SlideShare a Scribd company logo
1 of 39
Safety module
Overview of safety hazard:
What is hazard?
A hazard is any source of potential damage, harm or adverse health effects on
something or someone under certain condition at work.
How to behave inside the plant:
• No loose clothing.
• Safe distance is to be maintained from rotating machine.
• Any electrical installation should not be touched.
• Safe distance should be kept from bare live terminals.
• Helmet is a must.
• Nobody should move in dark spaces.
• Nobody should move alone.
• Be aware from floor opening.
• Avoid moving on checker plate.
• Nobody should move over the trenches.
• Railing should not be leant upon.
• Moving into confined spaces (congested closed area with lower concentration of oxygen,
and containing mixture of toxic and explosive gases) for eg any flue duct, furnace, inside
the condenser, cooling water duct, sewerage lines is to be avoided.
• One should not move in regions where lifting work is being carried out.
• One should not go into a unit which is under maintenance.
• One must avoid going near welding and gas cutting sparks and must use safety glasses.
uNSafe aCt aNd uNSafe CoNdItIoNS SHould tHeRefoRe Be
aVoIded.
CHEMICAL HAZARDS :
Hydrogen, chlorine, ammonia and carbon monoxide leakage-
 HYDROGEN: This being highly explosive, use of mobile phones should be avoided
and combustibles should not be kept near hydrogen cylinders.
 CHLORINE: Chlorine is used in water treatment plants.Inhalation of chlorine causes
its combination with water in mucus membrane to form Hydrochloric acid. It causes
pitting in the membrane and respiratory problems start.
o Precautions:
In case of chlorine leakage,one must go as up as possible because chlorine being
2.5 times heavier than air its density decreases with height.
STEL value : 3 ppm.
 AMMONIA : Ammonia is found near ESP and boiler. Inhalation of ammonia may
cause vomiting and head-ache.
 CARBON MONOXIDE: Carbon monoxide may be found in Feeder floor, bunker
floor etc. Inhalation causes it to mix with Haemoglobin in blood to form carboxy-
haemoglobin that chokes the person. So it is often termed as “killer gas”.
o Precautions:
It can be removed quickly from the body of the person if he is taken immediately into
an open area.
STEL value: 400 ppm.
BaSIC uNdeRStaNdINg of tHeRmal poweR geNeRatIoN
In a thermal power plant, the thermal energy of the superheated steam is used to drive
the generator, which in turn produces electricity. The superheated steam is produced from any
fossil fuel like coal, crude oil etc. Since coal is available in plenty and in cheap, we use coal as
the primary fuel in the thermal power plants. The coal is crushed and pulverized before it is used
in the boiler. The pulverization of coal increases the surface area of the coal, which helps in the
complete combustion of the coal. The coal is feed to the boiler where it is fired to produce heat.
Initially, a small quantity of crude oil is used for the purpose. The water is passed through the
pipes making up the walls of the boiler. The water is heated to produce steam, which is further
reheated to produce superheated steam. The superheated steam at an exceedingly high temp.
Steam pressure drives the turbine. The turbine rotates following which the generator, which is
coupled to the turbine, also rotates producing electricity.
Thus, the chemical energy of the coal is utilized to produce steam. The thermal energy
of the steam is converted to the mechanical energy of the rotating turbines, which is converted to
the electrical energy in the generator.
NtpC faRaKKa SupeR tHeRmal poweR plaNt
NTPC Farakka is a coal fired pit head based power plant. Lalmatia is the captive coal mine for
this plant. Total capacity of NTPC Farakka is 2100MW.The plant consists of three stages. These
are:
STAGE I : 3 units of 200MW
STAGE II : 2 units of 500MW
STAGE III : 1 unit of 500MW
Generation voltage level for Stage-I is 15.75 KV and for Stage-II and Stage-III is 21KV.The
generated voltage is stepped up to 400KV for transmitting over a long distance.
dIStINCtIoN BetweeN Stage-III aNd otHeR StageS :
STAGE-I and STAGE-II : Cooling Water is taken from the feeder canal and after using in the
condenser the hot water is returned to the feeder canal, hence it is an open cycle system. It
causes threat to aquatic life.
STAGE III : Cooling tower is used in this system. After using the water in the condenser it is
recirculated through cooling tower, where the hot water is cooled and reused. This is a closed
cycle system and causes less harm to the environment.
Supply of Raw mateRIalS:
A) COAL: There are 3 sources of coal supply as:
• Lalmatia situated 85 Kms away from the main plant.
• Imported coal from Indonesia.
• Indian railways who supply coal from different mines across the country.
B) WATER:
Feedwater: Collected from feeder canal cut across the river Ganga.
Cooling Water: Collected from the same source.
C) AIR: atmospheric air is used.
D) OIL: HFO is supplied by IOCL.
aSH dISpoSal:
For the quality of coal used here, approximately 80% Fly Ash and 20% bottom ash is produced.
Ash disposal is a major issue in coal fired power plants.Raw water is mixed with ash to form
slurry and pumped out through series pumps( 3 for Fly ash and 2 for Bottom ash ) into ash
dyke.Fly ash dyke is situated 12 Kms away and Bottom ash dyke MALANCHA is situated 5
Kms away from the main plant.
poweR eVaCuatIoN:
The generated power is evacuated through different outgoing lines:
1)Farakka-Malda (2 lines)
2) Farakka-Kahalgaon (2 lines)
3) Farakka-Durgapur (2 lines)
4) Farakka-Lalmatia (1 line)
5)Farakka-Jeerat(2 lines)
Initially there were 9 lines. Few more lines were added after commissioning of Stage III.
dIffeReNt CyCleS INVolVed IN tHe eNtIRe opeRatIoN:
• FUEL CIRCUIT :
• Coal is brought into CHP with the help of Wagon tipplers or track hoppers and
stored in the bunker.
• From bunker coal is sent to feeder via conveyer.
• The purpose of feeder is to vary the amount of coal as per load requirement.
• From feeder coal is taken to mill where it is pulverized.
• Primary air is sucked from atmosphere through PA fan and takes pulverized coal
to the furnace.
Fig1: Coal circuit
2) AIR & FLUE GAS CIRCUIT:
• Secondary air is sucked from atm. with the help of FD fan(Forced Draught) for
combustion.A fire ball is generated inside the boiler.The temp. of fire ball is
1000-1100 deg. C.
• Flue gas is generated due to combustion.
• Heat is extracted from flue gas to heat the steam in platen SH, reheater,final SH,
primary SH , economiser and to heat air in air preheater.
• Fly ash particles are collected from flue gas at ESP(Electrostatic Precipitator) and
flue gas is released to atm. with the help of ID fan(Induced Draught) which is
situated at the base of chimney.
Fig2: Air & Flue gas circuit
3) STEAM, CONDENSATE & FEED WATER CYCLE:
• In 200MW unit of the plant the boiler drum is located at the height of 54m.
• Inner wall of the boiler made up of water tubes which originate from bottom ring
header situated 7m from ground level.
• DM water picks up heat from fire ball and goes up as a mixture of steam and
water.Then it reaches drum .As steam being lighter it goes upward.Water comes
down through DOWNCOMER .In 200MW unit no. of downcomers is 6 and
natural circulation of steam and water takes place.But in 500MW unit the boiler
drum being at a height of 72m forced circulation is employed. by through 10
downcomers.
• Steam is separated from water in the boiler drum with the help of CYCLONE
SEPARATOR & SECONDARY SEPARATOR(corrugated sheets) and it follows
the circuit shown below.
Fig 3: Steam,Condensate & Feed Water cycle
4) COOLING WATER CIRCUIT:
• Raw water is taken from the feeder canal through CW pump.
• Raw water is passed through TRASH RACKS and TRAVELLING WATER
SCREENS to remove impurities (animal bodies, planktons etc) of different sizes.
• Raw water is stored at the water box at the inlet of condenser and it flows through
the innumerable number of condenser tubes. In stage I there are 13000 such tubes.
The water comes at the outlet and is stored at the outlet water box.
• The condensate is stored in the HOTWELL at a temperature of 45 deg C.
• In STAGE-I and STAGE-II, after using in the condenser the hot water is returned
to the feeder canal, hence it is an open cycle system.
• In STAGE III, Cooling tower is used. After using the water in the condenser it is
recirculated through cooling tower, where the hot water is cooled and reused. This
is a closed cycle system and causes less harm to the environment.
Fig4: Cooling Water circuit
5) ASH CIRCUIT:
• The ash is collected in two forms as Bottom ash(20%) and Fly ash(80%).
• Ash can be disposed in dry form or wet form.
• Fly ash particles are collected in ESP.In ESP,there are large numbers of
EMITTING ELECTRODE(supplied at 80 KV) and COLLECTING
ELECTRODE(at ground potential).
• Fly ash particles are deposited on the collecting electrodes and HAMMERED into
ESP HOPPERS.
• Slurry is formed by mixing raw water with Fly ash and pumped out to Fly ash
dyke with the help of FASPs(Fly ash slurry pumps)
• Similarly, Bottom ash is collected in the BOTTOM ASH HOPPERS and disposed
in slurry form in the Bottom ash dyke with the help of BASPs(Bottom ash slurry
pumps).
Fig5:Ash disposal system
BaSIC deSCRIptIoN of flow of Coal:
(1) CHP (Coal Handling Plant): The input coal is unloaded at this portion, which passes it to
the next block crusher house.
(2) Crusher house: crusher house crush the unloaded coal coming from the CHP in small
size.
(3) Coal Bunker: Coalbunker stores the crushed coal and passes it to the Feeder.
(4) RC Feeder: It is the raw coal feeder. The coal, comes from the crusher house is still of big
size. The feeder controls the quantity of the input coal to the boiler.
(5) Mill / pulveriser: Mill contains three rollers. It crushes it to powder finely. Primary air
takes the pulverized coal from the mill to the boiler.
(6) Furnace : At furnace pulverized coal is combusted with the help of secondary air.
BRIef deSCRIptIoN of SyStem CompoNeNtS:
Main components of the power plant are:
1) Boiler:
• In Farakka NTPC, corner fired boilers are used. In stage I, there are 6 mills
situated from a height of 18m to 27m. FIRING FLOORS of mill A is at a height
of 18m and that of mill F is at 27m. Rest of the firing floors are situated in
between. HFO OIL GUNS are situated at heights of AB, CD and EF.
• Purpose of oil gun: a) during boiler start up , b) emergency purpose.
Fig 6: HFO Flow System
• The working oil supplied by IOCL is stored in HFO tank 2. The oil in this tank is
replenished by oil in tanks 1 and 3. The heat lost due to transportation is compensated
by HEATER. HFO Circulation takes place all the time so that temperature of oil is
maintained at 120 deg C when plant is running.
• In case of shut down of any mill, the coal particles on the corresponding floor may not
get sufficient ignition energy and thereby the fireball distorts and subsequently two
separate balls are formed on either side of that mill. In that case HFO injection makes up
that gap and stabilizes the fire ball.
• The coal is composed of 4 parts – fixed carbon(FC),Volatile material(VM),Moisture &
ash. The VM supplies the initial ignition energy for the complete combustion of FC. If
the VM content in the coal used is less the coal particles have to travel a larger path to
attain the required ignition energy and hence the fireball is formed at greater height.
Fig7: Isometric View of Boiler schematic
Fig8: Top view of firing floor corresponding to mill A
• It is critical to maintain the level of water in boiler drum.
Case 1: level of water goes too high: water may go into the steam circuit. When water hits the
turbine blades, PITTING may occur. (the high velocity water particles may produce indentations
in the turbine blades)
Case 2: level of water goes low: If it is too low, the boiler drum base being close to the fire ball,
its shape gets deformed. Also low water level causes water in the drum to get evaporated at a
faster rate than the rate at which water is returned from hotwell to the drum
There are mainly three types of heater coils in boiler.
(1) Economiser
(2) Re heater
(3) Super heater
 Economizer:
Economizer is a device in which the feed water is heated before it enters into a boiler.
The heat is being taken from the waste flue gas of the boiler. It ensures economy of fuel. Hence
it is called economizer. The economizer is placed at the second pass of boiler. The flue gases of
the boiler furnace, after working inside the boiler, flows through it before passing into the
chimney.
 Coal bunker-
These are in process storage silos used for storing crushed coal from the coal handling
system. Generally, these are made up of welded steel plates. Normally there are six such bunkers
supplying coal of the corresponding mills. These are located on the top of the mills so as to aid in
gravity feeding of coal.
 P. A. Fan-
The primary air fans (2 per unit-50% capacity each) are designed to suck primary air
from atmosphere. Temperature of PA is increased to 300 deg C after passing through Air Pre-
heater. These fans are located at ‘0’M level near the boiler.
 Burners-
As evident from the name itself, these are used for burning pulverized coal. Every unit
has a set of such burners located at different elevations of the furnace.
 F. D. Fan-
These forced draught fans (2 per unit-50% capacity each) are designed for handling
secondary air for the boiler. These fans are located at ‘0’M level near the P.A Fan.
Electrostatic Precipitator-
 Air Pre-heater-
Air pre heater transfer the heat from the flue gas to cold primary and/or secondary air by
extracting heat from waste flue gas. These are located in the secondary pass of the furnace at a
height of around ‘16’M level. Each 200MW unit is provided with two such air pre-heaters.
 ID Fans-
These are two induced draught fans per boiler located between the ESP & chimney.
These fans are used for maintaining pressure inside the boiler by releasing flue gas through
chimney.
 Chimney-
These are tall RCC structures with single/multiple flue ducts (one flue duct per 200MW
unit). The heights of these chimneys vary, depending upon the location considerations; anywhere
between 150m to 220m.
Steam Circulation System
 Re-heaters-
This is the part of the boiler which receives the steam back from the turbine after it has given up
some of its heat energy in the high pressure section of the turbine. It raises the temperature of
this steam, usually to its original value, for further expansion in the turbine. The purpose of this
reheating is to add energy to the partially used steam. The construction & arrangement is similar
to super heater. It has two sections- hot & cold Reheat sections. Due to resistance of flow
through the reheat section, the hot reheat steam is at lower pressure compared to the cold reheat
steam.
water treatment plant and storage
USE OF MAKE UP WATER:
Since there is continuous withdrawal of steam and continuous return of condensate to the boiler,
losses due to blow down and leakages have to be made up to maintain a desired water level in
the boiler steam drum. For this, continuous make-up water is added to the boiler water system.
HARDNESS IN RAW WATER AND REMOVAL:
Impurities in the raw water input to the plant generally consist of calcium and magnesium salts
which impart hardness to the water. Hardness in the make-up water to the boiler will form
deposits on the tube water surfaces which will lead to overheating and failure of the tubes. This
is called SCALING. Thus, the salts have to be removed from the water, and that is done by a
water demineralizing treatment plant (DM). A DM plant generally contains ION
EXCHANGERS. Any ions in the final water from this process consist essentially of hydrogen
ions and hydroxide ions, which recombine to form pure water.
The capacity of the DM plant is dictated by the type and quantity of salts in the raw water input.
However, some storage is essential as the DM plant may be down for maintenance. For this
purpose, a storage tank is installed from which DM water is continuously withdrawn for boiler
make-up. The storage tank for DM water is made from materials not affected by corrosive water.
The piping and valves are generally of stainless steel.
 Boiler feed pump-
It takes water input from the deaeretor at a very low pressure and pumps it to the boiler
drum at a very high pressure (190Kg).
 Condenser-
 Ejectors-
There are two 100%capacity ejectors of the steam ejecting type. The purpose of the
ejector is to evacuate air and other non-condensing gases from the condensers and thus maintain
the vacuum in the condensers.
 Condensate Extraction Pump-
It extracts the condensate from the hot well of the condenser and pumps it to the de-
aerator.
 L. P. Heaters-
Turbine has been provided with non-controlled extractions which are utilized for heating
the condensate, from turbine bleed steam. There are 4 low pressure heaters in which last four
extractions are used.L.P.Heater-1 has two parts LPH-1A and LPH-1B located in the upper parts
of the condenser A & B respectively. These are of the horizontal type with shell and tube
construction. L.P.H 2,3,4 are of similar construction and they are mounted in row at 5M level.
 Deaerator-
This is used to remove oxygen. Due to the presence of certain gases like oxygen, carbon-
di-oxide, ammonia, etc. in water then it is considered harmful because of their corrosive effect on
metals, particularly at elevated temperatures. The boiler feed water should be free from all
dissolved gases. This can be achieved by embodying into the boiler feed system a de-aerating
system, whose function is to remove dissolved gases from the feed water by mechanical means.
 H. P. Heaters-
These are regenerative feed water heaters operating at high pressures and located at the
side of turbine. These are connected in series on feed-water side & by such arrangement feed-
water enters the HP heaters. The steam is supplied to these heaters from the bleed point of the
turbine through motor operated valves. These have a group bypass protection on the feed
waterside. Here the feed water flows through the tube spirals & is heated by steam around the
tubes in the shall of heaters. These heaters are cylindrical vessels with welded dished ends &
with integrated, de-super heating, condensing, & & sub cooling sections. This design offers the
advantage to optimize the arrangement of piping & the location of the heaters at power station.
2) TURBINE:
Fig 9: Turbine cycle
• Steam after working in the HP turbine temperature is reduced from 540 deg to 340 deg C.
Pressure is also substantially reduced. The line of flow of steam from HP turbine is
COLD REHEAT LINE or CRH LINE.
• CRH line again goes to the boiler to be reheated at 540 deg C by the heat of the flue gas.
This line is known as the HOT REHEAT LINE or HRH LINE. HRH Line goes to the IP
Turbine. Exhaust steam from IP Turbine goes to the LP Turbine.
• Exhaust of LP Turbine (80 deg C) goes to CONDENSER. COOLING WATER is
circulated to cool down the steam and the condensate drains into the HOTWELL at 35
deg C.
• From HOTWELL the condensate is sent back to boiler drum through different processes
and reused.
• The pressure of MS line is ~160 Kg/sqcm, that of HRH line is ~33-34 Kg/sq cm and
CRH Line pressure is ~34 Kg/sqcm.
• With the help of modulation of HP Control valves (HPCV) and IPCV alternator
frequency is kept constant by controlling the amount of inlet steam.
• STOP VALVE is used to stop the entry of steam into the turbine.
turbine section
 Turbine Lub. Oil System
This consists of Main Oil Pump (MOP), Starting Oil Pump (SOP), AC stand by oil
pumps and emergency DC oil pump and jacking oil pump (JOP) (one each per unit).
 Emergency stop valves and control valves
Turbine is equipped with emergency stop valves to cut off steam supply and with control
valves regulate steam supply. Emergency stop valves (ESV) are provided in the mainsteam line
and interceptor valves are provided in the hot reheat line. Emergency stop valves are actuated by
servomotor controlled by the protection system. Control valves are actuated by the governing
system through servomotors to regulate steam supply as required by the load.
 Generator
The main shaft of the turbine is connected to the rotor of the main generator. The shaft
rotates the rotor, which cuts the flux of the armature coil, and as a result an induced emf is
produced.
 Compressed Air System
There are two types of compressed air system namely Instrument air system or control air
system & Station air system.
 Air Compressor-
The station air compressor is a generally slow speed type & is arranged for belt drive.
The cylinder heads and barrel are enclosed in a jacket which extends around the valve also. The
inter cooler is provided between the low and high pressure cylinder which cools the air between
stage and collects the moisture that condenses.
switcHYard
Switch yard is the place adjacent to the power house where the transformers, circuit breakers,
isolators, bus bars, CT & PTs, lightning arrestors, current limiting reactors and other equipments
are installed. ACSR conductors are used in the line wires.
One and a half breaker scheme is used here. Three circuit breakers are used for controlling two
circuits which are connected between two bus bars. Normally, both the bus bars are in service. A
fault on any one of the bus bars is cleared by opening of the associated circuit breakers
connected to the faulty bus bar without affecting continuity of supply. Similarly, any circuit
breaker can be taken out for maintenance without causing interruption.
<| This is one and a half breaker scheme
Though unit 4 has double breaker scheme.
Reactor: A reactor is a coil having large inductive reactances in comparison to its ohmic
resistance and is introduced in a circuit or system to limit the short circuit currents to a safer
value in order to protect the electrical installation. Oil immersed type reactors are employed here.
Insulation and cooling arrangement employed are similar to those of an ordinary transformer.
Wave trap: This is used to block high frequency component.
Circuit Breaker: Circuit Breaker acts like a switch when a failure
occurs in transmission line.It is very
Costly equipment.
In one and a half scheme there is 3 breakers in one dia created by 2
main bay and one tie bay.
In one circle there is six breakers.
Isolator: Isolator isolates the breaker from the line for maintenance
purpose or to save breaker in
Switching time as breaker is costly.
CT & PT: CT and PT is there for protection and metering purpose.
Lightning Arrester: It is an electrical device inserted in a power line to protect equipment from
Sudden fluctuations in current. It is also known as Surge Protector.
CVT: It senses any overvoltage of line. It helps in communication
between two sub stations also. As capacitor gives low impedence for high frequency
so communication signal goes through it to PLCC (Power Linear Carrier Communication ) panel
. It helps in Tele-protection, Tele –metering and Tele-communication. This is called carrier-aided
protection system. The band of this signal is 30 kHz-500kHz, but to reduce noise it is kept as
50kHz to 500 kHz. It is trapped by Wave Trap before the transformer connection and maintain
communication process between substations using supply line as communication line.
Bus Reactor: To balance the reactive power consumed by transmission line shunt reactor is there
to make the line a lossless line.
TURBOGENERATOR
FSTPP has 5 units (stage-I : 3 x 200 and stage-II : 2 x 500)of 3-phase synchronous generators
which convert mechanical energy to electrical energy.The generators are coupled to the steam
turbine shaft.
Specification:
The following table shows the rating of the Generators of stage-I and stage-II.
Rated parameters Stage-I Stage-II
MAX. CONTINUOUS KVA RATING 247000 588000
MAX. CONTINUOUS KW RATING 210000 500000
RATED POWER FACTOR 0.83 lag 0.83 lag
STATOR Voltage 15750 21000
Current 9050 16200
ROTOR Voltage 310 240
Current 2600 4030
RATED SPEED 3000 3000
RATED FREQUENCY 50 50
PHASE CONNECTION YY YY
NO. OF TERMINALS BROUGHT OUT OF STATOR 9 9
COOLANT Water & Hydrogen Water & Hydrogen
GAS PRESSURE 3.5 kg/cm2
3.5 kg/cm2
INSULATION CLASS B B
MAKER’S NAME BHARAT HEAVY ELECTRICALS LTD.
DIFFERENT PARTS
1. Stator - Stator Frame (Fabrication & Machining)
2. Core Assembly - Stator Core, Core Suspension Arrangement
3. End Shield
4. Stator Winding Assembly - Stator Winding , Winding Assembly,Connecting Bus bar
5. Rotor - Rotor Shaft, Rotor Wedges, Rotor Coils, Wound Rotor, Rotor Assembly
6. Completing Assembly - Bearing Assembly, Shaft Seal Assembly, Oil Catchers,Insert Cover
etc
7. Exciter
8. Auxiliary System
The machine usually consists of two main parts:
1. STATOR
1) FRAME 2) MAGNET CORE
3) WINDINGS
STATOR FRAME
It is a fabricated gas tight steel
structure suitably ribbed internally.
It can withstand explosion pressure of
hydrogen air mixture without any
residual deformation. H2 gas coolers
are housed longitudinally inside stator
body.
STATOR CORE
Stator core is made up of insulated punchings of CRGO Si steel and is laminated to minimize
eddy current loss. It provides path for machines’ magnetic flux and has slots in which windings
are assembled.Core bars are designed to provide elastic suspension of core in stator.
STATOR WINDINGS
The windings are three phase fractional pitched distributed in two layers of individual bars.
Generator voltage is induced in the stator windings and use of water cooling permits a high value
of current density in the machine.
The use of combination of solid and hollow conductors effectively reduces the depth of the slot
which affect the losses in the winding, and better utilization of slots.
2. ROTOR
It is the rotating part and houses the field windings. It is a cylindrical type rotor.
Rotor body is a high strength alloy steel single forging prepared by vacuum cast steel,containing
slots for housing field windings and is supported on two bearings. The coils are held against
centrifugal forces by means of wedges and by means of non-magnetic retaining ring on the
overhang part of the winding.
FIELD WINDING
These are made from hard drawn silver bearing copper.
Gas(H2) pickup system is employed for complete cooling of rotor.
Two propeller type fans are shaft mounted on either side of rotor body for circulating cooling gas inside
generator.
Special ducts (fins) are provided in the rotor body, through which the cooling
gas flows to the rotor end windings.
SLIP RINGS
Helically grooved alloy steel rings are shrunk on rotor shafts and insulated from it.Slip rings are
connected to field windings through semi flexible copper lead
COOliNG sysTEm Of ThE GENERATOR
Generator auxiliary system are broadly classified into 3 parts:
1. STATOR WATER SYSTEM
Stator water cooling is a closed loop system. There are two full capacity single stage centrifugal pumps
with change over facility. The pumps are driven by 3Ph. 415V A.C. motors. The stator water cooler is
shell and tube type heat exchanger. DM water flows through the shell. There are two mechanical filters
and one magnetic filters. Mechanical filters are of wire mesh type. Magnetic filter is having permanent
magnet. The expansion tank is a hermetically sealed container made of S.S. Float valve is there in the
expansion tank to maintain water level in the tank which act as suction storage tank for stator water
pumps. Polishing unit (mixed bed ion exchanger) is there to maintain conductivity of stator water to
desired level.
2)SEAL OIL SYSTEM
Generator shaft seals are supplied with pressurized seal oil to prevent hydrogen escape at the shaft
Oil pressure is kept higher than the gas pressure. There are one AC seal oil pp. and one DC seal oil pp.
which feed oil to the seal through cooler and filter.
• A vacuum pump is provided to maintain vacuum in seal oil tank The seal oil pressure to the seal is
controlled by DPR which maintain specified DP between oil and hydrogen. There is provision for thrust
oil to hold the seal ring in position against H2 pressure (0.5kg/cm2 more than seal oil pressure). There are
2 oil coolers to cool the hot oil.
POLISH UNIT
FILTERS
COOLER
SS
PUMPS
GAS TRAP
FLOW
METERS
CCCCCC CONDUCTIVITY
CONDUCTIVITY
CTIVITYO
EXPANSION TANK
TANK
MAKE UP
up
UP
FSII
DIFF PRESS.
MAGNET
FILTER
BEARG
DRAINS
TG
1 2
EE
BEARING
TE
BEARING
GAS
EXHAUST
FROM GAS
SYSTEM
IOT
VACUUM
TANK
SOST
SOP
SOP-3
DC
DP
SW
TS
ES FR
FLOW M.
PS
PG
•
2. GAS SYSTEM
Generator gas system constitutes of hydrogen gas used to cool the rotor and certain parts of stator. H2-air
mixture is explosive. So filling the generator with H2 by replacing air is dangerous. So initially air is
replaced by CO2 and since CO2 is heavier than air CO2 is being filled from the bottom. Purging of air
with CO2 is being done till the purity of CO2 inside casing reaches above 95%.
Now H2 is dried and then passed from the top to replace the CO2. Purging of H2 is continued till purity
of H2 reaches 98%.
Why H2 is used as a coolant?
• H2 is lightest gas with 0.09 gm / litre while air’s 1.3 i.e. 14.4 times & high thermal capacity
• Thermal conductivity of H2 is 5 times that of air. Its specific heat is 3.42 at 0°C, as
compared to 0.237 of air.
• 2 H2 + O2 mixture ignites on adiabatic compression at 526°C, 3H2 + O2 at 544°C. H2 and
O2 combine slowly at 180°C or in bright sunlight. Explosion occurs with moist gases at 550
- 700°C. Ignition temp. of H2 in air is 538°C & Calorific value of H2 is 136 k Cal / gm.
• For filling in TGs, 99.9% v/v purity gas is used. Traces of SO2 & NH3 shall not be
detectable
• Two propeller type fans are shaft mounted on either side of rotor body for circulating H2 in the
generator.The H2 is itself cooled by DM water circulation.
TRANsfORmERs
A static electromagnetic device with two or more windings ,which transforms a system of
alternating voltage and current into another system of voltage and current usually of different
values and at the same frequency for the purpose of transmitting electrical power.
TYPES OF TRANSFORMERS:
Power transformers
Used in transmission network of higher voltages, deployed for step-up and step down transformer
application (400 kV, 200 kV, 110 kV, 66 kV, 33kV,22kV)
Distribution transformers
Used for lower voltage distribution networks as a means to end user connectivity. (11kV,
6.6 kV, 3.3 kV, 440V, 230V).
Transformer insulations
• Minor insulation
Like inter turn insulation, is achieved using cellulogic paper.
• Major insulation
Between primary and secondary, phase to phase and inner coil to core. This is
achieved by Bakelite, wooden blocks, cellulogic paper cylinders.
• Transformer Oil
Derivative of petroleum crude. This has good dielectric strength. Also a good
cooling medium and absorbs heat from the windings in transformer. The mineral oil has a
flash point of 140°C and 160°C fire point. This also 'can Sustain the combustion with its
own energy, once it catches fire. Thus this is unsuitable for the transformer located
indoors. •The indoor transformers are filled with a synthetic liquid known as silicate
liquid. This is fire assistant and has flash point well above 300°C.
Types of transformers in FSTPP:
 Generator Transformer:
The generator is connected to this transformer by means of isolated bus ducts. This transformer
is used to step up the generating voltage of around 15KV to grid voltage. This transformer is
generally provided with OFAF cooling. It is also provided with off circuit/on load taps on the
high voltage side. This transformer has elaborate cooling system consisting of number of oil
pumps and cooling fans apart from various accessories. For 500 MW units there are 3
individual single phase transformers for each phase. The rated input voltage is 21KV.
RATED O/P 250MVA
RATED VOLT. (HV) 420KV
RATED VOLT. (LV) 15.75KV
RATED CURRENT(HV) 344A
RATED CURRENT(LV) 9175A
VECTOR GROUP Y n d11
 Unit auxiliary transformer
The UAT draws its input from the main bus-duct connecting generator to the
generator Transformer. The total KVA capacity of unit auxiliary transformer required can be
determined by assuming 0.85 power factor and 0.9 efficiency for total auxiliary motor load. It is
safe and desirable to provide about 20% excess capacity than circulate so as to provide for
miscellaneous auxiliaries and possible increase in auxiliary load. With higher unit ratings and
higher steam conditions, the auxiliary power required also increases and limitations imposed by
the switchgear voltages available, indicate the maximum size of unit auxiliary transformer which
can be used.
 Station transformer
The station transformer is required to feed power to the auxiliaries during start ups. This
transformer is normally rated for the initial auxiliary load requirements of unit. In typical cases,
this load is of the order of 60% of the load at full generating capacity. But in large stations where
more than one units are operating, the station transformers should have sufficient capacity to
start two units at a time in addition to feeding the common auxiliaries. It is also provided with on
load tap changer to cater to the fluctuating voltage of the grid.
RATED OUTPUT(LV):6.6KV RATED INPUT( HV) : 33KV
 Excitation transformer
The excitation transformer is used in the static excitation system of the generator .The output of
the generator is fed to the primary of the excitation transformer. The secondary is the input to 4
thyristor banks .In addition there are protective relays for the excitation transformer.
 Auxiliary transformers
They are used to supply power to the LT auxiliary units like ESPs, lubricating oil pumps, seal
oil pumps etc.
 Tie / Auto transformer
Tie transformers are connected to the 400 KV bus. They are used to step down the voltage to 33
KV. Then the station transformers step down the voltage to 6.6 KV (station buses). The unit
buses are connected to the station buses through circuit breakers and isolaters. When the
generator trips, there is no supply to the unit buses and the tie-transformers supply the station
buses. Then the circuit breakers and the isolaters are closed. Thus the supply to the auxiliaries is
maintained.
 Instrument transformers
Potential Transformers step down values to safe levels for measurement. They are also called
voltage transformers. Their standard output is 120V.
Current Transformers have standard output of 1 or 5 amps. They can produce high voltages if
open circuited.
SWITCHGEAR
“The apparatus used for Switching, Controlling and Protecting the Electrical Circuits and
equipment” is known as Switchgear.
NEEDS OF SWITCHGEAR :
• Switching during normal operating conditions for the purpose of Operation and
Maintenance.
• Switching during Faults and Abnormal conditions and interrupting the fault currents.
PARTS OF SWITCHGEAR :
• Switching device:
Power circuit Control circuit
Measurement and display Protection
• Power Circuit:
Circuit breakers / contactors Isolators
Earthing switch
• Control Circuit :
Service / test /isolated position selectors Tripping and closing circuit
Spring charging, anti pumping arrangement Supply monitoring , space heaters ,
indications
• Measurement and Protection:
Ammeter, voltmeter, energy meter Relays, CT, PT,
• Classification of switchgears:
Method of arc quenching :
Bulk oil, Min. oil, Air Break, Air Blast, SF6 , Vacuum
Working voltage :
440V, 6.6 kV, 11 kV, 400 kV etc.
Indoor / out door
SOME INTERLOCKS :
Check synchronization for closing
Master relay contacts for trip and close
1.) HV & LV Breaker interlocks 2.) Main / Reserve supply change over
TT - 2
33 kV System
Stage -I
I/C
from
TT - 3
I/C
from
TT- 1
Stn.
Trf.1
Spare Col.
Trf.1
Bus
PT
Bus coupler
Bus
PT
Col.
Trf.2
Spare Stn.
Trf.2
I/C
from
33 kv Bus
Stage -II
Stn.
Trf.4
Stn.
Trf.3
Bus
PT
Bus
PT
Spare
I/C
from
TT - 3
I/C
from
TT - 1
I/C
from
TT - 2
Bus coupler
CHP
Trf.2
CHP
Trf.1
33 kv Bus
• The Auxiliary power system in a power plant must form a RELIABLE source of power to all
unit and Station auxiliaries. The basic function of Switchgear is to control supply of electric
power and to protect the equipment in the event of abnormal conditions. Hence the switchgears
have to be RELIABLE, SAFE, and ADEQUATE.
•
Defining the reliability, safety aspects and adequacy aspects in terms of Quantitative parameters
forms the essential part in “SPECIFICATIONS”
• 33KV, 11KV, 6.6KV and 3.3KV Switchgears
• Indoor, metal clad single front and fully Compartmentalized, with degree of protection IP42
and IP52 for metering compartments. For 33 KV the switchgears can be metal enclosed either.
•
Circuit Breakers are of either SF6 or Vacuum type. They shall comprise of three separate
identical single pole interrupting units operated through a common shaft by a sturdy mechanism.
• Breakers are suitable for Switching transformers and motors at any load and also for
starting 3.3 KV - Above 200 KW to1500 KW, 11 KV- above 1500 KW for 500MW units and
6.6 KV- above 200KW for 210MW units.
• Surge arresters are provided for all motor feeders to limit the over voltages. For Motors
where frequent start/stop of motors is called for HRC fuse backed contactors are provided.
• Suitable Interlocks are provided to ensure that Breaker is off before opening the rear
doors/covers.
BASIC dESIGn fEATuRES: ConTRol And SAfETy
• Circuit Breakers/contactors are being normally operated from remote through Distributed
Digital Control & Management of Information System (DDCMIS)/ Programmable Logic
Controller (PLC). The control Switch located on the Switchgear is normally used only for
testing.
• All the logic for incomers, bus couplers, ties, transformer feeders and motor feeders is being
generated in DDCMIS only. The reverse blocking schemes are still incorporated in Switchgear
(hardwired).
ACKnoWlEdGEMEnT
We the students of JADAVPUR UNIVERSITY,KOLKATA have undergone vocational training in
NATIONAL THERMAL POWER STATION (FSTPS). We wish to acknowledge the support and helping
hands extended by the entire members of the TRAINING DEPARTMENT and all those Engineers who
helped & guided us on our visit to the various departments of the famous Thermal Power Station during
the course of our training.
Any successful work is accompanied by the Helping & Co-
operation of well-wisher. Whatever we have tried to present in our project cum training report would
remains incomplete unless & until we extend our heartiest thanks to all the people who have spend their
valuable time to help & explain us all that we wanted to know. May words will fall short to describe their
importance to us, our gratefulness to them & also to their kind & co-operative attitude throughout the
course of our training in NTPC (Farakka) .
No matter wherever we will stand in our life & career in
the end, these glorious days of our short stay with all the people connected directly or indirectly to NTPC
(Farakka) will never fade away from my mind.
It’s my honor to extended my gratitude & thanks to
 Ms. Susmita Bhattacharya
 Mr. D.Mohanti
 Ms. Anwesha Mukherjee
 Mr. Rohit Agarwal
 Mr. S.K.SOM
This report summarizes the huge learning experience that we had in all the
sections of this modern Power Plant.
DATE: 15.06.2013
PLACE: MURSHIDABAD
Safety module overview

More Related Content

What's hot

Study of corrosion and erosion in boilers
Study of corrosion and erosion in boilersStudy of corrosion and erosion in boilers
Study of corrosion and erosion in boilersSajeed Mahaboob
 
Design and Fabrication of Vapour Absorption Refrigeration System [Libr-H20]
Design and Fabrication of Vapour Absorption Refrigeration  System [Libr-H20]Design and Fabrication of Vapour Absorption Refrigeration  System [Libr-H20]
Design and Fabrication of Vapour Absorption Refrigeration System [Libr-H20]IJMER
 
STEAM POWER PLANT : COMBUSTION PROCESS
STEAM POWER PLANT  : COMBUSTION PROCESS STEAM POWER PLANT  : COMBUSTION PROCESS
STEAM POWER PLANT : COMBUSTION PROCESS S.Vijaya Bhaskar
 
ASH HANDLING PLANT
ASH HANDLING PLANTASH HANDLING PLANT
ASH HANDLING PLANTAditya Anand
 
2013edusat lecture on steam plant(2)
2013edusat lecture on steam  plant(2)2013edusat lecture on steam  plant(2)
2013edusat lecture on steam plant(2)iimt college meerut
 
Ash handling system
Ash handling systemAsh handling system
Ash handling systemVvs Pradeep
 
Vapour Absorption Refrigeration System
Vapour Absorption Refrigeration SystemVapour Absorption Refrigeration System
Vapour Absorption Refrigeration SystemDeep Dalsania
 
OVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTS
OVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTSOVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTS
OVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTSharshavardhan sivadi
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boilerAshvani Shukla
 
BoilerS_____complete Introduction & Classification
BoilerS_____complete Introduction & ClassificationBoilerS_____complete Introduction & Classification
BoilerS_____complete Introduction & ClassificationHashim Hasnain Hadi
 
Power plant high pressure boilers
Power plant high pressure boilers Power plant high pressure boilers
Power plant high pressure boilers PRANAV PATEL
 
combustion equipment & power cycles
combustion equipment & power cyclescombustion equipment & power cycles
combustion equipment & power cyclesErasmus August
 
High pressure boilers (1)
High pressure boilers (1)High pressure boilers (1)
High pressure boilers (1)sneh patel
 
project report for vocational trainee
project report for vocational traineeproject report for vocational trainee
project report for vocational traineeSourav Jana
 
High pressure boilers
High pressure boilersHigh pressure boilers
High pressure boilerssneh patel
 

What's hot (20)

Study of corrosion and erosion in boilers
Study of corrosion and erosion in boilersStudy of corrosion and erosion in boilers
Study of corrosion and erosion in boilers
 
Steam power plant
Steam power plantSteam power plant
Steam power plant
 
Design and Fabrication of Vapour Absorption Refrigeration System [Libr-H20]
Design and Fabrication of Vapour Absorption Refrigeration  System [Libr-H20]Design and Fabrication of Vapour Absorption Refrigeration  System [Libr-H20]
Design and Fabrication of Vapour Absorption Refrigeration System [Libr-H20]
 
STEAM POWER PLANT : COMBUSTION PROCESS
STEAM POWER PLANT  : COMBUSTION PROCESS STEAM POWER PLANT  : COMBUSTION PROCESS
STEAM POWER PLANT : COMBUSTION PROCESS
 
ASH HANDLING PLANT
ASH HANDLING PLANTASH HANDLING PLANT
ASH HANDLING PLANT
 
2013edusat lecture on steam plant(2)
2013edusat lecture on steam  plant(2)2013edusat lecture on steam  plant(2)
2013edusat lecture on steam plant(2)
 
Ash handling system
Ash handling systemAsh handling system
Ash handling system
 
Vapour Absorption Refrigeration System
Vapour Absorption Refrigeration SystemVapour Absorption Refrigeration System
Vapour Absorption Refrigeration System
 
OVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTS
OVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTSOVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTS
OVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTS
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boiler
 
Power Generation and Steam power plant
Power Generation and Steam power plantPower Generation and Steam power plant
Power Generation and Steam power plant
 
BoilerS_____complete Introduction & Classification
BoilerS_____complete Introduction & ClassificationBoilerS_____complete Introduction & Classification
BoilerS_____complete Introduction & Classification
 
Steam power plant
Steam power plantSteam power plant
Steam power plant
 
Power plant high pressure boilers
Power plant high pressure boilers Power plant high pressure boilers
Power plant high pressure boilers
 
combustion equipment & power cycles
combustion equipment & power cyclescombustion equipment & power cycles
combustion equipment & power cycles
 
High pressure boilers (1)
High pressure boilers (1)High pressure boilers (1)
High pressure boilers (1)
 
project report for vocational trainee
project report for vocational traineeproject report for vocational trainee
project report for vocational trainee
 
Auxiliary Boilers
Auxiliary Boilers Auxiliary Boilers
Auxiliary Boilers
 
High pressure boilers
High pressure boilersHigh pressure boilers
High pressure boilers
 
Turbine
TurbineTurbine
Turbine
 

Similar to Safety module overview

Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant pptPrakash Jarotia
 
suratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadavsuratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadavmukesh yadav
 
panki power plant training.ppt
panki power plant training.pptpanki power plant training.ppt
panki power plant training.pptAbhishek Awasthi
 
CSTPS training REPORT
CSTPS training REPORTCSTPS training REPORT
CSTPS training REPORTUday Wankar
 
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptxCOAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptxCHANDRA KUMAR S
 
Overview of mejia thermal power station, DVC
Overview of mejia thermal power station, DVCOverview of mejia thermal power station, DVC
Overview of mejia thermal power station, DVCNITISHKHALKHO
 
powerplant Engg Unit 1
powerplant Engg Unit 1powerplant Engg Unit 1
powerplant Engg Unit 1sureshkcet
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plantVivek Pathak
 
A report of the vocational training at MTPS(DVC) for mechanical only
A report of the vocational training at MTPS(DVC) for mechanical onlyA report of the vocational training at MTPS(DVC) for mechanical only
A report of the vocational training at MTPS(DVC) for mechanical onlyShobhan Biswas
 
Cseb (chhattisgarh state electricity board) korba east vocational training pr...
Cseb (chhattisgarh state electricity board) korba east vocational training pr...Cseb (chhattisgarh state electricity board) korba east vocational training pr...
Cseb (chhattisgarh state electricity board) korba east vocational training pr...haxxo24
 
Lakvijaya_Presentation1.pptx
Lakvijaya_Presentation1.pptxLakvijaya_Presentation1.pptx
Lakvijaya_Presentation1.pptxBhathiyaRanawaka
 
Overview of Thermal Power Plants
Overview of Thermal Power PlantsOverview of Thermal Power Plants
Overview of Thermal Power PlantsDebajyoti Bose
 
POWER PLANT ENGINEERING
POWER PLANT ENGINEERING POWER PLANT ENGINEERING
POWER PLANT ENGINEERING SELVAN P
 
SURATGARH SUPER THERMAL POWER STATION
SURATGARH  SUPER  THERMAL POWER    STATION SURATGARH  SUPER  THERMAL POWER    STATION
SURATGARH SUPER THERMAL POWER STATION Sagar Sharma
 
kota thermal power plant
kota thermal power plantkota thermal power plant
kota thermal power plantravi kant
 
Steam power plant
Steam power plantSteam power plant
Steam power plantSlidegiant
 

Similar to Safety module overview (20)

hindalco power
hindalco powerhindalco power
hindalco power
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
 
suratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadavsuratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadav
 
panki power plant training.ppt
panki power plant training.pptpanki power plant training.ppt
panki power plant training.ppt
 
CSTPS training REPORT
CSTPS training REPORTCSTPS training REPORT
CSTPS training REPORT
 
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptxCOAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
 
Overview of mejia thermal power station, DVC
Overview of mejia thermal power station, DVCOverview of mejia thermal power station, DVC
Overview of mejia thermal power station, DVC
 
powerplant Engg Unit 1
powerplant Engg Unit 1powerplant Engg Unit 1
powerplant Engg Unit 1
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
A report of the vocational training at MTPS(DVC) for mechanical only
A report of the vocational training at MTPS(DVC) for mechanical onlyA report of the vocational training at MTPS(DVC) for mechanical only
A report of the vocational training at MTPS(DVC) for mechanical only
 
Cseb (chhattisgarh state electricity board) korba east vocational training pr...
Cseb (chhattisgarh state electricity board) korba east vocational training pr...Cseb (chhattisgarh state electricity board) korba east vocational training pr...
Cseb (chhattisgarh state electricity board) korba east vocational training pr...
 
Lakvijaya_Presentation1.pptx
Lakvijaya_Presentation1.pptxLakvijaya_Presentation1.pptx
Lakvijaya_Presentation1.pptx
 
Overview of Thermal Power Plants
Overview of Thermal Power PlantsOverview of Thermal Power Plants
Overview of Thermal Power Plants
 
POWER PLANT ENGINEERING
POWER PLANT ENGINEERING POWER PLANT ENGINEERING
POWER PLANT ENGINEERING
 
SURATGARH SUPER THERMAL POWER STATION
SURATGARH  SUPER  THERMAL POWER    STATION SURATGARH  SUPER  THERMAL POWER    STATION
SURATGARH SUPER THERMAL POWER STATION
 
Steam power plant presentation
Steam power plant presentationSteam power plant presentation
Steam power plant presentation
 
kota thermal power plant
kota thermal power plantkota thermal power plant
kota thermal power plant
 
Steam power plant
Steam power plantSteam power plant
Steam power plant
 
Emam training
Emam training Emam training
Emam training
 
ppt of ntpc dadri by emam raza khan
ppt of ntpc dadri by emam raza khan  ppt of ntpc dadri by emam raza khan
ppt of ntpc dadri by emam raza khan
 

More from Sourav Jana

reciprocating pump Project part 2
reciprocating pump Project part 2reciprocating pump Project part 2
reciprocating pump Project part 2Sourav Jana
 
Hydraulic press3dddd
Hydraulic press3ddddHydraulic press3dddd
Hydraulic press3ddddSourav Jana
 
Hydraulicpress2ddddddd
Hydraulicpress2dddddddHydraulicpress2ddddddd
Hydraulicpress2dddddddSourav Jana
 
pump system and curves
pump system and curvespump system and curves
pump system and curvesSourav Jana
 
Introduction page 1
Introduction page 1Introduction page 1
Introduction page 1Sourav Jana
 
Introduction page 2
Introduction page 2Introduction page 2
Introduction page 2Sourav Jana
 
Electrostatic precipitator
Electrostatic precipitatorElectrostatic precipitator
Electrostatic precipitatorSourav Jana
 
Introduction page 2
Introduction page 2Introduction page 2
Introduction page 2Sourav Jana
 
Introduction page 1
Introduction page 1Introduction page 1
Introduction page 1Sourav Jana
 
Shot blasting machine and flow chart for helical and lhb spring
Shot blasting machine and flow chart for helical and lhb springShot blasting machine and flow chart for helical and lhb spring
Shot blasting machine and flow chart for helical and lhb springSourav Jana
 

More from Sourav Jana (20)

reciprocating pump Project part 2
reciprocating pump Project part 2reciprocating pump Project part 2
reciprocating pump Project part 2
 
Hydraulic press3dddd
Hydraulic press3ddddHydraulic press3dddd
Hydraulic press3dddd
 
Hydraulicpress2ddddddd
Hydraulicpress2dddddddHydraulicpress2ddddddd
Hydraulicpress2ddddddd
 
hydraulic press
hydraulic presshydraulic press
hydraulic press
 
hydraulic press
hydraulic presshydraulic press
hydraulic press
 
pump system and curves
pump system and curvespump system and curves
pump system and curves
 
Introduction page 1
Introduction page 1Introduction page 1
Introduction page 1
 
Introduction page 2
Introduction page 2Introduction page 2
Introduction page 2
 
Layout page 3
Layout page 3Layout page 3
Layout page 3
 
Electrostatic precipitator
Electrostatic precipitatorElectrostatic precipitator
Electrostatic precipitator
 
Introduction page 2
Introduction page 2Introduction page 2
Introduction page 2
 
Introduction page 1
Introduction page 1Introduction page 1
Introduction page 1
 
Front page 1
Front page 1Front page 1
Front page 1
 
Dm plant
Dm plantDm plant
Dm plant
 
Acknowledgemet
AcknowledgemetAcknowledgemet
Acknowledgemet
 
C shop 1
C shop 1C shop 1
C shop 1
 
Welding shop 1
Welding shop 1Welding shop 1
Welding shop 1
 
Shot blasting machine and flow chart for helical and lhb spring
Shot blasting machine and flow chart for helical and lhb springShot blasting machine and flow chart for helical and lhb spring
Shot blasting machine and flow chart for helical and lhb spring
 
Rail
RailRail
Rail
 
Rail 2
Rail 2Rail 2
Rail 2
 

Recently uploaded

"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...Fwdays
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr LapshynFwdays
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clashcharlottematthew16
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxNavinnSomaal
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024The Digital Insurer
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piececharlottematthew16
 
APIForce Zurich 5 April Automation LPDG
APIForce Zurich 5 April  Automation LPDGAPIForce Zurich 5 April  Automation LPDG
APIForce Zurich 5 April Automation LPDGMarianaLemus7
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsRizwan Syed
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024Lorenzo Miniero
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 

Recently uploaded (20)

"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
 
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clash
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptx
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piece
 
APIForce Zurich 5 April Automation LPDG
APIForce Zurich 5 April  Automation LPDGAPIForce Zurich 5 April  Automation LPDG
APIForce Zurich 5 April Automation LPDG
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL Certs
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 

Safety module overview

  • 1. Safety module Overview of safety hazard: What is hazard? A hazard is any source of potential damage, harm or adverse health effects on something or someone under certain condition at work. How to behave inside the plant: • No loose clothing. • Safe distance is to be maintained from rotating machine. • Any electrical installation should not be touched. • Safe distance should be kept from bare live terminals. • Helmet is a must. • Nobody should move in dark spaces. • Nobody should move alone. • Be aware from floor opening. • Avoid moving on checker plate. • Nobody should move over the trenches. • Railing should not be leant upon. • Moving into confined spaces (congested closed area with lower concentration of oxygen, and containing mixture of toxic and explosive gases) for eg any flue duct, furnace, inside the condenser, cooling water duct, sewerage lines is to be avoided. • One should not move in regions where lifting work is being carried out. • One should not go into a unit which is under maintenance. • One must avoid going near welding and gas cutting sparks and must use safety glasses.
  • 2. uNSafe aCt aNd uNSafe CoNdItIoNS SHould tHeRefoRe Be aVoIded. CHEMICAL HAZARDS : Hydrogen, chlorine, ammonia and carbon monoxide leakage-  HYDROGEN: This being highly explosive, use of mobile phones should be avoided and combustibles should not be kept near hydrogen cylinders.  CHLORINE: Chlorine is used in water treatment plants.Inhalation of chlorine causes its combination with water in mucus membrane to form Hydrochloric acid. It causes pitting in the membrane and respiratory problems start. o Precautions: In case of chlorine leakage,one must go as up as possible because chlorine being 2.5 times heavier than air its density decreases with height. STEL value : 3 ppm.  AMMONIA : Ammonia is found near ESP and boiler. Inhalation of ammonia may cause vomiting and head-ache.  CARBON MONOXIDE: Carbon monoxide may be found in Feeder floor, bunker floor etc. Inhalation causes it to mix with Haemoglobin in blood to form carboxy- haemoglobin that chokes the person. So it is often termed as “killer gas”. o Precautions: It can be removed quickly from the body of the person if he is taken immediately into an open area. STEL value: 400 ppm.
  • 3. BaSIC uNdeRStaNdINg of tHeRmal poweR geNeRatIoN In a thermal power plant, the thermal energy of the superheated steam is used to drive the generator, which in turn produces electricity. The superheated steam is produced from any fossil fuel like coal, crude oil etc. Since coal is available in plenty and in cheap, we use coal as the primary fuel in the thermal power plants. The coal is crushed and pulverized before it is used in the boiler. The pulverization of coal increases the surface area of the coal, which helps in the complete combustion of the coal. The coal is feed to the boiler where it is fired to produce heat. Initially, a small quantity of crude oil is used for the purpose. The water is passed through the pipes making up the walls of the boiler. The water is heated to produce steam, which is further reheated to produce superheated steam. The superheated steam at an exceedingly high temp. Steam pressure drives the turbine. The turbine rotates following which the generator, which is coupled to the turbine, also rotates producing electricity. Thus, the chemical energy of the coal is utilized to produce steam. The thermal energy of the steam is converted to the mechanical energy of the rotating turbines, which is converted to the electrical energy in the generator. NtpC faRaKKa SupeR tHeRmal poweR plaNt NTPC Farakka is a coal fired pit head based power plant. Lalmatia is the captive coal mine for this plant. Total capacity of NTPC Farakka is 2100MW.The plant consists of three stages. These are: STAGE I : 3 units of 200MW STAGE II : 2 units of 500MW STAGE III : 1 unit of 500MW Generation voltage level for Stage-I is 15.75 KV and for Stage-II and Stage-III is 21KV.The generated voltage is stepped up to 400KV for transmitting over a long distance. dIStINCtIoN BetweeN Stage-III aNd otHeR StageS :
  • 4. STAGE-I and STAGE-II : Cooling Water is taken from the feeder canal and after using in the condenser the hot water is returned to the feeder canal, hence it is an open cycle system. It causes threat to aquatic life. STAGE III : Cooling tower is used in this system. After using the water in the condenser it is recirculated through cooling tower, where the hot water is cooled and reused. This is a closed cycle system and causes less harm to the environment. Supply of Raw mateRIalS: A) COAL: There are 3 sources of coal supply as: • Lalmatia situated 85 Kms away from the main plant. • Imported coal from Indonesia. • Indian railways who supply coal from different mines across the country. B) WATER: Feedwater: Collected from feeder canal cut across the river Ganga. Cooling Water: Collected from the same source. C) AIR: atmospheric air is used. D) OIL: HFO is supplied by IOCL. aSH dISpoSal: For the quality of coal used here, approximately 80% Fly Ash and 20% bottom ash is produced. Ash disposal is a major issue in coal fired power plants.Raw water is mixed with ash to form slurry and pumped out through series pumps( 3 for Fly ash and 2 for Bottom ash ) into ash dyke.Fly ash dyke is situated 12 Kms away and Bottom ash dyke MALANCHA is situated 5 Kms away from the main plant. poweR eVaCuatIoN: The generated power is evacuated through different outgoing lines:
  • 5. 1)Farakka-Malda (2 lines) 2) Farakka-Kahalgaon (2 lines) 3) Farakka-Durgapur (2 lines) 4) Farakka-Lalmatia (1 line) 5)Farakka-Jeerat(2 lines) Initially there were 9 lines. Few more lines were added after commissioning of Stage III. dIffeReNt CyCleS INVolVed IN tHe eNtIRe opeRatIoN: • FUEL CIRCUIT : • Coal is brought into CHP with the help of Wagon tipplers or track hoppers and stored in the bunker. • From bunker coal is sent to feeder via conveyer. • The purpose of feeder is to vary the amount of coal as per load requirement. • From feeder coal is taken to mill where it is pulverized. • Primary air is sucked from atmosphere through PA fan and takes pulverized coal to the furnace. Fig1: Coal circuit 2) AIR & FLUE GAS CIRCUIT: • Secondary air is sucked from atm. with the help of FD fan(Forced Draught) for combustion.A fire ball is generated inside the boiler.The temp. of fire ball is 1000-1100 deg. C.
  • 6. • Flue gas is generated due to combustion. • Heat is extracted from flue gas to heat the steam in platen SH, reheater,final SH, primary SH , economiser and to heat air in air preheater. • Fly ash particles are collected from flue gas at ESP(Electrostatic Precipitator) and flue gas is released to atm. with the help of ID fan(Induced Draught) which is situated at the base of chimney. Fig2: Air & Flue gas circuit 3) STEAM, CONDENSATE & FEED WATER CYCLE: • In 200MW unit of the plant the boiler drum is located at the height of 54m. • Inner wall of the boiler made up of water tubes which originate from bottom ring header situated 7m from ground level. • DM water picks up heat from fire ball and goes up as a mixture of steam and water.Then it reaches drum .As steam being lighter it goes upward.Water comes down through DOWNCOMER .In 200MW unit no. of downcomers is 6 and natural circulation of steam and water takes place.But in 500MW unit the boiler drum being at a height of 72m forced circulation is employed. by through 10 downcomers. • Steam is separated from water in the boiler drum with the help of CYCLONE SEPARATOR & SECONDARY SEPARATOR(corrugated sheets) and it follows the circuit shown below.
  • 7. Fig 3: Steam,Condensate & Feed Water cycle 4) COOLING WATER CIRCUIT: • Raw water is taken from the feeder canal through CW pump. • Raw water is passed through TRASH RACKS and TRAVELLING WATER SCREENS to remove impurities (animal bodies, planktons etc) of different sizes. • Raw water is stored at the water box at the inlet of condenser and it flows through the innumerable number of condenser tubes. In stage I there are 13000 such tubes. The water comes at the outlet and is stored at the outlet water box. • The condensate is stored in the HOTWELL at a temperature of 45 deg C. • In STAGE-I and STAGE-II, after using in the condenser the hot water is returned to the feeder canal, hence it is an open cycle system. • In STAGE III, Cooling tower is used. After using the water in the condenser it is recirculated through cooling tower, where the hot water is cooled and reused. This is a closed cycle system and causes less harm to the environment.
  • 8. Fig4: Cooling Water circuit 5) ASH CIRCUIT: • The ash is collected in two forms as Bottom ash(20%) and Fly ash(80%). • Ash can be disposed in dry form or wet form. • Fly ash particles are collected in ESP.In ESP,there are large numbers of EMITTING ELECTRODE(supplied at 80 KV) and COLLECTING ELECTRODE(at ground potential). • Fly ash particles are deposited on the collecting electrodes and HAMMERED into ESP HOPPERS. • Slurry is formed by mixing raw water with Fly ash and pumped out to Fly ash dyke with the help of FASPs(Fly ash slurry pumps) • Similarly, Bottom ash is collected in the BOTTOM ASH HOPPERS and disposed in slurry form in the Bottom ash dyke with the help of BASPs(Bottom ash slurry pumps).
  • 9. Fig5:Ash disposal system BaSIC deSCRIptIoN of flow of Coal: (1) CHP (Coal Handling Plant): The input coal is unloaded at this portion, which passes it to the next block crusher house. (2) Crusher house: crusher house crush the unloaded coal coming from the CHP in small size. (3) Coal Bunker: Coalbunker stores the crushed coal and passes it to the Feeder. (4) RC Feeder: It is the raw coal feeder. The coal, comes from the crusher house is still of big size. The feeder controls the quantity of the input coal to the boiler. (5) Mill / pulveriser: Mill contains three rollers. It crushes it to powder finely. Primary air takes the pulverized coal from the mill to the boiler. (6) Furnace : At furnace pulverized coal is combusted with the help of secondary air. BRIef deSCRIptIoN of SyStem CompoNeNtS: Main components of the power plant are:
  • 10. 1) Boiler: • In Farakka NTPC, corner fired boilers are used. In stage I, there are 6 mills situated from a height of 18m to 27m. FIRING FLOORS of mill A is at a height of 18m and that of mill F is at 27m. Rest of the firing floors are situated in between. HFO OIL GUNS are situated at heights of AB, CD and EF. • Purpose of oil gun: a) during boiler start up , b) emergency purpose. Fig 6: HFO Flow System • The working oil supplied by IOCL is stored in HFO tank 2. The oil in this tank is replenished by oil in tanks 1 and 3. The heat lost due to transportation is compensated by HEATER. HFO Circulation takes place all the time so that temperature of oil is maintained at 120 deg C when plant is running. • In case of shut down of any mill, the coal particles on the corresponding floor may not get sufficient ignition energy and thereby the fireball distorts and subsequently two
  • 11. separate balls are formed on either side of that mill. In that case HFO injection makes up that gap and stabilizes the fire ball. • The coal is composed of 4 parts – fixed carbon(FC),Volatile material(VM),Moisture & ash. The VM supplies the initial ignition energy for the complete combustion of FC. If the VM content in the coal used is less the coal particles have to travel a larger path to attain the required ignition energy and hence the fireball is formed at greater height. Fig7: Isometric View of Boiler schematic
  • 12. Fig8: Top view of firing floor corresponding to mill A • It is critical to maintain the level of water in boiler drum. Case 1: level of water goes too high: water may go into the steam circuit. When water hits the turbine blades, PITTING may occur. (the high velocity water particles may produce indentations in the turbine blades) Case 2: level of water goes low: If it is too low, the boiler drum base being close to the fire ball, its shape gets deformed. Also low water level causes water in the drum to get evaporated at a faster rate than the rate at which water is returned from hotwell to the drum There are mainly three types of heater coils in boiler. (1) Economiser (2) Re heater (3) Super heater  Economizer: Economizer is a device in which the feed water is heated before it enters into a boiler. The heat is being taken from the waste flue gas of the boiler. It ensures economy of fuel. Hence it is called economizer. The economizer is placed at the second pass of boiler. The flue gases of
  • 13. the boiler furnace, after working inside the boiler, flows through it before passing into the chimney.  Coal bunker- These are in process storage silos used for storing crushed coal from the coal handling system. Generally, these are made up of welded steel plates. Normally there are six such bunkers supplying coal of the corresponding mills. These are located on the top of the mills so as to aid in gravity feeding of coal.  P. A. Fan- The primary air fans (2 per unit-50% capacity each) are designed to suck primary air from atmosphere. Temperature of PA is increased to 300 deg C after passing through Air Pre- heater. These fans are located at ‘0’M level near the boiler.  Burners- As evident from the name itself, these are used for burning pulverized coal. Every unit has a set of such burners located at different elevations of the furnace.  F. D. Fan- These forced draught fans (2 per unit-50% capacity each) are designed for handling secondary air for the boiler. These fans are located at ‘0’M level near the P.A Fan. Electrostatic Precipitator-
  • 14.  Air Pre-heater- Air pre heater transfer the heat from the flue gas to cold primary and/or secondary air by extracting heat from waste flue gas. These are located in the secondary pass of the furnace at a height of around ‘16’M level. Each 200MW unit is provided with two such air pre-heaters.  ID Fans- These are two induced draught fans per boiler located between the ESP & chimney. These fans are used for maintaining pressure inside the boiler by releasing flue gas through chimney.  Chimney- These are tall RCC structures with single/multiple flue ducts (one flue duct per 200MW unit). The heights of these chimneys vary, depending upon the location considerations; anywhere between 150m to 220m.
  • 15. Steam Circulation System  Re-heaters- This is the part of the boiler which receives the steam back from the turbine after it has given up some of its heat energy in the high pressure section of the turbine. It raises the temperature of this steam, usually to its original value, for further expansion in the turbine. The purpose of this reheating is to add energy to the partially used steam. The construction & arrangement is similar to super heater. It has two sections- hot & cold Reheat sections. Due to resistance of flow through the reheat section, the hot reheat steam is at lower pressure compared to the cold reheat steam. water treatment plant and storage USE OF MAKE UP WATER:
  • 16. Since there is continuous withdrawal of steam and continuous return of condensate to the boiler, losses due to blow down and leakages have to be made up to maintain a desired water level in the boiler steam drum. For this, continuous make-up water is added to the boiler water system. HARDNESS IN RAW WATER AND REMOVAL: Impurities in the raw water input to the plant generally consist of calcium and magnesium salts which impart hardness to the water. Hardness in the make-up water to the boiler will form deposits on the tube water surfaces which will lead to overheating and failure of the tubes. This is called SCALING. Thus, the salts have to be removed from the water, and that is done by a water demineralizing treatment plant (DM). A DM plant generally contains ION EXCHANGERS. Any ions in the final water from this process consist essentially of hydrogen ions and hydroxide ions, which recombine to form pure water. The capacity of the DM plant is dictated by the type and quantity of salts in the raw water input. However, some storage is essential as the DM plant may be down for maintenance. For this purpose, a storage tank is installed from which DM water is continuously withdrawn for boiler make-up. The storage tank for DM water is made from materials not affected by corrosive water. The piping and valves are generally of stainless steel.  Boiler feed pump- It takes water input from the deaeretor at a very low pressure and pumps it to the boiler drum at a very high pressure (190Kg).  Condenser-  Ejectors- There are two 100%capacity ejectors of the steam ejecting type. The purpose of the ejector is to evacuate air and other non-condensing gases from the condensers and thus maintain the vacuum in the condensers.  Condensate Extraction Pump- It extracts the condensate from the hot well of the condenser and pumps it to the de- aerator.  L. P. Heaters- Turbine has been provided with non-controlled extractions which are utilized for heating the condensate, from turbine bleed steam. There are 4 low pressure heaters in which last four extractions are used.L.P.Heater-1 has two parts LPH-1A and LPH-1B located in the upper parts of the condenser A & B respectively. These are of the horizontal type with shell and tube construction. L.P.H 2,3,4 are of similar construction and they are mounted in row at 5M level.
  • 17.  Deaerator- This is used to remove oxygen. Due to the presence of certain gases like oxygen, carbon- di-oxide, ammonia, etc. in water then it is considered harmful because of their corrosive effect on metals, particularly at elevated temperatures. The boiler feed water should be free from all dissolved gases. This can be achieved by embodying into the boiler feed system a de-aerating system, whose function is to remove dissolved gases from the feed water by mechanical means.  H. P. Heaters- These are regenerative feed water heaters operating at high pressures and located at the side of turbine. These are connected in series on feed-water side & by such arrangement feed- water enters the HP heaters. The steam is supplied to these heaters from the bleed point of the turbine through motor operated valves. These have a group bypass protection on the feed waterside. Here the feed water flows through the tube spirals & is heated by steam around the tubes in the shall of heaters. These heaters are cylindrical vessels with welded dished ends & with integrated, de-super heating, condensing, & & sub cooling sections. This design offers the advantage to optimize the arrangement of piping & the location of the heaters at power station. 2) TURBINE:
  • 18. Fig 9: Turbine cycle • Steam after working in the HP turbine temperature is reduced from 540 deg to 340 deg C. Pressure is also substantially reduced. The line of flow of steam from HP turbine is COLD REHEAT LINE or CRH LINE. • CRH line again goes to the boiler to be reheated at 540 deg C by the heat of the flue gas. This line is known as the HOT REHEAT LINE or HRH LINE. HRH Line goes to the IP Turbine. Exhaust steam from IP Turbine goes to the LP Turbine. • Exhaust of LP Turbine (80 deg C) goes to CONDENSER. COOLING WATER is circulated to cool down the steam and the condensate drains into the HOTWELL at 35 deg C. • From HOTWELL the condensate is sent back to boiler drum through different processes and reused. • The pressure of MS line is ~160 Kg/sqcm, that of HRH line is ~33-34 Kg/sq cm and CRH Line pressure is ~34 Kg/sqcm.
  • 19. • With the help of modulation of HP Control valves (HPCV) and IPCV alternator frequency is kept constant by controlling the amount of inlet steam. • STOP VALVE is used to stop the entry of steam into the turbine. turbine section  Turbine Lub. Oil System This consists of Main Oil Pump (MOP), Starting Oil Pump (SOP), AC stand by oil pumps and emergency DC oil pump and jacking oil pump (JOP) (one each per unit).  Emergency stop valves and control valves Turbine is equipped with emergency stop valves to cut off steam supply and with control valves regulate steam supply. Emergency stop valves (ESV) are provided in the mainsteam line and interceptor valves are provided in the hot reheat line. Emergency stop valves are actuated by servomotor controlled by the protection system. Control valves are actuated by the governing system through servomotors to regulate steam supply as required by the load.  Generator The main shaft of the turbine is connected to the rotor of the main generator. The shaft rotates the rotor, which cuts the flux of the armature coil, and as a result an induced emf is produced.  Compressed Air System There are two types of compressed air system namely Instrument air system or control air system & Station air system.
  • 20.  Air Compressor- The station air compressor is a generally slow speed type & is arranged for belt drive. The cylinder heads and barrel are enclosed in a jacket which extends around the valve also. The inter cooler is provided between the low and high pressure cylinder which cools the air between stage and collects the moisture that condenses. switcHYard Switch yard is the place adjacent to the power house where the transformers, circuit breakers, isolators, bus bars, CT & PTs, lightning arrestors, current limiting reactors and other equipments are installed. ACSR conductors are used in the line wires. One and a half breaker scheme is used here. Three circuit breakers are used for controlling two circuits which are connected between two bus bars. Normally, both the bus bars are in service. A fault on any one of the bus bars is cleared by opening of the associated circuit breakers connected to the faulty bus bar without affecting continuity of supply. Similarly, any circuit breaker can be taken out for maintenance without causing interruption. <| This is one and a half breaker scheme Though unit 4 has double breaker scheme. Reactor: A reactor is a coil having large inductive reactances in comparison to its ohmic resistance and is introduced in a circuit or system to limit the short circuit currents to a safer value in order to protect the electrical installation. Oil immersed type reactors are employed here. Insulation and cooling arrangement employed are similar to those of an ordinary transformer. Wave trap: This is used to block high frequency component.
  • 21. Circuit Breaker: Circuit Breaker acts like a switch when a failure occurs in transmission line.It is very Costly equipment. In one and a half scheme there is 3 breakers in one dia created by 2 main bay and one tie bay. In one circle there is six breakers. Isolator: Isolator isolates the breaker from the line for maintenance purpose or to save breaker in Switching time as breaker is costly. CT & PT: CT and PT is there for protection and metering purpose. Lightning Arrester: It is an electrical device inserted in a power line to protect equipment from Sudden fluctuations in current. It is also known as Surge Protector. CVT: It senses any overvoltage of line. It helps in communication between two sub stations also. As capacitor gives low impedence for high frequency so communication signal goes through it to PLCC (Power Linear Carrier Communication ) panel . It helps in Tele-protection, Tele –metering and Tele-communication. This is called carrier-aided protection system. The band of this signal is 30 kHz-500kHz, but to reduce noise it is kept as 50kHz to 500 kHz. It is trapped by Wave Trap before the transformer connection and maintain communication process between substations using supply line as communication line. Bus Reactor: To balance the reactive power consumed by transmission line shunt reactor is there to make the line a lossless line.
  • 22.
  • 23. TURBOGENERATOR FSTPP has 5 units (stage-I : 3 x 200 and stage-II : 2 x 500)of 3-phase synchronous generators which convert mechanical energy to electrical energy.The generators are coupled to the steam turbine shaft. Specification: The following table shows the rating of the Generators of stage-I and stage-II. Rated parameters Stage-I Stage-II MAX. CONTINUOUS KVA RATING 247000 588000 MAX. CONTINUOUS KW RATING 210000 500000 RATED POWER FACTOR 0.83 lag 0.83 lag STATOR Voltage 15750 21000 Current 9050 16200 ROTOR Voltage 310 240 Current 2600 4030 RATED SPEED 3000 3000 RATED FREQUENCY 50 50 PHASE CONNECTION YY YY NO. OF TERMINALS BROUGHT OUT OF STATOR 9 9 COOLANT Water & Hydrogen Water & Hydrogen GAS PRESSURE 3.5 kg/cm2 3.5 kg/cm2 INSULATION CLASS B B MAKER’S NAME BHARAT HEAVY ELECTRICALS LTD. DIFFERENT PARTS
  • 24. 1. Stator - Stator Frame (Fabrication & Machining) 2. Core Assembly - Stator Core, Core Suspension Arrangement 3. End Shield 4. Stator Winding Assembly - Stator Winding , Winding Assembly,Connecting Bus bar 5. Rotor - Rotor Shaft, Rotor Wedges, Rotor Coils, Wound Rotor, Rotor Assembly 6. Completing Assembly - Bearing Assembly, Shaft Seal Assembly, Oil Catchers,Insert Cover etc 7. Exciter 8. Auxiliary System The machine usually consists of two main parts: 1. STATOR 1) FRAME 2) MAGNET CORE 3) WINDINGS STATOR FRAME It is a fabricated gas tight steel structure suitably ribbed internally. It can withstand explosion pressure of hydrogen air mixture without any residual deformation. H2 gas coolers are housed longitudinally inside stator body. STATOR CORE Stator core is made up of insulated punchings of CRGO Si steel and is laminated to minimize eddy current loss. It provides path for machines’ magnetic flux and has slots in which windings are assembled.Core bars are designed to provide elastic suspension of core in stator. STATOR WINDINGS The windings are three phase fractional pitched distributed in two layers of individual bars. Generator voltage is induced in the stator windings and use of water cooling permits a high value of current density in the machine. The use of combination of solid and hollow conductors effectively reduces the depth of the slot which affect the losses in the winding, and better utilization of slots. 2. ROTOR
  • 25. It is the rotating part and houses the field windings. It is a cylindrical type rotor. Rotor body is a high strength alloy steel single forging prepared by vacuum cast steel,containing slots for housing field windings and is supported on two bearings. The coils are held against centrifugal forces by means of wedges and by means of non-magnetic retaining ring on the overhang part of the winding. FIELD WINDING These are made from hard drawn silver bearing copper. Gas(H2) pickup system is employed for complete cooling of rotor. Two propeller type fans are shaft mounted on either side of rotor body for circulating cooling gas inside generator. Special ducts (fins) are provided in the rotor body, through which the cooling gas flows to the rotor end windings. SLIP RINGS Helically grooved alloy steel rings are shrunk on rotor shafts and insulated from it.Slip rings are connected to field windings through semi flexible copper lead COOliNG sysTEm Of ThE GENERATOR Generator auxiliary system are broadly classified into 3 parts: 1. STATOR WATER SYSTEM Stator water cooling is a closed loop system. There are two full capacity single stage centrifugal pumps with change over facility. The pumps are driven by 3Ph. 415V A.C. motors. The stator water cooler is shell and tube type heat exchanger. DM water flows through the shell. There are two mechanical filters and one magnetic filters. Mechanical filters are of wire mesh type. Magnetic filter is having permanent magnet. The expansion tank is a hermetically sealed container made of S.S. Float valve is there in the expansion tank to maintain water level in the tank which act as suction storage tank for stator water
  • 26. pumps. Polishing unit (mixed bed ion exchanger) is there to maintain conductivity of stator water to desired level. 2)SEAL OIL SYSTEM Generator shaft seals are supplied with pressurized seal oil to prevent hydrogen escape at the shaft Oil pressure is kept higher than the gas pressure. There are one AC seal oil pp. and one DC seal oil pp. which feed oil to the seal through cooler and filter. • A vacuum pump is provided to maintain vacuum in seal oil tank The seal oil pressure to the seal is controlled by DPR which maintain specified DP between oil and hydrogen. There is provision for thrust oil to hold the seal ring in position against H2 pressure (0.5kg/cm2 more than seal oil pressure). There are 2 oil coolers to cool the hot oil. POLISH UNIT FILTERS COOLER SS PUMPS GAS TRAP FLOW METERS CCCCCC CONDUCTIVITY CONDUCTIVITY CTIVITYO EXPANSION TANK TANK MAKE UP up UP FSII DIFF PRESS. MAGNET FILTER BEARG DRAINS TG 1 2 EE BEARING TE BEARING GAS EXHAUST FROM GAS SYSTEM IOT VACUUM TANK SOST SOP SOP-3 DC DP SW TS ES FR FLOW M. PS PG
  • 27. • 2. GAS SYSTEM Generator gas system constitutes of hydrogen gas used to cool the rotor and certain parts of stator. H2-air mixture is explosive. So filling the generator with H2 by replacing air is dangerous. So initially air is replaced by CO2 and since CO2 is heavier than air CO2 is being filled from the bottom. Purging of air with CO2 is being done till the purity of CO2 inside casing reaches above 95%. Now H2 is dried and then passed from the top to replace the CO2. Purging of H2 is continued till purity of H2 reaches 98%.
  • 28. Why H2 is used as a coolant? • H2 is lightest gas with 0.09 gm / litre while air’s 1.3 i.e. 14.4 times & high thermal capacity • Thermal conductivity of H2 is 5 times that of air. Its specific heat is 3.42 at 0°C, as compared to 0.237 of air. • 2 H2 + O2 mixture ignites on adiabatic compression at 526°C, 3H2 + O2 at 544°C. H2 and O2 combine slowly at 180°C or in bright sunlight. Explosion occurs with moist gases at 550 - 700°C. Ignition temp. of H2 in air is 538°C & Calorific value of H2 is 136 k Cal / gm. • For filling in TGs, 99.9% v/v purity gas is used. Traces of SO2 & NH3 shall not be detectable • Two propeller type fans are shaft mounted on either side of rotor body for circulating H2 in the generator.The H2 is itself cooled by DM water circulation. TRANsfORmERs A static electromagnetic device with two or more windings ,which transforms a system of alternating voltage and current into another system of voltage and current usually of different values and at the same frequency for the purpose of transmitting electrical power. TYPES OF TRANSFORMERS:
  • 29. Power transformers Used in transmission network of higher voltages, deployed for step-up and step down transformer application (400 kV, 200 kV, 110 kV, 66 kV, 33kV,22kV) Distribution transformers Used for lower voltage distribution networks as a means to end user connectivity. (11kV, 6.6 kV, 3.3 kV, 440V, 230V). Transformer insulations • Minor insulation Like inter turn insulation, is achieved using cellulogic paper. • Major insulation Between primary and secondary, phase to phase and inner coil to core. This is achieved by Bakelite, wooden blocks, cellulogic paper cylinders. • Transformer Oil Derivative of petroleum crude. This has good dielectric strength. Also a good cooling medium and absorbs heat from the windings in transformer. The mineral oil has a flash point of 140°C and 160°C fire point. This also 'can Sustain the combustion with its own energy, once it catches fire. Thus this is unsuitable for the transformer located indoors. •The indoor transformers are filled with a synthetic liquid known as silicate liquid. This is fire assistant and has flash point well above 300°C.
  • 30. Types of transformers in FSTPP:  Generator Transformer: The generator is connected to this transformer by means of isolated bus ducts. This transformer is used to step up the generating voltage of around 15KV to grid voltage. This transformer is generally provided with OFAF cooling. It is also provided with off circuit/on load taps on the high voltage side. This transformer has elaborate cooling system consisting of number of oil pumps and cooling fans apart from various accessories. For 500 MW units there are 3 individual single phase transformers for each phase. The rated input voltage is 21KV. RATED O/P 250MVA RATED VOLT. (HV) 420KV RATED VOLT. (LV) 15.75KV RATED CURRENT(HV) 344A RATED CURRENT(LV) 9175A VECTOR GROUP Y n d11  Unit auxiliary transformer The UAT draws its input from the main bus-duct connecting generator to the generator Transformer. The total KVA capacity of unit auxiliary transformer required can be determined by assuming 0.85 power factor and 0.9 efficiency for total auxiliary motor load. It is safe and desirable to provide about 20% excess capacity than circulate so as to provide for miscellaneous auxiliaries and possible increase in auxiliary load. With higher unit ratings and higher steam conditions, the auxiliary power required also increases and limitations imposed by the switchgear voltages available, indicate the maximum size of unit auxiliary transformer which can be used.  Station transformer The station transformer is required to feed power to the auxiliaries during start ups. This transformer is normally rated for the initial auxiliary load requirements of unit. In typical cases, this load is of the order of 60% of the load at full generating capacity. But in large stations where more than one units are operating, the station transformers should have sufficient capacity to
  • 31. start two units at a time in addition to feeding the common auxiliaries. It is also provided with on load tap changer to cater to the fluctuating voltage of the grid. RATED OUTPUT(LV):6.6KV RATED INPUT( HV) : 33KV  Excitation transformer The excitation transformer is used in the static excitation system of the generator .The output of the generator is fed to the primary of the excitation transformer. The secondary is the input to 4 thyristor banks .In addition there are protective relays for the excitation transformer.  Auxiliary transformers They are used to supply power to the LT auxiliary units like ESPs, lubricating oil pumps, seal oil pumps etc.  Tie / Auto transformer Tie transformers are connected to the 400 KV bus. They are used to step down the voltage to 33 KV. Then the station transformers step down the voltage to 6.6 KV (station buses). The unit buses are connected to the station buses through circuit breakers and isolaters. When the generator trips, there is no supply to the unit buses and the tie-transformers supply the station buses. Then the circuit breakers and the isolaters are closed. Thus the supply to the auxiliaries is maintained.  Instrument transformers Potential Transformers step down values to safe levels for measurement. They are also called voltage transformers. Their standard output is 120V. Current Transformers have standard output of 1 or 5 amps. They can produce high voltages if open circuited. SWITCHGEAR “The apparatus used for Switching, Controlling and Protecting the Electrical Circuits and equipment” is known as Switchgear. NEEDS OF SWITCHGEAR :
  • 32. • Switching during normal operating conditions for the purpose of Operation and Maintenance. • Switching during Faults and Abnormal conditions and interrupting the fault currents. PARTS OF SWITCHGEAR : • Switching device: Power circuit Control circuit Measurement and display Protection • Power Circuit: Circuit breakers / contactors Isolators Earthing switch • Control Circuit : Service / test /isolated position selectors Tripping and closing circuit Spring charging, anti pumping arrangement Supply monitoring , space heaters , indications • Measurement and Protection: Ammeter, voltmeter, energy meter Relays, CT, PT, • Classification of switchgears: Method of arc quenching : Bulk oil, Min. oil, Air Break, Air Blast, SF6 , Vacuum Working voltage : 440V, 6.6 kV, 11 kV, 400 kV etc. Indoor / out door SOME INTERLOCKS :
  • 33. Check synchronization for closing Master relay contacts for trip and close 1.) HV & LV Breaker interlocks 2.) Main / Reserve supply change over TT - 2 33 kV System Stage -I I/C from TT - 3 I/C from TT- 1 Stn. Trf.1 Spare Col. Trf.1 Bus PT Bus coupler Bus PT Col. Trf.2 Spare Stn. Trf.2 I/C from 33 kv Bus Stage -II Stn. Trf.4 Stn. Trf.3 Bus PT Bus PT Spare I/C from TT - 3 I/C from TT - 1 I/C from TT - 2 Bus coupler CHP Trf.2 CHP Trf.1 33 kv Bus • The Auxiliary power system in a power plant must form a RELIABLE source of power to all unit and Station auxiliaries. The basic function of Switchgear is to control supply of electric power and to protect the equipment in the event of abnormal conditions. Hence the switchgears have to be RELIABLE, SAFE, and ADEQUATE. • Defining the reliability, safety aspects and adequacy aspects in terms of Quantitative parameters forms the essential part in “SPECIFICATIONS” • 33KV, 11KV, 6.6KV and 3.3KV Switchgears
  • 34. • Indoor, metal clad single front and fully Compartmentalized, with degree of protection IP42 and IP52 for metering compartments. For 33 KV the switchgears can be metal enclosed either. • Circuit Breakers are of either SF6 or Vacuum type. They shall comprise of three separate identical single pole interrupting units operated through a common shaft by a sturdy mechanism. • Breakers are suitable for Switching transformers and motors at any load and also for starting 3.3 KV - Above 200 KW to1500 KW, 11 KV- above 1500 KW for 500MW units and 6.6 KV- above 200KW for 210MW units. • Surge arresters are provided for all motor feeders to limit the over voltages. For Motors where frequent start/stop of motors is called for HRC fuse backed contactors are provided. • Suitable Interlocks are provided to ensure that Breaker is off before opening the rear doors/covers. BASIC dESIGn fEATuRES: ConTRol And SAfETy • Circuit Breakers/contactors are being normally operated from remote through Distributed Digital Control & Management of Information System (DDCMIS)/ Programmable Logic Controller (PLC). The control Switch located on the Switchgear is normally used only for testing. • All the logic for incomers, bus couplers, ties, transformer feeders and motor feeders is being generated in DDCMIS only. The reverse blocking schemes are still incorporated in Switchgear (hardwired).
  • 35.
  • 36.
  • 37.
  • 38. ACKnoWlEdGEMEnT We the students of JADAVPUR UNIVERSITY,KOLKATA have undergone vocational training in NATIONAL THERMAL POWER STATION (FSTPS). We wish to acknowledge the support and helping hands extended by the entire members of the TRAINING DEPARTMENT and all those Engineers who helped & guided us on our visit to the various departments of the famous Thermal Power Station during the course of our training. Any successful work is accompanied by the Helping & Co- operation of well-wisher. Whatever we have tried to present in our project cum training report would remains incomplete unless & until we extend our heartiest thanks to all the people who have spend their valuable time to help & explain us all that we wanted to know. May words will fall short to describe their importance to us, our gratefulness to them & also to their kind & co-operative attitude throughout the course of our training in NTPC (Farakka) . No matter wherever we will stand in our life & career in the end, these glorious days of our short stay with all the people connected directly or indirectly to NTPC (Farakka) will never fade away from my mind. It’s my honor to extended my gratitude & thanks to  Ms. Susmita Bhattacharya  Mr. D.Mohanti  Ms. Anwesha Mukherjee  Mr. Rohit Agarwal  Mr. S.K.SOM This report summarizes the huge learning experience that we had in all the sections of this modern Power Plant. DATE: 15.06.2013 PLACE: MURSHIDABAD