SEM 4 PM SUMMER 2014 ASSIGNMENTS
FOR SOLVED ASSIGNMENTS AT NOMINAL COST
VISIT
WWW.SMUSOLVEDASSIGNMENTS.COM
Or Mail us at
solvemyassignments@gmail.com
PM 0015 – QUANTITATIVE METHODS IN PROJECT MANAGEMENT
1. Write short notes on: Scoring Method for project selection Rules for network construction Project
crashing using network analysis Graphical Evaluation & Review Technique
[Scoring Method for project selection Rules for network construction Project crashing using network
analysis Graphical Evaluation & Review Technique]
2. Describe the importance of Business Forecasting.
[Need for forecasting with examples
Two common approaches to forecasting]
3. Describe the different stages in Project management.
[Explanation of the different stages in Project management]
4. Write short notes on: Time-series Forecasting of Seasonal Data Setting resource calendar in MS
Project Network diagram chart Cost Performance Index
[Time-series Forecasting of Seasonal Data Setting resource calendar in MS Project Network diagram
chart Cost Performance Index]
5. How to create a report on the project activities in the MS Project.
[Explain how to set up of Reports
Explain the process of Creating or Editing Reports
Describe the reports that can be printed
List the steps of Printing a Report]
6. Discuss the algorithm for solving the shortest-route problem.
[Description of shortest-route problems
Description of the 5 steps of the algorithm]
FOR SOLVED ASSIGNMENTS AT NOMINAL COST
VISIT
WWW.SMUSOLVEDASSIGNMENTS.COM
Or Mail us at
solvemyassignments@gmail.com
PM 0016 –PROJECT RISK MANAGEMENT
1. Define Risk Management. Explain the seven step process in risk management planning.
[Definition of Risk Management
Explanation of the seven step process risk management planning]
2. The risk mitigation methodology describes the approach to control implementation. Explain the
steps of the methodology.
[Explain the steps of risk mitigation methodology
Conclusion]
3. Write short notes on: Keane’s Risk Process Monte Carlo Simulation Categories of project risk
Importance of a risk register
[Keane’s Risk Process Monte Carlo Simulation Categories of project risk Importance of a risk register]
4. What is a fishbone diagram? Explain the various tasks involved in constructing a Fishbone diagram.
[Definition of fishbone diagram
Why is it used
Describe the tasks involved in constructing a Fishbone diagram]
5. Benchmarking is considered as a component of Total Quality Management (TQM). Write a note on
benchmarking.
[Explain benchmarking( definition, what will happen if there is incorrect benchmarking)
List any four Advantages of benchmarking
List any our limitations of benchmarking]
6. What are the tips to remove the top three project estimating risks? Explain
[Listing of the tips
Explanation of the tips]
FOR SOLVED ASSIGNMENTS AT NOMINAL COST
VISIT
WWW.SMUSOLVEDASSIGNMENTS.COM
Or Mail us at
solvemyassignments@gmail.com
PM 0017 –PROJECT QUALITY MANAGEMENT
1. Discuss the various tools used for understanding data.
[Various tools: Graphs, Histograms, Pareto charts, and Scatter diagram.]
2. Write short notes on The Enterprise Project Management Model.
[Brief Explanation of Enterprise project management Working of EPM within the model
Implementation of EPM Advantages of an EPM System]
3. Explain communities of practice .
[Definition and description of Communities of Practice (CoP), The role of Communities of practice in
helping organisations to compete globally through information sharing across the globe]
4. The project management initiative program is a six step process which is designed to bring about a
measurement team from the introduction to the project management-focused measurements
through the design, the development and the implementation of the project management value
measurement program. Explain the six steps in the project management initiative program.
[Measurement readiness planning Initiative Planning Measures development Scorecard development
Measurement program Implementation Planning Measurement program implementation]
5. Briefly explain the seven forces involved in the success of quality in project management.
[Seven forces Placing the budgetary considerations ahead of the quality Placing schedule
considerations ahead of quality Placing political considerations ahead of quality Being arrogant Lack
of fundamental knowledge, research or education, the principles of quality assurance Pervasively
believing in entitlement Practicing autocratic behaviours, resulting in “enrolment
Conclusion]
6. Explain briefly the Inspection-Planning and necessity in quality.
[Explanation inspection and the test plans Activities of inspection planning Explanation of necessity in
quality Basic principles Amount of inspection]
FOR SOLVED ASSIGNMENTS AT NOMINAL COST
VISIT
WWW.SMUSOLVEDASSIGNMENTS.COM
Or Mail us at
solvemyassignments@gmail.com
PM 0018 –CONTRACTS MANAGEMENT IN PROJECTS
1. Fixed price contracts have a preset price that the vendor must adhere to in performing the work
and in providing materials. There are different types of fixed price contracts. Explain them.
[Explanation of various types of fixed price contracts]
2. Direct contracting is another procurement method that is used under a limited number of
exceptional circumstances. Explain the conditions for adopting direct contracting, requirements and
steps for direct contracting
[Conditions for adopting direct contracting Requirements for direct contracting and Steps for direct
contracting]
3. Write short notes on Cost Plus Fee Contracts.
[Explanation of Cost Plus Fee Contracts Features Conditions for adopting Advantages and
disadvantages]
4. The methods of selecting a consultant are designed to achieve the objectives of quality, efficiency,
fairness and transparency in the selection process and to encourage competition. Discuss any 2
methods of selecting consultants.
[Explanation of any 2 of the methods
With
Where it is appropriate
Type of assignments for which this method of selection is adopted]
5. The contract control process commences right at the beginning stage of bid document preparation
inviting contractors to bid, and proceeds through the contract negotiation, contractor selection,
monitoring and controlling of the contractor’s work and terminating the contract. Explain the areas
that need attention for effective control of the contracts in a project
[Core competence of the project manager Requirements of the working system Use of Work
Breakdown Structure (WBS) Recognising the limitations with flexibility]
6. Explain the need of Procurement law and what are its objectives?
[Explain the need of Procurement law
List the Objectives]
FOR SOLVED ASSIGNMENTS AT NOMINAL COST
VISIT
WWW.SMUSOLVEDASSIGNMENTS.COM
Or Mail us at
solvemyassignments@gmail.com

More Related Content

What's hot

PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK® Guide 5th edition Processes Flow in English - Simplified VersionPMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK® Guide 5th edition Processes Flow in English - Simplified VersionRicardo Viana Vargas
 
Project Management Class ( based on PMBOK) - Day 5
Project Management Class ( based on PMBOK) - Day 5Project Management Class ( based on PMBOK) - Day 5
Project Management Class ( based on PMBOK) - Day 5Highmark Health
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
PMP Flash Card
PMP Flash CardPMP Flash Card
PMP Flash Cardasim78
 
Pmp brain-dump
Pmp brain-dumpPmp brain-dump
Pmp brain-dumpPrakashRH
 
Pmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementYudha Pratama, PMP
 
Project Management Class ( based on PMBOK) - Day 2
Project Management Class ( based on PMBOK) - Day 2Project Management Class ( based on PMBOK) - Day 2
Project Management Class ( based on PMBOK) - Day 2Highmark Health
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
Management control of projects
Management control of projectsManagement control of projects
Management control of projectsSai Mahesh
 
Project management overview
Project management overviewProject management overview
Project management overviewSunil Guglani
 
Pm 0010 introduction to project management
Pm 0010   introduction to project managementPm 0010   introduction to project management
Pm 0010 introduction to project managementsmumbahelp
 
Project Management Class ( based on PMBOK) - Day 6
Project Management Class ( based on PMBOK) - Day 6Project Management Class ( based on PMBOK) - Day 6
Project Management Class ( based on PMBOK) - Day 6Highmark Health
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Concept of Value Management
 Concept of Value Management Concept of Value Management
Concept of Value Managementmsmayamin128
 
Project Quality Management
 Project Quality Management Project Quality Management
Project Quality ManagementSerdar Temiz
 

What's hot (20)

PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK® Guide 5th edition Processes Flow in English - Simplified VersionPMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
 
Project Management Class ( based on PMBOK) - Day 5
Project Management Class ( based on PMBOK) - Day 5Project Management Class ( based on PMBOK) - Day 5
Project Management Class ( based on PMBOK) - Day 5
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
PMP Flash Card
PMP Flash CardPMP Flash Card
PMP Flash Card
 
Pmp brain-dump
Pmp brain-dumpPmp brain-dump
Pmp brain-dump
 
Pmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost management
 
Project Management Class ( based on PMBOK) - Day 2
Project Management Class ( based on PMBOK) - Day 2Project Management Class ( based on PMBOK) - Day 2
Project Management Class ( based on PMBOK) - Day 2
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
Management control of projects
Management control of projectsManagement control of projects
Management control of projects
 
Project management overview
Project management overviewProject management overview
Project management overview
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
Pm 0010 introduction to project management
Pm 0010   introduction to project managementPm 0010   introduction to project management
Pm 0010 introduction to project management
 
Mg6088 spm unit-4
Mg6088 spm unit-4Mg6088 spm unit-4
Mg6088 spm unit-4
 
Project cost management
Project cost managementProject cost management
Project cost management
 
My MBA Course on Project Quality Management
My MBA Course on Project Quality ManagementMy MBA Course on Project Quality Management
My MBA Course on Project Quality Management
 
Project Management Class ( based on PMBOK) - Day 6
Project Management Class ( based on PMBOK) - Day 6Project Management Class ( based on PMBOK) - Day 6
Project Management Class ( based on PMBOK) - Day 6
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Concept of Value Management
 Concept of Value Management Concept of Value Management
Concept of Value Management
 
Project Quality Management
 Project Quality Management Project Quality Management
Project Quality Management
 
Project cost control
Project cost controlProject cost control
Project cost control
 

Viewers also liked

SEM 3 OM SUMMER 2014 ASSIGNMENTS
SEM 3 OM SUMMER 2014 ASSIGNMENTSSEM 3 OM SUMMER 2014 ASSIGNMENTS
SEM 3 OM SUMMER 2014 ASSIGNMENTSsolved_assignments
 
SEM 3 OM SUMMER 2014 ASSIGNMENTS
SEM 3 OM SUMMER 2014 ASSIGNMENTSSEM 3 OM SUMMER 2014 ASSIGNMENTS
SEM 3 OM SUMMER 2014 ASSIGNMENTSsolved_assignments
 
SMU mba sem 4 mis fall 2014 assignments
SMU mba sem 4 mis fall 2014 assignmentsSMU mba sem 4 mis fall 2014 assignments
SMU mba sem 4 mis fall 2014 assignmentssolved_assignments
 
SMU mba sem 3 om fall 2014 assignments
SMU mba sem 3 om fall 2014 assignmentsSMU mba sem 3 om fall 2014 assignments
SMU mba sem 3 om fall 2014 assignmentssolved_assignments
 
SMU BBA sem 5 fall 2014 assignments
SMU BBA sem 5 fall 2014 assignmentsSMU BBA sem 5 fall 2014 assignments
SMU BBA sem 5 fall 2014 assignmentssolved_assignments
 
Sem 1 SMU mba spring assignments
Sem 1 SMU mba spring assignmentsSem 1 SMU mba spring assignments
Sem 1 SMU mba spring assignmentssolved_assignments
 
SMU MBA SEM 2 FALL 2014 ASSIGNMENTS
SMU MBA SEM 2 FALL 2014 ASSIGNMENTSSMU MBA SEM 2 FALL 2014 ASSIGNMENTS
SMU MBA SEM 2 FALL 2014 ASSIGNMENTSsolved_assignments
 
SEM 3 MIS SUMMER 2014 ASSIGNMENTS
SEM 3 MIS SUMMER 2014 ASSIGNMENTSSEM 3 MIS SUMMER 2014 ASSIGNMENTS
SEM 3 MIS SUMMER 2014 ASSIGNMENTSsolved_assignments
 
SEM 3 Finance SUMMER 2014 ASSIGNMENTS
SEM 3 Finance SUMMER 2014 ASSIGNMENTSSEM 3 Finance SUMMER 2014 ASSIGNMENTS
SEM 3 Finance SUMMER 2014 ASSIGNMENTSsolved_assignments
 
SMU BBA SUMMER DRIVE ASSIGNMENTS
SMU BBA SUMMER DRIVE ASSIGNMENTSSMU BBA SUMMER DRIVE ASSIGNMENTS
SMU BBA SUMMER DRIVE ASSIGNMENTSsolved_assignments
 
SEM 3 PM SUMMER 2014 ASSIGNMENTS
SEM 3 PM SUMMER 2014 ASSIGNMENTSSEM 3 PM SUMMER 2014 ASSIGNMENTS
SEM 3 PM SUMMER 2014 ASSIGNMENTSsolved_assignments
 
SEM 3 OM SUMMER 2014 ASSIGNMENTS
SEM 3 OM SUMMER 2014 ASSIGNMENTSSEM 3 OM SUMMER 2014 ASSIGNMENTS
SEM 3 OM SUMMER 2014 ASSIGNMENTSsolved_assignments
 
SEM 3 BANKING SUMMER 2014 ASSIGNMENTS
SEM 3 BANKING SUMMER 2014 ASSIGNMENTSSEM 3 BANKING SUMMER 2014 ASSIGNMENTS
SEM 3 BANKING SUMMER 2014 ASSIGNMENTSsolved_assignments
 

Viewers also liked (18)

SEM 3 OM SUMMER 2014 ASSIGNMENTS
SEM 3 OM SUMMER 2014 ASSIGNMENTSSEM 3 OM SUMMER 2014 ASSIGNMENTS
SEM 3 OM SUMMER 2014 ASSIGNMENTS
 
SEM 3 OM SUMMER 2014 ASSIGNMENTS
SEM 3 OM SUMMER 2014 ASSIGNMENTSSEM 3 OM SUMMER 2014 ASSIGNMENTS
SEM 3 OM SUMMER 2014 ASSIGNMENTS
 
SMU mba sem 4 mis fall 2014 assignments
SMU mba sem 4 mis fall 2014 assignmentsSMU mba sem 4 mis fall 2014 assignments
SMU mba sem 4 mis fall 2014 assignments
 
Bscit winter 2013
Bscit winter 2013Bscit winter 2013
Bscit winter 2013
 
SMU mba sem 3 om fall 2014 assignments
SMU mba sem 3 om fall 2014 assignmentsSMU mba sem 3 om fall 2014 assignments
SMU mba sem 3 om fall 2014 assignments
 
SMU BBA sem 5 fall 2014 assignments
SMU BBA sem 5 fall 2014 assignmentsSMU BBA sem 5 fall 2014 assignments
SMU BBA sem 5 fall 2014 assignments
 
Sem 1 mba winter 2013
Sem 1 mba winter 2013Sem 1 mba winter 2013
Sem 1 mba winter 2013
 
Bca spring driveassignments
Bca spring driveassignmentsBca spring driveassignments
Bca spring driveassignments
 
Sem 1 SMU mba spring assignments
Sem 1 SMU mba spring assignmentsSem 1 SMU mba spring assignments
Sem 1 SMU mba spring assignments
 
SMU MBA SEM 2 FALL 2014 ASSIGNMENTS
SMU MBA SEM 2 FALL 2014 ASSIGNMENTSSMU MBA SEM 2 FALL 2014 ASSIGNMENTS
SMU MBA SEM 2 FALL 2014 ASSIGNMENTS
 
SEM 3 MIS SUMMER 2014 ASSIGNMENTS
SEM 3 MIS SUMMER 2014 ASSIGNMENTSSEM 3 MIS SUMMER 2014 ASSIGNMENTS
SEM 3 MIS SUMMER 2014 ASSIGNMENTS
 
SEM 3 Finance SUMMER 2014 ASSIGNMENTS
SEM 3 Finance SUMMER 2014 ASSIGNMENTSSEM 3 Finance SUMMER 2014 ASSIGNMENTS
SEM 3 Finance SUMMER 2014 ASSIGNMENTS
 
Mba smu solved assignemnts
Mba smu solved assignemntsMba smu solved assignemnts
Mba smu solved assignemnts
 
SMU BBA SUMMER DRIVE ASSIGNMENTS
SMU BBA SUMMER DRIVE ASSIGNMENTSSMU BBA SUMMER DRIVE ASSIGNMENTS
SMU BBA SUMMER DRIVE ASSIGNMENTS
 
SEM 3 PM SUMMER 2014 ASSIGNMENTS
SEM 3 PM SUMMER 2014 ASSIGNMENTSSEM 3 PM SUMMER 2014 ASSIGNMENTS
SEM 3 PM SUMMER 2014 ASSIGNMENTS
 
Sem4 mis
Sem4 misSem4 mis
Sem4 mis
 
SEM 3 OM SUMMER 2014 ASSIGNMENTS
SEM 3 OM SUMMER 2014 ASSIGNMENTSSEM 3 OM SUMMER 2014 ASSIGNMENTS
SEM 3 OM SUMMER 2014 ASSIGNMENTS
 
SEM 3 BANKING SUMMER 2014 ASSIGNMENTS
SEM 3 BANKING SUMMER 2014 ASSIGNMENTSSEM 3 BANKING SUMMER 2014 ASSIGNMENTS
SEM 3 BANKING SUMMER 2014 ASSIGNMENTS
 

Similar to SEM 4 PM SUMMER 2014 ASSIGNMENTS

SMU mba sem 4 om fall 2014 assignments
SMU mba sem 4 om fall 2014 assignmentsSMU mba sem 4 om fall 2014 assignments
SMU mba sem 4 om fall 2014 assignmentssolved_assignments
 
Smu mba sem 4 pm winter 2014 assignments
Smu mba sem 4 pm winter 2014 assignmentsSmu mba sem 4 pm winter 2014 assignments
Smu mba sem 4 pm winter 2014 assignmentssolved_assignments
 
Pm 4 th samples
Pm 4 th samplesPm 4 th samples
Pm 4 th samplessmumbahelp
 
Smu mba sem 4 pm winter 2015 assignments
Smu mba sem 4 pm winter 2015 assignmentsSmu mba sem 4 pm winter 2015 assignments
Smu mba sem 4 pm winter 2015 assignmentssolved_assignments
 
Smu mba sem 4 pm fall 2015 assignments
Smu mba sem 4 pm fall 2015 assignmentsSmu mba sem 4 pm fall 2015 assignments
Smu mba sem 4 pm fall 2015 assignmentssolved_assignments
 
SEM 3 PM SUMMER 2014 ASSIGNMENTS
SEM 3 PM SUMMER 2014 ASSIGNMENTSSEM 3 PM SUMMER 2014 ASSIGNMENTS
SEM 3 PM SUMMER 2014 ASSIGNMENTSsolved_assignments
 
SMU SEM 3 FINANCE Summer 2014 ASSIGNMENTS
SMU SEM 3 FINANCE Summer 2014 ASSIGNMENTSSMU SEM 3 FINANCE Summer 2014 ASSIGNMENTS
SMU SEM 3 FINANCE Summer 2014 ASSIGNMENTSsolved_assignments
 
Ops 571 free final exam sg 2014
Ops 571  free final exam sg 2014Ops 571  free final exam sg 2014
Ops 571 free final exam sg 2014Rogue Phoenix
 
Smu mba sem 4 pm winter 2016 assignments
Smu mba sem 4 pm winter 2016 assignmentsSmu mba sem 4 pm winter 2016 assignments
Smu mba sem 4 pm winter 2016 assignmentssolved_assignments
 
Smu mba sem 4 pm fall 2016 assignments
Smu mba sem 4 pm fall 2016 assignmentsSmu mba sem 4 pm fall 2016 assignments
Smu mba sem 4 pm fall 2016 assignmentssolved_assignments
 
Pm0011 project planning and scheduling
Pm0011   project planning and schedulingPm0011   project planning and scheduling
Pm0011 project planning and schedulingsmumbahelp
 
Project managment (pm) solved assignments summer 2015
Project managment  (pm) solved assignments summer 2015Project managment  (pm) solved assignments summer 2015
Project managment (pm) solved assignments summer 2015smumbahelp
 
Smu mba sem 4 pm summer 2015 assignments
Smu mba sem 4 pm summer 2015  assignmentsSmu mba sem 4 pm summer 2015  assignments
Smu mba sem 4 pm summer 2015 assignmentssolved_assignments
 
Smu mba sem 4 pm summer 2016 assignments
Smu mba sem 4 pm summer 2016 assignmentsSmu mba sem 4 pm summer 2016 assignments
Smu mba sem 4 pm summer 2016 assignmentsPradeep Sharma
 
Smu mba sem 3 pm spring 2015 assignments
Smu mba sem 3 pm spring 2015 assignmentsSmu mba sem 3 pm spring 2015 assignments
Smu mba sem 3 pm spring 2015 assignmentssolved_assignments
 
Integrated Project Management Measures in CMMI
Integrated Project Management Measures in CMMIIntegrated Project Management Measures in CMMI
Integrated Project Management Measures in CMMIijcsit
 
scribd.vdownloaders.com_day-6-quality.pdf
scribd.vdownloaders.com_day-6-quality.pdfscribd.vdownloaders.com_day-6-quality.pdf
scribd.vdownloaders.com_day-6-quality.pdfAbdullahSamy6
 
SEM 4 HR SUMMER 2014 ASSIGNMENTS
SEM 4 HR SUMMER 2014 ASSIGNMENTSSEM 4 HR SUMMER 2014 ASSIGNMENTS
SEM 4 HR SUMMER 2014 ASSIGNMENTSsolved_assignments
 
Smu mba sem 4 pm spring 2015 assignments
Smu mba sem 4 pm spring 2015  assignmentsSmu mba sem 4 pm spring 2015  assignments
Smu mba sem 4 pm spring 2015 assignmentssolved_assignments
 

Similar to SEM 4 PM SUMMER 2014 ASSIGNMENTS (20)

SMU mba sem 4 om fall 2014 assignments
SMU mba sem 4 om fall 2014 assignmentsSMU mba sem 4 om fall 2014 assignments
SMU mba sem 4 om fall 2014 assignments
 
Smu mba sem 4 pm winter 2014 assignments
Smu mba sem 4 pm winter 2014 assignmentsSmu mba sem 4 pm winter 2014 assignments
Smu mba sem 4 pm winter 2014 assignments
 
Pm 4 th samples
Pm 4 th samplesPm 4 th samples
Pm 4 th samples
 
Smu mba sem 4 pm winter 2015 assignments
Smu mba sem 4 pm winter 2015 assignmentsSmu mba sem 4 pm winter 2015 assignments
Smu mba sem 4 pm winter 2015 assignments
 
Smu mba sem 4 pm fall 2015 assignments
Smu mba sem 4 pm fall 2015 assignmentsSmu mba sem 4 pm fall 2015 assignments
Smu mba sem 4 pm fall 2015 assignments
 
SEM 3 PM SUMMER 2014 ASSIGNMENTS
SEM 3 PM SUMMER 2014 ASSIGNMENTSSEM 3 PM SUMMER 2014 ASSIGNMENTS
SEM 3 PM SUMMER 2014 ASSIGNMENTS
 
SMU SEM 3 FINANCE Summer 2014 ASSIGNMENTS
SMU SEM 3 FINANCE Summer 2014 ASSIGNMENTSSMU SEM 3 FINANCE Summer 2014 ASSIGNMENTS
SMU SEM 3 FINANCE Summer 2014 ASSIGNMENTS
 
Ops 571 free final exam sg 2014
Ops 571  free final exam sg 2014Ops 571  free final exam sg 2014
Ops 571 free final exam sg 2014
 
Mb0049 project management
Mb0049 project managementMb0049 project management
Mb0049 project management
 
Smu mba sem 4 pm winter 2016 assignments
Smu mba sem 4 pm winter 2016 assignmentsSmu mba sem 4 pm winter 2016 assignments
Smu mba sem 4 pm winter 2016 assignments
 
Smu mba sem 4 pm fall 2016 assignments
Smu mba sem 4 pm fall 2016 assignmentsSmu mba sem 4 pm fall 2016 assignments
Smu mba sem 4 pm fall 2016 assignments
 
Pm0011 project planning and scheduling
Pm0011   project planning and schedulingPm0011   project planning and scheduling
Pm0011 project planning and scheduling
 
Project managment (pm) solved assignments summer 2015
Project managment  (pm) solved assignments summer 2015Project managment  (pm) solved assignments summer 2015
Project managment (pm) solved assignments summer 2015
 
Smu mba sem 4 pm summer 2015 assignments
Smu mba sem 4 pm summer 2015  assignmentsSmu mba sem 4 pm summer 2015  assignments
Smu mba sem 4 pm summer 2015 assignments
 
Smu mba sem 4 pm summer 2016 assignments
Smu mba sem 4 pm summer 2016 assignmentsSmu mba sem 4 pm summer 2016 assignments
Smu mba sem 4 pm summer 2016 assignments
 
Smu mba sem 3 pm spring 2015 assignments
Smu mba sem 3 pm spring 2015 assignmentsSmu mba sem 3 pm spring 2015 assignments
Smu mba sem 3 pm spring 2015 assignments
 
Integrated Project Management Measures in CMMI
Integrated Project Management Measures in CMMIIntegrated Project Management Measures in CMMI
Integrated Project Management Measures in CMMI
 
scribd.vdownloaders.com_day-6-quality.pdf
scribd.vdownloaders.com_day-6-quality.pdfscribd.vdownloaders.com_day-6-quality.pdf
scribd.vdownloaders.com_day-6-quality.pdf
 
SEM 4 HR SUMMER 2014 ASSIGNMENTS
SEM 4 HR SUMMER 2014 ASSIGNMENTSSEM 4 HR SUMMER 2014 ASSIGNMENTS
SEM 4 HR SUMMER 2014 ASSIGNMENTS
 
Smu mba sem 4 pm spring 2015 assignments
Smu mba sem 4 pm spring 2015  assignmentsSmu mba sem 4 pm spring 2015  assignments
Smu mba sem 4 pm spring 2015 assignments
 

Recently uploaded

18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 

Recently uploaded (20)

18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 

SEM 4 PM SUMMER 2014 ASSIGNMENTS

  • 1. SEM 4 PM SUMMER 2014 ASSIGNMENTS FOR SOLVED ASSIGNMENTS AT NOMINAL COST VISIT WWW.SMUSOLVEDASSIGNMENTS.COM Or Mail us at solvemyassignments@gmail.com PM 0015 – QUANTITATIVE METHODS IN PROJECT MANAGEMENT 1. Write short notes on: Scoring Method for project selection Rules for network construction Project crashing using network analysis Graphical Evaluation & Review Technique [Scoring Method for project selection Rules for network construction Project crashing using network analysis Graphical Evaluation & Review Technique] 2. Describe the importance of Business Forecasting. [Need for forecasting with examples Two common approaches to forecasting] 3. Describe the different stages in Project management. [Explanation of the different stages in Project management] 4. Write short notes on: Time-series Forecasting of Seasonal Data Setting resource calendar in MS Project Network diagram chart Cost Performance Index [Time-series Forecasting of Seasonal Data Setting resource calendar in MS Project Network diagram chart Cost Performance Index] 5. How to create a report on the project activities in the MS Project. [Explain how to set up of Reports Explain the process of Creating or Editing Reports Describe the reports that can be printed List the steps of Printing a Report] 6. Discuss the algorithm for solving the shortest-route problem. [Description of shortest-route problems Description of the 5 steps of the algorithm] FOR SOLVED ASSIGNMENTS AT NOMINAL COST VISIT WWW.SMUSOLVEDASSIGNMENTS.COM Or Mail us at solvemyassignments@gmail.com PM 0016 –PROJECT RISK MANAGEMENT 1. Define Risk Management. Explain the seven step process in risk management planning. [Definition of Risk Management Explanation of the seven step process risk management planning] 2. The risk mitigation methodology describes the approach to control implementation. Explain the steps of the methodology. [Explain the steps of risk mitigation methodology Conclusion] 3. Write short notes on: Keane’s Risk Process Monte Carlo Simulation Categories of project risk Importance of a risk register [Keane’s Risk Process Monte Carlo Simulation Categories of project risk Importance of a risk register] 4. What is a fishbone diagram? Explain the various tasks involved in constructing a Fishbone diagram.
  • 2. [Definition of fishbone diagram Why is it used Describe the tasks involved in constructing a Fishbone diagram] 5. Benchmarking is considered as a component of Total Quality Management (TQM). Write a note on benchmarking. [Explain benchmarking( definition, what will happen if there is incorrect benchmarking) List any four Advantages of benchmarking List any our limitations of benchmarking] 6. What are the tips to remove the top three project estimating risks? Explain [Listing of the tips Explanation of the tips] FOR SOLVED ASSIGNMENTS AT NOMINAL COST VISIT WWW.SMUSOLVEDASSIGNMENTS.COM Or Mail us at solvemyassignments@gmail.com PM 0017 –PROJECT QUALITY MANAGEMENT 1. Discuss the various tools used for understanding data. [Various tools: Graphs, Histograms, Pareto charts, and Scatter diagram.] 2. Write short notes on The Enterprise Project Management Model. [Brief Explanation of Enterprise project management Working of EPM within the model Implementation of EPM Advantages of an EPM System] 3. Explain communities of practice . [Definition and description of Communities of Practice (CoP), The role of Communities of practice in helping organisations to compete globally through information sharing across the globe] 4. The project management initiative program is a six step process which is designed to bring about a measurement team from the introduction to the project management-focused measurements through the design, the development and the implementation of the project management value measurement program. Explain the six steps in the project management initiative program. [Measurement readiness planning Initiative Planning Measures development Scorecard development Measurement program Implementation Planning Measurement program implementation] 5. Briefly explain the seven forces involved in the success of quality in project management. [Seven forces Placing the budgetary considerations ahead of the quality Placing schedule considerations ahead of quality Placing political considerations ahead of quality Being arrogant Lack of fundamental knowledge, research or education, the principles of quality assurance Pervasively believing in entitlement Practicing autocratic behaviours, resulting in “enrolment Conclusion] 6. Explain briefly the Inspection-Planning and necessity in quality. [Explanation inspection and the test plans Activities of inspection planning Explanation of necessity in quality Basic principles Amount of inspection] FOR SOLVED ASSIGNMENTS AT NOMINAL COST VISIT WWW.SMUSOLVEDASSIGNMENTS.COM Or Mail us at solvemyassignments@gmail.com PM 0018 –CONTRACTS MANAGEMENT IN PROJECTS
  • 3. 1. Fixed price contracts have a preset price that the vendor must adhere to in performing the work and in providing materials. There are different types of fixed price contracts. Explain them. [Explanation of various types of fixed price contracts] 2. Direct contracting is another procurement method that is used under a limited number of exceptional circumstances. Explain the conditions for adopting direct contracting, requirements and steps for direct contracting [Conditions for adopting direct contracting Requirements for direct contracting and Steps for direct contracting] 3. Write short notes on Cost Plus Fee Contracts. [Explanation of Cost Plus Fee Contracts Features Conditions for adopting Advantages and disadvantages] 4. The methods of selecting a consultant are designed to achieve the objectives of quality, efficiency, fairness and transparency in the selection process and to encourage competition. Discuss any 2 methods of selecting consultants. [Explanation of any 2 of the methods With Where it is appropriate Type of assignments for which this method of selection is adopted] 5. The contract control process commences right at the beginning stage of bid document preparation inviting contractors to bid, and proceeds through the contract negotiation, contractor selection, monitoring and controlling of the contractor’s work and terminating the contract. Explain the areas that need attention for effective control of the contracts in a project [Core competence of the project manager Requirements of the working system Use of Work Breakdown Structure (WBS) Recognising the limitations with flexibility] 6. Explain the need of Procurement law and what are its objectives? [Explain the need of Procurement law List the Objectives] FOR SOLVED ASSIGNMENTS AT NOMINAL COST VISIT WWW.SMUSOLVEDASSIGNMENTS.COM Or Mail us at solvemyassignments@gmail.com