Running Head: Sample Project Management
Olympic Village
[Name of the Writer]
[Name of the Institution]
Project Management 1
Table of Contents
1.0 INTRODUCTION ............................................................................................3
2.0 WORK BREAKDOWN STRUCTURE .............................................................4
3.0 SCOPE AND SCALE OF THE PROJECT ......................................................5
3.1 Major Milestones .........................................................................................7
3.2 Limitations ...................................................................................................7
4.0 SYSTEMS TO ENSURE PROJECT SUCCESS.............................................7
5.0 IMPORTANCE OF USING COLLABORATION ..............................................8
6.0 ORGANIZATIONAL AND NATIONAL CULTURE ROLE IN PROJECT
SUCCESS ..........................................................................................................10
6.1 Organizational Culture...............................................................................10
6.2 National Culture.........................................................................................12
7.0 POTENTIAL RESOURCE CONFLICTS .......................................................13
8.0 INFORMATION COMMUNICATION TECHNOLOGY...................................15
9.0 PROJECT MANAGEMENT SOFTWARE .....................................................16
10.0 RISK MANAGEMENT.................................................................................17
10.1 Risk Identification.....................................................................................18
10.2 Risk Assessment .....................................................................................19
10.3 Risk control Strategies.............................................................................19
10.4 Risk Communication Plan........................................................................19
11. TOOLS AND METHODS USED IN PROJECT .............................................20
12. RECOMMENDATION ...................................................................................20
13. CONCLUSION..............................................................................................21
EXECUTIVE SUMMARY
The primary purpose of this project is to construct the Olympic Village in East
London to accommodate all the participating athletes for Olympic Games. The
ODA (London Delivery Authority) was the sponsoring organization for this
project. The paper critically discussed the scale and scope of the project
including deliverables, milestones, project objectives and limitations. The paper
also presented with the work breakdown structure to split the major tasks of
project into smaller components. The project shed light on PMOs, project control
system and other risk managements systems that have been used during the
project. A network diagram and Gantt chart was designed using project
management software to attain assistance in project planning.
The use of collaboration has been explained and how it fits with the ODA’s
organizational structure. Furthermore, the role of organizational culture and
national culture in ensuring the project success have been described in a
detailed manner. The potential resource conflicts have also been identified using
the iron triangle along with strategies to cope up with those conflicts. The ICT
resources that have been utilized in the project are identified and detailed risk
management plan was formulated for this purpose. Lastly, the paper discussed
Evaluate the tools and methods that were used in the project.
1.0 INTRODUCTION
The London Delivery Authority (ODA) is a well-known authority that have
transformed the Paralympic Village and Olympic into a number of more than
2,800 new homes after the completion of London 2012 Games. The need to
develop and undertake a project to deliver the infrastructure and venues
increased tremendously, following the successful bid for the Paralympic Games
and 2012 Summer Olympic (Epstein et al, 2011). The ODA is regarded as one of
the two integral agencies, together with London Organizing Committee of the
Olympic and Paralympic Games (LOCOG) that have structured and organized
the London Olympic Games. The ODA was formed in 2006 and is located in
Stratford, East London. The ODA had merely a number of 5 years of period
(2006-2012) to gather all the employees to carry out the work and execute the
major undertakings in the project. The ODA was developed by Paralympic
Games Act 2006 and London Olympic Games. The ODA has also been able to
provide a successful model to other construction projects of UK (Epstein et al,
2011). Furthermore, ODA was expected to satisfy the media, government, local
residents and public at the same time. This particular project specifically focuses
on building an Olympic village using the ODA as an accommodation center for
the athletes of the Olympic Games.
2.0 WORK BREAKDOWN STRUCTURE
FIGURE 2: WBS (PART 1)
(Source: Self-Made)
FIGURE 2: WBS (PART 2)
(Source: Self- Made)
3.0 SCOPE AND SCALE OF THE PROJECT
The project is responsible and have the major objective to ensure the delivery of
legacy, infrastructure, facilities, transport and venues for the Paralympic Games
and Summer Olympic 2012 in London (Epstein et al, 2011). The project required
to deliver and procure the major construction works which is worth of £6 billion.
The budget that had been allotted for the project was determined as £6bn with
£2bn contingency plan. The scope of building an Olympic Village through ODA
involved land remediation and deconstruction of about a 400 hectare (ha) site. A
large majority of over 11 million audience were directly and indirectly involved in
this project. The project covered the development of infrastructure which included
13km tunnels, 20 km roads, 26 bridges and new infrastructure utilities i.e.
electricity, water, gas and telecommunication. To convert and put up for sale a
number of 2,800 total homes through Athletes’ Village was also among the major
objectives of this project (Epstein et al, 2011). The project also involved the
development of nearly 100ha of public open space, gardens, parklands as well
as transport improvements, including infrastructure work and station to house all
the athletes.
In order to meet the proposed objectives of the project within the allotted budget
and provided time interval, the deliverables of the project were recognized
(Ahmad et al, 2013). The delivery strategy of this project was largely based on a
smaller number of main tenets. TELOSS framework was adopted for the purpose
to identify the project’s deliverables. A TELOSS is a systematic framework that
describes the five distinct filed of the project, which includes technical,
economical, legal, operational, scheduling and social. These elements are
integral for evaluating the success of the project. The figure 1 below represents
the TELOSS framework developed for the Olympic Village project.
Figure 3: TELOSS Framework
Technical Economic Legal
 Installation of video
conferencing
between LOCOD
and LOC
 HDTV Sport
lighting for 5bn
people
 Physical model of
park by 3D printing
 Change in budget
 Shift time
 Safety and Health
Issues
 Financial Penalties
 Usage of timber from
non-legal and
sustainable source
Operational Social Scheduling
 To prevent
software conflict,
DP provide
software training to
all contractors and
consultants to help
interface.
 DP applies Blenty
system to
centralize
engineering,
contacts,
management and
collaboration
system
 To provide all
stakeholders with level
of standards and
quality of work
 To maintain a sense
of Corporate Social
Responsibility while
executing the project.
 To satisfy all the
concerned
stakeholders
 Staff scheduling
 Various teams working
in different areas.
(Source: Self-Made)
3.1 MAJOR MILESTONES
 London announced as the winner – (July 2005)
 Planning and Land assembly– (2006- 2007)
 Demolish, Dig, Design– (2008)
 Interior Design – (September 2008)
 Foundation and Construction – ( 27 July 2009 – 27 July 2010)
 Installation of Technology – (June 2010)
 Testing and Certification –(Dec 2011)
 Completion –(2011 to 2012)
3.2 LIMITATIONS
There are certain limitations involved with every project and Olympic Village’s
project is no exception in this case (Valverde, 2012). The need to sustain the
interest of stakeholders and to have a constant support from the government is a
major challenge for this project. Apart from that, all the available resources have
to be allocated effectively to ensure the project’s success. There are also vendor
and supplier limitations since they have the capability to put limits on project
timelines. To ensure the timely delivery of a project, it is necessary to utilize an
effective vendor selection process before the start of a project (Bonaccorsi et al,
2014). The problem of maintaining the time and growing cost because of long
duration of project have raised major restraints on project’s viability.
4.0 SYSTEMS TO ENSURE PROJECT SUCCESS
For the purpose of determining the accomplishment level of the project, various
set of aspects will be taken into consideration. There is a dedicated department
also known as Project Management Office (PMO) that works within an
organization and focuses merely on the standards of Project management. For
example, a “directive PMO” have been implemented that goes beyond the control
and takes the responsibility of the major tasks pertain in the project (Tsaturyan &
Müller, 2015). It delivers the project management experience and resources in
order to accomplish the project in the timely and effective manner. For larger
projects like this one, directive PMO is highly effective since it implements a
common methodology and standardize terminology across the project
management process (Hayes, 2014). In any type of project, change is
unavoidable, whether it is from the external sources or from within the project.
Hence, it is important to develop an organized process for the purpose to identify,
evaluate and mitigate any major changes in the project.
For this project, change management and change control system have been
implemented to monitor and prevent any potential changes. The change
management system will allow the project management team to promote a
balanced change culture and transform the deleterious change into beneficial
change (Hayes, 2014). Moreover, the management will also deploy a Risk
Management Information System (RMIS) and risk analysis plan in order to
safeguard the health and safety measures involved in the project by monitoring
the project’s cost of risk.
5.0 IMPORTANCE OF USING COLLABORATION
The importance of collaboration across team members and various functional
areas in the organization should not be neglected. The collaborative project
management is grounded on the standards of containing all the members of a
project in the control and planning process and then linking them via
communication, information and collaboration modules. The act of collaboration
helps the team members to coordinate, monitor and implement the process of
projects that are complex in nature. In a project, collaboration can be used for the
purpose to simplify the time and tasks in the most effective manner. All the
project members should work with high cohesion and enjoy strong power which
is the essence of collaboration in a project.
Since the organizational structure of ODA is based on “pure project management
structure”, the collaboration will act as a tool to interlink the project members and
maintain the required level of communication and transparency between the
director and the different project managers (see fig 2). To achieve project goals,
integration, collaboration and mutual understanding is vital among the several
project modules. The structure is designed in such a way to promote
collaboration among individual team members, so as to attain the cost efficiency
with a least amount of duplication of efforts and overlaps. In project based
organizational structure, the director has all the authority and power to ensure the
smooth operations of the project and thus eliminating multiple leadership. The
reaction time is highly short in this structure because all the decision of the
project team is established within the project. The collaboration across different
functional areas of business is highly integral to sustain the level of coherence in
a project (Kauffeld et al, 2015). The degree of collaboration in this type of
structure is high since all the members share a common goal in a project which
ultimately results in reducing ambiguity and having clear-cut responsibilities by
each individuals (Smits, 2013).
Figure 4: Project -based organizational structure
Source: (Classtoolkit, 2007)
6.0 ORGANIZATIONAL AND NATIONAL CULTURE ROLE IN
PROJECT SUCCESS
6.1 ORGANIZATIONAL CULTURE FOR PROJECT SUCCESS
There are some organizations that are well-versed than others at managing
projects. In majority of the cases, the reason for project failure is because the
organizations do not align the project’s goals with their corporate strategy and
culture. There are numerous variables that may influence the ability to ensure the
project’s success (Alvesson, 2012). The organizational culture can be regarded
as the major roadblock or a solid foundation for a project’s success. The
organization’s culture is one of those variables and has a lot to do with the
project’s success rate. In the viewpoint of Alvesson (2012), "culture is regarded
as a more or less cohesive system of meanings and symbols, in terms of which
social interaction takes places” (Alvesson, 2012). A project is connected with
several aspects that must not be neglected and includes a wider environment.
The sponsoring organization in the project is part of this environment and hence
have the capability to affect the project’s success rate
Figure 5: Organizational Culture Profile
Source: (2012books, n.d)
The organizational culture of ODA is formal and bureaucratic in nature. This type
of organizational culture is related with the relationship between subordinate and
the authority. At the top of hierarchy, there is a senior leader, which is followed by
mid-level management and then subordinates. The ODA’s organizational
structure have good processes in place and make sure every employee follows
them properly to ensure project’s success. Hence, it helps the management to
remain engaged and interested in projects. Furthermore, there is no vagueness
and the roles are more defined in bureaucratic culture which aids in increasing
the project’s success rate. The culture of ODA is friendly, open and endorses an
open environment. The ODA’s culture directly influence the project operations
since its culture encourage an atmosphere where there free flow of
communication between various departments in the project team. The
employees of the organization are rewarded purely on merit-based performance
appraisal system and the same rewarding mechanism is applied in the project
operations i.e. the project’s team members are not evaluated on their position but
instead based on their performance and level of contribution.
6.2 NATIONAL CULTURE
FIGURE 6: FOUR DIMENSIONS OF UK’S CULTURE
Source: (Hofstede, n.d)
The national culture of a country in which the project is being implemented also
influence the project’s feasibility and viability in an extensive manner. A national
culture also have the capability to affect the culture of an organization since the
employees adopt the culture and norms adhered by a particular country in their
early stages of life. In 1994, Hofstede identified four dimensions of national
culture, namely Individualism versus Collectivism, Power Distance, Masculinity
versus Femininity and Uncertainty Avoidance (Geert-hofstede.com, 2015). In the
viewpoint of Hofstede, the culture of UK can be considered as highly masculine
and individualistic culture (see fig 4). A society will be motivated by achievement,
success competition, and competition when it shows a high score on masculinity
dimension. The masculinity dimensions shows a high score which indicates that.
Whereas, a low score on this dimension indicates that the society is feminine in
nature and is driven by factors such as cooperation, modesty, quality of life and
caring for the weak. Since UK is highly masculine society, it is highly success
oriented and possess success driven value system. The members in a project
are stimulated by success and appreciate a sense of achievement in masculine
society. Furthermore, this high level of motivation helps to exhibit high
performance teams (Hofstede, 2013). Another dimension on which UK scored
highest score is individualism versus collectivism. A high score on this dimension
represents that a society is individualistic, meaning the members of such a
society are expected to take care of only themselves and their immediate
families. In contrast, a low score on this dimension represents collectivism. In
collectivism, society prefer tightly-knit framework and belong to ‘in groups’ that
look after them in exchange for loyalty. In high individualistic culture, project team
members are emotionally attached and independent. Furthermore, the team
members are provided with the necessary freedom to think for new initiatives and
demand less supervision and guidance from their supervisors.
7.0 POTENTIAL RESOURCE CONFLICTS
The idea to construct an Olympic village in the heart of London came with huge
challenges. Conflict is invitable in project management and the cause of conflict
in project team can be connected to differences in attitudes, needs, values,
personalities, perceptions and resources. To dicuss to the potential resource
conflicts occurred in this project, a model of iron trianlge has been utilized (see
fig 5). Iron triangle is a well-known model of project management representing
constraints often occur during the project (Ebbesen & Hope, 2013). There are
three major attributes illustrated on each corner of a traingle, namely time, scope
and schedule. These three factors combined influence the overall quality of the
project. The project’ tasks can either take longer or duration amount of time to
conclude. There are number of factors on which the project’s completion is
depedentent such as workers’ skills, experience and commitment etc (Time,
2015). During this project, the project team faced numerous issues related to
time that caused the team leader to extend the deadline. Since the location of the
project is in populated city of London, it caused a major challenge to continue the
work without any interruption that ultimatley prolonged the duration of the project.
Relocation of the workers from one construction site to another was also a
concern. The second attribute in iron triangle is cost. It is often difficult to
estimate the exact cost for the project for both, organization and project
managers. The cost increased substantially during construction of Olympic
village due to changes in the duration of the project. The delay in procurment and
changing prices of raw materials such as bricks, stones, drainage system etc
also implacted the overall cost of the project. Lastly, the scope attribute views at
the outcome of the project undertaken (Thompson et al, 2011). To deliver the
outcome, various deliverables have to address by the project team. During this
project, the project goals were unclear and required more time to evaluate the
potential target audience for the final product. The scope of the existing work was
expanded and reconfigured together with all the deliverables to make the best
operational use of the proposed Olympic Village.
Despite of these aforementioned challenges, the project management team
effectivley attempted to cope up with these conflicts by devising the relevant
strategies and counterattack the unforseen circumstances during the project. The
risk management plan and risk analyis plan was formulated to lower the overall
cost of the project. Furthermore, the project management team also designed a
realistic scope statement so that the team should stick to the project’s goals and
be able to adddress the recognized project deliverables within the provided
budget.
Figure 7: Iron Triangle
Source: (Tutorialspoint, n.d)
8.0 INFORMATION COMMUNICATION TECHNOLOGY
The project management team made effective use of information communication
technology at several instances during the project so that every team member
remain connected and aware related to project’s progress. The project team
believes in the viewpoint that utilization of the modern IT technologies can
signicantly enhance the degree of success throughout the entire project lifecyle.
It requres good communication among team members for completing a complex
project. The team utilized informaiton technolgies such as live meeting, video
conference, computer-assissted conference and audio conference tools for free
flow of communication on both off-site and on-site and then convey the
information to the director for quick response. These communication
technologies helped in keeping all the members towards the common goal of the
project and to eliminate any potential ambiguity among the employees
(Schwalbe, 2013). Moreover, these tools facilitated in managing the issues in
budget variation in order to make sure the project was viable within the budget
scope.
9.0 PROJECT MANAGEMENT SOFTWARE
FIGURE 8: NETWORK DIAGRAM (PART 1)
(Source: Self-Made)
FIGURE 8: NETWORK DIAGRAM (PART 2)
(Source: Self-Made)
Figure 9: Gantt chart
(Source: Self-Made)
10.0 RISK MANAGEMENT
Risk management plan is a detailed document which project managers
formulates to predict risk, define responses to issues and estimate impacts
(Hubicki, 2014). The principles of risk management helps the project managers
to assess and prioritze the risks. It is regarded as systematic activity of
identifying, evaluating and recognizing the risk to enhance the chances of goals
accomplishment and ensuring individuals and organization are feasible. Risk
management plan has been developed for Olympic Village construction project
which comprises of:
Qtr1 Qtr2 Qtr3 Qtr4Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4
Londonannouncedasthe
winner
PlanningandLand
Assembly
Demolish,Dig,Design
InteriorDesign
Foundationand
Construction
Installationof
Technology
TestingandCertification
Completion
2011 20122005 2006 2007 2008 2009 2010
Figure 10: Risk Management Plan
Source: (Demvros, 2014)
10.1 RISK IDENTIFICATION
Risk identification is a procedure that defines risk that an entity may potentially
avert for the purpose to achieve its objectives. It is an integral part of Risk
Management process (Hubicki, 2014). Risk identification can be explained as
identifying, assessing and understanding the risk profile as well substantial risks
contained within it. In the Olympic Village construction project, the risks identified
are:
 Electrical risk
 Budget Variations
 Legal risks
 Foreigners and tourists travelling to London
 Scope and Schedule risk
 Relocation of people
10.2 RISK ASSESSMENT
Risk Assessment is a systematic procedure of detecting the events, predicting
unforeseen circumstances and taking suitable actions to prevent the risk from
causing harm to the project outcomes (Kerzner, 2013). During the operations of
the project, some of the risk that were assessed are as follows:
 IT challenges
 Lack of funds and outsourcing material
 Meeting deadline of the project
 Feasible architecture
 Structural challenges
 Power breakdown.
10.3 RISK CONTROL STRATEGIES
Risk control strategies can be develop d and implemented once the risks are
identified and contingency plans are in place (Hubicki, 2014). Risk control is
related to the selection and application of strategies to avoid and control risks. A
plan for developing a separate passage was made for tourists visiting the nearby
areas of the project to avoid interruptions. For power breakdown risk, it was
decided to install backup power source and generators to avoid stoppage any
potential disturbance. The cost was monitored from time to time to handle the
budget risk and the government was taken into confidence for preventing legal
risks.
10.4 RISK COMMUNICATION PLAN
After the risk has been identified, assessed and risk control strategies are
designed, it is highly important to communicate the plan to the concerned parties
so as to avoid any potential doubts and uncertainty (Kerzner, 2013). The risk
management plan was communicated to the stakeholders of the project through
information communication technologies such as emails and audio calls and their
feedback was also taken into consideration.
11. TOOLS AND METHODS USED IN PROJECT
The Olympic Village construction project was challenging task involving various
complex responsibilities. Also, the project team had the responsibility to maintain
the safe and healthy working environment by using green energy sources. The
project team formulated a dedicated software system to simplify the
communication process in project so that team members could stick to budget
and time constraints (Ahmad et al, 2013). Furthermore, the system also allowed
the information to be shared in real-time to the concerned stakeholders in order
to prevent any possible risk and delays that could hamper the project
performance. Apart from that, the project team utilized the widely used tool of
project management i.e. Gantt chart to monitor the progress and calculate the
differences in planned versus actual timeframe of project milestone
accomplishment. The project team also used PERT chart (Program Evaluation
Review Technique) for the purpose to organize, schedule and coordinate tasks
within a project.
12. RECOMMENDATION
It is recommended that project manager should realize the importance of human
resource by keeping the morale and motivation of team members high at all
times. The skills and quality of input of the workers, employees and personnel
who are actively involved in the project have direct influenced on the project’s
outcomes. It is also advised to make effective planning in terms of budget, time
and schedule before starting the actual project. The project team should
implement the project on the basis of “A Guide to the Project Management Body
of Knowledge (PMBOK® Guide)”. The book is regarded as a code of
professional standards and explains a set of standard guidelines for project
management. Furthermore, the project team can enhance the success rate of the
project by focusing on changes to technological function, business processes,
team roles and responsibilities and the effect of these change on budget.
13. CONCLUSION
The communications skills in project team members should be valued and use
effectively because they are the ones accountable for sustaining the quality of
the entire project (InfoQ, 2015).The Olympic Village construction project is a
highly complex project that requires constant support from the government, time,
patience and continuous efforts from the project team. The project is considered
as a successful endeavor only if it meets or even exceeds the client’s
expectations and satisfaction level (Time, 2015). The project management could
assist in gaining competitive edge to the organization by making efficient use of
resources, senior leadership support and following the standards. Apart from
accommodating and housing all the participating world athletes for the Olympic
Games, the Olympic Village construction project would also result in other
substantial benefits to the country such as overcoming recessions, betterment of
economic life, creation of jobs etc.
References
Ahmad, S. H., Bon, A. T., Rasi, R. M., Zuraidah, R., & Sie-Long, K. (2013).
Project management scheduling through integrated PERT and Gantt Chart.
Alvesson, M. (2012). Understanding organizational culture. Sage. Retrieved
from: https://books.google.com
/books?hl=en&lr=&id=BDsV8eHp0_MC&oi=fnd&pg=PP2&dq=organizational+cult
ure+and+project&ots=745i7oxLzF&sig=9ujKpcqdkZXyXwpqeNzOUTAZIr 5
Bonaccorsi, A., Daraio, C., & Simar, L. (2014). Efficiency and economies of scale
and scope in European universities. A directional distance approach (No. 2014-
08). Department of Computer, Control and Management Engineering,
Universita'degli Studi di Roma" La Sapienza".
Ebbesen, J. B., & Hope, A. (2013). Re-imagining the iron triangle: embedding
sustainability into project constraints. PM World Journal, 2(III).
Epstein, D., Jackson, R., & Braithwaite, P. (2011, May). Delivering London 2012:
sustainability strategy. In Proceedings of the ICE-Civil Engineering (Vol. 164, No.
5, pp. 27-33). Thomas Telford.
G., Ligthart, R., & Sydow, J. (2015). Collaboration in project networks: The case
of the Dutch shipbuilding industry. Managing interorganizational relations.
Geert-hofstede.com, (2015). United Kingdom - Geert Hofstede. [online] Retrieved
from: http://geert-hofstede.com/united-kingdom.html [Accessed 11 Sep. 2015].
Hayes, J. (2014). The theory and practice of change management. Palgrave
Macmillan.
Hofstede, G. (2013). Dimensions of national cultures. Retrieved from:
https://saylor.longsight.com/handle/1/10250
Hooghe, L., & Marks, G. (2013). The Authority of International Organizations: the
effects of scope and scale. Unpublished manuscript, University of North Carolina,
Chapel Hill, NC.
Hubicki, M. (2014). Risk Management Plan. Retrieved from:
http://www.mindsetting.net/assets/02-hubicki-coed-6150-risk-management-
plan.pdf
InfoQ, (2015). Investigation of Project Management Skills. [online] Available at:
http://www.infoq.com/news/2015/08/investigation-project-management
[Accessed 18 Sep. 2015].
Kauffeld, S., Lehmann-Willenbrock, N., & Grote, S. (2015). Dreamteam or
Nightmare? Collaboration in Project Teams. In Applied Psychology for Project
Managers (pp. 161-177). Springer Berlin Heidelberg.
Kerzner, H. R. (2013). Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Levering, R. C., Oerlemans, L. A. G.
Schwalbe, K. (2013). Information technology project management. Cengage
Learning. Retrieved from:
https://books.google.com/books?hl=en&lr=&id=xbEWAAAAQBAJ&oi=fnd&pg=PP
1&dq=information+technology+in+project&ots=URs1Nip84r&sig=LRsCV0T0HpD
2Xb0vYzpVevJvBls
Smits, K. C. M. (2013). Cross Culture Work:: Practices of Collaboration in the
Panama Canal Expansion Program.
Thompson, S. C., Kakar, A. K., & Hale, J. E. (2011). Breaking the Iron Triangle:
The Impact of Information Sufficiency on Project Portfolio Decisions. In AMCIS.
Time, P. (2015). Project Management: Eating the Elephant One Bite at a Time
(News). [online] Nojitter.com. Available at:
http://www.nojitter.com/post/240170496/project-management-eating-the-
elephant-one-bite-at-a-time [Accessed 18 Sep. 2015].
Tsaturyan, T., & Müller, R. (2015). Integration and governance of multiple project
management offices (PMOs) at large organizations. International Journal of
Project Management, 33(5), 1098-1110.
Valverde, M. (2012). Analyzing punishment: Scope and scale. Theoretical
Criminology, 16(2), 245-253.

More Related Content

What's hot

Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full courseMarten Schoonman
 
Project Management Overview for Aerospace and Defense Industry
Project Management Overview for Aerospace and Defense Industry Project Management Overview for Aerospace and Defense Industry
Project Management Overview for Aerospace and Defense Industry Fujitsu Glovia, Inc.
 
Project management chapter 2
Project management chapter 2Project management chapter 2
Project management chapter 2Dauda Jamada
 
Benefits of using Project Management Software
Benefits of using Project Management SoftwareBenefits of using Project Management Software
Benefits of using Project Management SoftwareForecast
 
Network diagram problems
Network diagram problemsNetwork diagram problems
Network diagram problemsSubhra Mishra
 
Stadium Project
Stadium ProjectStadium Project
Stadium Projectlakvij
 
Assignment coca cola by nilesh
Assignment coca cola by nileshAssignment coca cola by nilesh
Assignment coca cola by nileshNILESH SHUKLA
 
Pest Analysis of the Barbican Arts Centre
Pest Analysis of the Barbican Arts CentrePest Analysis of the Barbican Arts Centre
Pest Analysis of the Barbican Arts CentreerFarukyeni
 
Report on unilever limited
Report on unilever limitedReport on unilever limited
Report on unilever limitedIslam Fazal
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringSandeep Kumar
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...Yamini Kahaliya
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniquesguestc8140fe
 
Project Management: Business Case
Project Management: Business CaseProject Management: Business Case
Project Management: Business CaseYerbol Buranbay
 

What's hot (20)

Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full course
 
Project Management Overview for Aerospace and Defense Industry
Project Management Overview for Aerospace and Defense Industry Project Management Overview for Aerospace and Defense Industry
Project Management Overview for Aerospace and Defense Industry
 
Project management chapter 2
Project management chapter 2Project management chapter 2
Project management chapter 2
 
Benefits of using Project Management Software
Benefits of using Project Management SoftwareBenefits of using Project Management Software
Benefits of using Project Management Software
 
Network diagram problems
Network diagram problemsNetwork diagram problems
Network diagram problems
 
Stadium Project
Stadium ProjectStadium Project
Stadium Project
 
Assignment coca cola by nilesh
Assignment coca cola by nileshAssignment coca cola by nilesh
Assignment coca cola by nilesh
 
Pest Analysis of the Barbican Arts Centre
Pest Analysis of the Barbican Arts CentrePest Analysis of the Barbican Arts Centre
Pest Analysis of the Barbican Arts Centre
 
Report on unilever limited
Report on unilever limitedReport on unilever limited
Report on unilever limited
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoring
 
(Aoa) and (aon) networks
(Aoa) and (aon) networks(Aoa) and (aon) networks
(Aoa) and (aon) networks
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Chap 2 Organization Strategy
Chap 2 Organization StrategyChap 2 Organization Strategy
Chap 2 Organization Strategy
 
Dialog presentation
Dialog presentationDialog presentation
Dialog presentation
 
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
 
Project Management: Business Case
Project Management: Business CaseProject Management: Business Case
Project Management: Business Case
 
Project environment
Project environmentProject environment
Project environment
 
Chap04 project integration management
Chap04 project integration managementChap04 project integration management
Chap04 project integration management
 
Ratio analysis
Ratio analysisRatio analysis
Ratio analysis
 

Viewers also liked

Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for...
Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for...Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for...
Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for...Project Controls Expo
 
Senior project proposal approval
Senior project proposal approvalSenior project proposal approval
Senior project proposal approvalMissNikki18
 
Project management techniques workshop sample agenda
Project management techniques workshop sample agendaProject management techniques workshop sample agenda
Project management techniques workshop sample agendaShari Mullen
 
Document Examples
Document ExamplesDocument Examples
Document Exampleswmassie
 
Communications Management Presentation
Communications Management PresentationCommunications Management Presentation
Communications Management Presentationbrianbish10795
 
PMP Training - 10 project communication management
PMP Training - 10 project communication managementPMP Training - 10 project communication management
PMP Training - 10 project communication managementejlp12
 
Project Management Plan Template
Project Management Plan TemplateProject Management Plan Template
Project Management Plan TemplateSimplilearn
 
Project Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleProject Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleAndrew Schwartz
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project ManagementRodolfo Siles
 
Sample project plan
Sample project planSample project plan
Sample project planmamoonnift
 

Viewers also liked (10)

Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for...
Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for...Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for...
Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for...
 
Senior project proposal approval
Senior project proposal approvalSenior project proposal approval
Senior project proposal approval
 
Project management techniques workshop sample agenda
Project management techniques workshop sample agendaProject management techniques workshop sample agenda
Project management techniques workshop sample agenda
 
Document Examples
Document ExamplesDocument Examples
Document Examples
 
Communications Management Presentation
Communications Management PresentationCommunications Management Presentation
Communications Management Presentation
 
PMP Training - 10 project communication management
PMP Training - 10 project communication managementPMP Training - 10 project communication management
PMP Training - 10 project communication management
 
Project Management Plan Template
Project Management Plan TemplateProject Management Plan Template
Project Management Plan Template
 
Project Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleProject Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern Sample
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
 
Sample project plan
Sample project planSample project plan
Sample project plan
 

Similar to Sample project management

Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&tNishant Pandey
 
Project 27663255255255781771777166162666
Project 27663255255255781771777166162666Project 27663255255255781771777166162666
Project 27663255255255781771777166162666MilkiasMuse
 
Economics of project evaluation for reference cpm module2
Economics of project evaluation for reference cpm module2Economics of project evaluation for reference cpm module2
Economics of project evaluation for reference cpm module2ahsanrabbani
 
Construction Project Essay
Construction Project EssayConstruction Project Essay
Construction Project EssayAshley Thomas
 
Project Management.Project 1
Project Management.Project 1Project Management.Project 1
Project Management.Project 1suzzanekan
 
Q3 2011 Progress Report MoSS
Q3 2011 Progress Report   MoSSQ3 2011 Progress Report   MoSS
Q3 2011 Progress Report MoSSMoheebSattar
 
Lecture notes on_construction_project_ma
Lecture notes on_construction_project_maLecture notes on_construction_project_ma
Lecture notes on_construction_project_mamohammedsameer129
 
Engineering Project ManagementMse 402 .docx
Engineering Project ManagementMse 402                       .docxEngineering Project ManagementMse 402                       .docx
Engineering Project ManagementMse 402 .docxSALU18
 
Project Management Group Assignment Final Report
Project Management Group Assignment Final ReportProject Management Group Assignment Final Report
Project Management Group Assignment Final ReportArissa Loh
 
CHAPTER 1 - Project Management.pdf
CHAPTER 1 - Project Management.pdfCHAPTER 1 - Project Management.pdf
CHAPTER 1 - Project Management.pdfMartinsAras
 
Q1 2012 Progress Report MoSS
Q1 2012 Progress Report   MoSSQ1 2012 Progress Report   MoSS
Q1 2012 Progress Report MoSSMoheebSattar
 
Building construction manual btc nov_2013_en
Building construction manual btc nov_2013_enBuilding construction manual btc nov_2013_en
Building construction manual btc nov_2013_enAYM1979
 
Problems Associated With Flood Patterns And Poor Water...
Problems Associated With Flood Patterns And Poor Water...Problems Associated With Flood Patterns And Poor Water...
Problems Associated With Flood Patterns And Poor Water...Laura Benitez
 
Project Management
Project ManagementProject Management
Project ManagementAnton Orlov
 
Annual Work Plan 2012 Final
Annual Work Plan 2012 FinalAnnual Work Plan 2012 Final
Annual Work Plan 2012 FinalMoheebSattar
 
Q4 2011 Progress Report MoSS
Q4 2011 Progress Report   MoSSQ4 2011 Progress Report   MoSS
Q4 2011 Progress Report MoSSMoheebSattar
 
MPM621Ch12.pptx project identification A
MPM621Ch12.pptx project identification AMPM621Ch12.pptx project identification A
MPM621Ch12.pptx project identification ADebelaTekabe
 
Green buildings and role of projects Manager in success of project
Green buildings and role of projects Manager in success of project Green buildings and role of projects Manager in success of project
Green buildings and role of projects Manager in success of project Tehmas Saeed
 
Arcadia project- D ata Management Plan
Arcadia project- D ata Management PlanArcadia project- D ata Management Plan
Arcadia project- D ata Management PlanEU ARCADIA PROJECT
 

Similar to Sample project management (20)

Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&t
 
Project 27663255255255781771777166162666
Project 27663255255255781771777166162666Project 27663255255255781771777166162666
Project 27663255255255781771777166162666
 
Economics of project evaluation for reference cpm module2
Economics of project evaluation for reference cpm module2Economics of project evaluation for reference cpm module2
Economics of project evaluation for reference cpm module2
 
Construction Project Essay
Construction Project EssayConstruction Project Essay
Construction Project Essay
 
Project Management.Project 1
Project Management.Project 1Project Management.Project 1
Project Management.Project 1
 
Q3 2011 Progress Report MoSS
Q3 2011 Progress Report   MoSSQ3 2011 Progress Report   MoSS
Q3 2011 Progress Report MoSS
 
Lecture notes on_construction_project_ma
Lecture notes on_construction_project_maLecture notes on_construction_project_ma
Lecture notes on_construction_project_ma
 
Engineering Project ManagementMse 402 .docx
Engineering Project ManagementMse 402                       .docxEngineering Project ManagementMse 402                       .docx
Engineering Project ManagementMse 402 .docx
 
Project Management Group Assignment Final Report
Project Management Group Assignment Final ReportProject Management Group Assignment Final Report
Project Management Group Assignment Final Report
 
CHAPTER 1 - Project Management.pdf
CHAPTER 1 - Project Management.pdfCHAPTER 1 - Project Management.pdf
CHAPTER 1 - Project Management.pdf
 
Q1 2012 Progress Report MoSS
Q1 2012 Progress Report   MoSSQ1 2012 Progress Report   MoSS
Q1 2012 Progress Report MoSS
 
Building construction manual btc nov_2013_en
Building construction manual btc nov_2013_enBuilding construction manual btc nov_2013_en
Building construction manual btc nov_2013_en
 
Problems Associated With Flood Patterns And Poor Water...
Problems Associated With Flood Patterns And Poor Water...Problems Associated With Flood Patterns And Poor Water...
Problems Associated With Flood Patterns And Poor Water...
 
Topic 1.ppt
Topic 1.pptTopic 1.ppt
Topic 1.ppt
 
Project Management
Project ManagementProject Management
Project Management
 
Annual Work Plan 2012 Final
Annual Work Plan 2012 FinalAnnual Work Plan 2012 Final
Annual Work Plan 2012 Final
 
Q4 2011 Progress Report MoSS
Q4 2011 Progress Report   MoSSQ4 2011 Progress Report   MoSS
Q4 2011 Progress Report MoSS
 
MPM621Ch12.pptx project identification A
MPM621Ch12.pptx project identification AMPM621Ch12.pptx project identification A
MPM621Ch12.pptx project identification A
 
Green buildings and role of projects Manager in success of project
Green buildings and role of projects Manager in success of project Green buildings and role of projects Manager in success of project
Green buildings and role of projects Manager in success of project
 
Arcadia project- D ata Management Plan
Arcadia project- D ata Management PlanArcadia project- D ata Management Plan
Arcadia project- D ata Management Plan
 

Recently uploaded

A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 

Recently uploaded (20)

A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 

Sample project management

  • 1. Running Head: Sample Project Management Olympic Village [Name of the Writer] [Name of the Institution]
  • 2. Project Management 1 Table of Contents 1.0 INTRODUCTION ............................................................................................3 2.0 WORK BREAKDOWN STRUCTURE .............................................................4 3.0 SCOPE AND SCALE OF THE PROJECT ......................................................5 3.1 Major Milestones .........................................................................................7 3.2 Limitations ...................................................................................................7 4.0 SYSTEMS TO ENSURE PROJECT SUCCESS.............................................7 5.0 IMPORTANCE OF USING COLLABORATION ..............................................8 6.0 ORGANIZATIONAL AND NATIONAL CULTURE ROLE IN PROJECT SUCCESS ..........................................................................................................10 6.1 Organizational Culture...............................................................................10 6.2 National Culture.........................................................................................12 7.0 POTENTIAL RESOURCE CONFLICTS .......................................................13 8.0 INFORMATION COMMUNICATION TECHNOLOGY...................................15 9.0 PROJECT MANAGEMENT SOFTWARE .....................................................16 10.0 RISK MANAGEMENT.................................................................................17 10.1 Risk Identification.....................................................................................18 10.2 Risk Assessment .....................................................................................19 10.3 Risk control Strategies.............................................................................19 10.4 Risk Communication Plan........................................................................19 11. TOOLS AND METHODS USED IN PROJECT .............................................20 12. RECOMMENDATION ...................................................................................20 13. CONCLUSION..............................................................................................21
  • 3. EXECUTIVE SUMMARY The primary purpose of this project is to construct the Olympic Village in East London to accommodate all the participating athletes for Olympic Games. The ODA (London Delivery Authority) was the sponsoring organization for this project. The paper critically discussed the scale and scope of the project including deliverables, milestones, project objectives and limitations. The paper also presented with the work breakdown structure to split the major tasks of project into smaller components. The project shed light on PMOs, project control system and other risk managements systems that have been used during the project. A network diagram and Gantt chart was designed using project management software to attain assistance in project planning. The use of collaboration has been explained and how it fits with the ODA’s organizational structure. Furthermore, the role of organizational culture and national culture in ensuring the project success have been described in a detailed manner. The potential resource conflicts have also been identified using the iron triangle along with strategies to cope up with those conflicts. The ICT resources that have been utilized in the project are identified and detailed risk management plan was formulated for this purpose. Lastly, the paper discussed Evaluate the tools and methods that were used in the project.
  • 4. 1.0 INTRODUCTION The London Delivery Authority (ODA) is a well-known authority that have transformed the Paralympic Village and Olympic into a number of more than 2,800 new homes after the completion of London 2012 Games. The need to develop and undertake a project to deliver the infrastructure and venues increased tremendously, following the successful bid for the Paralympic Games and 2012 Summer Olympic (Epstein et al, 2011). The ODA is regarded as one of the two integral agencies, together with London Organizing Committee of the Olympic and Paralympic Games (LOCOG) that have structured and organized the London Olympic Games. The ODA was formed in 2006 and is located in Stratford, East London. The ODA had merely a number of 5 years of period (2006-2012) to gather all the employees to carry out the work and execute the major undertakings in the project. The ODA was developed by Paralympic Games Act 2006 and London Olympic Games. The ODA has also been able to provide a successful model to other construction projects of UK (Epstein et al, 2011). Furthermore, ODA was expected to satisfy the media, government, local residents and public at the same time. This particular project specifically focuses on building an Olympic village using the ODA as an accommodation center for the athletes of the Olympic Games.
  • 5. 2.0 WORK BREAKDOWN STRUCTURE FIGURE 2: WBS (PART 1) (Source: Self-Made) FIGURE 2: WBS (PART 2) (Source: Self- Made)
  • 6. 3.0 SCOPE AND SCALE OF THE PROJECT The project is responsible and have the major objective to ensure the delivery of legacy, infrastructure, facilities, transport and venues for the Paralympic Games and Summer Olympic 2012 in London (Epstein et al, 2011). The project required to deliver and procure the major construction works which is worth of £6 billion. The budget that had been allotted for the project was determined as £6bn with £2bn contingency plan. The scope of building an Olympic Village through ODA involved land remediation and deconstruction of about a 400 hectare (ha) site. A large majority of over 11 million audience were directly and indirectly involved in this project. The project covered the development of infrastructure which included 13km tunnels, 20 km roads, 26 bridges and new infrastructure utilities i.e. electricity, water, gas and telecommunication. To convert and put up for sale a number of 2,800 total homes through Athletes’ Village was also among the major objectives of this project (Epstein et al, 2011). The project also involved the development of nearly 100ha of public open space, gardens, parklands as well as transport improvements, including infrastructure work and station to house all the athletes. In order to meet the proposed objectives of the project within the allotted budget and provided time interval, the deliverables of the project were recognized (Ahmad et al, 2013). The delivery strategy of this project was largely based on a smaller number of main tenets. TELOSS framework was adopted for the purpose to identify the project’s deliverables. A TELOSS is a systematic framework that describes the five distinct filed of the project, which includes technical, economical, legal, operational, scheduling and social. These elements are integral for evaluating the success of the project. The figure 1 below represents the TELOSS framework developed for the Olympic Village project.
  • 7. Figure 3: TELOSS Framework Technical Economic Legal  Installation of video conferencing between LOCOD and LOC  HDTV Sport lighting for 5bn people  Physical model of park by 3D printing  Change in budget  Shift time  Safety and Health Issues  Financial Penalties  Usage of timber from non-legal and sustainable source Operational Social Scheduling  To prevent software conflict, DP provide software training to all contractors and consultants to help interface.  DP applies Blenty system to centralize engineering, contacts, management and collaboration system  To provide all stakeholders with level of standards and quality of work  To maintain a sense of Corporate Social Responsibility while executing the project.  To satisfy all the concerned stakeholders  Staff scheduling  Various teams working in different areas. (Source: Self-Made)
  • 8. 3.1 MAJOR MILESTONES  London announced as the winner – (July 2005)  Planning and Land assembly– (2006- 2007)  Demolish, Dig, Design– (2008)  Interior Design – (September 2008)  Foundation and Construction – ( 27 July 2009 – 27 July 2010)  Installation of Technology – (June 2010)  Testing and Certification –(Dec 2011)  Completion –(2011 to 2012) 3.2 LIMITATIONS There are certain limitations involved with every project and Olympic Village’s project is no exception in this case (Valverde, 2012). The need to sustain the interest of stakeholders and to have a constant support from the government is a major challenge for this project. Apart from that, all the available resources have to be allocated effectively to ensure the project’s success. There are also vendor and supplier limitations since they have the capability to put limits on project timelines. To ensure the timely delivery of a project, it is necessary to utilize an effective vendor selection process before the start of a project (Bonaccorsi et al, 2014). The problem of maintaining the time and growing cost because of long duration of project have raised major restraints on project’s viability. 4.0 SYSTEMS TO ENSURE PROJECT SUCCESS For the purpose of determining the accomplishment level of the project, various set of aspects will be taken into consideration. There is a dedicated department also known as Project Management Office (PMO) that works within an organization and focuses merely on the standards of Project management. For example, a “directive PMO” have been implemented that goes beyond the control and takes the responsibility of the major tasks pertain in the project (Tsaturyan & Müller, 2015). It delivers the project management experience and resources in order to accomplish the project in the timely and effective manner. For larger
  • 9. projects like this one, directive PMO is highly effective since it implements a common methodology and standardize terminology across the project management process (Hayes, 2014). In any type of project, change is unavoidable, whether it is from the external sources or from within the project. Hence, it is important to develop an organized process for the purpose to identify, evaluate and mitigate any major changes in the project. For this project, change management and change control system have been implemented to monitor and prevent any potential changes. The change management system will allow the project management team to promote a balanced change culture and transform the deleterious change into beneficial change (Hayes, 2014). Moreover, the management will also deploy a Risk Management Information System (RMIS) and risk analysis plan in order to safeguard the health and safety measures involved in the project by monitoring the project’s cost of risk. 5.0 IMPORTANCE OF USING COLLABORATION The importance of collaboration across team members and various functional areas in the organization should not be neglected. The collaborative project management is grounded on the standards of containing all the members of a project in the control and planning process and then linking them via communication, information and collaboration modules. The act of collaboration helps the team members to coordinate, monitor and implement the process of projects that are complex in nature. In a project, collaboration can be used for the purpose to simplify the time and tasks in the most effective manner. All the project members should work with high cohesion and enjoy strong power which is the essence of collaboration in a project. Since the organizational structure of ODA is based on “pure project management structure”, the collaboration will act as a tool to interlink the project members and maintain the required level of communication and transparency between the director and the different project managers (see fig 2). To achieve project goals,
  • 10. integration, collaboration and mutual understanding is vital among the several project modules. The structure is designed in such a way to promote collaboration among individual team members, so as to attain the cost efficiency with a least amount of duplication of efforts and overlaps. In project based organizational structure, the director has all the authority and power to ensure the smooth operations of the project and thus eliminating multiple leadership. The reaction time is highly short in this structure because all the decision of the project team is established within the project. The collaboration across different functional areas of business is highly integral to sustain the level of coherence in a project (Kauffeld et al, 2015). The degree of collaboration in this type of structure is high since all the members share a common goal in a project which ultimately results in reducing ambiguity and having clear-cut responsibilities by each individuals (Smits, 2013). Figure 4: Project -based organizational structure Source: (Classtoolkit, 2007)
  • 11. 6.0 ORGANIZATIONAL AND NATIONAL CULTURE ROLE IN PROJECT SUCCESS 6.1 ORGANIZATIONAL CULTURE FOR PROJECT SUCCESS There are some organizations that are well-versed than others at managing projects. In majority of the cases, the reason for project failure is because the organizations do not align the project’s goals with their corporate strategy and culture. There are numerous variables that may influence the ability to ensure the project’s success (Alvesson, 2012). The organizational culture can be regarded as the major roadblock or a solid foundation for a project’s success. The organization’s culture is one of those variables and has a lot to do with the project’s success rate. In the viewpoint of Alvesson (2012), "culture is regarded as a more or less cohesive system of meanings and symbols, in terms of which social interaction takes places” (Alvesson, 2012). A project is connected with several aspects that must not be neglected and includes a wider environment. The sponsoring organization in the project is part of this environment and hence have the capability to affect the project’s success rate Figure 5: Organizational Culture Profile Source: (2012books, n.d)
  • 12. The organizational culture of ODA is formal and bureaucratic in nature. This type of organizational culture is related with the relationship between subordinate and the authority. At the top of hierarchy, there is a senior leader, which is followed by mid-level management and then subordinates. The ODA’s organizational structure have good processes in place and make sure every employee follows them properly to ensure project’s success. Hence, it helps the management to remain engaged and interested in projects. Furthermore, there is no vagueness and the roles are more defined in bureaucratic culture which aids in increasing the project’s success rate. The culture of ODA is friendly, open and endorses an open environment. The ODA’s culture directly influence the project operations since its culture encourage an atmosphere where there free flow of communication between various departments in the project team. The employees of the organization are rewarded purely on merit-based performance appraisal system and the same rewarding mechanism is applied in the project operations i.e. the project’s team members are not evaluated on their position but instead based on their performance and level of contribution.
  • 13. 6.2 NATIONAL CULTURE FIGURE 6: FOUR DIMENSIONS OF UK’S CULTURE Source: (Hofstede, n.d) The national culture of a country in which the project is being implemented also influence the project’s feasibility and viability in an extensive manner. A national culture also have the capability to affect the culture of an organization since the employees adopt the culture and norms adhered by a particular country in their early stages of life. In 1994, Hofstede identified four dimensions of national culture, namely Individualism versus Collectivism, Power Distance, Masculinity versus Femininity and Uncertainty Avoidance (Geert-hofstede.com, 2015). In the viewpoint of Hofstede, the culture of UK can be considered as highly masculine and individualistic culture (see fig 4). A society will be motivated by achievement, success competition, and competition when it shows a high score on masculinity dimension. The masculinity dimensions shows a high score which indicates that. Whereas, a low score on this dimension indicates that the society is feminine in
  • 14. nature and is driven by factors such as cooperation, modesty, quality of life and caring for the weak. Since UK is highly masculine society, it is highly success oriented and possess success driven value system. The members in a project are stimulated by success and appreciate a sense of achievement in masculine society. Furthermore, this high level of motivation helps to exhibit high performance teams (Hofstede, 2013). Another dimension on which UK scored highest score is individualism versus collectivism. A high score on this dimension represents that a society is individualistic, meaning the members of such a society are expected to take care of only themselves and their immediate families. In contrast, a low score on this dimension represents collectivism. In collectivism, society prefer tightly-knit framework and belong to ‘in groups’ that look after them in exchange for loyalty. In high individualistic culture, project team members are emotionally attached and independent. Furthermore, the team members are provided with the necessary freedom to think for new initiatives and demand less supervision and guidance from their supervisors. 7.0 POTENTIAL RESOURCE CONFLICTS The idea to construct an Olympic village in the heart of London came with huge challenges. Conflict is invitable in project management and the cause of conflict in project team can be connected to differences in attitudes, needs, values, personalities, perceptions and resources. To dicuss to the potential resource conflicts occurred in this project, a model of iron trianlge has been utilized (see fig 5). Iron triangle is a well-known model of project management representing constraints often occur during the project (Ebbesen & Hope, 2013). There are three major attributes illustrated on each corner of a traingle, namely time, scope and schedule. These three factors combined influence the overall quality of the project. The project’ tasks can either take longer or duration amount of time to conclude. There are number of factors on which the project’s completion is depedentent such as workers’ skills, experience and commitment etc (Time, 2015). During this project, the project team faced numerous issues related to
  • 15. time that caused the team leader to extend the deadline. Since the location of the project is in populated city of London, it caused a major challenge to continue the work without any interruption that ultimatley prolonged the duration of the project. Relocation of the workers from one construction site to another was also a concern. The second attribute in iron triangle is cost. It is often difficult to estimate the exact cost for the project for both, organization and project managers. The cost increased substantially during construction of Olympic village due to changes in the duration of the project. The delay in procurment and changing prices of raw materials such as bricks, stones, drainage system etc also implacted the overall cost of the project. Lastly, the scope attribute views at the outcome of the project undertaken (Thompson et al, 2011). To deliver the outcome, various deliverables have to address by the project team. During this project, the project goals were unclear and required more time to evaluate the potential target audience for the final product. The scope of the existing work was expanded and reconfigured together with all the deliverables to make the best operational use of the proposed Olympic Village. Despite of these aforementioned challenges, the project management team effectivley attempted to cope up with these conflicts by devising the relevant strategies and counterattack the unforseen circumstances during the project. The risk management plan and risk analyis plan was formulated to lower the overall cost of the project. Furthermore, the project management team also designed a realistic scope statement so that the team should stick to the project’s goals and be able to adddress the recognized project deliverables within the provided budget.
  • 16. Figure 7: Iron Triangle Source: (Tutorialspoint, n.d) 8.0 INFORMATION COMMUNICATION TECHNOLOGY The project management team made effective use of information communication technology at several instances during the project so that every team member remain connected and aware related to project’s progress. The project team believes in the viewpoint that utilization of the modern IT technologies can signicantly enhance the degree of success throughout the entire project lifecyle. It requres good communication among team members for completing a complex project. The team utilized informaiton technolgies such as live meeting, video conference, computer-assissted conference and audio conference tools for free flow of communication on both off-site and on-site and then convey the information to the director for quick response. These communication technologies helped in keeping all the members towards the common goal of the project and to eliminate any potential ambiguity among the employees (Schwalbe, 2013). Moreover, these tools facilitated in managing the issues in budget variation in order to make sure the project was viable within the budget scope.
  • 17. 9.0 PROJECT MANAGEMENT SOFTWARE FIGURE 8: NETWORK DIAGRAM (PART 1) (Source: Self-Made) FIGURE 8: NETWORK DIAGRAM (PART 2) (Source: Self-Made)
  • 18. Figure 9: Gantt chart (Source: Self-Made) 10.0 RISK MANAGEMENT Risk management plan is a detailed document which project managers formulates to predict risk, define responses to issues and estimate impacts (Hubicki, 2014). The principles of risk management helps the project managers to assess and prioritze the risks. It is regarded as systematic activity of identifying, evaluating and recognizing the risk to enhance the chances of goals accomplishment and ensuring individuals and organization are feasible. Risk management plan has been developed for Olympic Village construction project which comprises of: Qtr1 Qtr2 Qtr3 Qtr4Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 Qtr4 Londonannouncedasthe winner PlanningandLand Assembly Demolish,Dig,Design InteriorDesign Foundationand Construction Installationof Technology TestingandCertification Completion 2011 20122005 2006 2007 2008 2009 2010
  • 19. Figure 10: Risk Management Plan Source: (Demvros, 2014) 10.1 RISK IDENTIFICATION Risk identification is a procedure that defines risk that an entity may potentially avert for the purpose to achieve its objectives. It is an integral part of Risk Management process (Hubicki, 2014). Risk identification can be explained as identifying, assessing and understanding the risk profile as well substantial risks contained within it. In the Olympic Village construction project, the risks identified are:  Electrical risk  Budget Variations  Legal risks  Foreigners and tourists travelling to London  Scope and Schedule risk  Relocation of people
  • 20. 10.2 RISK ASSESSMENT Risk Assessment is a systematic procedure of detecting the events, predicting unforeseen circumstances and taking suitable actions to prevent the risk from causing harm to the project outcomes (Kerzner, 2013). During the operations of the project, some of the risk that were assessed are as follows:  IT challenges  Lack of funds and outsourcing material  Meeting deadline of the project  Feasible architecture  Structural challenges  Power breakdown. 10.3 RISK CONTROL STRATEGIES Risk control strategies can be develop d and implemented once the risks are identified and contingency plans are in place (Hubicki, 2014). Risk control is related to the selection and application of strategies to avoid and control risks. A plan for developing a separate passage was made for tourists visiting the nearby areas of the project to avoid interruptions. For power breakdown risk, it was decided to install backup power source and generators to avoid stoppage any potential disturbance. The cost was monitored from time to time to handle the budget risk and the government was taken into confidence for preventing legal risks. 10.4 RISK COMMUNICATION PLAN After the risk has been identified, assessed and risk control strategies are designed, it is highly important to communicate the plan to the concerned parties so as to avoid any potential doubts and uncertainty (Kerzner, 2013). The risk management plan was communicated to the stakeholders of the project through
  • 21. information communication technologies such as emails and audio calls and their feedback was also taken into consideration. 11. TOOLS AND METHODS USED IN PROJECT The Olympic Village construction project was challenging task involving various complex responsibilities. Also, the project team had the responsibility to maintain the safe and healthy working environment by using green energy sources. The project team formulated a dedicated software system to simplify the communication process in project so that team members could stick to budget and time constraints (Ahmad et al, 2013). Furthermore, the system also allowed the information to be shared in real-time to the concerned stakeholders in order to prevent any possible risk and delays that could hamper the project performance. Apart from that, the project team utilized the widely used tool of project management i.e. Gantt chart to monitor the progress and calculate the differences in planned versus actual timeframe of project milestone accomplishment. The project team also used PERT chart (Program Evaluation Review Technique) for the purpose to organize, schedule and coordinate tasks within a project. 12. RECOMMENDATION It is recommended that project manager should realize the importance of human resource by keeping the morale and motivation of team members high at all times. The skills and quality of input of the workers, employees and personnel who are actively involved in the project have direct influenced on the project’s outcomes. It is also advised to make effective planning in terms of budget, time and schedule before starting the actual project. The project team should implement the project on the basis of “A Guide to the Project Management Body of Knowledge (PMBOK® Guide)”. The book is regarded as a code of professional standards and explains a set of standard guidelines for project management. Furthermore, the project team can enhance the success rate of the
  • 22. project by focusing on changes to technological function, business processes, team roles and responsibilities and the effect of these change on budget. 13. CONCLUSION The communications skills in project team members should be valued and use effectively because they are the ones accountable for sustaining the quality of the entire project (InfoQ, 2015).The Olympic Village construction project is a highly complex project that requires constant support from the government, time, patience and continuous efforts from the project team. The project is considered as a successful endeavor only if it meets or even exceeds the client’s expectations and satisfaction level (Time, 2015). The project management could assist in gaining competitive edge to the organization by making efficient use of resources, senior leadership support and following the standards. Apart from accommodating and housing all the participating world athletes for the Olympic Games, the Olympic Village construction project would also result in other substantial benefits to the country such as overcoming recessions, betterment of economic life, creation of jobs etc.
  • 23. References Ahmad, S. H., Bon, A. T., Rasi, R. M., Zuraidah, R., & Sie-Long, K. (2013). Project management scheduling through integrated PERT and Gantt Chart. Alvesson, M. (2012). Understanding organizational culture. Sage. Retrieved from: https://books.google.com /books?hl=en&lr=&id=BDsV8eHp0_MC&oi=fnd&pg=PP2&dq=organizational+cult ure+and+project&ots=745i7oxLzF&sig=9ujKpcqdkZXyXwpqeNzOUTAZIr 5 Bonaccorsi, A., Daraio, C., & Simar, L. (2014). Efficiency and economies of scale and scope in European universities. A directional distance approach (No. 2014- 08). Department of Computer, Control and Management Engineering, Universita'degli Studi di Roma" La Sapienza". Ebbesen, J. B., & Hope, A. (2013). Re-imagining the iron triangle: embedding sustainability into project constraints. PM World Journal, 2(III). Epstein, D., Jackson, R., & Braithwaite, P. (2011, May). Delivering London 2012: sustainability strategy. In Proceedings of the ICE-Civil Engineering (Vol. 164, No. 5, pp. 27-33). Thomas Telford. G., Ligthart, R., & Sydow, J. (2015). Collaboration in project networks: The case of the Dutch shipbuilding industry. Managing interorganizational relations. Geert-hofstede.com, (2015). United Kingdom - Geert Hofstede. [online] Retrieved from: http://geert-hofstede.com/united-kingdom.html [Accessed 11 Sep. 2015]. Hayes, J. (2014). The theory and practice of change management. Palgrave Macmillan. Hofstede, G. (2013). Dimensions of national cultures. Retrieved from: https://saylor.longsight.com/handle/1/10250 Hooghe, L., & Marks, G. (2013). The Authority of International Organizations: the effects of scope and scale. Unpublished manuscript, University of North Carolina, Chapel Hill, NC.
  • 24. Hubicki, M. (2014). Risk Management Plan. Retrieved from: http://www.mindsetting.net/assets/02-hubicki-coed-6150-risk-management- plan.pdf InfoQ, (2015). Investigation of Project Management Skills. [online] Available at: http://www.infoq.com/news/2015/08/investigation-project-management [Accessed 18 Sep. 2015]. Kauffeld, S., Lehmann-Willenbrock, N., & Grote, S. (2015). Dreamteam or Nightmare? Collaboration in Project Teams. In Applied Psychology for Project Managers (pp. 161-177). Springer Berlin Heidelberg. Kerzner, H. R. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Levering, R. C., Oerlemans, L. A. G. Schwalbe, K. (2013). Information technology project management. Cengage Learning. Retrieved from: https://books.google.com/books?hl=en&lr=&id=xbEWAAAAQBAJ&oi=fnd&pg=PP 1&dq=information+technology+in+project&ots=URs1Nip84r&sig=LRsCV0T0HpD 2Xb0vYzpVevJvBls Smits, K. C. M. (2013). Cross Culture Work:: Practices of Collaboration in the Panama Canal Expansion Program. Thompson, S. C., Kakar, A. K., & Hale, J. E. (2011). Breaking the Iron Triangle: The Impact of Information Sufficiency on Project Portfolio Decisions. In AMCIS. Time, P. (2015). Project Management: Eating the Elephant One Bite at a Time (News). [online] Nojitter.com. Available at: http://www.nojitter.com/post/240170496/project-management-eating-the- elephant-one-bite-at-a-time [Accessed 18 Sep. 2015]. Tsaturyan, T., & Müller, R. (2015). Integration and governance of multiple project management offices (PMOs) at large organizations. International Journal of Project Management, 33(5), 1098-1110.
  • 25. Valverde, M. (2012). Analyzing punishment: Scope and scale. Theoretical Criminology, 16(2), 245-253.