Pakistan.pptxAbdulrahmanAfabafal
 
Resume for Dhanalakshmi ttt
Resume for Dhanalakshmi  tttResume for Dhanalakshmi  ttt
Resume for Dhanalakshmi tttDhana Lakshmi
 

Similar to Process capital project (20)

Comfori red-sop seminar-ppt brochure-091012
Comfori red-sop seminar-ppt brochure-091012Comfori red-sop seminar-ppt brochure-091012
Comfori red-sop seminar-ppt brochure-091012
 
FMA - 2_CM651_Group.pptx
FMA - 2_CM651_Group.pptxFMA - 2_CM651_Group.pptx
FMA - 2_CM651_Group.pptx
 
Project management
Project managementProject management
Project management
 
CV Planning Manager (Sundeep Khare)
CV Planning Manager (Sundeep Khare)CV Planning Manager (Sundeep Khare)
CV Planning Manager (Sundeep Khare)
 
Guc arct 702 legislations lecture 4 - project delivery process and business...
Guc arct 702 legislations   lecture 4 - project delivery process and business...Guc arct 702 legislations   lecture 4 - project delivery process and business...
Guc arct 702 legislations lecture 4 - project delivery process and business...
 
Construction Stages and Construction Teams
Construction Stages and Construction TeamsConstruction Stages and Construction Teams
Construction Stages and Construction Teams
 
Updated Architecture Portfolio 2020
Updated Architecture Portfolio 2020Updated Architecture Portfolio 2020
Updated Architecture Portfolio 2020
 
resume-.PDF (2)
resume-.PDF (2)resume-.PDF (2)
resume-.PDF (2)
 
Bussiness planning process
Bussiness planning processBussiness planning process
Bussiness planning process
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUP
 
Project Phase, Project Teams & Construction Phase.pdf
Project Phase, Project Teams & Construction Phase.pdfProject Phase, Project Teams & Construction Phase.pdf
Project Phase, Project Teams & Construction Phase.pdf
 
T349
T349T349
T349
 
T349 Pi Web
T349 Pi WebT349 Pi Web
T349 Pi Web
 
EPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s Methodology
 
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
 
Resume for Dhanalakshmi ttt
Resume for Dhanalakshmi  tttResume for Dhanalakshmi  ttt
Resume for Dhanalakshmi ttt
 
1.Project Management in construction Industry
1.Project Management in construction Industry1.Project Management in construction Industry
1.Project Management in construction Industry
 
Presentation on manual PSDP in Pakistan.pptx
Presentation on manual PSDP in Pakistan.pptxPresentation on manual PSDP in Pakistan.pptx
Presentation on manual PSDP in Pakistan.pptx
 
SANPPT
SANPPTSANPPT
SANPPT
 
Resume for Dhanalakshmi ttt
Resume for Dhanalakshmi  tttResume for Dhanalakshmi  ttt
Resume for Dhanalakshmi ttt
 

More from cookcountyblog

Cook County Annual Report 2013
Cook County Annual Report 2013Cook County Annual Report 2013
Cook County Annual Report 2013cookcountyblog
 
Final Amendments to the Cook County Executive Budget Recommendation
Final Amendments to the Cook County Executive Budget RecommendationFinal Amendments to the Cook County Executive Budget Recommendation
Final Amendments to the Cook County Executive Budget Recommendationcookcountyblog
 
Tentative Amendments to the 2014 Executive Budget Recommendation
Tentative Amendments to the 2014 Executive Budget RecommendationTentative Amendments to the 2014 Executive Budget Recommendation
Tentative Amendments to the 2014 Executive Budget Recommendationcookcountyblog
 
2013 q2 star report final
2013 q2 star report   final2013 q2 star report   final
2013 q2 star report finalcookcountyblog
 
Fy2014 preliminary budget report (web)
Fy2014 preliminary budget report (web)Fy2014 preliminary budget report (web)
Fy2014 preliminary budget report (web)cookcountyblog
 
Full Report of the Cook County Sustainability Council, 060513
Full Report of the Cook County Sustainability Council, 060513Full Report of the Cook County Sustainability Council, 060513
Full Report of the Cook County Sustainability Council, 060513cookcountyblog
 
Executive Summary of Cook County Sustainability Advisory Report, 060513
Executive Summary of Cook County Sustainability Advisory Report, 060513Executive Summary of Cook County Sustainability Advisory Report, 060513
Executive Summary of Cook County Sustainability Advisory Report, 060513cookcountyblog
 
Uploading datasets to data site
Uploading datasets to data siteUploading datasets to data site
Uploading datasets to data sitecookcountyblog
 
2013 Rabies Vaccination and Microchip Clinic Calendar
2013 Rabies Vaccination and Microchip Clinic Calendar2013 Rabies Vaccination and Microchip Clinic Calendar
2013 Rabies Vaccination and Microchip Clinic Calendarcookcountyblog
 
Approved Amendments to the FY 2013 Cook County Budget
Approved Amendments to the FY 2013 Cook County BudgetApproved Amendments to the FY 2013 Cook County Budget
Approved Amendments to the FY 2013 Cook County Budgetcookcountyblog
 
2013 Cook County Suburban Warming Centers
2013 Cook County Suburban Warming Centers2013 Cook County Suburban Warming Centers
2013 Cook County Suburban Warming Centerscookcountyblog
 
2012 Cook County Government Midterm Report
2012 Cook County Government Midterm Report2012 Cook County Government Midterm Report
2012 Cook County Government Midterm Reportcookcountyblog
 
Cook County Government Budget Fy2013 Tentative Amendments
Cook County Government Budget Fy2013 Tentative AmendmentsCook County Government Budget Fy2013 Tentative Amendments
Cook County Government Budget Fy2013 Tentative Amendmentscookcountyblog
 
2013 Executive Budget Recommendation Briefing
2013 Executive Budget Recommendation Briefing2013 Executive Budget Recommendation Briefing
2013 Executive Budget Recommendation Briefingcookcountyblog
 

More from cookcountyblog (20)

Cook County Annual Report 2013
Cook County Annual Report 2013Cook County Annual Report 2013
Cook County Annual Report 2013
 
Final Amendments to the Cook County Executive Budget Recommendation
Final Amendments to the Cook County Executive Budget RecommendationFinal Amendments to the Cook County Executive Budget Recommendation
Final Amendments to the Cook County Executive Budget Recommendation
 
Tentative Amendments to the 2014 Executive Budget Recommendation
Tentative Amendments to the 2014 Executive Budget RecommendationTentative Amendments to the 2014 Executive Budget Recommendation
Tentative Amendments to the 2014 Executive Budget Recommendation
 
2013 q2 star report final
2013 q2 star report   final2013 q2 star report   final
2013 q2 star report final
 
Fy2014 preliminary budget report (web)
Fy2014 preliminary budget report (web)Fy2014 preliminary budget report (web)
Fy2014 preliminary budget report (web)
 
Full Report of the Cook County Sustainability Council, 060513
Full Report of the Cook County Sustainability Council, 060513Full Report of the Cook County Sustainability Council, 060513
Full Report of the Cook County Sustainability Council, 060513
 
Executive Summary of Cook County Sustainability Advisory Report, 060513
Executive Summary of Cook County Sustainability Advisory Report, 060513Executive Summary of Cook County Sustainability Advisory Report, 060513
Executive Summary of Cook County Sustainability Advisory Report, 060513
 
Uploading datasets to data site
Uploading datasets to data siteUploading datasets to data site
Uploading datasets to data site
 
2013 Rabies Vaccination and Microchip Clinic Calendar
2013 Rabies Vaccination and Microchip Clinic Calendar2013 Rabies Vaccination and Microchip Clinic Calendar
2013 Rabies Vaccination and Microchip Clinic Calendar
 
Finalpfp exec summary
Finalpfp exec summaryFinalpfp exec summary
Finalpfp exec summary
 
Finalpfp report
Finalpfp reportFinalpfp report
Finalpfp report
 
Approved Amendments to the FY 2013 Cook County Budget
Approved Amendments to the FY 2013 Cook County BudgetApproved Amendments to the FY 2013 Cook County Budget
Approved Amendments to the FY 2013 Cook County Budget
 
2013 Cook County Suburban Warming Centers
2013 Cook County Suburban Warming Centers2013 Cook County Suburban Warming Centers
2013 Cook County Suburban Warming Centers
 
DHSEM CCR 121012
DHSEM CCR 121012DHSEM CCR 121012
DHSEM CCR 121012
 
2012 Cook County Government Midterm Report
2012 Cook County Government Midterm Report2012 Cook County Government Midterm Report
2012 Cook County Government Midterm Report
 
Execsumrev
ExecsumrevExecsumrev
Execsumrev
 
Cook County Government Budget Fy2013 Tentative Amendments
Cook County Government Budget Fy2013 Tentative AmendmentsCook County Government Budget Fy2013 Tentative Amendments
Cook County Government Budget Fy2013 Tentative Amendments
 
2013 Executive Budget Recommendation Briefing
2013 Executive Budget Recommendation Briefing2013 Executive Budget Recommendation Briefing
2013 Executive Budget Recommendation Briefing
 
Public Meeting Notice
Public Meeting NoticePublic Meeting Notice
Public Meeting Notice
 
Public Hearing Notice
Public Hearing NoticePublic Hearing Notice
Public Hearing Notice
 

Recently uploaded

Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfAmzadHosen3
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756dollysharma2066
 

Recently uploaded (20)

Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdf
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 

Process capital project

  • 1. IMPLEMENTATION OF A CAPITAL PROJECT  The Office of Capital Planning & Policy (OCPP) is responsible for implementing and monitoring the County’s  Capital Program and reviewing policy as it pertains to capital construction throughout Cook County. REQUESTING A PROJECT • User Agencies submit requests for Capital Improvements (Projects) to OCPP once a year during the County budget year  • The requests include an explanation of the need for the project; a scope of work explaining the project in detail; any consultant or other  studies the User Agency commissioned to substantiate the need; copies of violation notices, and a cost estimate.  PROJECT APPROVAL PROJECT DEVELOPMENT  The Office of Capital Planning & Policy:  • Reviews the request, confirms the scope of work and estimate and develops a budget for the project.  • Prioritizes the project, adds it to a 5‐year plan and submits the Capital plan to the Board for approval.  • Assigns a Project Director to the project who manages the project from beginning to end.  THE PROJECT DIRECTOR FACILITIES MANAGEMENT (FM) & USER AGENCIES The OCPP Project Director  FM & the User Agency assign “Point People” to:  • Develops the project / refines the scope of work  • Maintain coordination and information flow within their  • Administers the Contract/s  organization for the project  • Manages and administers the approved budget and  • Participate in various phases to provide information and  schedule  input for design of the project  SELECTING A CONSULTANT • OCPP prepares a Request for a Proposal (RFP) for Consultants (Architects, Engineers, other specialists).  • Proposals are reviewed by OCPP, a Consultant is selected for the project, and an agreement is compiled.  • The County’s Agreement with the Consultant is placed on the Board Agenda for award and execution.  WORKING WITH THE CONSULTANT DESIGN • Under the supervision of OCPP the Consultant designs the  • PROGRAM PHASE: Consultant gathers information and confirms the project and prepares the Contract Documents.  intent and scope of the work • OCPP, Facilities Mgmnt. and the User Agency review the  • SCHEMATIC PHASE: Consultant prepares a preliminary design documents with the Consultant at set milestones.  concept • FM and the User Agency sign off on all phases before  • DESIGN PHASE: Consultant prepares detailed design drawings and OCPP gives the Consultant permission to continue to the  begins construction specifications next phase.  • CONTRACT DOCUMENTS: Consultant prepares the Bid Documents DESIGN & CONSTRUCTION THE BID PHASE • The Project is placed on the Board Agenda for permission to Advertise for Bid for Construction   • The Project is Advertised and available for pick up for a minimum of 15 business days  • There is a mandatory Pre‐Bid Meeting and Site Inspection with the Bidders  • Bidders have between 12 and 30 days or more, depending on the scope of work, to prepare a Bid  • The  Lowest  Responsive  Bidder  is  Awarded  the  Contract  for  Work which  is  placed  on  the  Board  Agenda  for PERMITTING & CONSTRUCTION • The General Contractor applies for and obtains a permit for construction. Depending on the size and scope of the work, this can take  from 30 days to 90 days or more.  • The  Construction  begins  after  OCPP  receives  a  copy  of the  permit and  issues  a  ‘Notice  to  Proceed with Construction’ to the General  Contractor. The Consultant performs construction observation to assure the Work is being performed per specifications.  • During Construction the point person for the User Agency and Facilities Management participates in scheduled progress meetings to  keep appraised of the project, address concerns, and maintain coordination and communication.  • When Construction is complete a walk‐through is performed to assure that all work has been properly executed.  ARROWS INDICATE CHRONOLOGICAL ORDER OF ACTIVITIES. PROCESSES ARE SUBJECT TO REVISION