5. 1. Why Commercial Management?
• Need for Effective Cost Control System
• Identifying Past Trends and Forecasting Future
• Identifying Deviations from Budget
• Risk Management
• Late Completion
• Cost Over Run
• Suspension
• Termination
• Successful closeout
6. Objective of Commercial Management in Construction
6
Commercial Management is defined as:
"The identification and development of business
opportunities and the profitable management of
projects and contracts, from inception to completion." -
ICM.
“The main objective of Commercial Management is
to see how commercial competitiveness balances
against profitability with through understanding of
the financial processes used to achieve profitability
and how these can integrate with the overall
delivery of the project “.
.
7. A) Need of Commercial
Management in Construction
B) How commercial
competitiveness balances
against Profitability?
C)Financial processes used to
achieve Profitability
D)How Financial processes
integrate with the overall
delivery of the project
8. 2. Role of a Commercial Manager
• With Contractor
• Review and Verification of Estimates, Preparation of / Response to
Tenders / Commercial Proposals, Drafting Contractual / Commercial
Correspondence, Identification & Management of Commercial Risks,
Linking with Procurement Team, Contract Administration &
Negotiation of Changes, Analyzing Costs & Profit for Project /
Business, Cost Control, etc.
• With Consultant
• Estimating, Cost Planning, Budget Preparation, Risk Management,
Value Management, Value Engineering, Benchmarking, Life Cycle
Costing, Procurement, Tender Evaluation, Change Control,
Assessment of Variations / Claims, Preparing Financial Statements,
Cash Flow Forecasts, Cost Control, Reconciliations, Interim
Valuations, Final Account, etc.
• With Client
• Managing Budgets, Change Control, Preparation and Management
of Tender / Procurement Process, Identification and Management of
Commercial Risks, Contract Administration, Cash Flow Forecasts,
Payment Certification, Final Account, etc.
9. Employer/
Developer
Project
Manager/
Engineer/
Consultants
Contractor
Commercial Manager role in
9
Sub-Contractor Suppliers
Specialists
B] Role of Commercial Manager
In any industry, the role of a commercial manager is to maximize the potential of a
business in terms of profitability. The manager monitors, or controls, internal
processes such as production, and manages external relationships with
customers, clients and trading partners.
10. 3. RICS – APC Reading List
3.1 Estimating and Establishing Budgets
3.2 Cash Flows
3.3 Reporting Financial Progress
3.4 Procurement of Labour, Plant and Materials
3.5 Procurement of Sub-Contracts
3.6 Financial Management
11. 3.1 Estimating & Establishing Budgets
• Components of Budget / Estimate
• Effect of the Design and Construction Processes on the Cost
• Estimating Techniques
Unit Method
Superficial Method
Elemental Cost Plan
Comparative Cost Plan
Approximate Quantities
• Operational Estimate
• Estimator’s Report
12. Estimate
An approximation of the cost of a construction project or
operation, produced to progress the project to the
construction phase. By its nature, this is usually
produced pre-construction and pre-contract.
Budget
(also ‘budget to build’ and ‘post- tender budget’).
An evolution of the estimate, updated to reflect information
not available when the estimate was first produced; an
estimated plan of the cost to complete the project from the
contract award, based on the project team’s planned
procurement and delivery methods.
The budget should be continually updated until project
completion.
13.
14. Estimates of regular items are
common in our practice.
Let us see
Estimation of Preliminaries
• Factors to be considered in
Estimation of Preliminaries /
General Requirements
• Documents to refer while
preparation of preliminaries
• Model Item : Elements to
consider to estimate the cost of
running a Site office .
14
15.
16. 3.2 Cash Flows
• Types of Cash Flow Forecasts
• Use of Cash Flows
• Preparing Cash Flows
Effect of Valuation Methods
Effect of Contractual Procedures
Curves & Formulae
Adjustments to Cash Flow Forecasts
• Monitoring, Analysing, Reporting and Advising on Cash Flows
• Financial Implications and Appropriate Management Actions
17. Project’s Cash Flow based upon the formulae and provides the flexibility to
specify how additional factors are handled including:
1.Retention
2.Defects Liability Period
3.Preliminaries –running costs to be valued on a ‘work done’ or ‘time related’
basis.
4.Lump Sum items – enables the user to specify when specific expenditure will
occur – particularly useful for a particular piece of equipment or a specific sub-
contract.
4.Advance Payment – when advance payments are required the user may specify
the amount, the date of payment, the date to start retrieval and the period over
which retrieval is required.
5.Actual Payments – once the contract is underway Actual Payments may be
inserted thus allowing a comparison with the Initial Forecast and Revised
Forecasts to be produced.
18. 3.3 Reporting Financial Progress
• Techniques to Reconcile Cost against Income
• Collecting of Data for Reports
• Preparing Reports
Cost to Complete (CC)
Cost Value Reconciliations (CVR)
Contract Variance
Earned Value Analysis (EVA)
• Monitoring, Analysing, Reporting and Advising on
Profitability
• Financial Implications and Appropriate Management
Actions
19.
20. 3.4 Procurement of Labour, Plant and Materials
• Supply Chain
• Labour Costs
• Material Costs
• Plant Costs
• Overhead & Profit
• Units of Measurement in BoQ
21. 3.5 Procurement of Sub-Contracts
• Domestic Sub-Contractors
• Named Sub-Contractors
• Nominated Sub-Contractors
• Techniques to Financially Manage Sub-Contractors /
Suppliers
22. 3.6 Financial Management
• Efficient Data Management
• Efficient Change Management
• Value Management / Value Engineering
• Efficient Management of Sub-Contractors & Suppliers
• Risk Management
• Cash Flow Management
• Effective Cost Control
23. MODEL VALUATION
FORMATS
Implementation
of agreed formats
for interim
valuations for
effective post
Contract
Administration
Proactive
Approach to
design and agree
Valuation formats
with Clients in
the beginning
stages
Successful
closeout of final
account with
minimum conflicts
24.
25. Main Contents in Payment Certificate
o Value of Works completed based on progress
o Value of Works completed in Agreed variations
o Advance Payments
o Recovery of advance payments
o Materials on-site
o Material off-site
o Retention amounts
o Agreed and approved Claims
o Previous interim payments paid
o Applicable LDs
26. COST VALUE RECONCILIATION FOR CONTRACTORS
In Building and Civil Engineering Works, the preparation of
Construction Contractor’s Cost – Value Reconciliation (CVR)’ is an
important tool in tracking the ‘financial health’ of construction
projects and early identification of potential commercial
problems.
Aims & Objectives :
•Show Profit/Loss on each individual contract on a monthly basis
•Show Profit/Loss for the current accounting period
•Current cash position of the company
•Ability to identify/action and reduce cost liabilities on a monthly
basis
•Plan company expenditure
•Monitor and adjust estimating rates based on the profit/loss
reporting.
27. What are the components of a financial report?
Contract Reference
Package name and reference
Budget associated with each contract / package
Contract Price
Instructed variations (agreed / not agreed)
Anticipated variations (forecast)
Claims / EOT
Forecast Out-turn Cost
Expenditure summary
Financial Status -Cumulative and for this month
28. Key Features of a Partnering Contract
• Collaborative approach
• A partnering charter signed by all the parties involved highlighting
the spirit of team work
• Provision for KPIs to measure project progress
• Non-adversarial nature of contract
• Provision of early warning signs and the mechanism for review of
problems and resolution of same
• Provision for Value Engineering
• Provision for incentives for the proposals that helps in reducing
the cost.
31. Special Skills of Commercial Manager
( Cost , Time , IT, Communications, Management , Leadership)
32. Main Reading List -Commercial Management in Construction
Estimating & Establishing budgets
Cash flows Reporting financial progress against budget
Preliminaries Bills - understand the methods of costing Preliminaries items
The method of costing management and Supervision
Value Engineering and Value Management
Life Cycle Costing
Financial management and Reports
Financial management of sub-contracts and multiple projects
33. Model APC Questions : Commercial Management in Construction
THANK YOU AND WISH YOU ALL THE BEST