SlideShare a Scribd company logo
WASTE HEAT RECOVERY
FROM HOT GASES IN
CEMENT INDUSTRY
Hanan Rehman, 2017138
Huzaifa Kamran, 2017160
Abu Bakar, 2017029
Noor Ahsan, 2017362
Advisor Name: Dr. Javaid Rabbani Khan
Co-Advisor Name: Dr. Hammad Amjad Khan
Introduction
DG Cement is the largest cement manufacturer of Pakistan with its production capacity of 14,000 tons
per day. DG Cement plant at Chakwal has a total power requirement of 31MW.
Cement Industry
 High energy dependent industry
 Loss of large amount of energy
(Kiln, Calciner and Clinker Cooler)
 Energy represents largest share
in overall manufacturing cost (40-
60%)
 Reducing the production cost by
minimizing the energy cost
 WHR is widely used throughout
the world.
 Heat energy from hot flue gases is
converted to electricity.
Types of WHR systems
 Rankine Cycle (Water)
 Kalina Cycle (Water & ammonia)
 Organic Cycle (N-Pentane)
Literature Review
Fig.1: Rankine cycle
Motivation
 Energy production:
 Utilization of waste hot flue gases to
produce electricity
 Increase in energy efficiency up to 20%
 Less burden on National grid of a low
energy producing country like Pakistan
 Economization:
 Reduction in operational and process cost
for example: clinker production
 Less cost of electricity
 Reduction in loss of water through cooling
tower
 Global warming:
 Lower CO2 emission
 Less use of water resources
 Low temperature of waste gases entering
the atmosphere
Gap Analysis
• In DG-Cement Kalina cycle is used for WHR system but it is:
a. Less efficient (10%-15%).
b. Storage problem.
c. Expensive (Additional cost of ammonia mixture).
d. Unable to fulfill energy requirements (produced only 5MW).
• Cooling tower which is currently being used results in:
a. Water loss through Evaporation and Drift
b. Use of make up water from nearby resources such as lakes and ponds For Example;
Katas Raj Temples.
Primary Objectives
• Heat recovery from different heat sources such as Calciner and Clinker Cooler From
Rankine Cycle.
• Modelling & Simulation will be performed using Aspen HYSYS simulation software.
• Calculations will be performed using industrial data for amount of fuel saved, turbine
efficiency, cooling tower efficiency and overall efficiency of system.
Secondary Objectives
• Introducing double turbine system to increase overall efficiency of the process.
• Replacing cooling tower with ACC to minimize water loss and operational cost.
• Utilization of waste heat from Diesel Generators
Cooling Tower Air Cooled Condenser
Fig.2: Cooling tower working principle Fig.3: ACC working principle
Parameters Values
Turbine Operating Pressure 1 MPa
Turbine Operating Temperature 315°C
Inlet hot air Temperature 383°C
Outlet hot air Temperature 95°C
Feedwater mass flow rate 45.8 ton/hr
Mass of air per kg of Clinker Produced 0.98 kg air/kg clinker
Mass of Clinker produced 291,000 kg/hr
Waste gases inlet Temperature 295°C
Waste gases outlet Temperature 200°C
The volumetric flow rate of gases 205000 m3/hr
Composition of CO2 68%
Composition of N2 8%
Composition of O2 2%
Composition of CO 2%
Composition of H2O 20%
Specific heat capacity of waste gases from generator 1.862 kJ/kg.K
Industrial Data
Process Flow Diagram
Fig.4: PFD for single pressure turbine
Process Flow Diagram
Fig.5: PFD for Dual pressure turbine
Aspen HYSYS Simulation Model
Fig.6: Aspen HYSYS Model
Aspen HYSYS Simulation Worksheet
Fig.6: Data of Aspen HYSYS
Commercialisation possibilities & social impact:
 This model of WHR can be used
as a reference for other
industries.
 Not only limited to cement
industries.
 Implementation of WHR
Commercially would reduce
energy crisis of Pakistan.
 Since it is Environmental friendly,
it won’t have any adverse effect
on health of employees
 It will increase job opportunities.
 Ensure safety of natural
habitats.
 Improvement of social
reputation.
ABOUT THE
PROJECT
Gantt
Chart
Gantt
Chart
Results
 Successfully utilized the Heat of Diesel Generators in driving
dual pressure turbine
 Saved water up to 5000 liters/month by using ACC instead of
Cooling Tower
 Reduced emission of CO2 up to 9000 tonnes
 Meeting the SDGs by reducing the risk of Global warming
 WHR system based on Rankine cycle operating at an
efficiency of up to 25%
 Reduced electrical power consumption from the national
grid up to 11MW through single pressure turbine and
14MW through dual pressure turbine
1. http://www.yuvaengineers.com/waste-heat-recovery-power-plant-sk-anwar-basha/
2. CEMENT, D. (2017-2018). Financial Report . Lahore: Nishat Group.
3. M.Rahim, A. A. (2015). Waste Heat Recovery Power Generation Systems for Cement Production Process.
EEE TRANSACTIONS ON INDUSTRY APPLICATIONS.
4. Robert McCaffrey. (2018, June 1). DG Khan Khairpur: The ‘self-sufficient’ cement plant. Retrieved from
Global Cement: https://www.globalcement.com/magazine/articles/1071-dg-khan-khairpur-the-self-
sufficient-cement-plant
5. Y. Redjeba*, K. K.-D. (2019). Aspen Plus based simulation for waste heat recovery in cement industries.
Department of process engineering, National Polytechnic School of Constantine, Algeria.
6. Waste Heat Recovery System. (2015, June 20). Retrieved from MAN Diesel & Turbo:
www.mandieselturbo.com
7. Performance of an air-cooled steam condenser for a waste-to-energy plant over its whole operating range
(Energy Conversion and Management 52 (2011) 1908–1913)
8. Thekdi, A. C. (1998). Industrial Waste Heat Recovery: Potential Applications, Available Technologies.
National Technical Information Service.
References
THANK YOU

More Related Content

What's hot

ORC - Organic Rankine Cycle technology for biomass and EfW cogeneration and t...
ORC - Organic Rankine Cycle technology for biomass and EfW cogeneration and t...ORC - Organic Rankine Cycle technology for biomass and EfW cogeneration and t...
ORC - Organic Rankine Cycle technology for biomass and EfW cogeneration and t...
Carlo Minini
 
cooling towers
cooling towerscooling towers
cooling towers
Khalid Nawaz
 
Waste Heat Recovery Devices by Varun Pratap Singh
Waste Heat Recovery Devices by Varun Pratap SinghWaste Heat Recovery Devices by Varun Pratap Singh
Waste Heat Recovery Devices by Varun Pratap Singh
Varun Pratap Singh
 
Condensing Economisers
Condensing EconomisersCondensing Economisers
Condensing Economisers
Aditya Shiva Appalla
 
Waste heat recovery
Waste heat recoveryWaste heat recovery
Waste heat recovery
Debajyoti Bose
 
waste heat recovery
waste heat recovery waste heat recovery
waste heat recovery
Sagar Joshi
 
Chapter 4 Gas Turbine
Chapter 4 Gas TurbineChapter 4 Gas Turbine
Chapter 4 Gas Turbine
ANIKET SURYAWANSHI
 
Gas turbines working ppt
Gas turbines working pptGas turbines working ppt
Gas turbines working ppt
luckyvarsha
 
METHODS OF IMPROVING STEAM TURBINE PERFORMANCE
METHODS OF IMPROVING STEAM TURBINE PERFORMANCEMETHODS OF IMPROVING STEAM TURBINE PERFORMANCE
METHODS OF IMPROVING STEAM TURBINE PERFORMANCE
Vanita Thakkar
 
Ammonia plant flowsheets
Ammonia plant flowsheetsAmmonia plant flowsheets
Ammonia plant flowsheets
Gerard B. Hawkins
 
performance analysis of steam boiler
performance analysis of steam boilerperformance analysis of steam boiler
performance analysis of steam boiler
sathish sak
 
PROJECT.CLINKER COOLER EFFICIENCY(last version).pptx
PROJECT.CLINKER COOLER EFFICIENCY(last version).pptxPROJECT.CLINKER COOLER EFFICIENCY(last version).pptx
PROJECT.CLINKER COOLER EFFICIENCY(last version).pptx
SirajALsharif
 
Boiler design-calculation 3
Boiler design-calculation 3Boiler design-calculation 3
Boiler design-calculation 3
Ebra21
 
Boiler efficiency by loss Method
Boiler efficiency by loss MethodBoiler efficiency by loss Method
Boiler efficiency by loss Method
Rajeev Saini
 
Direct contact or open condensers
Direct contact or open condensersDirect contact or open condensers
Direct contact or open condensersSam
 
Boiler calculations
Boiler calculationsBoiler calculations
Boiler calculations
Usman Shahdin
 
21. COFIRING BIOMASS WITH COAL FOR POWER GENERATION.ppt
21. COFIRING BIOMASS WITH COAL FOR POWER GENERATION.ppt21. COFIRING BIOMASS WITH COAL FOR POWER GENERATION.ppt
21. COFIRING BIOMASS WITH COAL FOR POWER GENERATION.ppt
RENERGISTICS
 
Pcm ppt
Pcm ppt Pcm ppt
Pcm ppt
Junaid Bhat
 
Thermo acoustic refrigeration BY SHOEB M KHAN
Thermo acoustic refrigeration BY SHOEB M KHANThermo acoustic refrigeration BY SHOEB M KHAN
Thermo acoustic refrigeration BY SHOEB M KHAN
shoeb khan
 

What's hot (20)

ORC - Organic Rankine Cycle technology for biomass and EfW cogeneration and t...
ORC - Organic Rankine Cycle technology for biomass and EfW cogeneration and t...ORC - Organic Rankine Cycle technology for biomass and EfW cogeneration and t...
ORC - Organic Rankine Cycle technology for biomass and EfW cogeneration and t...
 
cooling towers
cooling towerscooling towers
cooling towers
 
Waste Heat Recovery Devices by Varun Pratap Singh
Waste Heat Recovery Devices by Varun Pratap SinghWaste Heat Recovery Devices by Varun Pratap Singh
Waste Heat Recovery Devices by Varun Pratap Singh
 
Condensing Economisers
Condensing EconomisersCondensing Economisers
Condensing Economisers
 
Waste heat recovery
Waste heat recoveryWaste heat recovery
Waste heat recovery
 
waste heat recovery
waste heat recovery waste heat recovery
waste heat recovery
 
Chapter 4 Gas Turbine
Chapter 4 Gas TurbineChapter 4 Gas Turbine
Chapter 4 Gas Turbine
 
Gas turbines working ppt
Gas turbines working pptGas turbines working ppt
Gas turbines working ppt
 
METHODS OF IMPROVING STEAM TURBINE PERFORMANCE
METHODS OF IMPROVING STEAM TURBINE PERFORMANCEMETHODS OF IMPROVING STEAM TURBINE PERFORMANCE
METHODS OF IMPROVING STEAM TURBINE PERFORMANCE
 
Ammonia plant flowsheets
Ammonia plant flowsheetsAmmonia plant flowsheets
Ammonia plant flowsheets
 
performance analysis of steam boiler
performance analysis of steam boilerperformance analysis of steam boiler
performance analysis of steam boiler
 
PROJECT.CLINKER COOLER EFFICIENCY(last version).pptx
PROJECT.CLINKER COOLER EFFICIENCY(last version).pptxPROJECT.CLINKER COOLER EFFICIENCY(last version).pptx
PROJECT.CLINKER COOLER EFFICIENCY(last version).pptx
 
Presentation 2
Presentation 2Presentation 2
Presentation 2
 
Boiler design-calculation 3
Boiler design-calculation 3Boiler design-calculation 3
Boiler design-calculation 3
 
Boiler efficiency by loss Method
Boiler efficiency by loss MethodBoiler efficiency by loss Method
Boiler efficiency by loss Method
 
Direct contact or open condensers
Direct contact or open condensersDirect contact or open condensers
Direct contact or open condensers
 
Boiler calculations
Boiler calculationsBoiler calculations
Boiler calculations
 
21. COFIRING BIOMASS WITH COAL FOR POWER GENERATION.ppt
21. COFIRING BIOMASS WITH COAL FOR POWER GENERATION.ppt21. COFIRING BIOMASS WITH COAL FOR POWER GENERATION.ppt
21. COFIRING BIOMASS WITH COAL FOR POWER GENERATION.ppt
 
Pcm ppt
Pcm ppt Pcm ppt
Pcm ppt
 
Thermo acoustic refrigeration BY SHOEB M KHAN
Thermo acoustic refrigeration BY SHOEB M KHANThermo acoustic refrigeration BY SHOEB M KHAN
Thermo acoustic refrigeration BY SHOEB M KHAN
 

Similar to Waste heat recovery from hot gasses in cement industry

Thesis presentation.pptx
Thesis presentation.pptxThesis presentation.pptx
Thesis presentation.pptx
AKASH SAHA
 
IRJET- Performance and Evaluation of Aqua Ammonia Air Conditioner System ...
IRJET-  	  Performance and Evaluation of Aqua Ammonia Air Conditioner System ...IRJET-  	  Performance and Evaluation of Aqua Ammonia Air Conditioner System ...
IRJET- Performance and Evaluation of Aqua Ammonia Air Conditioner System ...
IRJET Journal
 
The Positive Environmental and Economical Impact of CHP
The Positive Environmental and Economical Impact of CHPThe Positive Environmental and Economical Impact of CHP
The Positive Environmental and Economical Impact of CHPDr. Roger Achkar
 
A OVERVIEW OF THE RANKIN CYCLE-BASED HEAT EXCHANGER USED IN INTERNAL COMBUSTI...
A OVERVIEW OF THE RANKIN CYCLE-BASED HEAT EXCHANGER USED IN INTERNAL COMBUSTI...A OVERVIEW OF THE RANKIN CYCLE-BASED HEAT EXCHANGER USED IN INTERNAL COMBUSTI...
A OVERVIEW OF THE RANKIN CYCLE-BASED HEAT EXCHANGER USED IN INTERNAL COMBUSTI...
IAEME Publication
 
OVERVIEW OF COGENERATION OPPORTUNITIES IN NEPALESE SUGAR SECTOR
OVERVIEW OF COGENERATION OPPORTUNITIES IN NEPALESE SUGAR SECTOR OVERVIEW OF COGENERATION OPPORTUNITIES IN NEPALESE SUGAR SECTOR
OVERVIEW OF COGENERATION OPPORTUNITIES IN NEPALESE SUGAR SECTOR
eecfncci
 
Eng. Demiss Alemu - Energy Efficiency Improvement and GHG Emission Reduction ...
Eng. Demiss Alemu - Energy Efficiency Improvement and GHG Emission Reduction ...Eng. Demiss Alemu - Energy Efficiency Improvement and GHG Emission Reduction ...
Eng. Demiss Alemu - Energy Efficiency Improvement and GHG Emission Reduction ...
The i-Capital Africa Institute
 
Combined Cycle Gas Turbine Power Plant Part 1
Combined Cycle Gas Turbine Power Plant Part 1Combined Cycle Gas Turbine Power Plant Part 1
Combined Cycle Gas Turbine Power Plant Part 1
Anurak Atthasit
 
Analysis of recoverable exhaust energy from a light duty gasoline engine by u...
Analysis of recoverable exhaust energy from a light duty gasoline engine by u...Analysis of recoverable exhaust energy from a light duty gasoline engine by u...
Analysis of recoverable exhaust energy from a light duty gasoline engine by u...
ijctet
 
report on thermal power plant
report on thermal power plantreport on thermal power plant
report on thermal power plant
sagar20jain
 
Training Report DCCPP, Dholpur
Training Report DCCPP, Dholpur Training Report DCCPP, Dholpur
Training Report DCCPP, Dholpur
Yuvraj Singh
 
INDUSTRIAL WASTE HEAT USED IN TYPICAL THERMAL POWER PLANT
  INDUSTRIAL WASTE HEAT USED IN TYPICAL THERMAL POWER PLANT  INDUSTRIAL WASTE HEAT USED IN TYPICAL THERMAL POWER PLANT
INDUSTRIAL WASTE HEAT USED IN TYPICAL THERMAL POWER PLANT
IAEME Publication
 
Introduction of CO2 Reduction Technologies in Steelworks
Introduction of  CO2 Reduction Technologies in SteelworksIntroduction of  CO2 Reduction Technologies in Steelworks
Introduction of CO2 Reduction Technologies in Steelworks
Energy-Education-Resource-Center
 
waste to energy by direct carbon fuel cells
waste to energy by direct carbon fuel cellswaste to energy by direct carbon fuel cells
waste to energy by direct carbon fuel cells
SABARINATH C D
 
DIRECT CARBON FUEL CELLS
DIRECT CARBON FUEL CELLSDIRECT CARBON FUEL CELLS
DIRECT CARBON FUEL CELLS
SABARINATH C D
 
DIRECT CARBON FUEL CELLS
DIRECT CARBON FUEL CELLSDIRECT CARBON FUEL CELLS
DIRECT CARBON FUEL CELLS
SABARINATH C D
 
SEAM Centre seminar - Sept 2010 (part 1)
SEAM Centre seminar - Sept 2010 (part 1)SEAM Centre seminar - Sept 2010 (part 1)
SEAM Centre seminar - Sept 2010 (part 1)The SEAM Centre
 
EIA thermal power plant
EIA thermal power plantEIA thermal power plant
EIA thermal power plant
vandana bharti
 
IRJET- Improve the Efficiency of Combined Cycle Power Plant
IRJET- Improve the Efficiency of Combined Cycle Power PlantIRJET- Improve the Efficiency of Combined Cycle Power Plant
IRJET- Improve the Efficiency of Combined Cycle Power Plant
IRJET Journal
 
Waste Heat recovery system
Waste Heat recovery systemWaste Heat recovery system
Waste Heat recovery system
MoienBhat
 

Similar to Waste heat recovery from hot gasses in cement industry (20)

Thesis presentation.pptx
Thesis presentation.pptxThesis presentation.pptx
Thesis presentation.pptx
 
IRJET- Performance and Evaluation of Aqua Ammonia Air Conditioner System ...
IRJET-  	  Performance and Evaluation of Aqua Ammonia Air Conditioner System ...IRJET-  	  Performance and Evaluation of Aqua Ammonia Air Conditioner System ...
IRJET- Performance and Evaluation of Aqua Ammonia Air Conditioner System ...
 
The Positive Environmental and Economical Impact of CHP
The Positive Environmental and Economical Impact of CHPThe Positive Environmental and Economical Impact of CHP
The Positive Environmental and Economical Impact of CHP
 
A OVERVIEW OF THE RANKIN CYCLE-BASED HEAT EXCHANGER USED IN INTERNAL COMBUSTI...
A OVERVIEW OF THE RANKIN CYCLE-BASED HEAT EXCHANGER USED IN INTERNAL COMBUSTI...A OVERVIEW OF THE RANKIN CYCLE-BASED HEAT EXCHANGER USED IN INTERNAL COMBUSTI...
A OVERVIEW OF THE RANKIN CYCLE-BASED HEAT EXCHANGER USED IN INTERNAL COMBUSTI...
 
OVERVIEW OF COGENERATION OPPORTUNITIES IN NEPALESE SUGAR SECTOR
OVERVIEW OF COGENERATION OPPORTUNITIES IN NEPALESE SUGAR SECTOR OVERVIEW OF COGENERATION OPPORTUNITIES IN NEPALESE SUGAR SECTOR
OVERVIEW OF COGENERATION OPPORTUNITIES IN NEPALESE SUGAR SECTOR
 
Eng. Demiss Alemu - Energy Efficiency Improvement and GHG Emission Reduction ...
Eng. Demiss Alemu - Energy Efficiency Improvement and GHG Emission Reduction ...Eng. Demiss Alemu - Energy Efficiency Improvement and GHG Emission Reduction ...
Eng. Demiss Alemu - Energy Efficiency Improvement and GHG Emission Reduction ...
 
Combined Cycle Gas Turbine Power Plant Part 1
Combined Cycle Gas Turbine Power Plant Part 1Combined Cycle Gas Turbine Power Plant Part 1
Combined Cycle Gas Turbine Power Plant Part 1
 
Analysis of recoverable exhaust energy from a light duty gasoline engine by u...
Analysis of recoverable exhaust energy from a light duty gasoline engine by u...Analysis of recoverable exhaust energy from a light duty gasoline engine by u...
Analysis of recoverable exhaust energy from a light duty gasoline engine by u...
 
report on thermal power plant
report on thermal power plantreport on thermal power plant
report on thermal power plant
 
Training Report DCCPP, Dholpur
Training Report DCCPP, Dholpur Training Report DCCPP, Dholpur
Training Report DCCPP, Dholpur
 
INDUSTRIAL WASTE HEAT USED IN TYPICAL THERMAL POWER PLANT
  INDUSTRIAL WASTE HEAT USED IN TYPICAL THERMAL POWER PLANT  INDUSTRIAL WASTE HEAT USED IN TYPICAL THERMAL POWER PLANT
INDUSTRIAL WASTE HEAT USED IN TYPICAL THERMAL POWER PLANT
 
Introduction of CO2 Reduction Technologies in Steelworks
Introduction of  CO2 Reduction Technologies in SteelworksIntroduction of  CO2 Reduction Technologies in Steelworks
Introduction of CO2 Reduction Technologies in Steelworks
 
waste to energy by direct carbon fuel cells
waste to energy by direct carbon fuel cellswaste to energy by direct carbon fuel cells
waste to energy by direct carbon fuel cells
 
DIRECT CARBON FUEL CELLS
DIRECT CARBON FUEL CELLSDIRECT CARBON FUEL CELLS
DIRECT CARBON FUEL CELLS
 
DIRECT CARBON FUEL CELLS
DIRECT CARBON FUEL CELLSDIRECT CARBON FUEL CELLS
DIRECT CARBON FUEL CELLS
 
SEAM Centre seminar - Sept 2010 (part 1)
SEAM Centre seminar - Sept 2010 (part 1)SEAM Centre seminar - Sept 2010 (part 1)
SEAM Centre seminar - Sept 2010 (part 1)
 
EIA thermal power plant
EIA thermal power plantEIA thermal power plant
EIA thermal power plant
 
IRJET- Improve the Efficiency of Combined Cycle Power Plant
IRJET- Improve the Efficiency of Combined Cycle Power PlantIRJET- Improve the Efficiency of Combined Cycle Power Plant
IRJET- Improve the Efficiency of Combined Cycle Power Plant
 
H2P_Energy_Final_Presentation_ENCH_531
H2P_Energy_Final_Presentation_ENCH_531H2P_Energy_Final_Presentation_ENCH_531
H2P_Energy_Final_Presentation_ENCH_531
 
Waste Heat recovery system
Waste Heat recovery systemWaste Heat recovery system
Waste Heat recovery system
 

Recently uploaded

WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 

Recently uploaded (20)

WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 

Waste heat recovery from hot gasses in cement industry

  • 1. WASTE HEAT RECOVERY FROM HOT GASES IN CEMENT INDUSTRY Hanan Rehman, 2017138 Huzaifa Kamran, 2017160 Abu Bakar, 2017029 Noor Ahsan, 2017362 Advisor Name: Dr. Javaid Rabbani Khan Co-Advisor Name: Dr. Hammad Amjad Khan
  • 2. Introduction DG Cement is the largest cement manufacturer of Pakistan with its production capacity of 14,000 tons per day. DG Cement plant at Chakwal has a total power requirement of 31MW. Cement Industry  High energy dependent industry  Loss of large amount of energy (Kiln, Calciner and Clinker Cooler)  Energy represents largest share in overall manufacturing cost (40- 60%)  Reducing the production cost by minimizing the energy cost  WHR is widely used throughout the world.  Heat energy from hot flue gases is converted to electricity. Types of WHR systems  Rankine Cycle (Water)  Kalina Cycle (Water & ammonia)  Organic Cycle (N-Pentane) Literature Review Fig.1: Rankine cycle
  • 3. Motivation  Energy production:  Utilization of waste hot flue gases to produce electricity  Increase in energy efficiency up to 20%  Less burden on National grid of a low energy producing country like Pakistan  Economization:  Reduction in operational and process cost for example: clinker production  Less cost of electricity  Reduction in loss of water through cooling tower  Global warming:  Lower CO2 emission  Less use of water resources  Low temperature of waste gases entering the atmosphere
  • 4. Gap Analysis • In DG-Cement Kalina cycle is used for WHR system but it is: a. Less efficient (10%-15%). b. Storage problem. c. Expensive (Additional cost of ammonia mixture). d. Unable to fulfill energy requirements (produced only 5MW). • Cooling tower which is currently being used results in: a. Water loss through Evaporation and Drift b. Use of make up water from nearby resources such as lakes and ponds For Example; Katas Raj Temples. Primary Objectives • Heat recovery from different heat sources such as Calciner and Clinker Cooler From Rankine Cycle. • Modelling & Simulation will be performed using Aspen HYSYS simulation software. • Calculations will be performed using industrial data for amount of fuel saved, turbine efficiency, cooling tower efficiency and overall efficiency of system. Secondary Objectives • Introducing double turbine system to increase overall efficiency of the process. • Replacing cooling tower with ACC to minimize water loss and operational cost. • Utilization of waste heat from Diesel Generators
  • 5. Cooling Tower Air Cooled Condenser Fig.2: Cooling tower working principle Fig.3: ACC working principle
  • 6. Parameters Values Turbine Operating Pressure 1 MPa Turbine Operating Temperature 315°C Inlet hot air Temperature 383°C Outlet hot air Temperature 95°C Feedwater mass flow rate 45.8 ton/hr Mass of air per kg of Clinker Produced 0.98 kg air/kg clinker Mass of Clinker produced 291,000 kg/hr Waste gases inlet Temperature 295°C Waste gases outlet Temperature 200°C The volumetric flow rate of gases 205000 m3/hr Composition of CO2 68% Composition of N2 8% Composition of O2 2% Composition of CO 2% Composition of H2O 20% Specific heat capacity of waste gases from generator 1.862 kJ/kg.K Industrial Data
  • 7. Process Flow Diagram Fig.4: PFD for single pressure turbine
  • 8. Process Flow Diagram Fig.5: PFD for Dual pressure turbine
  • 9. Aspen HYSYS Simulation Model Fig.6: Aspen HYSYS Model
  • 10. Aspen HYSYS Simulation Worksheet Fig.6: Data of Aspen HYSYS
  • 11. Commercialisation possibilities & social impact:  This model of WHR can be used as a reference for other industries.  Not only limited to cement industries.  Implementation of WHR Commercially would reduce energy crisis of Pakistan.  Since it is Environmental friendly, it won’t have any adverse effect on health of employees  It will increase job opportunities.  Ensure safety of natural habitats.  Improvement of social reputation.
  • 13. Gantt Chart Results  Successfully utilized the Heat of Diesel Generators in driving dual pressure turbine  Saved water up to 5000 liters/month by using ACC instead of Cooling Tower  Reduced emission of CO2 up to 9000 tonnes  Meeting the SDGs by reducing the risk of Global warming  WHR system based on Rankine cycle operating at an efficiency of up to 25%  Reduced electrical power consumption from the national grid up to 11MW through single pressure turbine and 14MW through dual pressure turbine
  • 14. 1. http://www.yuvaengineers.com/waste-heat-recovery-power-plant-sk-anwar-basha/ 2. CEMENT, D. (2017-2018). Financial Report . Lahore: Nishat Group. 3. M.Rahim, A. A. (2015). Waste Heat Recovery Power Generation Systems for Cement Production Process. EEE TRANSACTIONS ON INDUSTRY APPLICATIONS. 4. Robert McCaffrey. (2018, June 1). DG Khan Khairpur: The ‘self-sufficient’ cement plant. Retrieved from Global Cement: https://www.globalcement.com/magazine/articles/1071-dg-khan-khairpur-the-self- sufficient-cement-plant 5. Y. Redjeba*, K. K.-D. (2019). Aspen Plus based simulation for waste heat recovery in cement industries. Department of process engineering, National Polytechnic School of Constantine, Algeria. 6. Waste Heat Recovery System. (2015, June 20). Retrieved from MAN Diesel & Turbo: www.mandieselturbo.com 7. Performance of an air-cooled steam condenser for a waste-to-energy plant over its whole operating range (Energy Conversion and Management 52 (2011) 1908–1913) 8. Thekdi, A. C. (1998). Industrial Waste Heat Recovery: Potential Applications, Available Technologies. National Technical Information Service. References