A REVIEW OF
PROCUREMENT STRATEGIES
IN THE BUILDING INDUSTRY
GROUP 8
1
STRATEGIES IN BUILDING PROCUREMENT
 Briefly explain the concept of procurement
 Establish the methods of building procurement
 Highlight the attributes, pros and cons of each strategy
 Briefly compare the strategies
2
IN THIS SLIDE WE INTEND TO:
STRATEGIES IN BUILDING PROCUREMENT
 Procurement describes the merging of activities
undertaken by the client to obtain a building. It is
essentially a series of considered risk that can be
transferred between stakeholders in the building
industry.
3
STRATEGIES IN BUILDING PROCUREMENT
 Traditional procurement method
 Design and build procurement method
 Turnkey procurement method
 Direct labor procurement method
 Public private partnership method
 Management Method
4
BASIC METHODS OF PROCUREMENT
STRATEGIES IN BUILDING PROCUREMENT
 Selection of an absolute optimal procurement method is
difficult, because even the most experienced client or
contractor does not know all the potential benefits or
risks for each method. Procurement is, therefore, a
succession of ‘calculated risks’
5
TRADITIONAL PROCUREMENT METHOD
 Traditional method is one of the most
common strategies of procuring a building.
 The traditional method is sometimes called
Design-Bid-Build (or design/bid/build, and
abbreviated D-B-B or D/B/B accordingly)
(Akram, et al., 2012).
 The client who is also referred to as the
employer consents that the projects design
work is done independently from the
construction work. The design team is
different from the construction team.
 For the design work, consultants are
appointed for the design and cost control
while the contractor carries out the
construction works.
DESIGN BID BUILD
6
TRADITIONAL PROCUREMENT METHOD
CLIENT (EMPLOYER)
ARCHITECT
QUANTITY
SURVEYOR
ENGINEERS
OTHER
CONSULTANTS
CONTRACTOR
NOMINATED
SUBCONTRACTORS
DOMESTIC
SUBCONTRACTORS
NOMINATED
SUPPLIERS
 The contractor’s responsibility extends to all
workmanship and materials including all works by
sub-contractors and suppliers.
 The contractor is usually appointed by competitive
tendering.
 But may if necessary be appointed earlier by
negotiation on the basis of partial or notional
information.
 There are three types of contract under
the traditional procurement method:
 1. Lump sum contracts
 2. Measurement contracts
 3. Cost reimbursement
(Davis, Love, & Baccarini , 2008)
7
SEQUENTIAL PHASES TO THE
TRADITIONAL DELIVERY METHOD
Design Stage
 Schematic design is carried out,
reviewed and approved.
 Concept and preliminary specifications
are further developed.
 Final drawings and specifications are
prepared to form the contract
documents
Bidding (Bid) Stage
 The Owner obtains competitive
bids from a number of qualified
contractors.
 Each contractor obtains a copy of
tender documents which is fully
priced by them or split by sub
components.
 Project is awarded to the lowest
bidder.
Construction Stage
 In this stage, almost every component of the
project is supplied and installed by specialized
subcontractors.
 The contractor is responsible for undertaking
all of the works including provision of all
materials, labour, plant and equipment;
 also controls the sequence and coordination of
works to ensure that construction is
undertaken in an ordered and logical way.
8
ADVANTAGES
9
Easily understood by all
There is accountability
due to a competitive
selection
It is design lead; the
client is has direct
influence and control.
It is a ‘tried and test’
method of procurement
which the market is very
familiar with.
Price certainty at the
award of the contract
Variations (changes) to
the contract are
relatively easy to
arrange and manage.
competitive equity as all
tendering contractors bid
on the same basis
DISADVANTAGES
10
Can be a timely process to
produce the full contract
documentation.
Tenders documents from an
incomplete design can be
produced but can lead to
cost and time uncertainty,
and may lead to disputes.
Overall project duration
may be longer than other
procurement methods.
As the general contractor is
brought to the team post design,
there is little opportunity for
input on effective alternates
being presented.
DESIGN AND BUILD PROCUREMENT
DEFINITION
 DESIGN-BUILD (D-B) - According to the
Design-Build Institute of America (DBIA), the
design-build form of project delivery is a
system of contracting whereby one entity
performs both architectural & engineering
and construction under one single contract.
11
DESIGN AND BUILD PROCUREMENT
ATTRIBUTES OF D-B (NICHOLSON, 2005)
 Dynamic:
 Efficient:
 Single-source:
12
DESIGN AND BUILD PROCUREMENT
CATEGORIES OF DESIGN-BUILD (D-B)
 STIPULATED PRICE: With stipulated price design-build a
public agency specifies how much it will pay for
construction of a particular building
 CONSTRUCTION MANAGEMENT: With construction
management design-build the public agency awards a
contract to a "construction manager"
13
ADVANTAGES
14
Price Certainty
Agency May Avoid
Conflicts and
Disputes
Builder Involved in
Design Process
Faster Project Delivery
Agency Needs Less
Technical Staff
Better
communication
Fewer disputes and
litigation
Higher quality outcomes
Clear roles, responsibilities
and accountability
Less administrative burden
Reduced risk to the client
(because the design–build
entity assumes more)
DISADVANTAGES
15
Limited assurance of
quality control.
Subjective Contract Award
Limited access for small
contractors.
Typical project management
issues (establishing liability,
writing contracts, scoping
estimates and schedule)
Conflict of interest and
ethical issues
Greater business and
financial risks associated with
architect taking on general
contractor responsibilities
TURNKEY PROCUREMENT
DEFINITION
 A turnkey or a turnkey project is a type of
project that is constructed so that it could be
sold to any buyer as a completed product
16
TURNKEY PROCUREMENT
DEFINITION
 It is also described as a contract which a firm
agrees to fully design, construct and equip a
manufacturing, business, service facility and turn
the project over to the purchaser when it is
ready for operation for remuneration.
17
ADVANTAGES
18
The project is usually
owned by the
contractor.
It gives the client
enough time to seek
financing.
There is no room for
inexperienced clients
to make wrong
decisions.
Contractual
relationship with one
person.
Total commitment
from the contractor.
DISADVANTAGES
19
Lack of control by
the client.
Remuneration is
usually high.
Difficult to find
clients.
No intervention by
the client.
TURNKEY PROCUREMENT
SUMMARY
 The project is usually owned by the contractor
until the end of the project.
 Lack of control by the client over design
decisions.
 It takes more time to setup initially.
20
DIRECT LABOUR PROCUREMENT
DEFINITION
 Direct labour is a system that entails the client’s
usage of own resources to realize his projects
(Ogunsanmi et. al; 2003; )
21
CLIENT
TRADESMEN
DIRECT LABOUR PROCUREMENT
ATTTRIBUTE
 It is a method whereby the client design and
produces his project by himself with the aid of
in-house professionals void of the use of
contractors (Kadiri & Odusami, 2003).
22
ADVANTAGES
23
Tax effect, tax
deduction is almost
impossible
Cheaper than the
other procurement
methods
Cost monitoring and
control is easier
compared to other
methods
Greater client
satisfaction
Safety in
construction.
DISADVANTAGES
24
Limited to non-
complex projects
Sub-standard finished
product, where the client
doesn’t have a good
knowledge of
construction.
The client shoulders
the greater risk
PUBLIC PRIVATE PARTNERSHIP (PPP)
PROCUREMENT
DEFINITION
 Is a legally-binding contract between
government and business for the provision of
assets and the delivery of services that allocates
responsibilities and business risks among the
partners.
25
GOVERNMENT
BUSINESS
PPP
PUBLIC PRIVATE PARTNERSHIP (PPP)
PROCUREMENT
ATTRIBUTES
 In a P3s method, the government remains actively
involved throughout the project’s life cycle.
 The private sector is responsible for the more
commercial function such as PROJECT DESIGN,
CONSTRUCTION, FINANCE & OPERATIONS.
 The goal is to combine the best capabilities of both
partners for mutual benefits.
26
PPP are best for large projects
Source: Google Images
PUBLIC PRIVATE PARTNERSHIP (PPP)
PROCUREMENT
CHARACTERISTICS
 Executed between public and private sectors.
 Risk sharing between the parties.
 Long-term relationship between the parties.
 Ultimate regulatory responsibility remains in the public
sector.
 Encompass diverse types of infrastructure.
27
ADVANTAGES
28
Increase in efficiency
of a project’s
delivery, operations
& management.
Availability of additional
resources to meet the
growing need of
investment in the sector.
Reduces public
sector risks.
Makes better use of
assets.
Encourages “Life
cycle” approach to
planning &
budgeting.
DISADVANTAGES
29
The Private sector might not be
interested in a project due to perceived
high risks or may lack technical,
financial or managerial capacity to
implement the project.
A P3s project may be more costly.
MANAGEMENT BID
DEFINITION
 Management procurement has three basic
forms
 Management contracting
 Construction management (similar to
design and build)
 Design and manage
30
MANAGEMENT BID
 The client employs both the design
consultant and a management contractor.
 The Contractor is in charge of ensuring
timely completion of project
31
MANAGEMENT CONTRACTING
Client
Design team
Management
team
Worksmen
MANAGEMENT BID
 The client employs all the consultants, the
project manager, and the tradesmen
directly and goes into contractual
agreement with them directly
32
CONSTRUCTION MANAGEMENT
Client
Design team
Management
team
Worksmen
MANAGEMENT BID
 This is similar to management contracting,
however, in this type the contractor is paid
a fee to assume the responsibility for both
the construction team and design team
33
DESIGN AND MANAGE Client
Management
contractor
+ Design Works
Worksmen
COMPARISM
FACTOR TRADITIONAL DESIGN & BUILD TURNKEY
DIRECT
LABOUR
PPP
MANAGEMENT
BID
SCALE OF
PROJECT
SMALL-
MEDIUM
LARGE
REPEATITIVE
ALL SMALL VERY LARGE MEDIUM-LARGE
RISK CONTRACTOR
CONTRACTING
FIRM
CONTRACTING
FIRM
CLIENT
GOVT AND
PRIVATE BIZ
SHARED
COMPLEXITY - - SPECIALIZED SIMPLE - -
34
STRATEGIES IN BUILDING PROCUREMENT
 Briefly explain the concept of procurement
 Establish the methods of building procurement
 Highlight the attributes, pros and cons of each strategy
 Briefly compare the strategies
35
RECAP: WE HOPE WE HAVE BEEN ABLE TO:
REFERENCES
 Akram, S., Cavallini, C., Dizdar, A., Mukherjee, A., Kluczuk, P., Kujawa, Z., . . . Zaręba, K. (2012).
Manual “Procurement Strategy In Construction”. Europe: Lifelong Learning Programme.
 Davis, P., Love, P., & Baccarini , D. (2008). Building Procurement Methods. Bribane Qld 4001:
Cooperative Research Centre For Construction Innovation.
36
THANK YOU`
37

Strategies in building procurement (summarized)

  • 1.
    A REVIEW OF PROCUREMENTSTRATEGIES IN THE BUILDING INDUSTRY GROUP 8 1
  • 2.
    STRATEGIES IN BUILDINGPROCUREMENT  Briefly explain the concept of procurement  Establish the methods of building procurement  Highlight the attributes, pros and cons of each strategy  Briefly compare the strategies 2 IN THIS SLIDE WE INTEND TO:
  • 3.
    STRATEGIES IN BUILDINGPROCUREMENT  Procurement describes the merging of activities undertaken by the client to obtain a building. It is essentially a series of considered risk that can be transferred between stakeholders in the building industry. 3
  • 4.
    STRATEGIES IN BUILDINGPROCUREMENT  Traditional procurement method  Design and build procurement method  Turnkey procurement method  Direct labor procurement method  Public private partnership method  Management Method 4 BASIC METHODS OF PROCUREMENT
  • 5.
    STRATEGIES IN BUILDINGPROCUREMENT  Selection of an absolute optimal procurement method is difficult, because even the most experienced client or contractor does not know all the potential benefits or risks for each method. Procurement is, therefore, a succession of ‘calculated risks’ 5
  • 6.
    TRADITIONAL PROCUREMENT METHOD Traditional method is one of the most common strategies of procuring a building.  The traditional method is sometimes called Design-Bid-Build (or design/bid/build, and abbreviated D-B-B or D/B/B accordingly) (Akram, et al., 2012).  The client who is also referred to as the employer consents that the projects design work is done independently from the construction work. The design team is different from the construction team.  For the design work, consultants are appointed for the design and cost control while the contractor carries out the construction works. DESIGN BID BUILD 6
  • 7.
    TRADITIONAL PROCUREMENT METHOD CLIENT(EMPLOYER) ARCHITECT QUANTITY SURVEYOR ENGINEERS OTHER CONSULTANTS CONTRACTOR NOMINATED SUBCONTRACTORS DOMESTIC SUBCONTRACTORS NOMINATED SUPPLIERS  The contractor’s responsibility extends to all workmanship and materials including all works by sub-contractors and suppliers.  The contractor is usually appointed by competitive tendering.  But may if necessary be appointed earlier by negotiation on the basis of partial or notional information.  There are three types of contract under the traditional procurement method:  1. Lump sum contracts  2. Measurement contracts  3. Cost reimbursement (Davis, Love, & Baccarini , 2008) 7
  • 8.
    SEQUENTIAL PHASES TOTHE TRADITIONAL DELIVERY METHOD Design Stage  Schematic design is carried out, reviewed and approved.  Concept and preliminary specifications are further developed.  Final drawings and specifications are prepared to form the contract documents Bidding (Bid) Stage  The Owner obtains competitive bids from a number of qualified contractors.  Each contractor obtains a copy of tender documents which is fully priced by them or split by sub components.  Project is awarded to the lowest bidder. Construction Stage  In this stage, almost every component of the project is supplied and installed by specialized subcontractors.  The contractor is responsible for undertaking all of the works including provision of all materials, labour, plant and equipment;  also controls the sequence and coordination of works to ensure that construction is undertaken in an ordered and logical way. 8
  • 9.
    ADVANTAGES 9 Easily understood byall There is accountability due to a competitive selection It is design lead; the client is has direct influence and control. It is a ‘tried and test’ method of procurement which the market is very familiar with. Price certainty at the award of the contract Variations (changes) to the contract are relatively easy to arrange and manage. competitive equity as all tendering contractors bid on the same basis
  • 10.
    DISADVANTAGES 10 Can be atimely process to produce the full contract documentation. Tenders documents from an incomplete design can be produced but can lead to cost and time uncertainty, and may lead to disputes. Overall project duration may be longer than other procurement methods. As the general contractor is brought to the team post design, there is little opportunity for input on effective alternates being presented.
  • 11.
    DESIGN AND BUILDPROCUREMENT DEFINITION  DESIGN-BUILD (D-B) - According to the Design-Build Institute of America (DBIA), the design-build form of project delivery is a system of contracting whereby one entity performs both architectural & engineering and construction under one single contract. 11
  • 12.
    DESIGN AND BUILDPROCUREMENT ATTRIBUTES OF D-B (NICHOLSON, 2005)  Dynamic:  Efficient:  Single-source: 12
  • 13.
    DESIGN AND BUILDPROCUREMENT CATEGORIES OF DESIGN-BUILD (D-B)  STIPULATED PRICE: With stipulated price design-build a public agency specifies how much it will pay for construction of a particular building  CONSTRUCTION MANAGEMENT: With construction management design-build the public agency awards a contract to a "construction manager" 13
  • 14.
    ADVANTAGES 14 Price Certainty Agency MayAvoid Conflicts and Disputes Builder Involved in Design Process Faster Project Delivery Agency Needs Less Technical Staff Better communication Fewer disputes and litigation Higher quality outcomes Clear roles, responsibilities and accountability Less administrative burden Reduced risk to the client (because the design–build entity assumes more)
  • 15.
    DISADVANTAGES 15 Limited assurance of qualitycontrol. Subjective Contract Award Limited access for small contractors. Typical project management issues (establishing liability, writing contracts, scoping estimates and schedule) Conflict of interest and ethical issues Greater business and financial risks associated with architect taking on general contractor responsibilities
  • 16.
    TURNKEY PROCUREMENT DEFINITION  Aturnkey or a turnkey project is a type of project that is constructed so that it could be sold to any buyer as a completed product 16
  • 17.
    TURNKEY PROCUREMENT DEFINITION  Itis also described as a contract which a firm agrees to fully design, construct and equip a manufacturing, business, service facility and turn the project over to the purchaser when it is ready for operation for remuneration. 17
  • 18.
    ADVANTAGES 18 The project isusually owned by the contractor. It gives the client enough time to seek financing. There is no room for inexperienced clients to make wrong decisions. Contractual relationship with one person. Total commitment from the contractor.
  • 19.
    DISADVANTAGES 19 Lack of controlby the client. Remuneration is usually high. Difficult to find clients. No intervention by the client.
  • 20.
    TURNKEY PROCUREMENT SUMMARY  Theproject is usually owned by the contractor until the end of the project.  Lack of control by the client over design decisions.  It takes more time to setup initially. 20
  • 21.
    DIRECT LABOUR PROCUREMENT DEFINITION Direct labour is a system that entails the client’s usage of own resources to realize his projects (Ogunsanmi et. al; 2003; ) 21 CLIENT TRADESMEN
  • 22.
    DIRECT LABOUR PROCUREMENT ATTTRIBUTE It is a method whereby the client design and produces his project by himself with the aid of in-house professionals void of the use of contractors (Kadiri & Odusami, 2003). 22
  • 23.
    ADVANTAGES 23 Tax effect, tax deductionis almost impossible Cheaper than the other procurement methods Cost monitoring and control is easier compared to other methods Greater client satisfaction Safety in construction.
  • 24.
    DISADVANTAGES 24 Limited to non- complexprojects Sub-standard finished product, where the client doesn’t have a good knowledge of construction. The client shoulders the greater risk
  • 25.
    PUBLIC PRIVATE PARTNERSHIP(PPP) PROCUREMENT DEFINITION  Is a legally-binding contract between government and business for the provision of assets and the delivery of services that allocates responsibilities and business risks among the partners. 25 GOVERNMENT BUSINESS PPP
  • 26.
    PUBLIC PRIVATE PARTNERSHIP(PPP) PROCUREMENT ATTRIBUTES  In a P3s method, the government remains actively involved throughout the project’s life cycle.  The private sector is responsible for the more commercial function such as PROJECT DESIGN, CONSTRUCTION, FINANCE & OPERATIONS.  The goal is to combine the best capabilities of both partners for mutual benefits. 26 PPP are best for large projects Source: Google Images
  • 27.
    PUBLIC PRIVATE PARTNERSHIP(PPP) PROCUREMENT CHARACTERISTICS  Executed between public and private sectors.  Risk sharing between the parties.  Long-term relationship between the parties.  Ultimate regulatory responsibility remains in the public sector.  Encompass diverse types of infrastructure. 27
  • 28.
    ADVANTAGES 28 Increase in efficiency ofa project’s delivery, operations & management. Availability of additional resources to meet the growing need of investment in the sector. Reduces public sector risks. Makes better use of assets. Encourages “Life cycle” approach to planning & budgeting.
  • 29.
    DISADVANTAGES 29 The Private sectormight not be interested in a project due to perceived high risks or may lack technical, financial or managerial capacity to implement the project. A P3s project may be more costly.
  • 30.
    MANAGEMENT BID DEFINITION  Managementprocurement has three basic forms  Management contracting  Construction management (similar to design and build)  Design and manage 30
  • 31.
    MANAGEMENT BID  Theclient employs both the design consultant and a management contractor.  The Contractor is in charge of ensuring timely completion of project 31 MANAGEMENT CONTRACTING Client Design team Management team Worksmen
  • 32.
    MANAGEMENT BID  Theclient employs all the consultants, the project manager, and the tradesmen directly and goes into contractual agreement with them directly 32 CONSTRUCTION MANAGEMENT Client Design team Management team Worksmen
  • 33.
    MANAGEMENT BID  Thisis similar to management contracting, however, in this type the contractor is paid a fee to assume the responsibility for both the construction team and design team 33 DESIGN AND MANAGE Client Management contractor + Design Works Worksmen
  • 34.
    COMPARISM FACTOR TRADITIONAL DESIGN& BUILD TURNKEY DIRECT LABOUR PPP MANAGEMENT BID SCALE OF PROJECT SMALL- MEDIUM LARGE REPEATITIVE ALL SMALL VERY LARGE MEDIUM-LARGE RISK CONTRACTOR CONTRACTING FIRM CONTRACTING FIRM CLIENT GOVT AND PRIVATE BIZ SHARED COMPLEXITY - - SPECIALIZED SIMPLE - - 34
  • 35.
    STRATEGIES IN BUILDINGPROCUREMENT  Briefly explain the concept of procurement  Establish the methods of building procurement  Highlight the attributes, pros and cons of each strategy  Briefly compare the strategies 35 RECAP: WE HOPE WE HAVE BEEN ABLE TO:
  • 36.
    REFERENCES  Akram, S.,Cavallini, C., Dizdar, A., Mukherjee, A., Kluczuk, P., Kujawa, Z., . . . Zaręba, K. (2012). Manual “Procurement Strategy In Construction”. Europe: Lifelong Learning Programme.  Davis, P., Love, P., & Baccarini , D. (2008). Building Procurement Methods. Bribane Qld 4001: Cooperative Research Centre For Construction Innovation. 36
  • 37.