SlideShare a Scribd company logo
1 of 24
Presented By
Things Simplified
( A New Perspective )

 Quebec bridge is a rail, road and pedestrian bridge situated on the St.
Lawrence River, Quebec, Canada.
 It was at time of construction the longest cantilever bridge in the world with
clear span of 1800 ft.
 The bridge construction was finally completed in 1917 after two failures or
tragedies to bridge the harsh icy waters of the St. Lawrence river.
 First collapse occurred on August 26, 1907. Second collapse occurred almost
after a decade on September 11, 1916
 Quebec bridge is a cantilever truss bridge with two spans cantilever from both
sides and simple span suspended in between.
Quebec Bridge

 The story of the bridge begins back in 1887 with the formation of Quebec
Bridge company which came up with the proposal to erect the bridge over the
river to increase business traffic in the city of Quebec and places nearby.
 Various proposals for the bridge were submitted out of which The Phoenix
Bridge Company’s proposal was selected which called for a cantilever bridge
of 150 feet in height above the high water mark.
 Theodore Cooper, a well-known American bridge designer, was selected as
the project’s consulting engineer by the Quebec Bridge company. He endorsed
the Phoenix design as the “best and the cheapest” of those submitted,
although he decided to lengthen the centre span from 1,600 to 1,800 feet in
order to eliminate the uncertainty of constructing piers in such deep water,
lessen the effects of ice, and shorten the time of construction of the piers.
History

Dimensions of Bridge

Concept of Bridge

 As soon as the south anchor arm was completed (in early 1906) the assembly of
the cantilever arm could begin (the falsework was then also moved to the other
side of the river for the construction of the north anchor arm).
 Using the anchor arm as a counterweight – securely anchored at the end for
the uplift forces – the main span was being erected using the cantilever
technique (one half from either side of the river).
 At just about this point in the construction (in early 1906) it was discovered that
the amount of steel material delivered to the bridge site considerably
exceeded the originally estimated amount. It was because no correction for
self weight of the structure was made when the span length was increased from
488m to 549 m. Cooper however, decided to forge ahead and not introduce
any changes.
First Collapse

First Collapse (Cont.)

First Collapse (Cont.)
Member Numbers of the Bridge

 Cooper due to his ill health, worked out of his New York City office and did not
make visits to the site during the erection of the superstructure.
 In mid summer of 1907 the first signs of distress in the steel superstructure
began to show – a field splice in the ninth panel lower compression chord on
the left-hand side of the anchor arm (member A9-L) had become distorted.
First Collapse (Cont.)

First Collapse (Cont.)
Bridge Members Deflection at various instants of time

 As the lower chords of the anchor arm initially were subjected to tension –
when the falsework was removed and the span became simply supported – and
the normal force soon changed to compression as the cantilever arm grew
outwards, it was decided to temporarily use bolts in order to allow for the
structure (the anchor arm) to develop all of its deformations before riveting the
plates tight together.
 The anchor arm was quite simply judged to be allowed to adjust itself to the
changing load, otherwise secondary constraints could have been developed.
However, by taking this measure the buckling strength of the lower
compression chords became affected negatively. Besides having observed local
distortion of the plates in the field splice, it was discovered in the beginning of
August 1907 that chord A9-L was slightly bent out-of-plane as well.
First Collapse (Cont.)


 At the end of August – when the cantilever had been extended further out over
the river, increasing the stresses even more in the truss members – it was found
that the out of plane bending of chord A9-L had increased from some 20mm to
alarmingly 57 mm.
 Even though this deformation – representing an out-of-plane deflection of
L/305 (the length L of the member being 17.44 m) – is hard to detect by the
naked eye, it was a clear signal that something was quite wrong.
First Collapse (Cont.)

 Realizing the danger McLure immediately travelled to New York on the 27
August to consult with Cooper (telephoning was judged to be too risky – there
was always the possibility that the telephone operator would listen in and
reveal the situation to the newspapers).
 Cooper, realizing the danger of the situation, wanting the construction to
come to an immediate halt, telegraphed to the Phoenix Bridge Company: “Add
no more load till after due consideration of facts’’.
 However, the contractor (i.e. the Phoenix Bridge Company) was under great
pressure not to delay the construction, so the work continued by unfortunately
moving an erection crane one step further out on the cantilever.
First Collapse (Cont.)

 In late afternoon of 29 August 1907 – just some 15 minutes before the working
day was over – the entire bridge collapsed, starting with the buckling failure of
the A9-L lower chord of the south anchor arm. Of the 86 workmen that were on
the bridge at the time of the collapse 75 were killed.
 The A9L bottom compression chord, which was already bent, gave way under
the increasing weight of the bridge. The load transferred to the opposite A9R
chord, which also buckled. The piers were the only part of the structure that
survived.
First Collapse (Cont.)

 In spite of the enormity of the accident, it was decided that the project must be
completed. In 1908, a board of engineers was appointed that arranged for and
supervised the design and erection of a new bridge. Except for the piers,
nothing from the previous structure was recoverable.
 In April 1911, the contract was awarded to the St. Lawrence Bridge Company
of Montreal. As before, the design called for a cantilever-type bridge, but it
differed from the previous one with the lower chords of the cantilever arms
several times stronger. One important innovation that added strength to the
bridge was the K-truss design.
Second Collapse

 Construction of the bridge started in 1913, and eventually the two approach
spans, the anchor arms and cantilevers went up on either side of the river. By
1916, the bridge was nearly completed.
 All that remained was the job of hoisting the mammoth centre span that would
be connected to the cantilever arms. The 5,100-ton span had been built and
was sitting in Sillery Cove, approximately 3 1/2 miles from the bridge site.
 On the morning of Sept. 11, the workmen faced a difficult task in moving the
span upstream, but all went well with that part of the job. The span was carried
on scows that were guided by tugs. It was a slow process, but eventually the
span was manoeuvred into position between the cantilever arms where huge
lifting hangers, attached to the ends of the arms, raised it by hydraulic means
off the scows. The span was to be lifted two feet at a time in a repeat operation
until it was in place between the two arms.
Second Collapse (Cont.)

 At 10:50 a.m, soon after they returned to work, something went terribly wrong.
The southwest corner of the span tore away and sagged. A few seconds later,
the other ends pulled off their supports and the whole span came loose and
disappeared into the river. Thirteen men were carried to their deaths and
several others were injured.
 The investigation by the board of engineers determined that the span did not
buckle as Larocque and others claimed. Rather, the loss resulted from the
failure of a casting in the erection equipment that temporarily supported the
southwest corner of the span.
Second Collapse (Cont.)

 On Sept. 20, 1917, the suspended span was lifted into position and fastened to
the cantilever arms. At last, the world’s longest cantilever bridge was
completed and the first train crossed it in October. Two months later it was
opened to regular trains, vehicle and pedestrian traffic.
 In 1919, the Prince of Wales officially opened the Quebec Bridge to the public.
Final Completion

 An underestimation of the self-weight of the structure
 Temporary splicing of the chords using bolts
 The load carrying capacity had been overestimated resulting in weak cross-
sections
 The stabilizing bars (the crossing diagonals and horizontals) were not strong
enough to resist out-of-plane buckling of the compression chords
Major Causes of Failure

 The collapse of the bridge finally led to the development of Canadian design
specifications for bridge structures.
 Engineering design is necessary for the means and methods of lifting
operations.
 The responsibility of execution and design of such an important structure must
not be left in the hands of one person.
Lessons Learned
Any Query, ask
in
comments
Thanks for your
Attention
Have a Nice Day

 Quebec Bridge Collapse
https://www.youtube.com/watch?v=xk1xEctDK0k
 Quebec Bridge Second Collapse
https://www.youtube.com/watch?v=bCrZCzuf72A
Video References

More Related Content

What's hot

Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhiRajesh Prasad
 
Suspension Bridges VS Cable-Stayed Bridges
Suspension Bridges VS Cable-Stayed BridgesSuspension Bridges VS Cable-Stayed Bridges
Suspension Bridges VS Cable-Stayed BridgesHussein Zidan
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineeringPooja Lonare
 
DESIGN OF T BEAM BRIDGE PROCEDURE
DESIGN OF T BEAM BRIDGE PROCEDUREDESIGN OF T BEAM BRIDGE PROCEDURE
DESIGN OF T BEAM BRIDGE PROCEDUREbabji syed
 
Design of Lined Canal and Canal Lining
Design of Lined Canal and Canal LiningDesign of Lined Canal and Canal Lining
Design of Lined Canal and Canal LiningRamanuj Jaldhari
 
Cable suspension bridge pdf
Cable suspension bridge pdfCable suspension bridge pdf
Cable suspension bridge pdfGaurav Rawat
 
case study on failed construction projects
case study on failed construction projectscase study on failed construction projects
case study on failed construction projectsSULAKSHYA GAUR
 
Bridge Construction & Its Types
Bridge Construction & Its TypesBridge Construction & Its Types
Bridge Construction & Its TypesZakaria Yahya
 
Fettuccine truss bridge report
Fettuccine truss bridge reportFettuccine truss bridge report
Fettuccine truss bridge reportIvy Yee
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing TechniqueSeminar Links
 
Reinforced slab bridge design(AASHTO allowable stress design method)
Reinforced slab bridge design(AASHTO allowable stress design method)Reinforced slab bridge design(AASHTO allowable stress design method)
Reinforced slab bridge design(AASHTO allowable stress design method)Shekh Muhsen Uddin Ahmed
 
MODULE-III INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-III INFRASTRUCTURE ENGINEERING BTCVC702MODULE-III INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-III INFRASTRUCTURE ENGINEERING BTCVC702Dr. BASWESHWAR JIRWANKAR
 
Bridge
Bridge Bridge
Bridge illpa
 

What's hot (20)

Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
 
Design of arch bridges
Design of arch bridgesDesign of arch bridges
Design of arch bridges
 
Suspension Bridges VS Cable-Stayed Bridges
Suspension Bridges VS Cable-Stayed BridgesSuspension Bridges VS Cable-Stayed Bridges
Suspension Bridges VS Cable-Stayed Bridges
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
DESIGN OF T BEAM BRIDGE PROCEDURE
DESIGN OF T BEAM BRIDGE PROCEDUREDESIGN OF T BEAM BRIDGE PROCEDURE
DESIGN OF T BEAM BRIDGE PROCEDURE
 
Suspension Bridges
Suspension BridgesSuspension Bridges
Suspension Bridges
 
Design of Lined Canal and Canal Lining
Design of Lined Canal and Canal LiningDesign of Lined Canal and Canal Lining
Design of Lined Canal and Canal Lining
 
Bridge introduction
Bridge introductionBridge introduction
Bridge introduction
 
Cable suspension bridge pdf
Cable suspension bridge pdfCable suspension bridge pdf
Cable suspension bridge pdf
 
case study on failed construction projects
case study on failed construction projectscase study on failed construction projects
case study on failed construction projects
 
Bridge,types of bridges
Bridge,types of bridgesBridge,types of bridges
Bridge,types of bridges
 
Prestressed Concrete Design
Prestressed Concrete DesignPrestressed Concrete Design
Prestressed Concrete Design
 
Bridge Construction & Its Types
Bridge Construction & Its TypesBridge Construction & Its Types
Bridge Construction & Its Types
 
Hoover dam ppt
Hoover dam pptHoover dam ppt
Hoover dam ppt
 
Fettuccine truss bridge report
Fettuccine truss bridge reportFettuccine truss bridge report
Fettuccine truss bridge report
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 
Reinforced slab bridge design(AASHTO allowable stress design method)
Reinforced slab bridge design(AASHTO allowable stress design method)Reinforced slab bridge design(AASHTO allowable stress design method)
Reinforced slab bridge design(AASHTO allowable stress design method)
 
Steel truss ppt
Steel truss pptSteel truss ppt
Steel truss ppt
 
MODULE-III INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-III INFRASTRUCTURE ENGINEERING BTCVC702MODULE-III INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-III INFRASTRUCTURE ENGINEERING BTCVC702
 
Bridge
Bridge Bridge
Bridge
 

Similar to Quebec Bridge Collapse - A Case Study

Case Study 7.3 249 CASE STUDY 7.3 Classic Case Tacoma Narrows Suspen.pdf
Case Study 7.3 249 CASE STUDY 7.3 Classic Case Tacoma Narrows Suspen.pdfCase Study 7.3 249 CASE STUDY 7.3 Classic Case Tacoma Narrows Suspen.pdf
Case Study 7.3 249 CASE STUDY 7.3 Classic Case Tacoma Narrows Suspen.pdfSANDEEPARIHANT
 
Engineering mistakes in the world
Engineering mistakes in the worldEngineering mistakes in the world
Engineering mistakes in the worldAnishaJalathota
 
Golden gate bridge 2
Golden gate bridge 2Golden gate bridge 2
Golden gate bridge 2caltec
 
Golden gate bridge, San Francisco
Golden gate bridge, San Francisco Golden gate bridge, San Francisco
Golden gate bridge, San Francisco Ankur Saxena
 
Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridgeMohit Kumar
 
Bridgeprojectsource online-120723110339-phpapp02
Bridgeprojectsource online-120723110339-phpapp02Bridgeprojectsource online-120723110339-phpapp02
Bridgeprojectsource online-120723110339-phpapp02Ferit Fazliu
 
Suspension bridge (modern const. tech)
Suspension bridge (modern const. tech)Suspension bridge (modern const. tech)
Suspension bridge (modern const. tech)Vivek Chauhan
 
suspension bridge ppt
suspension bridge pptsuspension bridge ppt
suspension bridge pptSAI KIRAN
 
S5c9 chapter 9-facts and figures related to surface and underground canals.
S5c9 chapter 9-facts and figures related to surface and underground canals.S5c9 chapter 9-facts and figures related to surface and underground canals.
S5c9 chapter 9-facts and figures related to surface and underground canals.Shivu P
 
2009 civil engineering modern date
2009 civil engineering modern date2009 civil engineering modern date
2009 civil engineering modern date信瑜 單信瑜
 
Brooklyn Bridge: A Case sudy
Brooklyn Bridge: A Case sudyBrooklyn Bridge: A Case sudy
Brooklyn Bridge: A Case sudyBhavik A Shah
 
Bridge Report
Bridge ReportBridge Report
Bridge Reportsaif khan
 

Similar to Quebec Bridge Collapse - A Case Study (20)

Quebec disaster
Quebec disasterQuebec disaster
Quebec disaster
 
Saga of a steel bridge
Saga of a steel bridgeSaga of a steel bridge
Saga of a steel bridge
 
Case Study 7.3 249 CASE STUDY 7.3 Classic Case Tacoma Narrows Suspen.pdf
Case Study 7.3 249 CASE STUDY 7.3 Classic Case Tacoma Narrows Suspen.pdfCase Study 7.3 249 CASE STUDY 7.3 Classic Case Tacoma Narrows Suspen.pdf
Case Study 7.3 249 CASE STUDY 7.3 Classic Case Tacoma Narrows Suspen.pdf
 
Engineering mistakes in the world
Engineering mistakes in the worldEngineering mistakes in the world
Engineering mistakes in the world
 
Golden gate bridge 2
Golden gate bridge 2Golden gate bridge 2
Golden gate bridge 2
 
Golden gate bridge, San Francisco
Golden gate bridge, San Francisco Golden gate bridge, San Francisco
Golden gate bridge, San Francisco
 
Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridge
 
Bridge and its types
Bridge and its types Bridge and its types
Bridge and its types
 
Bridge project
Bridge projectBridge project
Bridge project
 
Bridgeprojectsource online-120723110339-phpapp02
Bridgeprojectsource online-120723110339-phpapp02Bridgeprojectsource online-120723110339-phpapp02
Bridgeprojectsource online-120723110339-phpapp02
 
Bridge project
Bridge projectBridge project
Bridge project
 
Suspension bridge (modern const. tech)
Suspension bridge (modern const. tech)Suspension bridge (modern const. tech)
Suspension bridge (modern const. tech)
 
suspension bridge ppt
suspension bridge pptsuspension bridge ppt
suspension bridge ppt
 
S5c9 chapter 9-facts and figures related to surface and underground canals.
S5c9 chapter 9-facts and figures related to surface and underground canals.S5c9 chapter 9-facts and figures related to surface and underground canals.
S5c9 chapter 9-facts and figures related to surface and underground canals.
 
2009 civil engineering modern date
2009 civil engineering modern date2009 civil engineering modern date
2009 civil engineering modern date
 
Brooklyn Bridge: A Case sudy
Brooklyn Bridge: A Case sudyBrooklyn Bridge: A Case sudy
Brooklyn Bridge: A Case sudy
 
Resonance Phenomenon
Resonance PhenomenonResonance Phenomenon
Resonance Phenomenon
 
Bridge Report
Bridge ReportBridge Report
Bridge Report
 
golden gate bridge
golden gate bridgegolden gate bridge
golden gate bridge
 
Bridge
BridgeBridge
Bridge
 

More from Things Simplified

More from Things Simplified (7)

Knickerbocker Theatre Collapse - A Case Study
Knickerbocker Theatre Collapse - A Case StudyKnickerbocker Theatre Collapse - A Case Study
Knickerbocker Theatre Collapse - A Case Study
 
Leaning Tower of Pisa, Italy
Leaning Tower of Pisa, ItalyLeaning Tower of Pisa, Italy
Leaning Tower of Pisa, Italy
 
Sinkholes
SinkholesSinkholes
Sinkholes
 
Geology Rocks
Geology RocksGeology Rocks
Geology Rocks
 
Diaphragm Wall
Diaphragm WallDiaphragm Wall
Diaphragm Wall
 
Glaciers
GlaciersGlaciers
Glaciers
 
Winds
WindsWinds
Winds
 

Recently uploaded

MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupJonathanParaisoCruz
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfadityarao40181
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentInMediaRes1
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...jaredbarbolino94
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 

Recently uploaded (20)

MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized Group
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdf
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media Component
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 

Quebec Bridge Collapse - A Case Study

  • 1. Presented By Things Simplified ( A New Perspective )
  • 2.   Quebec bridge is a rail, road and pedestrian bridge situated on the St. Lawrence River, Quebec, Canada.  It was at time of construction the longest cantilever bridge in the world with clear span of 1800 ft.  The bridge construction was finally completed in 1917 after two failures or tragedies to bridge the harsh icy waters of the St. Lawrence river.  First collapse occurred on August 26, 1907. Second collapse occurred almost after a decade on September 11, 1916  Quebec bridge is a cantilever truss bridge with two spans cantilever from both sides and simple span suspended in between. Quebec Bridge
  • 3.   The story of the bridge begins back in 1887 with the formation of Quebec Bridge company which came up with the proposal to erect the bridge over the river to increase business traffic in the city of Quebec and places nearby.  Various proposals for the bridge were submitted out of which The Phoenix Bridge Company’s proposal was selected which called for a cantilever bridge of 150 feet in height above the high water mark.  Theodore Cooper, a well-known American bridge designer, was selected as the project’s consulting engineer by the Quebec Bridge company. He endorsed the Phoenix design as the “best and the cheapest” of those submitted, although he decided to lengthen the centre span from 1,600 to 1,800 feet in order to eliminate the uncertainty of constructing piers in such deep water, lessen the effects of ice, and shorten the time of construction of the piers. History
  • 6.   As soon as the south anchor arm was completed (in early 1906) the assembly of the cantilever arm could begin (the falsework was then also moved to the other side of the river for the construction of the north anchor arm).  Using the anchor arm as a counterweight – securely anchored at the end for the uplift forces – the main span was being erected using the cantilever technique (one half from either side of the river).  At just about this point in the construction (in early 1906) it was discovered that the amount of steel material delivered to the bridge site considerably exceeded the originally estimated amount. It was because no correction for self weight of the structure was made when the span length was increased from 488m to 549 m. Cooper however, decided to forge ahead and not introduce any changes. First Collapse
  • 8.  First Collapse (Cont.) Member Numbers of the Bridge
  • 9.   Cooper due to his ill health, worked out of his New York City office and did not make visits to the site during the erection of the superstructure.  In mid summer of 1907 the first signs of distress in the steel superstructure began to show – a field splice in the ninth panel lower compression chord on the left-hand side of the anchor arm (member A9-L) had become distorted. First Collapse (Cont.)
  • 10.  First Collapse (Cont.) Bridge Members Deflection at various instants of time
  • 11.   As the lower chords of the anchor arm initially were subjected to tension – when the falsework was removed and the span became simply supported – and the normal force soon changed to compression as the cantilever arm grew outwards, it was decided to temporarily use bolts in order to allow for the structure (the anchor arm) to develop all of its deformations before riveting the plates tight together.  The anchor arm was quite simply judged to be allowed to adjust itself to the changing load, otherwise secondary constraints could have been developed. However, by taking this measure the buckling strength of the lower compression chords became affected negatively. Besides having observed local distortion of the plates in the field splice, it was discovered in the beginning of August 1907 that chord A9-L was slightly bent out-of-plane as well. First Collapse (Cont.)
  • 12.
  • 13.   At the end of August – when the cantilever had been extended further out over the river, increasing the stresses even more in the truss members – it was found that the out of plane bending of chord A9-L had increased from some 20mm to alarmingly 57 mm.  Even though this deformation – representing an out-of-plane deflection of L/305 (the length L of the member being 17.44 m) – is hard to detect by the naked eye, it was a clear signal that something was quite wrong. First Collapse (Cont.)
  • 14.   Realizing the danger McLure immediately travelled to New York on the 27 August to consult with Cooper (telephoning was judged to be too risky – there was always the possibility that the telephone operator would listen in and reveal the situation to the newspapers).  Cooper, realizing the danger of the situation, wanting the construction to come to an immediate halt, telegraphed to the Phoenix Bridge Company: “Add no more load till after due consideration of facts’’.  However, the contractor (i.e. the Phoenix Bridge Company) was under great pressure not to delay the construction, so the work continued by unfortunately moving an erection crane one step further out on the cantilever. First Collapse (Cont.)
  • 15.   In late afternoon of 29 August 1907 – just some 15 minutes before the working day was over – the entire bridge collapsed, starting with the buckling failure of the A9-L lower chord of the south anchor arm. Of the 86 workmen that were on the bridge at the time of the collapse 75 were killed.  The A9L bottom compression chord, which was already bent, gave way under the increasing weight of the bridge. The load transferred to the opposite A9R chord, which also buckled. The piers were the only part of the structure that survived. First Collapse (Cont.)
  • 16.   In spite of the enormity of the accident, it was decided that the project must be completed. In 1908, a board of engineers was appointed that arranged for and supervised the design and erection of a new bridge. Except for the piers, nothing from the previous structure was recoverable.  In April 1911, the contract was awarded to the St. Lawrence Bridge Company of Montreal. As before, the design called for a cantilever-type bridge, but it differed from the previous one with the lower chords of the cantilever arms several times stronger. One important innovation that added strength to the bridge was the K-truss design. Second Collapse
  • 17.   Construction of the bridge started in 1913, and eventually the two approach spans, the anchor arms and cantilevers went up on either side of the river. By 1916, the bridge was nearly completed.  All that remained was the job of hoisting the mammoth centre span that would be connected to the cantilever arms. The 5,100-ton span had been built and was sitting in Sillery Cove, approximately 3 1/2 miles from the bridge site.  On the morning of Sept. 11, the workmen faced a difficult task in moving the span upstream, but all went well with that part of the job. The span was carried on scows that were guided by tugs. It was a slow process, but eventually the span was manoeuvred into position between the cantilever arms where huge lifting hangers, attached to the ends of the arms, raised it by hydraulic means off the scows. The span was to be lifted two feet at a time in a repeat operation until it was in place between the two arms. Second Collapse (Cont.)
  • 18.   At 10:50 a.m, soon after they returned to work, something went terribly wrong. The southwest corner of the span tore away and sagged. A few seconds later, the other ends pulled off their supports and the whole span came loose and disappeared into the river. Thirteen men were carried to their deaths and several others were injured.  The investigation by the board of engineers determined that the span did not buckle as Larocque and others claimed. Rather, the loss resulted from the failure of a casting in the erection equipment that temporarily supported the southwest corner of the span. Second Collapse (Cont.)
  • 19.   On Sept. 20, 1917, the suspended span was lifted into position and fastened to the cantilever arms. At last, the world’s longest cantilever bridge was completed and the first train crossed it in October. Two months later it was opened to regular trains, vehicle and pedestrian traffic.  In 1919, the Prince of Wales officially opened the Quebec Bridge to the public. Final Completion
  • 20.   An underestimation of the self-weight of the structure  Temporary splicing of the chords using bolts  The load carrying capacity had been overestimated resulting in weak cross- sections  The stabilizing bars (the crossing diagonals and horizontals) were not strong enough to resist out-of-plane buckling of the compression chords Major Causes of Failure
  • 21.   The collapse of the bridge finally led to the development of Canadian design specifications for bridge structures.  Engineering design is necessary for the means and methods of lifting operations.  The responsibility of execution and design of such an important structure must not be left in the hands of one person. Lessons Learned
  • 24.   Quebec Bridge Collapse https://www.youtube.com/watch?v=xk1xEctDK0k  Quebec Bridge Second Collapse https://www.youtube.com/watch?v=bCrZCzuf72A Video References