Electrical Installations Inspection Checklist
(To be completed on Weekly basis)
Page 1 of 1 Form # HSEQ – EIIC (Rev 7 – Mar 23)
Sl.
No
Description Yes No N/A Comments
DBs/ SDBs
1. Is earth conducted continued up to DB/ SDB?
2.
Whether DBs & extension boards are protected from
rain/ water?
3. Is there any overloading of DBs/ SDBs?
4.
Are correct rated Circuit breakers provided in all main
boards and sub-boards?
5.
Is energized wiring in junction boxes, Circuit board panels
& similar places covered all times?
CABLES
6. Whether the condition of cable is checked?
7.
Are cables received checked for insulation resistance
before using them?
8. Are all main cables taken either underground/ overhead?
9. Are main cables protected from sharp/ heavy materials?
10. Is any improper jointing of cable identified?
11. Are all plugs and sockets in good condition?
RCD (ELCB)
12. Is the connections routed through 30mA RCD?
13. EARTHING
14.
Are main DB, Generator and other panel’s ear thing
done?
15. Earth resistance checked and found within limits?
ELECTRICALLY OPERATED MACHINES/ ACCESSORIES
16.
Whether the machine supply cable has industrial type
socket and plug?
17.
Are all metal parts of electrical equipment and light
fittings/ accessories grounded?
18. Is there any shed/ cover for machines?
19.
Are flood lights/ task lights fixed properly away from
combustibles?
20. Others if any:
Remarks:
Inspected By: Signature:
Reviewed By HSE Manager / In charge : Signature:
Noted by Project Leader : Signature:
Project Information:
Project Name: Company Name:
Location: Date :

More Related Content

What's hot

AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docx
AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docxAIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docx
AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docxDwarika Bhushan Sharma
 
Electrical safety ppt
Electrical safety pptElectrical safety ppt
Electrical safety pptEr Ramgarhia
 
Electrical Safety
Electrical  Safety Electrical  Safety
Electrical Safety Reliance
 
Electrical Maintenance for Engineers and Technicians
Electrical Maintenance for Engineers and TechniciansElectrical Maintenance for Engineers and Technicians
Electrical Maintenance for Engineers and TechniciansLiving Online
 
Industrial electrical safety
Industrial electrical safetyIndustrial electrical safety
Industrial electrical safetyvtsiri
 
RA- Pressure Testing Of Pipe Works
RA- Pressure Testing Of Pipe WorksRA- Pressure Testing Of Pipe Works
RA- Pressure Testing Of Pipe WorksSajid Ali
 
Electrical safety training based on osha 1910 standards sw
Electrical safety training based on osha 1910 standards swElectrical safety training based on osha 1910 standards sw
Electrical safety training based on osha 1910 standards swAniruddha Kulkarni
 
LOTO Training
LOTO TrainingLOTO Training
LOTO TrainingCM Tiwari
 
Electrical safety in construction
Electrical safety in constructionElectrical safety in construction
Electrical safety in constructionsrinivas2036
 
LOCKOUT-TAGOUT-SAFETY PRESENTATION-CONTROL OF HAZARDOUS ENERGY
LOCKOUT-TAGOUT-SAFETY PRESENTATION-CONTROL OF HAZARDOUS ENERGYLOCKOUT-TAGOUT-SAFETY PRESENTATION-CONTROL OF HAZARDOUS ENERGY
LOCKOUT-TAGOUT-SAFETY PRESENTATION-CONTROL OF HAZARDOUS ENERGYjasonmorgan
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputGaurav Singh Rajput
 
Electrical Safety and Risk Assessments
Electrical Safety and Risk AssessmentsElectrical Safety and Risk Assessments
Electrical Safety and Risk AssessmentsMohd Azmatullah
 
Complete Guide to Electrical Safety in the Workplace
Complete Guide to Electrical Safety in the WorkplaceComplete Guide to Electrical Safety in the Workplace
Complete Guide to Electrical Safety in the Workplacehudsonelectrical
 

What's hot (20)

AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docx
AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docxAIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docx
AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docx
 
Electrical safety
Electrical safetyElectrical safety
Electrical safety
 
Electrical safety ppt
Electrical safety pptElectrical safety ppt
Electrical safety ppt
 
Electrical Safety
Electrical  Safety Electrical  Safety
Electrical Safety
 
Fire extinguisher monthly checklist report
Fire extinguisher monthly checklist reportFire extinguisher monthly checklist report
Fire extinguisher monthly checklist report
 
Testing And Commissioning
Testing And CommissioningTesting And Commissioning
Testing And Commissioning
 
Electrical Maintenance for Engineers and Technicians
Electrical Maintenance for Engineers and TechniciansElectrical Maintenance for Engineers and Technicians
Electrical Maintenance for Engineers and Technicians
 
ELECTRICAL ENGINEER CV
ELECTRICAL ENGINEER CVELECTRICAL ENGINEER CV
ELECTRICAL ENGINEER CV
 
Industrial electrical safety
Industrial electrical safetyIndustrial electrical safety
Industrial electrical safety
 
Scissor lift 2 daily inspection log
Scissor lift 2 daily inspection logScissor lift 2 daily inspection log
Scissor lift 2 daily inspection log
 
Electrical maintenance
Electrical maintenanceElectrical maintenance
Electrical maintenance
 
RA- Pressure Testing Of Pipe Works
RA- Pressure Testing Of Pipe WorksRA- Pressure Testing Of Pipe Works
RA- Pressure Testing Of Pipe Works
 
Electrical safety training based on osha 1910 standards sw
Electrical safety training based on osha 1910 standards swElectrical safety training based on osha 1910 standards sw
Electrical safety training based on osha 1910 standards sw
 
LOTO Training
LOTO TrainingLOTO Training
LOTO Training
 
Electrical safety in construction
Electrical safety in constructionElectrical safety in construction
Electrical safety in construction
 
LOCKOUT-TAGOUT-SAFETY PRESENTATION-CONTROL OF HAZARDOUS ENERGY
LOCKOUT-TAGOUT-SAFETY PRESENTATION-CONTROL OF HAZARDOUS ENERGYLOCKOUT-TAGOUT-SAFETY PRESENTATION-CONTROL OF HAZARDOUS ENERGY
LOCKOUT-TAGOUT-SAFETY PRESENTATION-CONTROL OF HAZARDOUS ENERGY
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
 
Electrical Safety and Risk Assessments
Electrical Safety and Risk AssessmentsElectrical Safety and Risk Assessments
Electrical Safety and Risk Assessments
 
Power tools safety
Power tools safetyPower tools safety
Power tools safety
 
Complete Guide to Electrical Safety in the Workplace
Complete Guide to Electrical Safety in the WorkplaceComplete Guide to Electrical Safety in the Workplace
Complete Guide to Electrical Safety in the Workplace
 

Similar to ELECTRICAL INSTALLATIONS INSPECTION CHECKLIST Form # HSEQ - EIIC Rev 7.docx

Power Cable Fault Location - Medium & High Voltage Cables
Power Cable Fault Location - Medium & High Voltage CablesPower Cable Fault Location - Medium & High Voltage Cables
Power Cable Fault Location - Medium & High Voltage CablesThorne & Derrick International
 
HT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
HT & LT Bus Ducts Manufacturer in Telangana and Andhra PradeshHT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
HT & LT Bus Ducts Manufacturer in Telangana and Andhra PradeshMohit Bathineni
 
testing-grounding-systems.ppt
testing-grounding-systems.ppttesting-grounding-systems.ppt
testing-grounding-systems.pptBayuAnggoro46
 
New project report
New project reportNew project report
New project reportSai Printers
 
Hazards in the home from mains electricity
Hazards in the home from mains electricityHazards in the home from mains electricity
Hazards in the home from mains electricitym55mick
 
30 Workplace Temporary Electrical Supply Risk Assessment Templates.docx
30 Workplace Temporary Electrical Supply Risk Assessment Templates.docx30 Workplace Temporary Electrical Supply Risk Assessment Templates.docx
30 Workplace Temporary Electrical Supply Risk Assessment Templates.docxDwarika Bhushan Sharma
 
Electrical and Electronics lab manual
Electrical and Electronics lab manualElectrical and Electronics lab manual
Electrical and Electronics lab manualCyber4Tech
 
Electronics lecture Sanoop A P 2
Electronics lecture Sanoop A P 2Electronics lecture Sanoop A P 2
Electronics lecture Sanoop A P 2Sanoop Ap
 
Indian railway&metro rail,others electrical safety first periorty
Indian railway&metro rail,others electrical safety first periortyIndian railway&metro rail,others electrical safety first periorty
Indian railway&metro rail,others electrical safety first periortyMahesh Chandra Manav
 
Experiment no. 1
Experiment no. 1Experiment no. 1
Experiment no. 1Suhas Chate
 
IRMC-2021-Preventing-Failures-in-Isolated-Phase-Bus-Timperley.pdf
IRMC-2021-Preventing-Failures-in-Isolated-Phase-Bus-Timperley.pdfIRMC-2021-Preventing-Failures-in-Isolated-Phase-Bus-Timperley.pdf
IRMC-2021-Preventing-Failures-in-Isolated-Phase-Bus-Timperley.pdfMichaelDelaCruz418510
 
Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission lineFazlur Rahman
 
Equipment Audits for LV, MV, HV for annual mandatory record keeping by Niels
Equipment Audits for LV, MV, HV for annual mandatory record keeping by NielsEquipment Audits for LV, MV, HV for annual mandatory record keeping by Niels
Equipment Audits for LV, MV, HV for annual mandatory record keeping by NielsNiels Inderbiethen
 
Nbc2016 and iec information jmv lps
Nbc2016 and iec information jmv lpsNbc2016 and iec information jmv lps
Nbc2016 and iec information jmv lpsMahesh Chandra Manav
 
Water level indicator by bhushan kumbhalkar
Water level indicator by  bhushan kumbhalkarWater level indicator by  bhushan kumbhalkar
Water level indicator by bhushan kumbhalkarBhushan Kumbhalkar
 
VG Railway S & T wiring check list rev 00
VG  Railway S & T wiring check list rev 00VG  Railway S & T wiring check list rev 00
VG Railway S & T wiring check list rev 00Varadharajalu Gopal
 

Similar to ELECTRICAL INSTALLATIONS INSPECTION CHECKLIST Form # HSEQ - EIIC Rev 7.docx (20)

Power Cable Fault Location - Medium & High Voltage Cables
Power Cable Fault Location - Medium & High Voltage CablesPower Cable Fault Location - Medium & High Voltage Cables
Power Cable Fault Location - Medium & High Voltage Cables
 
HT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
HT & LT Bus Ducts Manufacturer in Telangana and Andhra PradeshHT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
HT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
 
Tan Delta on MV Cables (Megger)
Tan Delta on MV Cables (Megger)Tan Delta on MV Cables (Megger)
Tan Delta on MV Cables (Megger)
 
testing-grounding-systems.ppt
testing-grounding-systems.ppttesting-grounding-systems.ppt
testing-grounding-systems.ppt
 
New project report
New project reportNew project report
New project report
 
Hazards in the home from mains electricity
Hazards in the home from mains electricityHazards in the home from mains electricity
Hazards in the home from mains electricity
 
Code questions
Code questionsCode questions
Code questions
 
30 Workplace Temporary Electrical Supply Risk Assessment Templates.docx
30 Workplace Temporary Electrical Supply Risk Assessment Templates.docx30 Workplace Temporary Electrical Supply Risk Assessment Templates.docx
30 Workplace Temporary Electrical Supply Risk Assessment Templates.docx
 
Electrical and Electronics lab manual
Electrical and Electronics lab manualElectrical and Electronics lab manual
Electrical and Electronics lab manual
 
Electronics lecture Sanoop A P 2
Electronics lecture Sanoop A P 2Electronics lecture Sanoop A P 2
Electronics lecture Sanoop A P 2
 
Indian railway&metro rail,others electrical safety first periorty
Indian railway&metro rail,others electrical safety first periortyIndian railway&metro rail,others electrical safety first periorty
Indian railway&metro rail,others electrical safety first periorty
 
Experiment no. 1
Experiment no. 1Experiment no. 1
Experiment no. 1
 
IPBD-Timperley.pdf
IPBD-Timperley.pdfIPBD-Timperley.pdf
IPBD-Timperley.pdf
 
IRMC-2021-Preventing-Failures-in-Isolated-Phase-Bus-Timperley.pdf
IRMC-2021-Preventing-Failures-in-Isolated-Phase-Bus-Timperley.pdfIRMC-2021-Preventing-Failures-in-Isolated-Phase-Bus-Timperley.pdf
IRMC-2021-Preventing-Failures-in-Isolated-Phase-Bus-Timperley.pdf
 
Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission line
 
Equipment Audits for LV, MV, HV for annual mandatory record keeping by Niels
Equipment Audits for LV, MV, HV for annual mandatory record keeping by NielsEquipment Audits for LV, MV, HV for annual mandatory record keeping by Niels
Equipment Audits for LV, MV, HV for annual mandatory record keeping by Niels
 
Nbc2016 and iec information jmv lps
Nbc2016 and iec information jmv lpsNbc2016 and iec information jmv lps
Nbc2016 and iec information jmv lps
 
Water level indicator by bhushan kumbhalkar
Water level indicator by  bhushan kumbhalkarWater level indicator by  bhushan kumbhalkar
Water level indicator by bhushan kumbhalkar
 
VG Railway S & T wiring check list rev 00
VG  Railway S & T wiring check list rev 00VG  Railway S & T wiring check list rev 00
VG Railway S & T wiring check list rev 00
 
ELVD Shock Preventer
ELVD Shock Preventer ELVD Shock Preventer
ELVD Shock Preventer
 

More from Dwarika Bhushan Sharma

4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdfDwarika Bhushan Sharma
 
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdfDwarika Bhushan Sharma
 
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdfDwarika Bhushan Sharma
 
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdfDwarika Bhushan Sharma
 
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docxDwarika Bhushan Sharma
 
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docxFIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docxDwarika Bhushan Sharma
 
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxSUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxDwarika Bhushan Sharma
 
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxSTORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxDwarika Bhushan Sharma
 
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxPROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxDwarika Bhushan Sharma
 
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docxHSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docxDwarika Bhushan Sharma
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxDwarika Bhushan Sharma
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxDwarika Bhushan Sharma
 
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxMOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxDwarika Bhushan Sharma
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxDwarika Bhushan Sharma
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docxDwarika Bhushan Sharma
 
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docHSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docDwarika Bhushan Sharma
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docDwarika Bhushan Sharma
 
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxOFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxDwarika Bhushan Sharma
 

More from Dwarika Bhushan Sharma (20)

4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
 
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
 
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
 
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
 
1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf
 
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
 
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docxFIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
 
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxSUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
 
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxSTORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
 
WITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docxWITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docx
 
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxPROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
 
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docxHSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
 
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxMOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
 
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docHSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
 
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxOFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
 

Recently uploaded

Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...HenryBriggs2
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptxrouholahahmadi9876
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksMagic Marks
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...jabtakhaidam7
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxmaisarahman1
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesMayuraD1
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 

Recently uploaded (20)

Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic Marks
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 

ELECTRICAL INSTALLATIONS INSPECTION CHECKLIST Form # HSEQ - EIIC Rev 7.docx

  • 1. Electrical Installations Inspection Checklist (To be completed on Weekly basis) Page 1 of 1 Form # HSEQ – EIIC (Rev 7 – Mar 23) Sl. No Description Yes No N/A Comments DBs/ SDBs 1. Is earth conducted continued up to DB/ SDB? 2. Whether DBs & extension boards are protected from rain/ water? 3. Is there any overloading of DBs/ SDBs? 4. Are correct rated Circuit breakers provided in all main boards and sub-boards? 5. Is energized wiring in junction boxes, Circuit board panels & similar places covered all times? CABLES 6. Whether the condition of cable is checked? 7. Are cables received checked for insulation resistance before using them? 8. Are all main cables taken either underground/ overhead? 9. Are main cables protected from sharp/ heavy materials? 10. Is any improper jointing of cable identified? 11. Are all plugs and sockets in good condition? RCD (ELCB) 12. Is the connections routed through 30mA RCD? 13. EARTHING 14. Are main DB, Generator and other panel’s ear thing done? 15. Earth resistance checked and found within limits? ELECTRICALLY OPERATED MACHINES/ ACCESSORIES 16. Whether the machine supply cable has industrial type socket and plug? 17. Are all metal parts of electrical equipment and light fittings/ accessories grounded? 18. Is there any shed/ cover for machines? 19. Are flood lights/ task lights fixed properly away from combustibles? 20. Others if any: Remarks: Inspected By: Signature: Reviewed By HSE Manager / In charge : Signature: Noted by Project Leader : Signature: Project Information: Project Name: Company Name: Location: Date :