SlideShare a Scribd company logo
1 of 30
INDUSTRIAL PRESENTAION
ON
KOTA SUPER THERMAL POWER PLANT
COOLING TOWERS
BY: ABHISHEK MEENA
21/303
B1
Submitted To: A. BHARGAV
• HISTROY OF KTSPS
• CURRENT STATE (FROM REQUIREMENTS TO PRODUCTION QTY)
• EQUIPMENTS (INVOLING COOLING TOWERS)
• FUTURE PLANS
CONTENT
KSTPS is Rajasthan's first chief coal-fired power plant. It is
located on the west bank of the Chambal River in Kota in
Rajasthan. commissioned in 01 April 1983. With an approved
capacity of 1240 Megawatt.
The owner and operator of the thermal power plant is Rajasthan
Rajya Vidyut Utpadan Nigam Limited (RVUNL). Type of a sub
critical plant. The manufacturer of Boiler, Turbine and Generator
of the thermal power plant is BHEL Hyderabad, BHEL Bhopal and
BHEL Haridwar.
HISTROY
In a subcritical plant, steam pressure
is below 3200 psi and temperature is
below 1025 degrees Fahrenheit (550
degrees Celsius). Subcritical units
have efficiencies of between 33% and
37%; i.e. between 33% and 37% of
the energy in the coal is converted
into electricity.
It’s a plan divided into 5 stages for the completion. As follows:
• Stage 1 - Unit 1- 110 Megawatt – 01 April 1983
• Stage 1 - Unit 2- 110 Megawatt – 01 April 1984
• Stage 2 - Unit 3- 210 Megawatt – 11 March 1989
• Stage 2 - Unit 4- 210 Megawatt – 06 March 1990
• Stage 3 - Unit 5- 210 Megawatt – 18 July 1995
• Stage 4 - Unit 6- 195 Megawatt – 30 July 2003
• Stage 5 - Unit 7- 195 Megawatt – 31 August 2009
With an addition of new unit increasing production.
There are seven units in Operation and they are from Unit 1 to
Unit 7.
In Stage 1, the first and second units are commissioned in 01
April 1983 and 01 April 1984 respectively with an installed
capacity of 110 Megawatt.
In Stage 2, the third and fourth units are commissioned in 11
March 1989 and 06 March 1990 respectively with an installed
capacity of 210 Megawatt.
Stage 3, the fifth unit is commissioned in 18 July 1995 with an
installed capacity of 210 Megawatt.
Stage 4, the sixth unit is commissioned in 30 July 2003 with an
installed capacity of 195 Megawatt.
Stage 5, the seventh unit is commissioned in 31 August 2009.
With an addition of new unit increasing production.
CURRENT STATE
Unit Sizes – 1240 Megawatt (110 MW x 2 units + 210
MW x 3 units + 195 MW x 2 units)
Water Source – Chambal River
Primary Fuel – Coal
Secondary Fuel – Fuel Oil
Supplies – Inter state
EQUPMENTS
CAN BE DIVIDED INTO PORTION OR PARTS:
 CONTROL ROOM
 BOILER GENERATOR TURBINE ASSEMBLY
 COOLING TOWERS
CONTROL ROOM: The control room is significant in a
power plant. The control room
monitors the power plant’s control
systems, ensuring that the generators
and other elements of the power
plant are working correctly. That is
why it is an essential part of a power
plant, as what happens in the control
room can have far-reaching
consequences if it goes wrong.
Operation
control and
status
Operatores
Command
screen
Operatores
Control
room
screen of
operations
and status
BOILER
Boiler is main equipment on a thermal power station. It made up
of thousands of tubes Generally called water walls. And these
walls are insulated by the insulating material. Andwater is flowing
through these tubes. And the height of the boiler is approx. 55-60
meter. The plant efficiency is mainly depending upon boiler
efficiency.
Inside
view of
fire tube
boiler
TECHNICAL SPECIFICATION OF BOILER (2x110MW UNITS)
1. Type : Water tube Boiler
2. No. of Units. : Two.
3. Make : BHEL.
4. Capacity. : 375 tones per hour.
5. Steam Pressure. : 139 Kg./Cm
6. Efficiency : 86.6
The boiler drum contains both steam and water, a number of
accessories such as water level indicator, safety valve,
automaticalarms, pressure gauge etc.
The purpose of economizer is to heat feed water so as to
recover a part of heat, Which would otherwise be lost through
flue gases.
An Air preheater increases the temperature of the air supplied for
coal burning byderiving heat from flue gases
Water
Tube
Boiler
Drum
Boiler
Air Pre
Heater
Steam turbine
The dry and superheated steam from the superheater is fed to
the steam turbine through main valve. It converts Kinetic energy
to Mechanical Energy. ( i.e. The heat energy of steam passing
over the blades of turbine is converted into mechanical energy)
On the Basis of Principle of Operation :
i. Impulse turbine
ii. Impulse-reaction turbine
Impulse turbine, the drop in pressure of steam takes place only
in nozzles and not in moving blades
Impulse reaction turbine, this turbine, the drop in pressure of
steam takes place infixed (nozzles) as well as moving blades.
Technical data of steam turbine (210mw)
Rated Output : 210 MW.Rated
Speed. : 3000 rpm.Main
steam pressure. : 150 Kg./Cm
Main steam temperature. : 535
Reheat steam temperature. : 535
Weight of turbine. : 475 T approx.
Overall length. : 16.975 Mtrs.approx
A generator is a machine which converts mechanical energy into
electrical energy.
TURBO GENERATOR manufactured by B.H.E.L. and
incorporated with most modern design concepts and
constructional features, which ensures reliability, with
constructional & operational economy. Cooling medium
hydrogen is contained within frame & circulated by fans mounted
at either ends of rotor. The generator is driven by directly
coupled steam turbine at a speed of 3000r.p.m. the Generator is
designed for continuous operation at the rated output.
Technical data of turbo-generator:
Make: KWVC Craftworks, German Manufacturer BHEL
Rated Capacity: 247 MVARated
Output: 210 MWRated
Current: 9050 Amp.
Rated Terminal Voltage: 15.75 KVRated
Speed: 3000 RpmPower
Factor: 0.8 Lagging
Excitation Voltage: 310 V
Generator
A cooling tower is equipment used to reduce the temperature of
a water stream by extracting heat from water and emitting it to
the atmosphere. Cooling towers makeuse of evaporation
whereby some of the water is evaporated into a moving air
stream andsubsequently discharged into the atmosphere. As a
result, the remainder of the water is cooled down significantly.
Cooling
Towers
FUTURE PLANS
"India Thermal Power Analysis: Market Outlook to 2035,
Update 2023" is the latest report from GlobalData, the
industry analysis specialist.
The report discusses the thermal power market in the
the country and provides forecasts up to 2035.
The report gives information on the different types of power
of power sources available in the country.
Which resulting in changing the source to
another power plants in order to fullfill the
requirements.
Which also states no new establishment of
thermal power plant form the coming of BJP
as an rulling party. Giving more importance to
less and effective future options and joining
the race with the developed nations.
It states,
An overview of the country’s power market,
highlighting installed capacity trends (2010-
2035), generation trends (2010-2035) and
installed capacity split by various power
sources.
Stating and reduction in establishing new
thermal powerplants as an resolution to save
environment and as per the policy of INIDAN
GOVT..
THANKS
THE END

More Related Content

Similar to Ind lab.pptx

Kota super thermal power plant
Kota super thermal power plantKota super thermal power plant
Kota super thermal power plantR G Sanjay Prakash
 
Presentation 1 (2).pptx
Presentation 1 (2).pptxPresentation 1 (2).pptx
Presentation 1 (2).pptxNaveenJarwal1
 
CESC SGS project report
CESC SGS project reportCESC SGS project report
CESC SGS project reportSayanSarkar55
 
Kota super thermal power plant seminar
Kota super thermal power plant seminarKota super thermal power plant seminar
Kota super thermal power plant seminarCentury Rayon
 
kota super thermal power plant (kstps)
kota super thermal power plant (kstps)kota super thermal power plant (kstps)
kota super thermal power plant (kstps)vaibyfrndz
 
Ranjan NTPC KAHALGAON ppt
Ranjan  NTPC KAHALGAON pptRanjan  NTPC KAHALGAON ppt
Ranjan NTPC KAHALGAON pptRanjan kumar
 
Anil thermal power plant
Anil thermal power plantAnil thermal power plant
Anil thermal power plantANIL SHARMA
 
Vocational training at mejia thermal power plant
Vocational training at mejia thermal power plantVocational training at mejia thermal power plant
Vocational training at mejia thermal power plantNipak Banerjee
 
NTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPTNTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPTShivam Sharma
 
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC KantiTarun Kumar
 
KSTPS PPT Astha.pptx
KSTPS PPT Astha.pptxKSTPS PPT Astha.pptx
KSTPS PPT Astha.pptxssuser4c2635
 
Summer Training Presentation Kota Super Thermal Power Station
Summer Training Presentation Kota Super Thermal Power StationSummer Training Presentation Kota Super Thermal Power Station
Summer Training Presentation Kota Super Thermal Power StationFellowBuddy.com
 
Ppt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distributionPpt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distributionSuvamSahu2
 
NTPC Auraiya Industrial Training
NTPC Auraiya Industrial TrainingNTPC Auraiya Industrial Training
NTPC Auraiya Industrial TrainingAbhitendra Singh
 
Mejia Thermal Power Station
Mejia Thermal Power StationMejia Thermal Power Station
Mejia Thermal Power Stationsagnikchoudhury
 
THERMAL POWER PLANT
THERMAL POWER PLANTTHERMAL POWER PLANT
THERMAL POWER PLANTCyber4Tech
 
CSTPS training REPORT
CSTPS training REPORTCSTPS training REPORT
CSTPS training REPORTUday Wankar
 

Similar to Ind lab.pptx (20)

Kota super thermal power plant
Kota super thermal power plantKota super thermal power plant
Kota super thermal power plant
 
Presentation 1 (2).pptx
Presentation 1 (2).pptxPresentation 1 (2).pptx
Presentation 1 (2).pptx
 
CESC SGS project report
CESC SGS project reportCESC SGS project report
CESC SGS project report
 
Kota super thermal power plant seminar
Kota super thermal power plant seminarKota super thermal power plant seminar
Kota super thermal power plant seminar
 
NTPC DADRI.
NTPC DADRI.NTPC DADRI.
NTPC DADRI.
 
kota super thermal power plant (kstps)
kota super thermal power plant (kstps)kota super thermal power plant (kstps)
kota super thermal power plant (kstps)
 
Ranjan NTPC KAHALGAON ppt
Ranjan  NTPC KAHALGAON pptRanjan  NTPC KAHALGAON ppt
Ranjan NTPC KAHALGAON ppt
 
Anil thermal power plant
Anil thermal power plantAnil thermal power plant
Anil thermal power plant
 
Vocational training at mejia thermal power plant
Vocational training at mejia thermal power plantVocational training at mejia thermal power plant
Vocational training at mejia thermal power plant
 
NTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPTNTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPT
 
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC Kanti
 
KSTPS PPT Astha.pptx
KSTPS PPT Astha.pptxKSTPS PPT Astha.pptx
KSTPS PPT Astha.pptx
 
Summer Training Presentation Kota Super Thermal Power Station
Summer Training Presentation Kota Super Thermal Power StationSummer Training Presentation Kota Super Thermal Power Station
Summer Training Presentation Kota Super Thermal Power Station
 
Ppt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distributionPpt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distribution
 
kstps training report
kstps training reportkstps training report
kstps training report
 
K.s.t.p.s. ppt
K.s.t.p.s.  pptK.s.t.p.s.  ppt
K.s.t.p.s. ppt
 
NTPC Auraiya Industrial Training
NTPC Auraiya Industrial TrainingNTPC Auraiya Industrial Training
NTPC Auraiya Industrial Training
 
Mejia Thermal Power Station
Mejia Thermal Power StationMejia Thermal Power Station
Mejia Thermal Power Station
 
THERMAL POWER PLANT
THERMAL POWER PLANTTHERMAL POWER PLANT
THERMAL POWER PLANT
 
CSTPS training REPORT
CSTPS training REPORTCSTPS training REPORT
CSTPS training REPORT
 

Recently uploaded

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 

Recently uploaded (20)

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 

Ind lab.pptx

  • 1. INDUSTRIAL PRESENTAION ON KOTA SUPER THERMAL POWER PLANT COOLING TOWERS BY: ABHISHEK MEENA 21/303 B1 Submitted To: A. BHARGAV
  • 2. • HISTROY OF KTSPS • CURRENT STATE (FROM REQUIREMENTS TO PRODUCTION QTY) • EQUIPMENTS (INVOLING COOLING TOWERS) • FUTURE PLANS CONTENT
  • 3. KSTPS is Rajasthan's first chief coal-fired power plant. It is located on the west bank of the Chambal River in Kota in Rajasthan. commissioned in 01 April 1983. With an approved capacity of 1240 Megawatt. The owner and operator of the thermal power plant is Rajasthan Rajya Vidyut Utpadan Nigam Limited (RVUNL). Type of a sub critical plant. The manufacturer of Boiler, Turbine and Generator of the thermal power plant is BHEL Hyderabad, BHEL Bhopal and BHEL Haridwar. HISTROY
  • 4. In a subcritical plant, steam pressure is below 3200 psi and temperature is below 1025 degrees Fahrenheit (550 degrees Celsius). Subcritical units have efficiencies of between 33% and 37%; i.e. between 33% and 37% of the energy in the coal is converted into electricity.
  • 5. It’s a plan divided into 5 stages for the completion. As follows: • Stage 1 - Unit 1- 110 Megawatt – 01 April 1983 • Stage 1 - Unit 2- 110 Megawatt – 01 April 1984 • Stage 2 - Unit 3- 210 Megawatt – 11 March 1989 • Stage 2 - Unit 4- 210 Megawatt – 06 March 1990 • Stage 3 - Unit 5- 210 Megawatt – 18 July 1995 • Stage 4 - Unit 6- 195 Megawatt – 30 July 2003 • Stage 5 - Unit 7- 195 Megawatt – 31 August 2009 With an addition of new unit increasing production.
  • 6. There are seven units in Operation and they are from Unit 1 to Unit 7. In Stage 1, the first and second units are commissioned in 01 April 1983 and 01 April 1984 respectively with an installed capacity of 110 Megawatt. In Stage 2, the third and fourth units are commissioned in 11 March 1989 and 06 March 1990 respectively with an installed capacity of 210 Megawatt. Stage 3, the fifth unit is commissioned in 18 July 1995 with an installed capacity of 210 Megawatt. Stage 4, the sixth unit is commissioned in 30 July 2003 with an installed capacity of 195 Megawatt. Stage 5, the seventh unit is commissioned in 31 August 2009. With an addition of new unit increasing production.
  • 7. CURRENT STATE Unit Sizes – 1240 Megawatt (110 MW x 2 units + 210 MW x 3 units + 195 MW x 2 units) Water Source – Chambal River Primary Fuel – Coal Secondary Fuel – Fuel Oil Supplies – Inter state
  • 8. EQUPMENTS CAN BE DIVIDED INTO PORTION OR PARTS:  CONTROL ROOM  BOILER GENERATOR TURBINE ASSEMBLY  COOLING TOWERS
  • 9. CONTROL ROOM: The control room is significant in a power plant. The control room monitors the power plant’s control systems, ensuring that the generators and other elements of the power plant are working correctly. That is why it is an essential part of a power plant, as what happens in the control room can have far-reaching consequences if it goes wrong.
  • 12. BOILER Boiler is main equipment on a thermal power station. It made up of thousands of tubes Generally called water walls. And these walls are insulated by the insulating material. Andwater is flowing through these tubes. And the height of the boiler is approx. 55-60 meter. The plant efficiency is mainly depending upon boiler efficiency.
  • 14. TECHNICAL SPECIFICATION OF BOILER (2x110MW UNITS) 1. Type : Water tube Boiler 2. No. of Units. : Two. 3. Make : BHEL. 4. Capacity. : 375 tones per hour. 5. Steam Pressure. : 139 Kg./Cm 6. Efficiency : 86.6
  • 15. The boiler drum contains both steam and water, a number of accessories such as water level indicator, safety valve, automaticalarms, pressure gauge etc. The purpose of economizer is to heat feed water so as to recover a part of heat, Which would otherwise be lost through flue gases. An Air preheater increases the temperature of the air supplied for coal burning byderiving heat from flue gases
  • 19. Steam turbine The dry and superheated steam from the superheater is fed to the steam turbine through main valve. It converts Kinetic energy to Mechanical Energy. ( i.e. The heat energy of steam passing over the blades of turbine is converted into mechanical energy)
  • 20. On the Basis of Principle of Operation : i. Impulse turbine ii. Impulse-reaction turbine Impulse turbine, the drop in pressure of steam takes place only in nozzles and not in moving blades Impulse reaction turbine, this turbine, the drop in pressure of steam takes place infixed (nozzles) as well as moving blades.
  • 21. Technical data of steam turbine (210mw) Rated Output : 210 MW.Rated Speed. : 3000 rpm.Main steam pressure. : 150 Kg./Cm Main steam temperature. : 535 Reheat steam temperature. : 535 Weight of turbine. : 475 T approx. Overall length. : 16.975 Mtrs.approx
  • 22. A generator is a machine which converts mechanical energy into electrical energy. TURBO GENERATOR manufactured by B.H.E.L. and incorporated with most modern design concepts and constructional features, which ensures reliability, with constructional & operational economy. Cooling medium hydrogen is contained within frame & circulated by fans mounted at either ends of rotor. The generator is driven by directly coupled steam turbine at a speed of 3000r.p.m. the Generator is designed for continuous operation at the rated output.
  • 23. Technical data of turbo-generator: Make: KWVC Craftworks, German Manufacturer BHEL Rated Capacity: 247 MVARated Output: 210 MWRated Current: 9050 Amp. Rated Terminal Voltage: 15.75 KVRated Speed: 3000 RpmPower Factor: 0.8 Lagging Excitation Voltage: 310 V
  • 25. A cooling tower is equipment used to reduce the temperature of a water stream by extracting heat from water and emitting it to the atmosphere. Cooling towers makeuse of evaporation whereby some of the water is evaporated into a moving air stream andsubsequently discharged into the atmosphere. As a result, the remainder of the water is cooled down significantly.
  • 27. FUTURE PLANS "India Thermal Power Analysis: Market Outlook to 2035, Update 2023" is the latest report from GlobalData, the industry analysis specialist. The report discusses the thermal power market in the the country and provides forecasts up to 2035. The report gives information on the different types of power of power sources available in the country.
  • 28. Which resulting in changing the source to another power plants in order to fullfill the requirements. Which also states no new establishment of thermal power plant form the coming of BJP as an rulling party. Giving more importance to less and effective future options and joining the race with the developed nations.
  • 29. It states, An overview of the country’s power market, highlighting installed capacity trends (2010- 2035), generation trends (2010-2035) and installed capacity split by various power sources. Stating and reduction in establishing new thermal powerplants as an resolution to save environment and as per the policy of INIDAN GOVT..