SlideShare a Scribd company logo
1 of 16
Hanoi – Hochiminh city railway line                         Do Vang Bridge’s construction
 bridges safety improvement project                    technology of beam casted on
scaffolding


                  CHAPTER II: TECHNOLOGY PROCESS
I. CONSTRUCTION SEQUENCES
   Concrete beams of Do Vang Bridge are casted in place on the scaffolding.
   Construction scaffoldings are made up of shape steel including of: longitudinal beam
H200 and horizontal beam and scaffolding system for supporting side formworks.
   Side formworks, bottom formworks, internal formworks with splint system, through
bar must be stably, firmly throughout concreting process.
   After completion span 2 and span 5, formwork scaffolding will be transferred to
construct the next spans.
   Concrete shall be provided from batching plan at Site with capacity 60m 3/h to the
constructed position by truck mixer and concrete pump.
   • Construction sequences
       + Step 1: Land levelling at position of girder construction, filling sand and
       compacting to K95. Installing the concrete plank 1x1x0.2m.
       + Step 2: Installing the scafolding, longitudinal beam H200 and horizontal beam
       H200
       + Step 3: Testing of scaffold.
       + Step 4: Install external formwork, side formwork
       + Step 5: Install reinforcing steel, pouring concrete
       + Step 6: Stretch prestressed cable.
       + Step 7: Removal of scaffolding, internal formwork, pushing scaffolding
       system.
       + Step 8: Connect projecting reinforcement couplers of diagraphm,
       reinforcement, diaphragm formwork. Placing concrete and stressing horizontally
       prestressed cable of diaphragm.
       + Step 9: Construction of the next span.
II. TECHNOLOGY STEPS
1. Land levelling
    Land levelling at position of girder construction, filling sand and compacting to K95.
Installing the concrete plank 1.2x1.2x0.18m2. Production and erection of scaffolding
   Scaffolding, formwork must be designed to resist any unfavouble displacement during
superstructure construction process.
   Construction scaffolding is included:
       + Supporting scaffolding of side formwork
       + Installing the scafolding, longitudinal beam H200 and horizontal beam H200



                                             5
Hanoi – Hochiminh city railway line                           Do Vang Bridge’s construction
 bridges safety improvement project                      technology of beam casted on
scaffolding




                      Figure 1: Span structure’s construction scaffolding
3. Testing scaffolding
   This test aims to remove the settlement of scaffolding system, check the pressure
bearing ability of scaffolding. Load test results must be reported immediately to The
Engineer.
4. Install beam formwork
• Concreting formwork design

       + Bottom formwork is combined by flat formwork 1x2m, placed directly on
       diaphragm steel shape H200..

       + Side formwork and flange beam is combined by flat formwork and special
       formwork put on modules of steel shape H200x200, wihch are associated with
       diagram steel shape H200x200.

       +     Core formworks shall be fabricated by modulus 0.25x1.0m, fitness, easy
       working, and convenient removing. The formwork is designed by the type of



                                               6
Hanoi – Hochiminh city railway line                          Do Vang Bridge’s construction
 bridges safety improvement project                     technology of beam casted on
scaffolding

       modulus 1m including formworks- supporting bars- bands, ready erected on the
       ground and hoisted into its position.
       + Elevation of formwork at each section must be included design deflection of
       the bridge and deflection resulting from pre-stressing and deformation of
       scaffolding.
• Install bottom formwork
   Erection sequence as follows:
       + Formwork boards are placed directly on the diaphragm steel shape H200x200
       + Erection of formwork boards with the length 2m is in the direction of bridge
       and parallel to connecting centre line between two piers.
       + After completing bottom formwork installations, in a maximum distance of 4m
       between sections, measure the level to adjust the level of beam bottom.
       + Insert the steel wedge below the formwork to adjust the level of formwork
       surface (beam bottom).
       + Installation of a special formwork at pier position
• Installation of external wall formwork
   Erection sequence as follows:
      + Installation of outside scaffolding system and protective handrail.
      + Completely erecting formworks modulus and supporting frame for beam web
      consisting of: web formworks, supporting frames.
       + Hoisting each formwork modulus and supporting frames into exact position.

       + Adjust level of formworks.

       + Tighten the connection bolts, fix geometric position of formwork segment and
       install the next segment until finish a span of beam.

• Installation of core formwork

   The installing sequence shall be as follows:

       + Formwork system and supporting frame of core formwork shall be installed in
       every modulus at 4~6m length, suitable with the capacity of the hoist.

       + Hoisting each formwork modulus into exact position.


                                               7
Hanoi – Hochiminh city railway line                        Do Vang Bridge’s construction
 bridges safety improvement project                   technology of beam casted on
scaffolding

       + Adjusting elevation and coordinate of formwork.

       + Tighten the connection bolts, fix geometric position of formwork segment and
       install the next formwork segment until finish a concreting segmentation.

5. Beam bearing installation

   The Contractor will install bearing before casting concrete. Detailed construction is
follows:

• Step 1

       Cleanning reinforcement of bearing stone, installing formwork of bearing stone,
       casting non-shrinkage motar for bearing stone construction.

• Step 2

       When the motar of bearing stone meets requirements of strength, locating exactly
       bearing position, defining the horizontal and vertical position of bearing stone,
       installing the bearing.

6. Installation of reinforcement, duct and high strength cable
• Installation of reinforcement
   Reinforcement is fabricated at yard according to the designed geometric dimension,
numbered and bundled for hoisting into installed position.

    Sequence for installing rebar will be prepared by construction team and informed to
foreman during installation of beam rebar with the below principles:

       + Fully installing bars in accordance with the size and location indicated in the
       design.

       + Steel structural members must be removed or fixed at designed position by
       using supporting bar, chock or tie to resist the excessive movement or bending
       during construction process.

       + The distance from formwork surface to steel structural member must be
       remained by using supporting bars and chocks. The chocks must be placed in a
       suitable distance to make the formwork be free from cracking or excessive
       deflection.
                                            8
Hanoi – Hochiminh city railway line                          Do Vang Bridge’s construction
 bridges safety improvement project                     technology of beam casted on
scaffolding

       + The chocks must be enough hardness, strength and suitable shape to not form
       holes around them.

       + The position tolerance for internal reinforcement of concrete:

                Bar detail and bending dimension for the rebars must satisfy the
                 requirement stipulated in Section 5.11 of Bridge Construction
                 Instruction AASHTO LRFD 98.

                The installation tolerance for the super structure as follows:

                              d ≤ 200   200 < d < 500 500 <d ≤ 2000        d>2000

        Tolerance (mm)            5           10             20               30

       In there: d may be:

                Dimension by measurement direction (mm)

                   Height of cross section (mm)

• Installation of Duct and high strength Cable

   Install holing duct:

       + The holing ducts for high strength tendon are put into designed position before
       concreting. The duct is installed segmentally (according to produced length) ducts
       are connected together with linking pipe and joint tape around to prevent motar
       from inner leakaging.

       + To fix ducts into reinforcement mesh, using D6 bars supporting below and
       binding into the mesh at each coordinates adjusting position of the strand
       according to design requirements.

       + The head of duct is inserted in the anchor head fixed into beam formwork.

       + The duct is associated to ventilation pipe and grouting chute at the lowest and
       the highest points to ensure the pumped grout will completely seal the duct, free
       from air bubble.




                                              9
Hanoi – Hochiminh city railway line                            Do Vang Bridge’s construction
 bridges safety improvement project                       technology of beam casted on
scaffolding




  Figure 5 : The process of connection cladding             Figure 6: Setting mortar




                                                                         Wrap joint tape
                                                                         to be sealed and
                                                                         free from grout
                                                                         leakage




                                 Figure 7: Field duct connection

   Install duct and high strength tendon:

       + Install duct and high strength tendon, using cupler to connect tendon.

       + High strength tendon will be cut up to designed length, bundled and inserted
       into the duct then put into place.
       + Fix cable into head of dead end, locate the dead end.
   Notes when installing duct and tendon:
       +     Duct position must be installed in right designed place within allowed
       tolerance.
       + Curve of cable must be smooth when visually check.

                                               10
Hanoi – Hochiminh city railway line                          Do Vang Bridge’s construction
 bridges safety improvement project                     technology of beam casted on
scaffolding

       + Duct must have enough tightness so that mortar can not run into there.
7. Placing concrete for beam
• Concrete mix design
   Concrete of approach beam of Do Vang bridge has relatively dimension and quantity,
thus mix design work greatly affects the concrete quality. The mix design shall be in
accordance with requirements of Specification.
   Concrete shall ensure to be enough strength, waterproofing as requirement of design
also meet demand of yield to ease the construction with minimum cement content.
   Minimum compressive strength of cylinder specimen at 28 days shall be 40Mpa to
ensure concrete reach to strength 40Mpa as designed.
   In any case, the required slump of concrete shall be 14 ± 2 cm. It shall be rejected if it
is not as requirement. Do not add water to fresh concrete.
   Concrete shall have enough adhesiveness and flexibility to ensure it is not segregated
throughout concrete transporting and placing process.
       Water-cement ratio in concrete mix shall be less than 0.40.
       Concrete mortar shall have setting time over 6 hours.
       The parameters of beam concrete:
       + Grade:                                   40 Mpa
       + Slump:                                   14 ± 2 cm

• Concrete materials

   Beam concrete of Do Vang Bridge as shown in the Specification of Project has
cylinder strength 40MPa.

   Mix design shall conform to Specification of Project.

   Admixture of concrete is produced by Sika manufacturer. This is a super-plastically
high-tech substance at the thirdly versioned polyme origin to push concrete harden. The
admixture will affect on the below characteristics of concrete:

       + The ability of reducing water is so high.

       + To be deliveried in a great distance.

                                             11
Hanoi – Hochiminh city railway line                            Do Vang Bridge’s construction
 bridges safety improvement project                       technology of beam casted on
scaffolding

         + The yield strength is high (decrease the works of placing and compacting)

         + Boost the development of strength

         + Improve the ability of creeping, shrinkage.

• Construction plan layout

   + Currently, construction plan of the Do Vang Bridge has already leveled off material
store yard, reinforcing yard to ready for installing, testing load and placing concrete for
beam.
   + Night lighting system: The Contractor shall arrange fully lighting system along the
service road, beam and all constructing positions throughout the concreting process. The
bulbs used during construction have capacity 500W and shall be disposed at the distance
of 5÷10m per bulb. The minimum illumination level for concreting is 30lux/m2. (When it
comes to horizontal concrete plane – Refer to “Bridge constructing manual” composed by
Pham Huy Chinh- Construction Publisher 2007).
   + Standby power system: The Contractor has standby power system 250KVA in case
of power loss. This system shall be always maintained and checked to find out defects
and treat immediately.

• Construction Equipment

    No                Equipment              Unit        Quantity             Note

    01      Mixing plant 60m3/h              each          01

    02      Mixer Truck                      each          03

    03      Pumpcrete machine Puztmaiter     each          02

    04      Generator 250KVA                 each          01

    05      Crane 40T                        each          01

    06      Purchase tackle                  each          04

    07      Jacking and oil pump house         Set         02

    08      Mortar mixer and pump              Set         02



                                            12
Hanoi – Hochiminh city railway line                        Do Vang Bridge’s construction
 bridges safety improvement project                   technology of beam casted on
scaffolding


    09     Surveyor's level                 each        01

    10     Tachometer                       each        01

    11     Vibrators                        each        15

    12     Pumpcrete pipe                    m         250

    13     Welding machine 400A             each        04

    14     Pump 60m3/h                      each        02

• Arrangement manpower

    No                 Equipment            Unit    Quantity              Note

    01     Engineering                     person       03

    02     Investigation                   person       02

    03     Woker drive crane               person       04

    04     Worker support crane            person       06

    05     Woker drive electric            person       02

    06     Woker drive mixing plant        person       02

    07     Worker drive shovel             person       02

           Worker drive pumpcrete                       02
    08                                     person
           machine

    09     Woker weld                      person       15

    10     Woker jack                      person       05


• Concrete mixing

   Use batching plants that can automatically measure and weigh at Site. The scales shall
be checked accuracy, meet the Specification of Project as stipulated.
   Concrete of each batch shall be in accordance with Specification as required.
   The slump of concrete must conform to requirements. Therefore, before each concrete
placing time, determine the material moisture to caculate suitable water content for
                                           13
Hanoi – Hochiminh city railway line                          Do Vang Bridge’s construction
 bridges safety improvement project                     technology of beam casted on
scaffolding

concrete mix.
• Provide concrete

   Concrete shall be provided from batching plant to constructed position by truck mixer
and concrete pump.
    Time from mixing, placing to compacting concrete is not over 90 minutes to ensure
the works of concreting finish before concrete setting.
   Components and slump of concrete mix shall be tested and trial pumped to ensure the
quality of concrete and construction conditions simutanously suitalbe with technical
funtions of pump.

   When construction in hot weather, the external surface of concrete must be covered or
whitened to restrict sunlight effect causing hot concrete.

• Method for decrease concrete mix temperature

   The Contractor intends to cast concrete from 16 p.m to 10 a.m next morning. In case
of daytime construction, the Contractor shall not construct on the day that temperature is
over 35°C.

   Construction in nightime to reduce temperature, direct sunlight causing hot pump pipe
and newly placed concrete.

   Concrete mix temperature from batching plant shall be controlled to not excess 25°C
and when placing it is not over 35°C. For these purposes, beside construction in nightime
to decrease temperature, the Contractor also use the following methods to decrease
aggregate temperature:

       + Spray water on balast, gravel: Ballast, gravel in store yard shall be sprayed
       periodcally for keeping wet surface to create evaporating mechanism so that
       reducing agrregate temperature.

       + Use cool water to mix concrete, water tankers shall be covered from sunlight.

• Pour concrete

       + Concrete is poured by mix truck and pumping machine

                                             14
Hanoi – Hochiminh city railway line                          Do Vang Bridge’s construction
 bridges safety improvement project                     technology of beam casted on
scaffolding

    Concrete placing direction: Concrete shall be casted from the low head to the high
head of beam and placed alternately on all beam webs, ensure that height defference
between these webs is not over 50cm.

    Pour concrete vertically by each segment that splayed a 45 0 angle against to horizontal
direction.

    Attention when pour concrete

       + Slump of concrete must be as required. Therefore, before each concreting
       batch, it is necessary to determine the moisture of material to calculate the suitable
       water content for concrete aggregate.

       + The height of the concrete to fall is not more than 1.5 m to avoid segregating.

       +     Fresh concrete is poured into formwork by a small amount and using methods
       to remain rebar not movement during concreting process.

       + Mixxing speed must ensure that when pouring the above layer, the below layer
       has not yet cured to create perfect bonds between layers.

•   Tamping

       + In the concrete mix, the Contractor has used superplasticizer with high
       mobility of manufacturer Sika to decrease significantly placing and compacting
       work.

       + Fresh concrete must be placed into formwork and compacted for each layer
       from 250mm to 300mm thickness. By this time, compacting to the previous
       concrete layers.

       + During compaction, at the position near ducts, pay attention to advoid touching
       the duct to be broken. Do not use vibrator to push concrete.

       + Special attention to concrete quality at anchor heads.

• Curing concrete



                                             15
Hanoi – Hochiminh city railway line                         Do Vang Bridge’s construction
 bridges safety improvement project                    technology of beam casted on
scaffolding

   Curing for concrete beam casted on scaffolding is conducted immediately after
finishing a surface area of concrete beams. Usually use wet sacks to cover on concrete
surface around one hour or when the concrete surface will begin to dry.

   After finishing surface and until the surface can resist water (usually after 2 hours of
concreting) must water regularly to the concrete surface which face is finished. When
finishing pouring concrete for girder segments, watering to cure all concrete and wall
formwork. After removing the formwork must water to the concrete regularly throughout
day and nighttime.

   Water for curing process shall be fresh water used to mix concrete.

   Setting time must prolong at least 7 days from finishing of beam concrete.

• Emegency occurrences that may happen and resolving method.

    Treatment method in case of work suspension because of Force Majeure.

   The concreting work shall not be executed in the following cases: hard rain, flood,
storm, or the conditions for placing concrete still not ready…

   In the event that concreting process is suspended because of the interruption in
concrete providing source (long-time traffic jam, accident…) the problem shall be
resolved as below:

   + Use the standby mixing plants at the Site.

   + If the quantity of concrete required to place is further more than capacity of standby
   mixing plants, the construction must be suspended and the Contractor continuously
   compacts to finish the casted concrete. In the vertical direction, concrete shall be
   made by diagonal section bias an angle ≤ 450 against horizontal plane. This special
   construction joint shall be treated, roughed in accordance with procedure and
   specification for the next concreting stage.

    Measure to prevent honeycomb:




                                            16
Hanoi – Hochiminh city railway line                      Do Vang Bridge’s construction
 bridges safety improvement project                 technology of beam casted on
scaffolding

   Honeycomb at concrete is easy to happen because of special shape of box girder.
Positions where honeycomb can happen and method which is carried out in process of
pouring concrete to prevent honeycomb is showed in below table:



  No.     Position where honeycomb can         Reason             Preventative measure
                     happen

    1    The lower chamfer of web        Concrete pouring to Need to guide workers
                                         web is easy to flow not hesitate when
                                         to bottom slab      compact concrete
                                         Workers      hesitate
                                         when        compact
                                         concrete     because
                                         concrete flow to
                                         bottom slab
                                         The lower chamfer       The vibrating tampers
                                         of web can’t be         are often associated
                                         compacted       well    with     a    burning
                                         because outside web     bamboo or a straight
                                         isn’t straight          pipe to pass thread
                                                                 along     shape    of
                                                                 diagonal web
                                                                 Projector      flashlight
                                                                 into the side of web
                                                                 These parts will be
                                                                 hammered handwork
                                                                 by wooden hammer
                                         It is difficult to Vibrator       will   be
                                         compact by vibrator associated with a
    2    The angle of bottom slab
                                                             straight bar to compact
                                                             that part.




                                         17
Hanoi – Hochiminh city railway line                        Do Vang Bridge’s construction
 bridges safety improvement project                   technology of beam casted on
scaffolding


                                          The claddings will Pour concrete slowly
    3    The lower part of cladding       prevent compacting and compact concrete
                                          concrete below them more carefully
    4    The anchorage zone               Much reinforcement     Compact carefully



    Beam casting formwork

 No.               Problem                                 Resolve
        Load capacity of formwork     Before fabricating the formwork shall be
                                      caculated, designed to ensure enough load
   1
                                      capacity. Checking their quality and geometrical
                                      dimension before leaving workshop.
        Formwork that is bad The formworks shall be checked, taken-over in
        quality, defected during quality  and     geometrical    dimension     to
   2
        transportation           immediately discover and substitute the defected
                                 boards.
        The camber of formwork During installation, the formwork elevation shall
        resulting from designed be adjusted to be suitable with the camber.
   3    camber of the bridge,
        stressing prestressed cable,
        scaffolding deformation

8. Prestressed cable tension

• Preparation work

   It is necessary to make sure that before constructing all persons attending directly in
stretching works, especially technicants and stretching team leaders must have full
knowledge of stretch controlling steps to ensure the technical quality and safety
regulation.

   Check concrete strength (taking sample before stressing). The strength shall reach to
90%Rtk (90%*40Mpa = 36 for cylinder sample).

   Check jack, pump, jack bracket, chain hoist and work platform.

                                           18
Hanoi – Hochiminh city railway line                           Do Vang Bridge’s construction
 bridges safety improvement project                      technology of beam casted on
scaffolding

       + Jack, pump for stressing shall be checked and approved before using.

       + Jack and pump shall be inspected by specialist authority.

       + Jack shall be inspected in the following moments:

           • Before using to avoid accident or occurrence.

           • Change jack set.

       + Anchor test:

           • Anchor using for Project must be in accordance with Specification and
           inspected to pass testing criterium and approved by Engineer.

           • Anchor using for installation shall be free from crack, warp, and the chap
           must be sealed with anchor.

   Show stressing steps on the visble positions for the stressing team leader.

   Fill up enough points stipulated in stressing note.

• Stressing equipment.

    Prestressed Cable

   High strength cable shall use kind of tendon as 7 lowly saged plies 12 strands 15.2m
bundled cable Grade 270 according to ASTM A416 – 90A standard.

                        No                Item                Value

                         1      Nominal diameter            15.2 mm

                         2      Area of cross section       140 mm2

                         3      Ultimate strength          1860 Mpa

                         4      Yield point stress         1670 MPa

   Prestressed cable shall be protected in store that has screen, be dry, apart 30cm from
the ground.



                                                 19
Hanoi – Hochiminh city railway line                                 Do Vang Bridge’s construction
 bridges safety improvement project                            technology of beam casted on
scaffolding

   Pretressed cable must have Certificate of Producer approved by Employer and
Engineer.

   Test for tendon in accordance with Design Document and criterium: breaking force,
elastic modulus, yeild strength, elongation, dimension of each ply in tendon, condition of
external surface. Any change that not be in accordance with Design Document shall be
approved in writing by Design Unit, Employer, Engineer beforce constructing.

    Anchor

   Use imported anchor of OVM manufacturer for cable 15,2mm .

   Imported anchor must have Quality Certificate of Manufacturer.

    Jack

   All of jacks, oil pumps shall be inspected before using.

                 Jack                                  Area      Strain     Sroke
                                      Type of
   No                                               pittong       max      pittong       Note
            Name         Mark          Pump
                                                       (cm2)      (KN)      (mm)

                                                                                      Horizontally
    1     YCQ500Q        0707         ZB4 - 500        1000       5000       200
                                                                                       stretching

                                                                                      Horizontally
    2     YCQ500Q        1001         ZB4 - 500        1000       5000       200
                                                                                       stretching

• Prestressed cable tension

   Use one-head tensioning method. Using jack 500T applying for tendon as 7 lowly
saged plies 12 strands 15.2m bundled cable.

   Stretch every twin cables symmetrically through centreline of beam in the following
sequence:

        + From centerline to outside.

        + From neutral axis to outside.

   Sequence of stressing tendons on each segment: Stressing longitudinally then
stretching horizontally prestressed cable of bridge.
                                                  20

More Related Content

What's hot

Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structuresRithika Ravishankar
 
Form work_Advanced Construction Technology (Semester-6), Civil Engineering
Form work_Advanced Construction Technology (Semester-6), Civil EngineeringForm work_Advanced Construction Technology (Semester-6), Civil Engineering
Form work_Advanced Construction Technology (Semester-6), Civil EngineeringA Makwana
 
Speedy construction presentation
Speedy construction presentationSpeedy construction presentation
Speedy construction presentationsomitra bhardwaj
 
Forms and materials for speedy construction
Forms and materials for speedy constructionForms and materials for speedy construction
Forms and materials for speedy constructionMudassir khan
 
Formwork-Types and Their Advantages
Formwork-Types and Their AdvantagesFormwork-Types and Their Advantages
Formwork-Types and Their AdvantagesJay1997Singhania
 
Industrial construction
Industrial constructionIndustrial construction
Industrial constructionCharlie Gupta
 
Slip form Construction Technology
Slip form Construction TechnologySlip form Construction Technology
Slip form Construction TechnologyDarshit
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shutteringKishor Ade
 
Concrete framework
Concrete frameworkConcrete framework
Concrete frameworkJustin Myint
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete constructionJenilPatel22
 
Reinforcement ppt assignment
Reinforcement ppt assignmentReinforcement ppt assignment
Reinforcement ppt assignmenthailnur1794
 
house construction
house constructionhouse construction
house constructionAbhinav Saha
 

What's hot (20)

Formwork
FormworkFormwork
Formwork
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
Form work_Advanced Construction Technology (Semester-6), Civil Engineering
Form work_Advanced Construction Technology (Semester-6), Civil EngineeringForm work_Advanced Construction Technology (Semester-6), Civil Engineering
Form work_Advanced Construction Technology (Semester-6), Civil Engineering
 
construction study project sjce ctm
construction study project sjce ctmconstruction study project sjce ctm
construction study project sjce ctm
 
Speedy construction presentation
Speedy construction presentationSpeedy construction presentation
Speedy construction presentation
 
PreCast Construction
PreCast ConstructionPreCast Construction
PreCast Construction
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Form Work
Form Work Form Work
Form Work
 
Forms and materials for speedy construction
Forms and materials for speedy constructionForms and materials for speedy construction
Forms and materials for speedy construction
 
Formwork-Types and Their Advantages
Formwork-Types and Their AdvantagesFormwork-Types and Their Advantages
Formwork-Types and Their Advantages
 
Formwork
FormworkFormwork
Formwork
 
Industrial construction
Industrial constructionIndustrial construction
Industrial construction
 
Speedy construction
Speedy constructionSpeedy construction
Speedy construction
 
Slip form Construction Technology
Slip form Construction TechnologySlip form Construction Technology
Slip form Construction Technology
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
 
Concrete framework
Concrete frameworkConcrete framework
Concrete framework
 
Table formwork
Table formwork Table formwork
Table formwork
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Reinforcement ppt assignment
Reinforcement ppt assignmentReinforcement ppt assignment
Reinforcement ppt assignment
 
house construction
house constructionhouse construction
house construction
 

Similar to 04.chapter ii

Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxtoddr4
 
Internship project Report Gammon India pvt. ltd.
Internship project Report Gammon India pvt. ltd.Internship project Report Gammon India pvt. ltd.
Internship project Report Gammon India pvt. ltd.SHWETABH SINHA
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02Minh Bui Si
 
ADTO Ringlock System introduction and projects list
ADTO Ringlock System introduction and projects listADTO Ringlock System introduction and projects list
ADTO Ringlock System introduction and projects listColin Cai
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated ColumnAnees Khan
 
Construction Technology
Construction TechnologyConstruction Technology
Construction TechnologySwapnilGorade1
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentationRahul bhatnagar
 
Building Technology 1
Building Technology 1Building Technology 1
Building Technology 1chongyih2
 
Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insituLingWei11
 
Slipform construction
Slipform constructionSlipform construction
Slipform constructionErankajKumar
 
Industrialised Building System
Industrialised Building SystemIndustrialised Building System
Industrialised Building Systemjisunfoo
 
Guidelines on technical_specifications_for_the_installation_of_telecommunicat...
Guidelines on technical_specifications_for_the_installation_of_telecommunicat...Guidelines on technical_specifications_for_the_installation_of_telecommunicat...
Guidelines on technical_specifications_for_the_installation_of_telecommunicat...Patrice Adjei
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptxssuser480182
 
2016-03-17 Velocity 2_Construction of Steel Dome
2016-03-17 Velocity 2_Construction of Steel Dome2016-03-17 Velocity 2_Construction of Steel Dome
2016-03-17 Velocity 2_Construction of Steel DomeWAIKIT CHEOR
 

Similar to 04.chapter ii (20)

Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
 
Closure Report
Closure ReportClosure Report
Closure Report
 
Internship project Report Gammon India pvt. ltd.
Internship project Report Gammon India pvt. ltd.Internship project Report Gammon India pvt. ltd.
Internship project Report Gammon India pvt. ltd.
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02
 
ADTO Ringlock System introduction and projects list
ADTO Ringlock System introduction and projects listADTO Ringlock System introduction and projects list
ADTO Ringlock System introduction and projects list
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated Column
 
Construction Technology
Construction TechnologyConstruction Technology
Construction Technology
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentation
 
Metroppt
MetropptMetroppt
Metroppt
 
Building Technology 1
Building Technology 1Building Technology 1
Building Technology 1
 
Bridge-SGI-01_Pranoti.pdf
Bridge-SGI-01_Pranoti.pdfBridge-SGI-01_Pranoti.pdf
Bridge-SGI-01_Pranoti.pdf
 
Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insitu
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
8课
8课8课
8课
 
Railway over bridge
Railway over bridgeRailway over bridge
Railway over bridge
 
Industrialised Building System
Industrialised Building SystemIndustrialised Building System
Industrialised Building System
 
Microtunel Construction / Secant Pile
Microtunel Construction / Secant PileMicrotunel Construction / Secant Pile
Microtunel Construction / Secant Pile
 
Guidelines on technical_specifications_for_the_installation_of_telecommunicat...
Guidelines on technical_specifications_for_the_installation_of_telecommunicat...Guidelines on technical_specifications_for_the_installation_of_telecommunicat...
Guidelines on technical_specifications_for_the_installation_of_telecommunicat...
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
 
2016-03-17 Velocity 2_Construction of Steel Dome
2016-03-17 Velocity 2_Construction of Steel Dome2016-03-17 Velocity 2_Construction of Steel Dome
2016-03-17 Velocity 2_Construction of Steel Dome
 

More from GTVT

Biện pháp thay dàn cầu đường sắt Tân An - Bình Định
Biện pháp thay dàn cầu đường sắt Tân An -  Bình ĐịnhBiện pháp thay dàn cầu đường sắt Tân An -  Bình Định
Biện pháp thay dàn cầu đường sắt Tân An - Bình ĐịnhGTVT
 
De cuong tn 17
De cuong tn 17De cuong tn 17
De cuong tn 17GTVT
 
Cong nghe duc dam i
Cong nghe duc dam iCong nghe duc dam i
Cong nghe duc dam iGTVT
 
Liên kết trong kết cấu thép
Liên kết trong kết cấu thépLiên kết trong kết cấu thép
Liên kết trong kết cấu thépGTVT
 
2.de cuong thi cong coc ep
2.de cuong thi cong coc ep2.de cuong thi cong coc ep
2.de cuong thi cong coc epGTVT
 
06.chapter iv
06.chapter iv06.chapter iv
06.chapter ivGTVT
 
05.chapter iii
05.chapter iii05.chapter iii
05.chapter iiiGTVT
 
03.chapter i
03.chapter i03.chapter i
03.chapter iGTVT
 
02.contents
02.contents02.contents
02.contentsGTVT
 
22 tcn 18 79 (phu luc 9-14)
22 tcn 18 79 (phu luc 9-14)22 tcn 18 79 (phu luc 9-14)
22 tcn 18 79 (phu luc 9-14)GTVT
 
22 tcn 18 79 (phu luc 1-8)
22 tcn 18 79 (phu luc 1-8)22 tcn 18 79 (phu luc 1-8)
22 tcn 18 79 (phu luc 1-8)GTVT
 
22 tcn 18 79 (chuong 7, nen va mong)
22 tcn 18 79 (chuong 7, nen va mong)22 tcn 18 79 (chuong 7, nen va mong)
22 tcn 18 79 (chuong 7, nen va mong)GTVT
 
22 tcn 18 79 (chuong 6, ket cau bt, khoi xay va da xay)
22 tcn 18 79 (chuong 6, ket cau bt, khoi xay va da xay)22 tcn 18 79 (chuong 6, ket cau bt, khoi xay va da xay)
22 tcn 18 79 (chuong 6, ket cau bt, khoi xay va da xay)GTVT
 
22 tcn 18 79 (chuong 5-3, ket cau bt toan khoi va btct)
22 tcn 18 79 (chuong 5-3, ket cau bt toan khoi va btct)22 tcn 18 79 (chuong 5-3, ket cau bt toan khoi va btct)
22 tcn 18 79 (chuong 5-3, ket cau bt toan khoi va btct)GTVT
 
22 tcn 18 79 (chuong 5-2, ket cau bt toan khoi va btct)
22 tcn 18 79 (chuong 5-2, ket cau bt toan khoi va btct)22 tcn 18 79 (chuong 5-2, ket cau bt toan khoi va btct)
22 tcn 18 79 (chuong 5-2, ket cau bt toan khoi va btct)GTVT
 
22 tcn 18 79 (chuong 5-1, ket cau bt toan khoi va btct)
22 tcn 18 79 (chuong 5-1, ket cau bt toan khoi va btct)22 tcn 18 79 (chuong 5-1, ket cau bt toan khoi va btct)
22 tcn 18 79 (chuong 5-1, ket cau bt toan khoi va btct)GTVT
 
22 tcn 18 79 (chuong 4, ket cau thep lien hop voi ban btct)
22 tcn 18 79 (chuong 4, ket cau thep lien hop voi ban btct)22 tcn 18 79 (chuong 4, ket cau thep lien hop voi ban btct)
22 tcn 18 79 (chuong 4, ket cau thep lien hop voi ban btct)GTVT
 
22 tcn 18 79 (chuong 3, ket cau thep)
22 tcn 18 79 (chuong 3, ket cau thep)22 tcn 18 79 (chuong 3, ket cau thep)
22 tcn 18 79 (chuong 3, ket cau thep)GTVT
 
22 tcn 18 79 (chuong 2, tai trong va he so tai trong)
22 tcn 18 79 (chuong 2, tai trong va he so tai trong)22 tcn 18 79 (chuong 2, tai trong va he so tai trong)
22 tcn 18 79 (chuong 2, tai trong va he so tai trong)GTVT
 
22 tcn 18 79 (chuong 1, quy dinh co ban)
22 tcn 18 79 (chuong 1, quy dinh co ban)22 tcn 18 79 (chuong 1, quy dinh co ban)
22 tcn 18 79 (chuong 1, quy dinh co ban)GTVT
 

More from GTVT (20)

Biện pháp thay dàn cầu đường sắt Tân An - Bình Định
Biện pháp thay dàn cầu đường sắt Tân An -  Bình ĐịnhBiện pháp thay dàn cầu đường sắt Tân An -  Bình Định
Biện pháp thay dàn cầu đường sắt Tân An - Bình Định
 
De cuong tn 17
De cuong tn 17De cuong tn 17
De cuong tn 17
 
Cong nghe duc dam i
Cong nghe duc dam iCong nghe duc dam i
Cong nghe duc dam i
 
Liên kết trong kết cấu thép
Liên kết trong kết cấu thépLiên kết trong kết cấu thép
Liên kết trong kết cấu thép
 
2.de cuong thi cong coc ep
2.de cuong thi cong coc ep2.de cuong thi cong coc ep
2.de cuong thi cong coc ep
 
06.chapter iv
06.chapter iv06.chapter iv
06.chapter iv
 
05.chapter iii
05.chapter iii05.chapter iii
05.chapter iii
 
03.chapter i
03.chapter i03.chapter i
03.chapter i
 
02.contents
02.contents02.contents
02.contents
 
22 tcn 18 79 (phu luc 9-14)
22 tcn 18 79 (phu luc 9-14)22 tcn 18 79 (phu luc 9-14)
22 tcn 18 79 (phu luc 9-14)
 
22 tcn 18 79 (phu luc 1-8)
22 tcn 18 79 (phu luc 1-8)22 tcn 18 79 (phu luc 1-8)
22 tcn 18 79 (phu luc 1-8)
 
22 tcn 18 79 (chuong 7, nen va mong)
22 tcn 18 79 (chuong 7, nen va mong)22 tcn 18 79 (chuong 7, nen va mong)
22 tcn 18 79 (chuong 7, nen va mong)
 
22 tcn 18 79 (chuong 6, ket cau bt, khoi xay va da xay)
22 tcn 18 79 (chuong 6, ket cau bt, khoi xay va da xay)22 tcn 18 79 (chuong 6, ket cau bt, khoi xay va da xay)
22 tcn 18 79 (chuong 6, ket cau bt, khoi xay va da xay)
 
22 tcn 18 79 (chuong 5-3, ket cau bt toan khoi va btct)
22 tcn 18 79 (chuong 5-3, ket cau bt toan khoi va btct)22 tcn 18 79 (chuong 5-3, ket cau bt toan khoi va btct)
22 tcn 18 79 (chuong 5-3, ket cau bt toan khoi va btct)
 
22 tcn 18 79 (chuong 5-2, ket cau bt toan khoi va btct)
22 tcn 18 79 (chuong 5-2, ket cau bt toan khoi va btct)22 tcn 18 79 (chuong 5-2, ket cau bt toan khoi va btct)
22 tcn 18 79 (chuong 5-2, ket cau bt toan khoi va btct)
 
22 tcn 18 79 (chuong 5-1, ket cau bt toan khoi va btct)
22 tcn 18 79 (chuong 5-1, ket cau bt toan khoi va btct)22 tcn 18 79 (chuong 5-1, ket cau bt toan khoi va btct)
22 tcn 18 79 (chuong 5-1, ket cau bt toan khoi va btct)
 
22 tcn 18 79 (chuong 4, ket cau thep lien hop voi ban btct)
22 tcn 18 79 (chuong 4, ket cau thep lien hop voi ban btct)22 tcn 18 79 (chuong 4, ket cau thep lien hop voi ban btct)
22 tcn 18 79 (chuong 4, ket cau thep lien hop voi ban btct)
 
22 tcn 18 79 (chuong 3, ket cau thep)
22 tcn 18 79 (chuong 3, ket cau thep)22 tcn 18 79 (chuong 3, ket cau thep)
22 tcn 18 79 (chuong 3, ket cau thep)
 
22 tcn 18 79 (chuong 2, tai trong va he so tai trong)
22 tcn 18 79 (chuong 2, tai trong va he so tai trong)22 tcn 18 79 (chuong 2, tai trong va he so tai trong)
22 tcn 18 79 (chuong 2, tai trong va he so tai trong)
 
22 tcn 18 79 (chuong 1, quy dinh co ban)
22 tcn 18 79 (chuong 1, quy dinh co ban)22 tcn 18 79 (chuong 1, quy dinh co ban)
22 tcn 18 79 (chuong 1, quy dinh co ban)
 

04.chapter ii

  • 1. Hanoi – Hochiminh city railway line Do Vang Bridge’s construction bridges safety improvement project technology of beam casted on scaffolding CHAPTER II: TECHNOLOGY PROCESS I. CONSTRUCTION SEQUENCES Concrete beams of Do Vang Bridge are casted in place on the scaffolding. Construction scaffoldings are made up of shape steel including of: longitudinal beam H200 and horizontal beam and scaffolding system for supporting side formworks. Side formworks, bottom formworks, internal formworks with splint system, through bar must be stably, firmly throughout concreting process. After completion span 2 and span 5, formwork scaffolding will be transferred to construct the next spans. Concrete shall be provided from batching plan at Site with capacity 60m 3/h to the constructed position by truck mixer and concrete pump. • Construction sequences + Step 1: Land levelling at position of girder construction, filling sand and compacting to K95. Installing the concrete plank 1x1x0.2m. + Step 2: Installing the scafolding, longitudinal beam H200 and horizontal beam H200 + Step 3: Testing of scaffold. + Step 4: Install external formwork, side formwork + Step 5: Install reinforcing steel, pouring concrete + Step 6: Stretch prestressed cable. + Step 7: Removal of scaffolding, internal formwork, pushing scaffolding system. + Step 8: Connect projecting reinforcement couplers of diagraphm, reinforcement, diaphragm formwork. Placing concrete and stressing horizontally prestressed cable of diaphragm. + Step 9: Construction of the next span. II. TECHNOLOGY STEPS 1. Land levelling Land levelling at position of girder construction, filling sand and compacting to K95. Installing the concrete plank 1.2x1.2x0.18m2. Production and erection of scaffolding Scaffolding, formwork must be designed to resist any unfavouble displacement during superstructure construction process. Construction scaffolding is included: + Supporting scaffolding of side formwork + Installing the scafolding, longitudinal beam H200 and horizontal beam H200 5
  • 2. Hanoi – Hochiminh city railway line Do Vang Bridge’s construction bridges safety improvement project technology of beam casted on scaffolding Figure 1: Span structure’s construction scaffolding 3. Testing scaffolding This test aims to remove the settlement of scaffolding system, check the pressure bearing ability of scaffolding. Load test results must be reported immediately to The Engineer. 4. Install beam formwork • Concreting formwork design + Bottom formwork is combined by flat formwork 1x2m, placed directly on diaphragm steel shape H200.. + Side formwork and flange beam is combined by flat formwork and special formwork put on modules of steel shape H200x200, wihch are associated with diagram steel shape H200x200. + Core formworks shall be fabricated by modulus 0.25x1.0m, fitness, easy working, and convenient removing. The formwork is designed by the type of 6
  • 3. Hanoi – Hochiminh city railway line Do Vang Bridge’s construction bridges safety improvement project technology of beam casted on scaffolding modulus 1m including formworks- supporting bars- bands, ready erected on the ground and hoisted into its position. + Elevation of formwork at each section must be included design deflection of the bridge and deflection resulting from pre-stressing and deformation of scaffolding. • Install bottom formwork Erection sequence as follows: + Formwork boards are placed directly on the diaphragm steel shape H200x200 + Erection of formwork boards with the length 2m is in the direction of bridge and parallel to connecting centre line between two piers. + After completing bottom formwork installations, in a maximum distance of 4m between sections, measure the level to adjust the level of beam bottom. + Insert the steel wedge below the formwork to adjust the level of formwork surface (beam bottom). + Installation of a special formwork at pier position • Installation of external wall formwork Erection sequence as follows: + Installation of outside scaffolding system and protective handrail. + Completely erecting formworks modulus and supporting frame for beam web consisting of: web formworks, supporting frames. + Hoisting each formwork modulus and supporting frames into exact position. + Adjust level of formworks. + Tighten the connection bolts, fix geometric position of formwork segment and install the next segment until finish a span of beam. • Installation of core formwork The installing sequence shall be as follows: + Formwork system and supporting frame of core formwork shall be installed in every modulus at 4~6m length, suitable with the capacity of the hoist. + Hoisting each formwork modulus into exact position. 7
  • 4. Hanoi – Hochiminh city railway line Do Vang Bridge’s construction bridges safety improvement project technology of beam casted on scaffolding + Adjusting elevation and coordinate of formwork. + Tighten the connection bolts, fix geometric position of formwork segment and install the next formwork segment until finish a concreting segmentation. 5. Beam bearing installation The Contractor will install bearing before casting concrete. Detailed construction is follows: • Step 1 Cleanning reinforcement of bearing stone, installing formwork of bearing stone, casting non-shrinkage motar for bearing stone construction. • Step 2 When the motar of bearing stone meets requirements of strength, locating exactly bearing position, defining the horizontal and vertical position of bearing stone, installing the bearing. 6. Installation of reinforcement, duct and high strength cable • Installation of reinforcement Reinforcement is fabricated at yard according to the designed geometric dimension, numbered and bundled for hoisting into installed position. Sequence for installing rebar will be prepared by construction team and informed to foreman during installation of beam rebar with the below principles: + Fully installing bars in accordance with the size and location indicated in the design. + Steel structural members must be removed or fixed at designed position by using supporting bar, chock or tie to resist the excessive movement or bending during construction process. + The distance from formwork surface to steel structural member must be remained by using supporting bars and chocks. The chocks must be placed in a suitable distance to make the formwork be free from cracking or excessive deflection. 8
  • 5. Hanoi – Hochiminh city railway line Do Vang Bridge’s construction bridges safety improvement project technology of beam casted on scaffolding + The chocks must be enough hardness, strength and suitable shape to not form holes around them. + The position tolerance for internal reinforcement of concrete:  Bar detail and bending dimension for the rebars must satisfy the requirement stipulated in Section 5.11 of Bridge Construction Instruction AASHTO LRFD 98.  The installation tolerance for the super structure as follows: d ≤ 200 200 < d < 500 500 <d ≤ 2000 d>2000 Tolerance (mm) 5 10 20 30 In there: d may be:  Dimension by measurement direction (mm)  Height of cross section (mm) • Installation of Duct and high strength Cable Install holing duct: + The holing ducts for high strength tendon are put into designed position before concreting. The duct is installed segmentally (according to produced length) ducts are connected together with linking pipe and joint tape around to prevent motar from inner leakaging. + To fix ducts into reinforcement mesh, using D6 bars supporting below and binding into the mesh at each coordinates adjusting position of the strand according to design requirements. + The head of duct is inserted in the anchor head fixed into beam formwork. + The duct is associated to ventilation pipe and grouting chute at the lowest and the highest points to ensure the pumped grout will completely seal the duct, free from air bubble. 9
  • 6. Hanoi – Hochiminh city railway line Do Vang Bridge’s construction bridges safety improvement project technology of beam casted on scaffolding Figure 5 : The process of connection cladding Figure 6: Setting mortar Wrap joint tape to be sealed and free from grout leakage Figure 7: Field duct connection Install duct and high strength tendon: + Install duct and high strength tendon, using cupler to connect tendon. + High strength tendon will be cut up to designed length, bundled and inserted into the duct then put into place. + Fix cable into head of dead end, locate the dead end. Notes when installing duct and tendon: + Duct position must be installed in right designed place within allowed tolerance. + Curve of cable must be smooth when visually check. 10
  • 7. Hanoi – Hochiminh city railway line Do Vang Bridge’s construction bridges safety improvement project technology of beam casted on scaffolding + Duct must have enough tightness so that mortar can not run into there. 7. Placing concrete for beam • Concrete mix design Concrete of approach beam of Do Vang bridge has relatively dimension and quantity, thus mix design work greatly affects the concrete quality. The mix design shall be in accordance with requirements of Specification. Concrete shall ensure to be enough strength, waterproofing as requirement of design also meet demand of yield to ease the construction with minimum cement content. Minimum compressive strength of cylinder specimen at 28 days shall be 40Mpa to ensure concrete reach to strength 40Mpa as designed. In any case, the required slump of concrete shall be 14 ± 2 cm. It shall be rejected if it is not as requirement. Do not add water to fresh concrete. Concrete shall have enough adhesiveness and flexibility to ensure it is not segregated throughout concrete transporting and placing process. Water-cement ratio in concrete mix shall be less than 0.40. Concrete mortar shall have setting time over 6 hours. The parameters of beam concrete: + Grade: 40 Mpa + Slump: 14 ± 2 cm • Concrete materials Beam concrete of Do Vang Bridge as shown in the Specification of Project has cylinder strength 40MPa. Mix design shall conform to Specification of Project. Admixture of concrete is produced by Sika manufacturer. This is a super-plastically high-tech substance at the thirdly versioned polyme origin to push concrete harden. The admixture will affect on the below characteristics of concrete: + The ability of reducing water is so high. + To be deliveried in a great distance. 11
  • 8. Hanoi – Hochiminh city railway line Do Vang Bridge’s construction bridges safety improvement project technology of beam casted on scaffolding + The yield strength is high (decrease the works of placing and compacting) + Boost the development of strength + Improve the ability of creeping, shrinkage. • Construction plan layout + Currently, construction plan of the Do Vang Bridge has already leveled off material store yard, reinforcing yard to ready for installing, testing load and placing concrete for beam. + Night lighting system: The Contractor shall arrange fully lighting system along the service road, beam and all constructing positions throughout the concreting process. The bulbs used during construction have capacity 500W and shall be disposed at the distance of 5÷10m per bulb. The minimum illumination level for concreting is 30lux/m2. (When it comes to horizontal concrete plane – Refer to “Bridge constructing manual” composed by Pham Huy Chinh- Construction Publisher 2007). + Standby power system: The Contractor has standby power system 250KVA in case of power loss. This system shall be always maintained and checked to find out defects and treat immediately. • Construction Equipment No Equipment Unit Quantity Note 01 Mixing plant 60m3/h each 01 02 Mixer Truck each 03 03 Pumpcrete machine Puztmaiter each 02 04 Generator 250KVA each 01 05 Crane 40T each 01 06 Purchase tackle each 04 07 Jacking and oil pump house Set 02 08 Mortar mixer and pump Set 02 12
  • 9. Hanoi – Hochiminh city railway line Do Vang Bridge’s construction bridges safety improvement project technology of beam casted on scaffolding 09 Surveyor's level each 01 10 Tachometer each 01 11 Vibrators each 15 12 Pumpcrete pipe m 250 13 Welding machine 400A each 04 14 Pump 60m3/h each 02 • Arrangement manpower No Equipment Unit Quantity Note 01 Engineering person 03 02 Investigation person 02 03 Woker drive crane person 04 04 Worker support crane person 06 05 Woker drive electric person 02 06 Woker drive mixing plant person 02 07 Worker drive shovel person 02 Worker drive pumpcrete 02 08 person machine 09 Woker weld person 15 10 Woker jack person 05 • Concrete mixing Use batching plants that can automatically measure and weigh at Site. The scales shall be checked accuracy, meet the Specification of Project as stipulated. Concrete of each batch shall be in accordance with Specification as required. The slump of concrete must conform to requirements. Therefore, before each concrete placing time, determine the material moisture to caculate suitable water content for 13
  • 10. Hanoi – Hochiminh city railway line Do Vang Bridge’s construction bridges safety improvement project technology of beam casted on scaffolding concrete mix. • Provide concrete Concrete shall be provided from batching plant to constructed position by truck mixer and concrete pump. Time from mixing, placing to compacting concrete is not over 90 minutes to ensure the works of concreting finish before concrete setting. Components and slump of concrete mix shall be tested and trial pumped to ensure the quality of concrete and construction conditions simutanously suitalbe with technical funtions of pump. When construction in hot weather, the external surface of concrete must be covered or whitened to restrict sunlight effect causing hot concrete. • Method for decrease concrete mix temperature The Contractor intends to cast concrete from 16 p.m to 10 a.m next morning. In case of daytime construction, the Contractor shall not construct on the day that temperature is over 35°C. Construction in nightime to reduce temperature, direct sunlight causing hot pump pipe and newly placed concrete. Concrete mix temperature from batching plant shall be controlled to not excess 25°C and when placing it is not over 35°C. For these purposes, beside construction in nightime to decrease temperature, the Contractor also use the following methods to decrease aggregate temperature: + Spray water on balast, gravel: Ballast, gravel in store yard shall be sprayed periodcally for keeping wet surface to create evaporating mechanism so that reducing agrregate temperature. + Use cool water to mix concrete, water tankers shall be covered from sunlight. • Pour concrete + Concrete is poured by mix truck and pumping machine 14
  • 11. Hanoi – Hochiminh city railway line Do Vang Bridge’s construction bridges safety improvement project technology of beam casted on scaffolding Concrete placing direction: Concrete shall be casted from the low head to the high head of beam and placed alternately on all beam webs, ensure that height defference between these webs is not over 50cm. Pour concrete vertically by each segment that splayed a 45 0 angle against to horizontal direction. Attention when pour concrete + Slump of concrete must be as required. Therefore, before each concreting batch, it is necessary to determine the moisture of material to calculate the suitable water content for concrete aggregate. + The height of the concrete to fall is not more than 1.5 m to avoid segregating. + Fresh concrete is poured into formwork by a small amount and using methods to remain rebar not movement during concreting process. + Mixxing speed must ensure that when pouring the above layer, the below layer has not yet cured to create perfect bonds between layers. • Tamping + In the concrete mix, the Contractor has used superplasticizer with high mobility of manufacturer Sika to decrease significantly placing and compacting work. + Fresh concrete must be placed into formwork and compacted for each layer from 250mm to 300mm thickness. By this time, compacting to the previous concrete layers. + During compaction, at the position near ducts, pay attention to advoid touching the duct to be broken. Do not use vibrator to push concrete. + Special attention to concrete quality at anchor heads. • Curing concrete 15
  • 12. Hanoi – Hochiminh city railway line Do Vang Bridge’s construction bridges safety improvement project technology of beam casted on scaffolding Curing for concrete beam casted on scaffolding is conducted immediately after finishing a surface area of concrete beams. Usually use wet sacks to cover on concrete surface around one hour or when the concrete surface will begin to dry. After finishing surface and until the surface can resist water (usually after 2 hours of concreting) must water regularly to the concrete surface which face is finished. When finishing pouring concrete for girder segments, watering to cure all concrete and wall formwork. After removing the formwork must water to the concrete regularly throughout day and nighttime. Water for curing process shall be fresh water used to mix concrete. Setting time must prolong at least 7 days from finishing of beam concrete. • Emegency occurrences that may happen and resolving method.  Treatment method in case of work suspension because of Force Majeure. The concreting work shall not be executed in the following cases: hard rain, flood, storm, or the conditions for placing concrete still not ready… In the event that concreting process is suspended because of the interruption in concrete providing source (long-time traffic jam, accident…) the problem shall be resolved as below: + Use the standby mixing plants at the Site. + If the quantity of concrete required to place is further more than capacity of standby mixing plants, the construction must be suspended and the Contractor continuously compacts to finish the casted concrete. In the vertical direction, concrete shall be made by diagonal section bias an angle ≤ 450 against horizontal plane. This special construction joint shall be treated, roughed in accordance with procedure and specification for the next concreting stage.  Measure to prevent honeycomb: 16
  • 13. Hanoi – Hochiminh city railway line Do Vang Bridge’s construction bridges safety improvement project technology of beam casted on scaffolding Honeycomb at concrete is easy to happen because of special shape of box girder. Positions where honeycomb can happen and method which is carried out in process of pouring concrete to prevent honeycomb is showed in below table: No. Position where honeycomb can Reason Preventative measure happen 1 The lower chamfer of web Concrete pouring to Need to guide workers web is easy to flow not hesitate when to bottom slab compact concrete Workers hesitate when compact concrete because concrete flow to bottom slab The lower chamfer The vibrating tampers of web can’t be are often associated compacted well with a burning because outside web bamboo or a straight isn’t straight pipe to pass thread along shape of diagonal web Projector flashlight into the side of web These parts will be hammered handwork by wooden hammer It is difficult to Vibrator will be compact by vibrator associated with a 2 The angle of bottom slab straight bar to compact that part. 17
  • 14. Hanoi – Hochiminh city railway line Do Vang Bridge’s construction bridges safety improvement project technology of beam casted on scaffolding The claddings will Pour concrete slowly 3 The lower part of cladding prevent compacting and compact concrete concrete below them more carefully 4 The anchorage zone Much reinforcement Compact carefully  Beam casting formwork No. Problem Resolve Load capacity of formwork Before fabricating the formwork shall be caculated, designed to ensure enough load 1 capacity. Checking their quality and geometrical dimension before leaving workshop. Formwork that is bad The formworks shall be checked, taken-over in quality, defected during quality and geometrical dimension to 2 transportation immediately discover and substitute the defected boards. The camber of formwork During installation, the formwork elevation shall resulting from designed be adjusted to be suitable with the camber. 3 camber of the bridge, stressing prestressed cable, scaffolding deformation 8. Prestressed cable tension • Preparation work It is necessary to make sure that before constructing all persons attending directly in stretching works, especially technicants and stretching team leaders must have full knowledge of stretch controlling steps to ensure the technical quality and safety regulation. Check concrete strength (taking sample before stressing). The strength shall reach to 90%Rtk (90%*40Mpa = 36 for cylinder sample). Check jack, pump, jack bracket, chain hoist and work platform. 18
  • 15. Hanoi – Hochiminh city railway line Do Vang Bridge’s construction bridges safety improvement project technology of beam casted on scaffolding + Jack, pump for stressing shall be checked and approved before using. + Jack and pump shall be inspected by specialist authority. + Jack shall be inspected in the following moments: • Before using to avoid accident or occurrence. • Change jack set. + Anchor test: • Anchor using for Project must be in accordance with Specification and inspected to pass testing criterium and approved by Engineer. • Anchor using for installation shall be free from crack, warp, and the chap must be sealed with anchor. Show stressing steps on the visble positions for the stressing team leader. Fill up enough points stipulated in stressing note. • Stressing equipment.  Prestressed Cable High strength cable shall use kind of tendon as 7 lowly saged plies 12 strands 15.2m bundled cable Grade 270 according to ASTM A416 – 90A standard. No Item Value 1 Nominal diameter 15.2 mm 2 Area of cross section 140 mm2 3 Ultimate strength 1860 Mpa 4 Yield point stress 1670 MPa Prestressed cable shall be protected in store that has screen, be dry, apart 30cm from the ground. 19
  • 16. Hanoi – Hochiminh city railway line Do Vang Bridge’s construction bridges safety improvement project technology of beam casted on scaffolding Pretressed cable must have Certificate of Producer approved by Employer and Engineer. Test for tendon in accordance with Design Document and criterium: breaking force, elastic modulus, yeild strength, elongation, dimension of each ply in tendon, condition of external surface. Any change that not be in accordance with Design Document shall be approved in writing by Design Unit, Employer, Engineer beforce constructing.  Anchor Use imported anchor of OVM manufacturer for cable 15,2mm . Imported anchor must have Quality Certificate of Manufacturer.  Jack All of jacks, oil pumps shall be inspected before using. Jack Area Strain Sroke Type of No pittong max pittong Note Name Mark Pump (cm2) (KN) (mm) Horizontally 1 YCQ500Q 0707 ZB4 - 500 1000 5000 200 stretching Horizontally 2 YCQ500Q 1001 ZB4 - 500 1000 5000 200 stretching • Prestressed cable tension Use one-head tensioning method. Using jack 500T applying for tendon as 7 lowly saged plies 12 strands 15.2m bundled cable. Stretch every twin cables symmetrically through centreline of beam in the following sequence: + From centerline to outside. + From neutral axis to outside. Sequence of stressing tendons on each segment: Stressing longitudinally then stretching horizontally prestressed cable of bridge. 20