Tamer Samy Nassr
Sr. Structural Design and Cost Estimate Engineer
E-mail : tamernassrz1986@Gmail.com
Core Skills:
 Structural Design .
 Design Management.
 Cost Estimate.
 Planning.
 Site Coordinator.
 Technical Office work
Details
Position:
Sr. Structural design
and Cost Estimate Engineer.
Education:
Bachelor degree in civil Engineer
from ZAGAZIG University at 2008.
Qualification:
 SAP 2000 course.
 AutoCAD course.
 ETABS.
 SAFE12.
 Microsoft Office
Contact Details
Phone : 00966 5 49303615
E-mail :
tamernassrz1986@Gmail.com
With over 9 years of experience as a Structural Design
Engineer, Site Engineer and Cost Estimate Engineer in various
construction projects such as retail, hotels, mosque, shopping
mall, warehouses, strip malls and residential developments
across Egypt and Saudi Arabia.
Career History
RAM Contracting / KPS - Saudi Arabia - 2014 till date
A Senior Structural Engineer and Cost Estimate Engineer, Responsible for
the Design review for the tender Structural Drawings and Ensuring its adequacy
, Preparing VALUE ENGINEERING studies , Introducing and adequate a cheaper
and a time shorten alternative solutions among the different structural
systems, Cost analysis, quantity surveying, cash flow forecasting ,planning and
scheduling, preparing and Reviewing project's contract as well as leading a
team of draftsmen and quantity surveyors to ensure the time and quality
efficiency .
ALWASSAT ENGINEERING OFFICE - Saudi Arabia - 2010 till 2014
A Structural Design Engineer, Responsible for Designing Concrete Buildings
,Designing Steel Buildings, quantity surveying, reinforcement Details , preparing
Biding documents such as the B.O.Q and the project's contract, price analysis
for Biding companies, Redesign for coast reduction and following up on site
during the construction phase as well as leading a team of draftsmen and
quantity surveyors to ensure the time and quality efficiency .
Alexandria Company for construction- Talat Moustafa- Egypt -
2009 till 2010
A Site Engineer Responsible for following up all construction activities including
but not limited to following up the subcontractors to ensure the quality and
time efficiency, preparing IR for the consultant, Planning and scheduling
Demanded Resources, Reporting the construction updates to the construction
manager.
ACCESS office for consultants - Egypt - 2008 till 2009
A Structural Design Engineer, Responsible for Designing Concrete Buildings
,Designing Steel Buildings, quantity surveying, reinforcement Details and
following up on site during the construction phase.
Projects History
RAM Contracting / KPS ,Arrayed, KSA, 2014 till date
Project 01: Centro Hotel By Rotana-Riyadh-KSA Value SAR 16 Millions(Skeleton
work only).
the project was 150 bed room hotel consisted of mini tower of 10 floors built over two
basements with a total built up area of 14250 square meters.
As a structural and a technical project's engineer based on the site I was responsible for
Reviewing the tender Package structural Drawings which was totally un coordinated and un
adequate, so I started preparing a new set of structural design coordinated and adequate
drawings including structural calculations and models, submitting them for approval,
following up with the project consultant (EHAF ) for approving the updated set of drawings
for construction then starting over preparing a full set of shop drawings for all the hotel
structural elements.
Hereinafter listed some of the major issues that I overcame while preparing the restudy:
- We faced a huge underestimating material costs , so I bearded this into my mind while
updating the structural drawings through proposing a post tension slab system for the
project instead of the traditional RC slab as well as customizing the number of columns and
reducing the shear walls and cores quantity so we manage to reduce the losses and the
time needed for construction.
- We faced an Unstable Building as per the tender drawings the was a planted columns -
to resist the loads from 10 upcoming floors - on the ground floor slab without a suitable
precautions for such case , so I manage to overcame the problem by increasing some of the
basement's columns , implementing a new beam elements under the planted columns
bearing to mind the not to increase the cost.
Project 02: Al Nabet Commercial and Residential project-Khamis mushait-Abha-
KSA Value SAR 20 Millions (skeleton work only ).
the project was consisting of two parts one of them was commercial building of 5 floors
built over one basements with a total built up area of 14000 square meters and another
residential building of 4 building with a total built up area of 4000 square meter .
Since the handing over of Centro Hotel project I was Promoted to become a senior
structural and Cost Estimate Engineer based on the company headquarter and I started my
new position with the above mentioned project , here in after what I had accomplished for
the project:
- Preparing the BOQ sine there was only drawings provided by the owner.
- establishing a cost break down structure.
- obtaining Quotations for materials and labors .
- Preparing the forecasted indirect cost for the project.
- Reviewing the Contact Conditions and Its financial terms .
- discussing the margins with the management.
- Finalizing the selling Prices.
- preparing the offer letter based on our stipulations.
- Negotiating with the owner till we won the tender and signed the contract.
Project 03: Wyndham Garden Hotel-Riyadh-KSA Value SAR 135 Millions (a
turnkey project ).
the project was 260 bed rooms Hotel consisted of mini tower of 8 floors built over two
basements with a total built up area of 36000 square meters .
As a senior Structural design and a cost estimate Engineer I was responsible for hereinafter
listed:
- checking over the BOQ sine the project was a lump sum contract.
- establishing a cost break down structure.
- obtaining Quotations for materials and labors .
- coordinating all the project's disciplines Costs.
- Preparing the forecasted indirect cost for the project.
- Reviewing the Contact Conditions and Its financial terms .
- discussing the margins with the management.
- Finalizing the selling Prices.
- preparing the offer letter based on our stipulations.
- Negotiating with the owner.
- Suggesting alternative cost efficiency solution to meet the client budget.
- still in the negotiating process.
Project 04: Makarm arriyadh Hotel-Riyadh-KSA Value SAR 75 Millions (a
turnkey project ).
the project was 200 bed rooms Hotel consisted of mini tower of 10 floors built over two
basements with a total built up area of 18000 square meters .
As a senior Structural design and a cost estimate Engineer I was responsible for hereinafter
listed:
- checking over the BOQ sine the project was a lump sum contract.
- establishing a cost break down structure.
- obtaining Quotations for materials and labors .
- coordinating all the project's disciplines Costs.
- Preparing the forecasted indirect cost for the project.
- Reviewing the Contact Conditions and Its financial terms .
- discussing the margins with the management.
- Finalizing the selling Prices.
- preparing the offer letter based on our stipulations.
- Negotiating with the owner.
- Suggesting alternative cost efficiency solution to meet the client budget.
- still in the negotiating process.
Alwassat Engineering Office ,Riyadh, KSA, 2010 till 2014
As a structural design engineer in charge of the preparation of the preliminary and final structural design
documents on the following projects:
1. Al Thaghar Plaza in Riyadh - KSA
that project was a shopping mall project , it contained a huge retails , coffee shops and restaurants , the
project was built over 64000 square meter plot area, and it was containing steel structure buildings and
concrete structure buildings.
2. Al Ghamdy warehouses in Riyadh - KSA
the project was built over 22400 square meter plot area, and it was containing steel structure buildings
and concrete structure buildings.
3. Al Nafl Residential Complex in Riyadh - KSA
the project was consist of 40 duplex villas beside a recreation area and facilities , and it was built over one
basement. the plot area for the project was 13800 M2 and a total built up area of 23000 square meters .
4. Al Moroj Residential Complex in Riyadh - KSA
the project was consist of 14 duplex villas, 5 residential buildings of 4 floors each, beside a recreation area
and facilities , and it was built over one basement. the plot area for the project was 9350 M2 and a total
built up area of 30000 square meters.
5. Al Taawoon Residential Complex in Riyadh - KSA
the project was consist of 10 duplex villas, 6 residential buildings of 4 floors each, beside a recreation area
and facilities , and it was built over one basement. the plot area for the project was 12941 M2 and a total
built up area of 35000 square meters.
6. Almousa Mousque.
the project was consist of men's Prayer area , Women's Prayer area, a school for QURAAN and two
minarets of 48.0 m length besides two villas for the Imam and the Mo'zan , and it was built over one
basement. the plot area for the project was 4680 M2
7. Al Saedan Duples Villa
the project was consist of two duplex villas and it was built over one basement. the plot area for the
project was 900 M2 and a total built up area of 2200 square meters.
8. Al Safwa Rest House(Steel structure ).
the project was consist of a public figures and prestigious rest house belongs to Sheikh Ibrahim Al saedan
and it was built over one basement. the plot area for the project was 2500 M2 and a total built up area of
3500 square meters worth to be mentioned that the project were a steel structure building.
9. Al Salman Duplex Villa
the project was consist of four duplex villas and it was built over one basement. the plot area for the
project was 1200 M2 and a total built up area of 2000 square meters.
10. Al Solimania Restaurants Complex.
the project was consist of seven restaurants of 2 floors each and it was built over one basement. the plot
area for the project was 5750 M2 and a total built up area of 9000 square meters.
11. Al Rihab Strip Mall and office building.
the project was consist of a one floor office building built over a ground floor strip mall and it was built,
the plot area for the project was 10000 M2 and a total built up area of 7000 square meters.
12. Khaled Alsalman Mosque.
the project was consist of men's Prayer area , Women's Prayer area, and one minarets of 25.0 m length,
and it was built over one basement. the plot area for the project was 2380 M2
13.Mohammad Al Saedan Rest House.
the project was consist of a prestigious 2 floors rest house and it was built over one basement. the plot
area for the project was 1645 M2 and a total built up area of 2000 square meters .
14. Olaya Duplex Villa.
the project was consist of four duplex villas and it was built over one basement. the plot area for the
project was 875 M2 and a total built up area of 1800 square meters.
15. Al Nagashy Rest House.
the project was a prestigious rest house, the plot area for the project was 2000 M2 and a total built up
area of 800 square meters worth to be mentioned that the project were a steel structure building.
16. Al Salman Rest House.
the project was a prestigious rest house, the plot area for the project was 1500 M2 and a total built up
area of 600 square meters worth to be mentioned that the project were a steel structure building.
17. Mohammad Al Saedan Villa.
the project was a prestigious Duplex Villa built over a basement , the plot area for the project was 1650 M2
and a total built up area of 2000 square .
18. Ahmed Al Saedan Villa.
the project was a prestigious Duplex Villa built over a basement , the plot area for the project was 950 M2
and a total built up area of 1850 square .
19. Staff Residence for Alwassat Engineering Office.
the project was a 3 floor residential building built over a basement , the plot area for the project was 600
M2 and a total built up area of 1500 square .
Alexandria Company for construction- Talat Moustafa- Egypt - 2009 till 2010
Project 01: 6 Residential Building at MADINTY project -Egypt Value LE 60 Millions.
the Project was consisting of 6 residential building of 7 floors each located inside the mega project of MADIATY at
zone B2 within the group 24, my role as a Site Engineer to be Responsible for following up all construction activities
including but not limited to following up the subcontractors to ensure the quality and time efficiency, preparing IR
for the consultant, Planning and scheduling Demanded Resources, Reporting the construction updates to the
construction manager.
ACCESS office for consultants - Egypt - 2008 till 2009
As a structural design engineer in charge of the preparation of the preliminary and final structural design
documents on the following projects:
1. Al WAHA RESIDENTIAL BUILDING in Nassr City - Cairo - EGYPT
the project was a residential building consisted of mini tower of 12 floors built over one basements with a
total built up area of 14250 square meters.
2. Al Tagamoa Building in New Cairo - Cairo - EGYPT
the project was a residential Building consisted of 4 floors building built over one basements with a total
built up area of 3000 square meters.
3. A villa in New Cairo - Cairo - EGYPT
the project was a residential Villa consisted of 2 floors building built over one basements with a total built
up area of 1800 square meters.

More Related Content

What's hot

MEP Design Draughtsman Ducoment
MEP Design Draughtsman DucomentMEP Design Draughtsman Ducoment
MEP Design Draughtsman Ducoment
Hussain Sajid
 
Mustafa Hatem Kadry -CV-00
Mustafa Hatem Kadry -CV-00Mustafa Hatem Kadry -CV-00
Mustafa Hatem Kadry -CV-00
Mustafa Kadry
 
Curriculum vitae1
Curriculum vitae1Curriculum vitae1
Curriculum vitae1
jawadhd
 

What's hot (20)

John CV
John CVJohn CV
John CV
 
Faisal Kazi CV & Portfolio
Faisal Kazi CV & PortfolioFaisal Kazi CV & Portfolio
Faisal Kazi CV & Portfolio
 
Eng. Tarek Ali cv - 29 oct 2015
Eng. Tarek Ali   cv - 29 oct 2015Eng. Tarek Ali   cv - 29 oct 2015
Eng. Tarek Ali cv - 29 oct 2015
 
CV MZ
CV MZCV MZ
CV MZ
 
R PROFILE 0216
R PROFILE 0216R PROFILE 0216
R PROFILE 0216
 
MAA CV 2015
MAA CV 2015MAA CV 2015
MAA CV 2015
 
aboazaar CV.
aboazaar CV.aboazaar CV.
aboazaar CV.
 
Curriculum vita mohamed nabil
Curriculum vita  mohamed nabilCurriculum vita  mohamed nabil
Curriculum vita mohamed nabil
 
Mohamed Nabil Omar - CV
Mohamed Nabil Omar - CVMohamed Nabil Omar - CV
Mohamed Nabil Omar - CV
 
Wael CV Latest1
Wael CV Latest1Wael CV Latest1
Wael CV Latest1
 
Prajeesh K. CV - Sep 2016
Prajeesh K. CV - Sep 2016Prajeesh K. CV - Sep 2016
Prajeesh K. CV - Sep 2016
 
Eng. tarek ali cv - 29 oct 2015
Eng. tarek ali   cv - 29 oct 2015Eng. tarek ali   cv - 29 oct 2015
Eng. tarek ali cv - 29 oct 2015
 
cv porto2
cv porto2cv porto2
cv porto2
 
MEP Design Draughtsman Ducoment
MEP Design Draughtsman DucomentMEP Design Draughtsman Ducoment
MEP Design Draughtsman Ducoment
 
AKANLAR 2015
AKANLAR 2015AKANLAR 2015
AKANLAR 2015
 
Mustafa Hatem Kadry -CV-00
Mustafa Hatem Kadry -CV-00Mustafa Hatem Kadry -CV-00
Mustafa Hatem Kadry -CV-00
 
Curriculum vitae1
Curriculum vitae1Curriculum vitae1
Curriculum vitae1
 
CV2
CV2CV2
CV2
 
Ahmed Abdel Salam 03.2016
Ahmed Abdel Salam 03.2016Ahmed Abdel Salam 03.2016
Ahmed Abdel Salam 03.2016
 
Mohammed Al Naggar Resume
Mohammed Al Naggar ResumeMohammed Al Naggar Resume
Mohammed Al Naggar Resume
 

Similar to Latest C.V (20)

zk resume
zk resumezk resume
zk resume
 
Adly CV111
Adly CV111Adly CV111
Adly CV111
 
Ibrahim al kishki -cv
Ibrahim al kishki -cvIbrahim al kishki -cv
Ibrahim al kishki -cv
 
Personal Profile April 2015
Personal Profile April 2015Personal Profile April 2015
Personal Profile April 2015
 
CV 2015
CV   2015CV   2015
CV 2015
 
NOHA ALI MAHMOUD EL KORDY CV
NOHA ALI  MAHMOUD EL KORDY CVNOHA ALI  MAHMOUD EL KORDY CV
NOHA ALI MAHMOUD EL KORDY CV
 
Ahmed Mohamed Maher Shafik
Ahmed Mohamed Maher ShafikAhmed Mohamed Maher Shafik
Ahmed Mohamed Maher Shafik
 
1 Essam CV
1 Essam CV1 Essam CV
1 Essam CV
 
C.V@ Haytham2015 final
C.V@ Haytham2015 finalC.V@ Haytham2015 final
C.V@ Haytham2015 final
 
Ahmed fergany CV 2642016
Ahmed fergany CV 2642016Ahmed fergany CV 2642016
Ahmed fergany CV 2642016
 
WAEL_CURRICULUM_VITAE-2
WAEL_CURRICULUM_VITAE-2WAEL_CURRICULUM_VITAE-2
WAEL_CURRICULUM_VITAE-2
 
Tarek Hassanain Eladawi - Final
Tarek Hassanain Eladawi - FinalTarek Hassanain Eladawi - Final
Tarek Hassanain Eladawi - Final
 
C.V mr.srdc@yahoo.com DCM
C.V mr.srdc@yahoo.com DCMC.V mr.srdc@yahoo.com DCM
C.V mr.srdc@yahoo.com DCM
 
Emad Hamdy Resume
Emad Hamdy ResumeEmad Hamdy Resume
Emad Hamdy Resume
 
NASEER CV JUNE 2015
NASEER CV JUNE 2015NASEER CV JUNE 2015
NASEER CV JUNE 2015
 
1-Ahmed Amin's C.V
1-Ahmed Amin's C.V1-Ahmed Amin's C.V
1-Ahmed Amin's C.V
 
Resume (final cv)
Resume (final cv)Resume (final cv)
Resume (final cv)
 
kareem zeyada CV
kareem zeyada CVkareem zeyada CV
kareem zeyada CV
 
ARC-HU_C.V-2014 en
ARC-HU_C.V-2014 enARC-HU_C.V-2014 en
ARC-HU_C.V-2014 en
 
CV HASSAN SHARIF ARCHITECT DIYAR
CV HASSAN SHARIF ARCHITECT DIYARCV HASSAN SHARIF ARCHITECT DIYAR
CV HASSAN SHARIF ARCHITECT DIYAR
 

Latest C.V

  • 1. Tamer Samy Nassr Sr. Structural Design and Cost Estimate Engineer E-mail : tamernassrz1986@Gmail.com Core Skills:  Structural Design .  Design Management.  Cost Estimate.  Planning.  Site Coordinator.  Technical Office work Details Position: Sr. Structural design and Cost Estimate Engineer. Education: Bachelor degree in civil Engineer from ZAGAZIG University at 2008. Qualification:  SAP 2000 course.  AutoCAD course.  ETABS.  SAFE12.  Microsoft Office Contact Details Phone : 00966 5 49303615 E-mail : tamernassrz1986@Gmail.com With over 9 years of experience as a Structural Design Engineer, Site Engineer and Cost Estimate Engineer in various construction projects such as retail, hotels, mosque, shopping mall, warehouses, strip malls and residential developments across Egypt and Saudi Arabia. Career History RAM Contracting / KPS - Saudi Arabia - 2014 till date A Senior Structural Engineer and Cost Estimate Engineer, Responsible for the Design review for the tender Structural Drawings and Ensuring its adequacy , Preparing VALUE ENGINEERING studies , Introducing and adequate a cheaper and a time shorten alternative solutions among the different structural systems, Cost analysis, quantity surveying, cash flow forecasting ,planning and scheduling, preparing and Reviewing project's contract as well as leading a team of draftsmen and quantity surveyors to ensure the time and quality efficiency . ALWASSAT ENGINEERING OFFICE - Saudi Arabia - 2010 till 2014 A Structural Design Engineer, Responsible for Designing Concrete Buildings ,Designing Steel Buildings, quantity surveying, reinforcement Details , preparing Biding documents such as the B.O.Q and the project's contract, price analysis for Biding companies, Redesign for coast reduction and following up on site during the construction phase as well as leading a team of draftsmen and quantity surveyors to ensure the time and quality efficiency . Alexandria Company for construction- Talat Moustafa- Egypt - 2009 till 2010 A Site Engineer Responsible for following up all construction activities including but not limited to following up the subcontractors to ensure the quality and time efficiency, preparing IR for the consultant, Planning and scheduling Demanded Resources, Reporting the construction updates to the construction manager. ACCESS office for consultants - Egypt - 2008 till 2009 A Structural Design Engineer, Responsible for Designing Concrete Buildings ,Designing Steel Buildings, quantity surveying, reinforcement Details and following up on site during the construction phase.
  • 2. Projects History RAM Contracting / KPS ,Arrayed, KSA, 2014 till date Project 01: Centro Hotel By Rotana-Riyadh-KSA Value SAR 16 Millions(Skeleton work only). the project was 150 bed room hotel consisted of mini tower of 10 floors built over two basements with a total built up area of 14250 square meters. As a structural and a technical project's engineer based on the site I was responsible for Reviewing the tender Package structural Drawings which was totally un coordinated and un adequate, so I started preparing a new set of structural design coordinated and adequate drawings including structural calculations and models, submitting them for approval, following up with the project consultant (EHAF ) for approving the updated set of drawings for construction then starting over preparing a full set of shop drawings for all the hotel structural elements. Hereinafter listed some of the major issues that I overcame while preparing the restudy: - We faced a huge underestimating material costs , so I bearded this into my mind while updating the structural drawings through proposing a post tension slab system for the project instead of the traditional RC slab as well as customizing the number of columns and reducing the shear walls and cores quantity so we manage to reduce the losses and the time needed for construction. - We faced an Unstable Building as per the tender drawings the was a planted columns - to resist the loads from 10 upcoming floors - on the ground floor slab without a suitable precautions for such case , so I manage to overcame the problem by increasing some of the basement's columns , implementing a new beam elements under the planted columns bearing to mind the not to increase the cost. Project 02: Al Nabet Commercial and Residential project-Khamis mushait-Abha- KSA Value SAR 20 Millions (skeleton work only ). the project was consisting of two parts one of them was commercial building of 5 floors built over one basements with a total built up area of 14000 square meters and another residential building of 4 building with a total built up area of 4000 square meter . Since the handing over of Centro Hotel project I was Promoted to become a senior structural and Cost Estimate Engineer based on the company headquarter and I started my new position with the above mentioned project , here in after what I had accomplished for the project: - Preparing the BOQ sine there was only drawings provided by the owner. - establishing a cost break down structure. - obtaining Quotations for materials and labors . - Preparing the forecasted indirect cost for the project. - Reviewing the Contact Conditions and Its financial terms . - discussing the margins with the management. - Finalizing the selling Prices. - preparing the offer letter based on our stipulations. - Negotiating with the owner till we won the tender and signed the contract.
  • 3. Project 03: Wyndham Garden Hotel-Riyadh-KSA Value SAR 135 Millions (a turnkey project ). the project was 260 bed rooms Hotel consisted of mini tower of 8 floors built over two basements with a total built up area of 36000 square meters . As a senior Structural design and a cost estimate Engineer I was responsible for hereinafter listed: - checking over the BOQ sine the project was a lump sum contract. - establishing a cost break down structure. - obtaining Quotations for materials and labors . - coordinating all the project's disciplines Costs. - Preparing the forecasted indirect cost for the project. - Reviewing the Contact Conditions and Its financial terms . - discussing the margins with the management. - Finalizing the selling Prices. - preparing the offer letter based on our stipulations. - Negotiating with the owner. - Suggesting alternative cost efficiency solution to meet the client budget. - still in the negotiating process. Project 04: Makarm arriyadh Hotel-Riyadh-KSA Value SAR 75 Millions (a turnkey project ). the project was 200 bed rooms Hotel consisted of mini tower of 10 floors built over two basements with a total built up area of 18000 square meters . As a senior Structural design and a cost estimate Engineer I was responsible for hereinafter listed: - checking over the BOQ sine the project was a lump sum contract. - establishing a cost break down structure. - obtaining Quotations for materials and labors . - coordinating all the project's disciplines Costs. - Preparing the forecasted indirect cost for the project. - Reviewing the Contact Conditions and Its financial terms . - discussing the margins with the management. - Finalizing the selling Prices. - preparing the offer letter based on our stipulations. - Negotiating with the owner. - Suggesting alternative cost efficiency solution to meet the client budget. - still in the negotiating process.
  • 4. Alwassat Engineering Office ,Riyadh, KSA, 2010 till 2014 As a structural design engineer in charge of the preparation of the preliminary and final structural design documents on the following projects: 1. Al Thaghar Plaza in Riyadh - KSA that project was a shopping mall project , it contained a huge retails , coffee shops and restaurants , the project was built over 64000 square meter plot area, and it was containing steel structure buildings and concrete structure buildings. 2. Al Ghamdy warehouses in Riyadh - KSA the project was built over 22400 square meter plot area, and it was containing steel structure buildings and concrete structure buildings. 3. Al Nafl Residential Complex in Riyadh - KSA the project was consist of 40 duplex villas beside a recreation area and facilities , and it was built over one basement. the plot area for the project was 13800 M2 and a total built up area of 23000 square meters . 4. Al Moroj Residential Complex in Riyadh - KSA the project was consist of 14 duplex villas, 5 residential buildings of 4 floors each, beside a recreation area and facilities , and it was built over one basement. the plot area for the project was 9350 M2 and a total built up area of 30000 square meters. 5. Al Taawoon Residential Complex in Riyadh - KSA the project was consist of 10 duplex villas, 6 residential buildings of 4 floors each, beside a recreation area and facilities , and it was built over one basement. the plot area for the project was 12941 M2 and a total built up area of 35000 square meters. 6. Almousa Mousque. the project was consist of men's Prayer area , Women's Prayer area, a school for QURAAN and two minarets of 48.0 m length besides two villas for the Imam and the Mo'zan , and it was built over one basement. the plot area for the project was 4680 M2 7. Al Saedan Duples Villa the project was consist of two duplex villas and it was built over one basement. the plot area for the project was 900 M2 and a total built up area of 2200 square meters. 8. Al Safwa Rest House(Steel structure ). the project was consist of a public figures and prestigious rest house belongs to Sheikh Ibrahim Al saedan and it was built over one basement. the plot area for the project was 2500 M2 and a total built up area of 3500 square meters worth to be mentioned that the project were a steel structure building. 9. Al Salman Duplex Villa the project was consist of four duplex villas and it was built over one basement. the plot area for the project was 1200 M2 and a total built up area of 2000 square meters. 10. Al Solimania Restaurants Complex. the project was consist of seven restaurants of 2 floors each and it was built over one basement. the plot area for the project was 5750 M2 and a total built up area of 9000 square meters.
  • 5. 11. Al Rihab Strip Mall and office building. the project was consist of a one floor office building built over a ground floor strip mall and it was built, the plot area for the project was 10000 M2 and a total built up area of 7000 square meters. 12. Khaled Alsalman Mosque. the project was consist of men's Prayer area , Women's Prayer area, and one minarets of 25.0 m length, and it was built over one basement. the plot area for the project was 2380 M2 13.Mohammad Al Saedan Rest House. the project was consist of a prestigious 2 floors rest house and it was built over one basement. the plot area for the project was 1645 M2 and a total built up area of 2000 square meters . 14. Olaya Duplex Villa. the project was consist of four duplex villas and it was built over one basement. the plot area for the project was 875 M2 and a total built up area of 1800 square meters. 15. Al Nagashy Rest House. the project was a prestigious rest house, the plot area for the project was 2000 M2 and a total built up area of 800 square meters worth to be mentioned that the project were a steel structure building. 16. Al Salman Rest House. the project was a prestigious rest house, the plot area for the project was 1500 M2 and a total built up area of 600 square meters worth to be mentioned that the project were a steel structure building. 17. Mohammad Al Saedan Villa. the project was a prestigious Duplex Villa built over a basement , the plot area for the project was 1650 M2 and a total built up area of 2000 square . 18. Ahmed Al Saedan Villa. the project was a prestigious Duplex Villa built over a basement , the plot area for the project was 950 M2 and a total built up area of 1850 square . 19. Staff Residence for Alwassat Engineering Office. the project was a 3 floor residential building built over a basement , the plot area for the project was 600 M2 and a total built up area of 1500 square .
  • 6. Alexandria Company for construction- Talat Moustafa- Egypt - 2009 till 2010 Project 01: 6 Residential Building at MADINTY project -Egypt Value LE 60 Millions. the Project was consisting of 6 residential building of 7 floors each located inside the mega project of MADIATY at zone B2 within the group 24, my role as a Site Engineer to be Responsible for following up all construction activities including but not limited to following up the subcontractors to ensure the quality and time efficiency, preparing IR for the consultant, Planning and scheduling Demanded Resources, Reporting the construction updates to the construction manager. ACCESS office for consultants - Egypt - 2008 till 2009 As a structural design engineer in charge of the preparation of the preliminary and final structural design documents on the following projects: 1. Al WAHA RESIDENTIAL BUILDING in Nassr City - Cairo - EGYPT the project was a residential building consisted of mini tower of 12 floors built over one basements with a total built up area of 14250 square meters. 2. Al Tagamoa Building in New Cairo - Cairo - EGYPT the project was a residential Building consisted of 4 floors building built over one basements with a total built up area of 3000 square meters. 3. A villa in New Cairo - Cairo - EGYPT the project was a residential Villa consisted of 2 floors building built over one basements with a total built up area of 1800 square meters.