Open Compute Project, Critical Facilities Operations Framework
Process: Lifecycle & Financial Management
Rev 2020-07-29
Information classification: Public
Contents
• Process overview
• Lessons learned / customer experiences
• Final notes
LIFECYCLE & FINANCIAL MANAGEMENT
OCP Critical Facilities Operations Framework
Site Operations
Integration
Terms &
Conditions
OCP CFOPS Delivery model
Incidents
Work Orders & Projects
On-site Access
Service Levels
Organization
KPI Monitoring
& Reporting
Lifecycle &
Financial
Mgmt
On-site
services
Security &
Access
Maintenance
In / outdoor
FM
Site
assistance
Site Inspection
Audits and
Compliance
Site Management
Delivery Support
Service Level
Mgmt
Lifecycle &
Financial
Mgmt
WO & Project
Mgmt
Monitoring &
Reporting
Governance
and BCP
Advisory and
Benchmarking
Supply Chain
and Sourcing
Service Desk
24/7
Incident Mgmt
Team &
Suppliers
Capacity
Mgmt &
Optimization
Document
Mgmt
Compliance
Mgmt
Service
Improvements
Asset List
Border List
Customer
Managed
Operating
Center
Source: OCP CFOPS 2019 v1.4
Lifecycle and Financial Management
MindMap Overview Process Summary
Site systems lifecycle management
• At time of purchase of a site system, lifecycle
management rely on the vendors’
specifications for End Of Life (EOL).
• Those specifications are based on laboratory
measurements and there can be a significant
deviation from the specification and
operation in a real site.
• Therefore, lifecycle management monitors
the actual costs and operational properties
of the supply system items during their
lifetime.
• The aim is to control warranty rights and
requirements and create a change-out
forecast for the items.
Source: OCP CFOPS 2019 v1.4
Lessons learned / Customer experiences
“When outsourcing the inhouse Site Management Function, one key
need for the Site Owner was to improve warranty management.
There was a frustration that OPEX was higher than planned due to
vendors charging for replacement components earlier than expected.
The root-cause turned out to be issues in another Site Management
process: Document Management.
The earlier inhouse function did not have control over the Asset Lists,
e.g. commissioning dates for site systems, vendors’ specifications for
End Of Life, or a repository for vendor warranties or compliance
certificates…”
Lifecycle and Financial Management
MindMap Overview Process Summary
Financial management
• The aim is to budget and
forecast site costs.
• This is done by analyzing and
accounting all services and site
systems costs.
• Costs that are not directly
related to an item or service
should be distributed by cost
distribution models.
Source: OCP CFOPS 2019 v1.4
Lessons learned / Customer experiences
“The Site management function had made three-year forecasts and calendar-
year budgets for a portfolio of multiple sites in several cities for many years.
The costs were split by site system and vendor categories, e.g. power
distribution or security services. These costs were shared among the sites.
The sites were sold to a new owner who had a different Cost Distribution
Model: no costs were to be shared between the sites. These should be broken
down and related to each site system for each site (e.g. planned preventive
maintenance works for UPS 1 on site A).
After some rework, the Cost Distribution Model was re-established with 80%
being split by site system category and site (e.g. Maintenance to the Power
Distribution of Site A) and 20% was considered shared costs (e.g. Site
Management for portfolio of sites)...”
Lifecycle and Financial Management
MindMap Overview Process Summary
Tender and selection
• Purchasing of services and site systems
should consider requirements on
– Resilience
– Robustness
– Total Cost of Ownership (TCO)
• The approach should include energy costs as
well as investment and services.
• Requirements of operations concerning
reliability, maintainability and integration
into monitoring should also be considered.
• Decommissioning of infrastructure elements
should be based on actual TCO and according
to recycling and sustainability obligations.
Source: OCP CFOPS 2019 v1.4
Lessons learned / Customer experiences
“A Critical Facility-as-a-Service has been contracted for a 10+
year period. The Customer pays a fixed quarterly fee to cover
all Site Operations, its required materials and any asset risks.
To ensure opportunities to improve margins are considered,
the Site Management function continuously considers
challenging suppliers with more cost-efficient options.
A joint project with the corporate Supply Chain Manager
resulted in an annual reduction of costs for technical cleaning
with 12 percent…”
Final notes
• Change out forecast should not be confused
with vendor End-of-Life
• Cost Distribution Models should be clarified
• Selecting service providers and site systems
should consider more than price
Questions?
coromatic.com
3. Process: ocp cfops lifecycle and financial mgmt

More Related Content

What's hot

2. Process: ocp cfops service level mgmt
2. Process: ocp cfops service level mgmt2. Process: ocp cfops service level mgmt
2. Process: ocp cfops service level mgmtssusereb347d
 
11. Process: ocp cfops maintenance
11. Process: ocp cfops maintenance11. Process: ocp cfops maintenance
11. Process: ocp cfops maintenancessusereb347d
 
7. Process: ocp cfops compliance mgmt
7. Process: ocp cfops compliance mgmt7. Process: ocp cfops compliance mgmt
7. Process: ocp cfops compliance mgmtssusereb347d
 
13. Process: ocp cfops site inspections
13. Process: ocp cfops site inspections13. Process: ocp cfops site inspections
13. Process: ocp cfops site inspectionsssusereb347d
 
8. Process: ocp cfops document mgmt
8. Process: ocp cfops document mgmt8. Process: ocp cfops document mgmt
8. Process: ocp cfops document mgmtssusereb347d
 
4. ocp cfops.monitoring reporting.guideline.2019.5
4. ocp cfops.monitoring reporting.guideline.2019.54. ocp cfops.monitoring reporting.guideline.2019.5
4. ocp cfops.monitoring reporting.guideline.2019.5ssusereb347d
 
6. Process: ocp cfops capacity mgmt and optimization
6. Process: ocp cfops capacity mgmt and optimization6. Process: ocp cfops capacity mgmt and optimization
6. Process: ocp cfops capacity mgmt and optimizationssusereb347d
 
16. Process: ocp cfops delivery support
16. Process: ocp cfops delivery support16. Process: ocp cfops delivery support
16. Process: ocp cfops delivery supportssusereb347d
 
17. Process: ocp cfops integration
17. Process: ocp cfops integration17. Process: ocp cfops integration
17. Process: ocp cfops integrationssusereb347d
 
17. ocp cfops.integration.guideline.2019.1
17. ocp cfops.integration.guideline.2019.117. ocp cfops.integration.guideline.2019.1
17. ocp cfops.integration.guideline.2019.1ssusereb347d
 
12. Process: ocp cfops indoor outdoor fm
12. Process: ocp cfops indoor outdoor fm12. Process: ocp cfops indoor outdoor fm
12. Process: ocp cfops indoor outdoor fmssusereb347d
 
0. ocp cfops flyby
0. ocp cfops flyby0. ocp cfops flyby
0. ocp cfops flybyssusereb347d
 
8. ocp cfops.document mgmt.guideline.2019.2
8. ocp cfops.document mgmt.guideline.2019.28. ocp cfops.document mgmt.guideline.2019.2
8. ocp cfops.document mgmt.guideline.2019.2ssusereb347d
 
IAB Europe Metrics & KPIs Brand Advertiser Bulletin
IAB Europe Metrics & KPIs Brand Advertiser BulletinIAB Europe Metrics & KPIs Brand Advertiser Bulletin
IAB Europe Metrics & KPIs Brand Advertiser BulletinIAB Europe
 
RealWinWin Wholesale Rebate Administration Services
RealWinWin Wholesale Rebate Administration ServicesRealWinWin Wholesale Rebate Administration Services
RealWinWin Wholesale Rebate Administration ServicesRealWinWin, Inc.
 
Shared Services_Compliance_credential
Shared Services_Compliance_credentialShared Services_Compliance_credential
Shared Services_Compliance_credentialGene Goziker
 
Telefonica Case Study
Telefonica Case Study  Telefonica Case Study
Telefonica Case Study Felipe Scholz
 
Curriculum Vitae esure
Curriculum Vitae esureCurriculum Vitae esure
Curriculum Vitae esureIan Richmond
 

What's hot (20)

2. Process: ocp cfops service level mgmt
2. Process: ocp cfops service level mgmt2. Process: ocp cfops service level mgmt
2. Process: ocp cfops service level mgmt
 
11. Process: ocp cfops maintenance
11. Process: ocp cfops maintenance11. Process: ocp cfops maintenance
11. Process: ocp cfops maintenance
 
7. Process: ocp cfops compliance mgmt
7. Process: ocp cfops compliance mgmt7. Process: ocp cfops compliance mgmt
7. Process: ocp cfops compliance mgmt
 
13. Process: ocp cfops site inspections
13. Process: ocp cfops site inspections13. Process: ocp cfops site inspections
13. Process: ocp cfops site inspections
 
8. Process: ocp cfops document mgmt
8. Process: ocp cfops document mgmt8. Process: ocp cfops document mgmt
8. Process: ocp cfops document mgmt
 
4. ocp cfops.monitoring reporting.guideline.2019.5
4. ocp cfops.monitoring reporting.guideline.2019.54. ocp cfops.monitoring reporting.guideline.2019.5
4. ocp cfops.monitoring reporting.guideline.2019.5
 
6. Process: ocp cfops capacity mgmt and optimization
6. Process: ocp cfops capacity mgmt and optimization6. Process: ocp cfops capacity mgmt and optimization
6. Process: ocp cfops capacity mgmt and optimization
 
16. Process: ocp cfops delivery support
16. Process: ocp cfops delivery support16. Process: ocp cfops delivery support
16. Process: ocp cfops delivery support
 
17. Process: ocp cfops integration
17. Process: ocp cfops integration17. Process: ocp cfops integration
17. Process: ocp cfops integration
 
17. ocp cfops.integration.guideline.2019.1
17. ocp cfops.integration.guideline.2019.117. ocp cfops.integration.guideline.2019.1
17. ocp cfops.integration.guideline.2019.1
 
12. Process: ocp cfops indoor outdoor fm
12. Process: ocp cfops indoor outdoor fm12. Process: ocp cfops indoor outdoor fm
12. Process: ocp cfops indoor outdoor fm
 
0. ocp cfops flyby
0. ocp cfops flyby0. ocp cfops flyby
0. ocp cfops flyby
 
8. ocp cfops.document mgmt.guideline.2019.2
8. ocp cfops.document mgmt.guideline.2019.28. ocp cfops.document mgmt.guideline.2019.2
8. ocp cfops.document mgmt.guideline.2019.2
 
IAB Europe Metrics & KPIs Brand Advertiser Bulletin
IAB Europe Metrics & KPIs Brand Advertiser BulletinIAB Europe Metrics & KPIs Brand Advertiser Bulletin
IAB Europe Metrics & KPIs Brand Advertiser Bulletin
 
RealWinWin Wholesale Rebate Administration Services
RealWinWin Wholesale Rebate Administration ServicesRealWinWin Wholesale Rebate Administration Services
RealWinWin Wholesale Rebate Administration Services
 
Shared Services_Compliance_credential
Shared Services_Compliance_credentialShared Services_Compliance_credential
Shared Services_Compliance_credential
 
Telefonica Case Study
Telefonica Case Study  Telefonica Case Study
Telefonica Case Study
 
Development Services Technology Update
Development Services Technology UpdateDevelopment Services Technology Update
Development Services Technology Update
 
Curriculum Vitae esure
Curriculum Vitae esureCurriculum Vitae esure
Curriculum Vitae esure
 
MainManager Specifications
MainManager SpecificationsMainManager Specifications
MainManager Specifications
 

Similar to 3. Process: ocp cfops lifecycle and financial mgmt

Mobility in Field Services Management: Part One
Mobility in Field Services Management: Part OneMobility in Field Services Management: Part One
Mobility in Field Services Management: Part OneCognizant
 
Mobility in Field Services Management: Part One
Mobility in Field Services Management: Part OneMobility in Field Services Management: Part One
Mobility in Field Services Management: Part OneCognizant
 
Cloud Migration Business Case.pptx
Cloud Migration Business Case.pptxCloud Migration Business Case.pptx
Cloud Migration Business Case.pptxAbhishek232103
 
Innovations in program controls integrating primavera and cost systems
Innovations in program controls   integrating primavera and cost systemsInnovations in program controls   integrating primavera and cost systems
Innovations in program controls integrating primavera and cost systemsp6academy
 
Bridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems pptBridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems pptp6academy
 
High Performance Building Management System.Ppt
High Performance Building Management System.PptHigh Performance Building Management System.Ppt
High Performance Building Management System.Pptpcholakis30
 
0.Commercial Management slides _Lvl3.pdf
0.Commercial Management slides _Lvl3.pdf0.Commercial Management slides _Lvl3.pdf
0.Commercial Management slides _Lvl3.pdfRahulSamadhiya2
 
April 20 Briefing With Team
April 20 Briefing With TeamApril 20 Briefing With Team
April 20 Briefing With TeamWilliam Francis
 
Softchoice Discovery Series: Cloud Cost Governance
Softchoice Discovery Series: Cloud Cost GovernanceSoftchoice Discovery Series: Cloud Cost Governance
Softchoice Discovery Series: Cloud Cost GovernanceSoftchoice Corporation
 
Switch to Results in Commercial Buildings by Wipro EcoEnergy
Switch to Results in Commercial Buildings by Wipro EcoEnergySwitch to Results in Commercial Buildings by Wipro EcoEnergy
Switch to Results in Commercial Buildings by Wipro EcoEnergyShreeja Sahadevan
 
Applicability of Activity-Based Costing and Related Management Tools: The c...
Applicability of Activity-Based Costing and Related Management Tools: The c...Applicability of Activity-Based Costing and Related Management Tools: The c...
Applicability of Activity-Based Costing and Related Management Tools: The c...Faculty of Economics Ljubljana in Skopje
 
Agile Transformation
Agile TransformationAgile Transformation
Agile TransformationBosnia Agile
 
5 itil v3 service transition 5 v1.8
5 itil v3 service transition 5 v1.85 itil v3 service transition 5 v1.8
5 itil v3 service transition 5 v1.8Karthik Arumugham
 
3.0 UK Link Platform Performance Update V2.0.pptx
3.0 UK Link Platform Performance Update V2.0.pptx3.0 UK Link Platform Performance Update V2.0.pptx
3.0 UK Link Platform Performance Update V2.0.pptxssuserc1306e
 
Savannah memorial rf success ap44
Savannah memorial rf success ap44Savannah memorial rf success ap44
Savannah memorial rf success ap44lponssa
 
Chapter 18 Contract and Relationship Management
Chapter 18 Contract and Relationship ManagementChapter 18 Contract and Relationship Management
Chapter 18 Contract and Relationship ManagementTran Thang
 
Linked In Presentation 2012
Linked In Presentation 2012Linked In Presentation 2012
Linked In Presentation 2012EnergyROI
 

Similar to 3. Process: ocp cfops lifecycle and financial mgmt (20)

Mobility in Field Services Management: Part One
Mobility in Field Services Management: Part OneMobility in Field Services Management: Part One
Mobility in Field Services Management: Part One
 
Mobility in Field Services Management: Part One
Mobility in Field Services Management: Part OneMobility in Field Services Management: Part One
Mobility in Field Services Management: Part One
 
Cloud Migration Business Case.pptx
Cloud Migration Business Case.pptxCloud Migration Business Case.pptx
Cloud Migration Business Case.pptx
 
Innovations in program controls integrating primavera and cost systems
Innovations in program controls   integrating primavera and cost systemsInnovations in program controls   integrating primavera and cost systems
Innovations in program controls integrating primavera and cost systems
 
The Journey Towards Asset Management Excellence
The Journey Towards Asset Management ExcellenceThe Journey Towards Asset Management Excellence
The Journey Towards Asset Management Excellence
 
Bridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems pptBridging the cost schedule divide - integrating primavera and cost systems ppt
Bridging the cost schedule divide - integrating primavera and cost systems ppt
 
High Performance Building Management System.Ppt
High Performance Building Management System.PptHigh Performance Building Management System.Ppt
High Performance Building Management System.Ppt
 
0.Commercial Management slides _Lvl3.pdf
0.Commercial Management slides _Lvl3.pdf0.Commercial Management slides _Lvl3.pdf
0.Commercial Management slides _Lvl3.pdf
 
April 20 Briefing With Team
April 20 Briefing With TeamApril 20 Briefing With Team
April 20 Briefing With Team
 
Softchoice Discovery Series: Cloud Cost Governance
Softchoice Discovery Series: Cloud Cost GovernanceSoftchoice Discovery Series: Cloud Cost Governance
Softchoice Discovery Series: Cloud Cost Governance
 
Switch to Results in Commercial Buildings by Wipro EcoEnergy
Switch to Results in Commercial Buildings by Wipro EcoEnergySwitch to Results in Commercial Buildings by Wipro EcoEnergy
Switch to Results in Commercial Buildings by Wipro EcoEnergy
 
Applicability of Activity-Based Costing and Related Management Tools: The c...
Applicability of Activity-Based Costing and Related Management Tools: The c...Applicability of Activity-Based Costing and Related Management Tools: The c...
Applicability of Activity-Based Costing and Related Management Tools: The c...
 
Outsourcing - Reza Hagel CPO & Principle
Outsourcing - Reza Hagel CPO & PrincipleOutsourcing - Reza Hagel CPO & Principle
Outsourcing - Reza Hagel CPO & Principle
 
Agile Transformation
Agile TransformationAgile Transformation
Agile Transformation
 
5 itil v3 service transition 5 v1.8
5 itil v3 service transition 5 v1.85 itil v3 service transition 5 v1.8
5 itil v3 service transition 5 v1.8
 
3.0 UK Link Platform Performance Update V2.0.pptx
3.0 UK Link Platform Performance Update V2.0.pptx3.0 UK Link Platform Performance Update V2.0.pptx
3.0 UK Link Platform Performance Update V2.0.pptx
 
West CPSM, C.P.M. Lisa Resume 6.28.2016
West CPSM, C.P.M. Lisa Resume 6.28.2016West CPSM, C.P.M. Lisa Resume 6.28.2016
West CPSM, C.P.M. Lisa Resume 6.28.2016
 
Savannah memorial rf success ap44
Savannah memorial rf success ap44Savannah memorial rf success ap44
Savannah memorial rf success ap44
 
Chapter 18 Contract and Relationship Management
Chapter 18 Contract and Relationship ManagementChapter 18 Contract and Relationship Management
Chapter 18 Contract and Relationship Management
 
Linked In Presentation 2012
Linked In Presentation 2012Linked In Presentation 2012
Linked In Presentation 2012
 

Recently uploaded

Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIkoyaldeepu123
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 

Recently uploaded (20)

Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AI
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 

3. Process: ocp cfops lifecycle and financial mgmt

  • 1. Coromatic Academy Open Compute Project, Critical Facilities Operations Framework Process: Lifecycle & Financial Management Rev 2020-07-29 Information classification: Public
  • 2. Contents • Process overview • Lessons learned / customer experiences • Final notes
  • 3. LIFECYCLE & FINANCIAL MANAGEMENT OCP Critical Facilities Operations Framework
  • 4. Site Operations Integration Terms & Conditions OCP CFOPS Delivery model Incidents Work Orders & Projects On-site Access Service Levels Organization KPI Monitoring & Reporting Lifecycle & Financial Mgmt On-site services Security & Access Maintenance In / outdoor FM Site assistance Site Inspection Audits and Compliance Site Management Delivery Support Service Level Mgmt Lifecycle & Financial Mgmt WO & Project Mgmt Monitoring & Reporting Governance and BCP Advisory and Benchmarking Supply Chain and Sourcing Service Desk 24/7 Incident Mgmt Team & Suppliers Capacity Mgmt & Optimization Document Mgmt Compliance Mgmt Service Improvements Asset List Border List Customer Managed Operating Center Source: OCP CFOPS 2019 v1.4
  • 5. Lifecycle and Financial Management MindMap Overview Process Summary Site systems lifecycle management • At time of purchase of a site system, lifecycle management rely on the vendors’ specifications for End Of Life (EOL). • Those specifications are based on laboratory measurements and there can be a significant deviation from the specification and operation in a real site. • Therefore, lifecycle management monitors the actual costs and operational properties of the supply system items during their lifetime. • The aim is to control warranty rights and requirements and create a change-out forecast for the items. Source: OCP CFOPS 2019 v1.4
  • 6. Lessons learned / Customer experiences “When outsourcing the inhouse Site Management Function, one key need for the Site Owner was to improve warranty management. There was a frustration that OPEX was higher than planned due to vendors charging for replacement components earlier than expected. The root-cause turned out to be issues in another Site Management process: Document Management. The earlier inhouse function did not have control over the Asset Lists, e.g. commissioning dates for site systems, vendors’ specifications for End Of Life, or a repository for vendor warranties or compliance certificates…”
  • 7. Lifecycle and Financial Management MindMap Overview Process Summary Financial management • The aim is to budget and forecast site costs. • This is done by analyzing and accounting all services and site systems costs. • Costs that are not directly related to an item or service should be distributed by cost distribution models. Source: OCP CFOPS 2019 v1.4
  • 8. Lessons learned / Customer experiences “The Site management function had made three-year forecasts and calendar- year budgets for a portfolio of multiple sites in several cities for many years. The costs were split by site system and vendor categories, e.g. power distribution or security services. These costs were shared among the sites. The sites were sold to a new owner who had a different Cost Distribution Model: no costs were to be shared between the sites. These should be broken down and related to each site system for each site (e.g. planned preventive maintenance works for UPS 1 on site A). After some rework, the Cost Distribution Model was re-established with 80% being split by site system category and site (e.g. Maintenance to the Power Distribution of Site A) and 20% was considered shared costs (e.g. Site Management for portfolio of sites)...”
  • 9. Lifecycle and Financial Management MindMap Overview Process Summary Tender and selection • Purchasing of services and site systems should consider requirements on – Resilience – Robustness – Total Cost of Ownership (TCO) • The approach should include energy costs as well as investment and services. • Requirements of operations concerning reliability, maintainability and integration into monitoring should also be considered. • Decommissioning of infrastructure elements should be based on actual TCO and according to recycling and sustainability obligations. Source: OCP CFOPS 2019 v1.4
  • 10. Lessons learned / Customer experiences “A Critical Facility-as-a-Service has been contracted for a 10+ year period. The Customer pays a fixed quarterly fee to cover all Site Operations, its required materials and any asset risks. To ensure opportunities to improve margins are considered, the Site Management function continuously considers challenging suppliers with more cost-efficient options. A joint project with the corporate Supply Chain Manager resulted in an annual reduction of costs for technical cleaning with 12 percent…”
  • 11. Final notes • Change out forecast should not be confused with vendor End-of-Life • Cost Distribution Models should be clarified • Selecting service providers and site systems should consider more than price

Editor's Notes

  1. Clear market leader in turnkey data centers and other critical facilities Highly skilled and experienced workforce operating out of 20 locations Unrivalled experience as a full-service provider of turnkey critical facilities solutions Proven international delivery capabilities Strong Nordic customer base across a wide range of industries