SlideShare a Scribd company logo
1 of 13
SUBMITTED TO-
Prof. Harpinder Singh
SUBMITTED BY-
Aman Kumar
GU-2015-0352-L
B.Tech CE 7th sem.
CONTENTS…
•Introduction
•Necessity of Well Foundation
•Forces acting on Well
•Shapes of Well
•Components of Well
•Sinking of Well
WELL FOUNDATION
The deep foundations which are usually provided in situations
where the loads are heavy and have to be transferred to a lower strata
are termed as Well Foundations or Caissions.
Wells or caissons have been in use for foundations of bridges and other
Important structures since the Roman and Moghul periods.
Taj Mahal at Agra built during the reign of Shah Jahan was constructed
over Well Foundation.
The word ‘Caisson’ is derived from french word ‘Caisse’ meaning a box.
Thus it refers to a box like structure, round or rectangular which is sunk
from the surface of ground or water to some required depth.
Well Foundations have been used for most of the major bridges in India.
NECESSITY OF WELL FOUNDATION
A well foundation is a type of foundation which is generally built in parts
at the surface and then sunk to its final position, where the part of the
permanent foundation. The uses of Well Foundations are described
below:
•Well Foundations are widely used in India for foundations of piers and
abutments of roads and railway bridges.
•Wells are effectively used as foundation base for heavy machinery and
equipments.
•Well Foundations can resist large lateral loads in case of bridges.
•Wells can also resist large uplifting loads as in case of transmission
towers.
FORECS ACTING ON WELL FOUNDATION
•Dead Loads (self weight of well and super structure)
•Live Loads
•Impact Loads (impact effect due to live load only)
•Wind Loads
•Water Pressure
•Longitudinal Forces (due to tractive and braking forces)
•Centrifugal Force
•Buoyant Forces
•Earth Pressure
•Temperature Stresses
•Seismic Forces
SHAPES OF WELL FOUNDATION
•Circular Well
•Double-D Well
•Rectangular Well
•Dumb Well
•Twin Circular Well
•Double Octagonal with circular Dredge Holes
COMPONENTS OF WELL
1. Well Cap
2. Steining
3. Curb
4. Cutting Edge
5. Bottom Plug
6. Dredge Hole
7. Top Plug
SINKING OF WELL
The operation of ‘Sinking of Well’ consists of following stages:
1. Laying of Well Curb
2. Construction of Well Steining
3. Sinking Operation
Laying of Well
Curb
If the river bed is dry, there is
no problem in laying the well
curb.
An exacavation is made and
the cutting edge over which
the well curb is to be laid is
placed at the proper position.
However, if the river bed is
not dry and the depth of
water is less then 5 m,simple
sand islands may be made by
laying a few layers of sand
beds,before laying the well
curb.
Construction of
Well Steining
After laying the well curb,
the well steining should be
built initially in small heights
of about 2 m.The sinking
operation is started after
allowing atleast 24 hours for
setting.
Sinking Operation
The well is sunk by
excavating material from
inside under the curb;
manually or mechanically.
Chisels are used for breaking
the hard soil and explosives
are used for sinking through
rock.
To accelerate the process of
sinking, additional load is
placed on the well in the
form of sand bags by
erecting a suitable platform.
This load is termed as
Kentledge.
Contact on Facebook- https://www.facebook.com/amn.kmr352

More Related Content

What's hot

Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundationSourabh Jain
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundationsDar Hilal
 
Prefabricated Vertical Drains (PVD) method statement
Prefabricated Vertical Drains  (PVD) method statementPrefabricated Vertical Drains  (PVD) method statement
Prefabricated Vertical Drains (PVD) method statementKhaza Ahmed Palash
 
Vibration method for ground improvement technique
Vibration method for ground improvement techniqueVibration method for ground improvement technique
Vibration method for ground improvement techniqueABHISHEK THAKKAE
 
Ct pad-foundation
Ct pad-foundationCt pad-foundation
Ct pad-foundationWan Nee
 
Lining of tunnel
Lining of tunnelLining of tunnel
Lining of tunnelGiri Guru
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Make Mannan
 
Condition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concreteCondition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concreteAvinash Kumar Gupta
 

What's hot (20)

Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundation
 
Coffer dam and its type
Coffer dam and its typeCoffer dam and its type
Coffer dam and its type
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
 
Geotechnical investigation
Geotechnical investigationGeotechnical investigation
Geotechnical investigation
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
 
Wash boring
Wash boringWash boring
Wash boring
 
Cofferdam
CofferdamCofferdam
Cofferdam
 
Prefabricated Vertical Drains (PVD) method statement
Prefabricated Vertical Drains  (PVD) method statementPrefabricated Vertical Drains  (PVD) method statement
Prefabricated Vertical Drains (PVD) method statement
 
Vibration method for ground improvement technique
Vibration method for ground improvement techniqueVibration method for ground improvement technique
Vibration method for ground improvement technique
 
Lecture 4
Lecture 4Lecture 4
Lecture 4
 
Shallowfoundations
ShallowfoundationsShallowfoundations
Shallowfoundations
 
Pile load test
Pile load testPile load test
Pile load test
 
Lecture 5
Lecture 5Lecture 5
Lecture 5
 
Ct pad-foundation
Ct pad-foundationCt pad-foundation
Ct pad-foundation
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
 
Lining of tunnel
Lining of tunnelLining of tunnel
Lining of tunnel
 
Bearing capacity of soil final
Bearing capacity of soil  final Bearing capacity of soil  final
Bearing capacity of soil final
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)
 
Condition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concreteCondition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concrete
 
Cofferdam
CofferdamCofferdam
Cofferdam
 

Similar to Well foundation by Aman Kumar

Chapter 4.2 coffer dam, well foundation-final1
Chapter 4.2   coffer dam, well foundation-final1Chapter 4.2   coffer dam, well foundation-final1
Chapter 4.2 coffer dam, well foundation-final1DYPCET
 
1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptxAkshayGhorpade19
 
Foundation selection
Foundation selectionFoundation selection
Foundation selectiondhara dattani
 
earthen dams - 2022-12-16T235122.473.pptx
earthen dams - 2022-12-16T235122.473.pptxearthen dams - 2022-12-16T235122.473.pptx
earthen dams - 2022-12-16T235122.473.pptxDualAccount1
 
caissons and cofferdam in substructure construction
caissons and cofferdam in substructure constructioncaissons and cofferdam in substructure construction
caissons and cofferdam in substructure constructionChinnuNinan
 
Rock mechanics for engineering geology (part 2)
Rock mechanics for engineering geology (part 2)Rock mechanics for engineering geology (part 2)
Rock mechanics for engineering geology (part 2)Jyoti Khatiwada
 
Coffer Dams and Caissons
Coffer Dams and CaissonsCoffer Dams and Caissons
Coffer Dams and CaissonsRizwan Samor
 
Chapter 4.3 well foundation-final-ppt
Chapter 4.3   well foundation-final-pptChapter 4.3   well foundation-final-ppt
Chapter 4.3 well foundation-final-pptDYPCET
 
Design of Hydraulic Structures
Design of Hydraulic StructuresDesign of Hydraulic Structures
Design of Hydraulic StructuresGAURAV. H .TANDON
 
Cofferdam_ppt.pptx
Cofferdam_ppt.pptxCofferdam_ppt.pptx
Cofferdam_ppt.pptxJackRider12
 
underwater construction
underwater constructionunderwater construction
underwater constructionYasir Hashmi
 

Similar to Well foundation by Aman Kumar (20)

Chapter 4.2 coffer dam, well foundation-final1
Chapter 4.2   coffer dam, well foundation-final1Chapter 4.2   coffer dam, well foundation-final1
Chapter 4.2 coffer dam, well foundation-final1
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx
 
Well foundation
Well foundationWell foundation
Well foundation
 
Foundation selection
Foundation selectionFoundation selection
Foundation selection
 
Chapter 3 caisson
Chapter 3 caissonChapter 3 caisson
Chapter 3 caisson
 
earthen dams - 2022-12-16T235122.473.pptx
earthen dams - 2022-12-16T235122.473.pptxearthen dams - 2022-12-16T235122.473.pptx
earthen dams - 2022-12-16T235122.473.pptx
 
Dams and spillways
Dams and spillwaysDams and spillways
Dams and spillways
 
caissons and cofferdam in substructure construction
caissons and cofferdam in substructure constructioncaissons and cofferdam in substructure construction
caissons and cofferdam in substructure construction
 
Rock mechanics for engineering geology (part 2)
Rock mechanics for engineering geology (part 2)Rock mechanics for engineering geology (part 2)
Rock mechanics for engineering geology (part 2)
 
Coffer Dams and Caissons
Coffer Dams and CaissonsCoffer Dams and Caissons
Coffer Dams and Caissons
 
Dams.ppt
Dams.pptDams.ppt
Dams.ppt
 
Arch and Buttress Dams
Arch and Buttress DamsArch and Buttress Dams
Arch and Buttress Dams
 
Cofferdams
Cofferdams Cofferdams
Cofferdams
 
Chapter 4.3 well foundation-final-ppt
Chapter 4.3   well foundation-final-pptChapter 4.3   well foundation-final-ppt
Chapter 4.3 well foundation-final-ppt
 
Design of Hydraulic Structures
Design of Hydraulic StructuresDesign of Hydraulic Structures
Design of Hydraulic Structures
 
CAISSON PPT.pptx
CAISSON PPT.pptxCAISSON PPT.pptx
CAISSON PPT.pptx
 
Cofferdam_ppt.pptx
Cofferdam_ppt.pptxCofferdam_ppt.pptx
Cofferdam_ppt.pptx
 
DAM ENGINEERING
DAM ENGINEERINGDAM ENGINEERING
DAM ENGINEERING
 
underwater construction
underwater constructionunderwater construction
underwater construction
 

Recently uploaded

CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 

Recently uploaded (20)

CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 

Well foundation by Aman Kumar

  • 1. SUBMITTED TO- Prof. Harpinder Singh SUBMITTED BY- Aman Kumar GU-2015-0352-L B.Tech CE 7th sem.
  • 2. CONTENTS… •Introduction •Necessity of Well Foundation •Forces acting on Well •Shapes of Well •Components of Well •Sinking of Well
  • 3. WELL FOUNDATION The deep foundations which are usually provided in situations where the loads are heavy and have to be transferred to a lower strata are termed as Well Foundations or Caissions. Wells or caissons have been in use for foundations of bridges and other Important structures since the Roman and Moghul periods. Taj Mahal at Agra built during the reign of Shah Jahan was constructed over Well Foundation. The word ‘Caisson’ is derived from french word ‘Caisse’ meaning a box. Thus it refers to a box like structure, round or rectangular which is sunk from the surface of ground or water to some required depth. Well Foundations have been used for most of the major bridges in India.
  • 4. NECESSITY OF WELL FOUNDATION A well foundation is a type of foundation which is generally built in parts at the surface and then sunk to its final position, where the part of the permanent foundation. The uses of Well Foundations are described below: •Well Foundations are widely used in India for foundations of piers and abutments of roads and railway bridges. •Wells are effectively used as foundation base for heavy machinery and equipments. •Well Foundations can resist large lateral loads in case of bridges. •Wells can also resist large uplifting loads as in case of transmission towers.
  • 5. FORECS ACTING ON WELL FOUNDATION •Dead Loads (self weight of well and super structure) •Live Loads •Impact Loads (impact effect due to live load only) •Wind Loads •Water Pressure •Longitudinal Forces (due to tractive and braking forces) •Centrifugal Force •Buoyant Forces •Earth Pressure •Temperature Stresses •Seismic Forces
  • 6. SHAPES OF WELL FOUNDATION •Circular Well •Double-D Well •Rectangular Well •Dumb Well •Twin Circular Well •Double Octagonal with circular Dredge Holes
  • 7. COMPONENTS OF WELL 1. Well Cap 2. Steining 3. Curb 4. Cutting Edge 5. Bottom Plug 6. Dredge Hole 7. Top Plug
  • 8. SINKING OF WELL The operation of ‘Sinking of Well’ consists of following stages: 1. Laying of Well Curb 2. Construction of Well Steining 3. Sinking Operation
  • 9. Laying of Well Curb If the river bed is dry, there is no problem in laying the well curb. An exacavation is made and the cutting edge over which the well curb is to be laid is placed at the proper position. However, if the river bed is not dry and the depth of water is less then 5 m,simple sand islands may be made by laying a few layers of sand beds,before laying the well curb.
  • 10. Construction of Well Steining After laying the well curb, the well steining should be built initially in small heights of about 2 m.The sinking operation is started after allowing atleast 24 hours for setting.
  • 11. Sinking Operation The well is sunk by excavating material from inside under the curb; manually or mechanically. Chisels are used for breaking the hard soil and explosives are used for sinking through rock. To accelerate the process of sinking, additional load is placed on the well in the form of sand bags by erecting a suitable platform. This load is termed as Kentledge.
  • 12.
  • 13. Contact on Facebook- https://www.facebook.com/amn.kmr352