SlideShare a Scribd company logo
UW- Energy Audit Class
Energy Efficiency Measures (EEM)
for Lowell Hall
Sarah Maston, Ryan Meyers, Kevin Preuss & Paul White
Executive Summary
Over the 1st week of August, our team provided a Level 2 Energy Audit of
the Lowell Hall Building on the University of Wisconsin’s Madison Campus.
We looked for Energy Efficiency Measures (EEMs) for the building envelope,
lighting, and HVAC systems. After some quick calculations, we found that:
EUI = 119.2 kBtu/SF/yr (EnergyStar National Median EUI = 74)
ECI = $1.66/SF/yr
…which indicates a myriad of opportunities for improvement. We have
included 5 EEMs for consideration. The first EEM for the building envelope,
has a lengthy payback, but may want to be considered for other reasons.
EEMs 2-4 have simple paybacks of under 4 years. EEM-5 addresses a code
violation. We also listed other EEMs for consideration.
Energy End Use Pie Charts (Gas & Electric)
Annual Energy Use
Building EUI:
119.2 kBtu/SF/yr
Building ECI:
$1.66/SF/yr
Monthly Energy Use
EEM-1: Replace Inefficient Windows
• By reviewing the background information on Lowell Hall, that was
provided, we determined that some of the windows were less
efficient than others.
• We originally were going to propose replacing the 7700 SF of the old
glass windows with high-performance glass, but the payback was too
large.
kBTU Savings Cost Savings
(Annual)
Cost to Install
Windows
Simple
Payback
583,552 $3282 $80.75/ SF 191 years
EEM-2: Add Time Clock to Dining Rm Lights
• During our building walkthrough, we noted that the cove lighting in
the Dining Room stayed on 24/7, which is very inefficient.
• We propose adding two time clocks to the lighting circuits for the
cove lighting in the Dining Room. This time clock will turn the lights
off over night, when no one is using the space.
kWh Savings Cost Savings
(Annual)
Cost to Install Time
Clocks
Simple
Payback
2135 kWh $278 $910 39 months
EEM-3: Reduce Redundant Lobby Lighting
• During our building walkthrough, we thought that the lobby lighting
was excessive.
• We recommend reducing the cove lighting by ½ and wiring the
ballasts in tandem.
kWh Savings Cost Savings
(Annual)
Cost to Remove Lights/
Rewire Ballasts
Simple
Payback
8970 kWh $493 $904 1.83 years
EEM-4: VFDs for CHW & HW Pumps
• During our walk-through, we noted that the primary CHW pump and the duty/
standby HW pumps had their balancing valves throttled down to 60% open.
• The VFDs for these pumps were operating in hand, at 100%. This is extremely
inefficient, and there was no indication as to why this was done.
• We recommend opening the balancing valves to 100% open and then adjusting
the pump speed down until the control valves in the system at the furthest point
from the pumps just start to close down.
Estimated CHW Pump
Power Savings
Savings Cost Savings
(Annual)
Cost to Adjust
System
Simple
Payback
3 HP 6,445 kWh $354 $300 10 months
Estimated HW Pump
Power Savings
Savings Cost Savings
(Annual)
Cost to Adjust
System
Simple
Payback
5 HP 32,674 kWh $1797 $300 2 months
EEM-5: Add modulation to OA damper (HV-1)
• During our walk-through, we noted that the outside air (OA) damper to HV-1, serving
the conference room did not modulate to bring in OA when the room was occupied.
• The OA damper had been linked with the return air damper with a 2-position switch,
such that the OA damper was either 100% open or 100% closed. The default is 100%
closed, which does not provide the code-required fresh air to the room.
• We recommend adding controls, such that the OA damper can modulate to bring in
OA to meet the code requirements.
Current Difference
with damper open
Savings Cost Savings
(Annual)
Cost to Install
Controls
Simple
Payback
2.3 A 2135 kW $35.11 $300 8.5 years
Additional EEMs to be Considered
• The following are other issues that we witnessed in the building. Some
additional research is required to determine costs and paybacks:
• Consider replacing the 2 oversized HW boilers with modular condensing boilers.
• Consider replacing oversized chiller with smaller chiller to reduce cycling.
• Investigate use of check valves on two condenser water pumps that are tied
together, to eliminate risk of recirculating water without cooling.
• If replacing boilers is not possible, investigate installation of controls on both
Kewanee boilers to control boiler temperature based on outside temperature.
• Investigate potential for shutting down chiller pumps PE-3 on inlet side, or P1 on
outlet side, of new chiller. Pumps are rated for 678 gpm. System requires 555
gpm. Pump P1 is connected to VFD, but 40% closed.
• Building automation system is not utilized effectively, nor is it installed completely.
Consider bringing in vendor for training.
• Replace roof section that was not replaced in the last renovation. Many guest rooms
are very hot.
Conclusions
There are many opportunities to improve the efficiencies of the
systems in this building, but we have only focused on five key EEMs.
With more research and time, more opportunities can be explored.
Best Wishes!

More Related Content

What's hot

heat pump presentation 25-8-15
heat pump presentation  25-8-15heat pump presentation  25-8-15
heat pump presentation 25-8-15
Satish Joshi
 
ENER-G Heat pump technology CPD
ENER-G Heat pump technology CPD ENER-G Heat pump technology CPD
ENER-G Heat pump technology CPD
energ1
 
Cold-Climate Air-Source Heat Pumps: Insights form the Field
Cold-Climate Air-Source Heat Pumps: Insights form the FieldCold-Climate Air-Source Heat Pumps: Insights form the Field
Cold-Climate Air-Source Heat Pumps: Insights form the Field
Center for Energy and Environment
 
Field Assessment of Cold-Climate Air-Source Heat Pumps in Minnesota
Field Assessment of Cold-Climate Air-Source Heat Pumps in MinnesotaField Assessment of Cold-Climate Air-Source Heat Pumps in Minnesota
Field Assessment of Cold-Climate Air-Source Heat Pumps in Minnesota
Center for Energy and Environment
 
Geothermal / Geoexchange Systems
Geothermal /  Geoexchange SystemsGeothermal /  Geoexchange Systems
Geothermal / Geoexchange Systems
M.E. Group
 
2013 ASME Power Conference Analysis of Turbine Cycle Performance, Operation a...
2013 ASME Power Conference Analysis of Turbine Cycle Performance, Operation a...2013 ASME Power Conference Analysis of Turbine Cycle Performance, Operation a...
2013 ASME Power Conference Analysis of Turbine Cycle Performance, Operation a...
Komandur Sunder Raj, P.E.
 
Energy Efficiency Potential in Food & Beverage Industries in Nepal
Energy Efficiency Potential in Food & Beverage Industries in NepalEnergy Efficiency Potential in Food & Beverage Industries in Nepal
Energy Efficiency Potential in Food & Beverage Industries in Nepal
eecfncci
 
INVISTA
INVISTAINVISTA
INVISTA
FMA Summits
 
Performance and Optimization of Residential Condensing Combi Systems
Performance and Optimization of Residential Condensing Combi SystemsPerformance and Optimization of Residential Condensing Combi Systems
Performance and Optimization of Residential Condensing Combi Systems
Center for Energy and Environment
 
An Introduction to Air to water, Air Source, Heat Pump Systems
An Introduction to Air to water, Air Source, Heat Pump SystemsAn Introduction to Air to water, Air Source, Heat Pump Systems
An Introduction to Air to water, Air Source, Heat Pump Systems
SpaceAir
 
Write up - DP1
Write up - DP1Write up - DP1
Write up - DP1
Kiran Dhatt-Gauthier
 
Water Efficiency in Thermal power Plant
Water Efficiency in Thermal power PlantWater Efficiency in Thermal power Plant
Water Efficiency in Thermal power Plant
Atanu Maity
 
Energy Audit & Energy Conservation Opportunities in Electrical Equipments ...
Energy Audit & Energy  Conservation  Opportunities in  Electrical Equipments ...Energy Audit & Energy  Conservation  Opportunities in  Electrical Equipments ...
Energy Audit & Energy Conservation Opportunities in Electrical Equipments ...
Manohar Tatwawadi
 
Boilers Classifications and Cost per kWh
Boilers Classifications and Cost per kWh Boilers Classifications and Cost per kWh
Boilers Classifications and Cost per kWh
salehkhan
 
Heat pump presentation
Heat pump presentation Heat pump presentation
Heat pump presentation
GreeningPetersfield
 
performance analysis and modification of an air conditioner
performance analysis and modification of an air conditionerperformance analysis and modification of an air conditioner
performance analysis and modification of an air conditioner
Juvenile Trader
 
Combined Space and Water Heating: Making it Work
Combined Space and Water Heating: Making it WorkCombined Space and Water Heating: Making it Work
Combined Space and Water Heating: Making it Work
Center for Energy and Environment
 
Air to Water Low Temperature Heat Pump
Air to Water Low Temperature Heat PumpAir to Water Low Temperature Heat Pump
Air to Water Low Temperature Heat Pump
CCSE Host
 
ganesh ppts on supercritical thenology
ganesh ppts on supercritical thenologyganesh ppts on supercritical thenology
ganesh ppts on supercritical thenology
nirgudebhau111
 
Gas vs. Electricity for Heat Treatment Furnacces
Gas vs. Electricity for  Heat Treatment FurnaccesGas vs. Electricity for  Heat Treatment Furnacces
Gas vs. Electricity for Heat Treatment Furnacces
HTCourses
 

What's hot (20)

heat pump presentation 25-8-15
heat pump presentation  25-8-15heat pump presentation  25-8-15
heat pump presentation 25-8-15
 
ENER-G Heat pump technology CPD
ENER-G Heat pump technology CPD ENER-G Heat pump technology CPD
ENER-G Heat pump technology CPD
 
Cold-Climate Air-Source Heat Pumps: Insights form the Field
Cold-Climate Air-Source Heat Pumps: Insights form the FieldCold-Climate Air-Source Heat Pumps: Insights form the Field
Cold-Climate Air-Source Heat Pumps: Insights form the Field
 
Field Assessment of Cold-Climate Air-Source Heat Pumps in Minnesota
Field Assessment of Cold-Climate Air-Source Heat Pumps in MinnesotaField Assessment of Cold-Climate Air-Source Heat Pumps in Minnesota
Field Assessment of Cold-Climate Air-Source Heat Pumps in Minnesota
 
Geothermal / Geoexchange Systems
Geothermal /  Geoexchange SystemsGeothermal /  Geoexchange Systems
Geothermal / Geoexchange Systems
 
2013 ASME Power Conference Analysis of Turbine Cycle Performance, Operation a...
2013 ASME Power Conference Analysis of Turbine Cycle Performance, Operation a...2013 ASME Power Conference Analysis of Turbine Cycle Performance, Operation a...
2013 ASME Power Conference Analysis of Turbine Cycle Performance, Operation a...
 
Energy Efficiency Potential in Food & Beverage Industries in Nepal
Energy Efficiency Potential in Food & Beverage Industries in NepalEnergy Efficiency Potential in Food & Beverage Industries in Nepal
Energy Efficiency Potential in Food & Beverage Industries in Nepal
 
INVISTA
INVISTAINVISTA
INVISTA
 
Performance and Optimization of Residential Condensing Combi Systems
Performance and Optimization of Residential Condensing Combi SystemsPerformance and Optimization of Residential Condensing Combi Systems
Performance and Optimization of Residential Condensing Combi Systems
 
An Introduction to Air to water, Air Source, Heat Pump Systems
An Introduction to Air to water, Air Source, Heat Pump SystemsAn Introduction to Air to water, Air Source, Heat Pump Systems
An Introduction to Air to water, Air Source, Heat Pump Systems
 
Write up - DP1
Write up - DP1Write up - DP1
Write up - DP1
 
Water Efficiency in Thermal power Plant
Water Efficiency in Thermal power PlantWater Efficiency in Thermal power Plant
Water Efficiency in Thermal power Plant
 
Energy Audit & Energy Conservation Opportunities in Electrical Equipments ...
Energy Audit & Energy  Conservation  Opportunities in  Electrical Equipments ...Energy Audit & Energy  Conservation  Opportunities in  Electrical Equipments ...
Energy Audit & Energy Conservation Opportunities in Electrical Equipments ...
 
Boilers Classifications and Cost per kWh
Boilers Classifications and Cost per kWh Boilers Classifications and Cost per kWh
Boilers Classifications and Cost per kWh
 
Heat pump presentation
Heat pump presentation Heat pump presentation
Heat pump presentation
 
performance analysis and modification of an air conditioner
performance analysis and modification of an air conditionerperformance analysis and modification of an air conditioner
performance analysis and modification of an air conditioner
 
Combined Space and Water Heating: Making it Work
Combined Space and Water Heating: Making it WorkCombined Space and Water Heating: Making it Work
Combined Space and Water Heating: Making it Work
 
Air to Water Low Temperature Heat Pump
Air to Water Low Temperature Heat PumpAir to Water Low Temperature Heat Pump
Air to Water Low Temperature Heat Pump
 
ganesh ppts on supercritical thenology
ganesh ppts on supercritical thenologyganesh ppts on supercritical thenology
ganesh ppts on supercritical thenology
 
Gas vs. Electricity for Heat Treatment Furnacces
Gas vs. Electricity for  Heat Treatment FurnaccesGas vs. Electricity for  Heat Treatment Furnacces
Gas vs. Electricity for Heat Treatment Furnacces
 

Viewers also liked

Cpda cpdh 2008
Cpda cpdh 2008Cpda cpdh 2008
Cpda cpdh 2008
jrcompressores
 
Cpfl normas
Cpfl normasCpfl normas
Cpfl normas
Nícolas Moraes
 
Metodologia de Analise Energetica_Trane Brasil
Metodologia de Analise Energetica_Trane BrasilMetodologia de Analise Energetica_Trane Brasil
Metodologia de Analise Energetica_Trane Brasil
Matt Chmielewski
 
Performing A Life Cycle Cost Analysis
Performing A Life Cycle Cost AnalysisPerforming A Life Cycle Cost Analysis
Performing A Life Cycle Cost Analysis
chrishvaceng
 
Cooling curve
Cooling curveCooling curve
Chilled Water Plant Optimization
Chilled Water Plant OptimizationChilled Water Plant Optimization
Chilled Water Plant Optimization
JoePessa
 
Cooling load calculations and principles
Cooling load calculations and principlesCooling load calculations and principles
Cooling load calculations and principles
Dheiy Myth
 
HVAC Cooling Load Calculation
HVAC Cooling Load CalculationHVAC Cooling Load Calculation
HVAC Cooling Load Calculation
Orange Slides
 
12 Cooling Load Calculations
12 Cooling Load Calculations12 Cooling Load Calculations
12 Cooling Load Calculations
spsu
 

Viewers also liked (9)

Cpda cpdh 2008
Cpda cpdh 2008Cpda cpdh 2008
Cpda cpdh 2008
 
Cpfl normas
Cpfl normasCpfl normas
Cpfl normas
 
Metodologia de Analise Energetica_Trane Brasil
Metodologia de Analise Energetica_Trane BrasilMetodologia de Analise Energetica_Trane Brasil
Metodologia de Analise Energetica_Trane Brasil
 
Performing A Life Cycle Cost Analysis
Performing A Life Cycle Cost AnalysisPerforming A Life Cycle Cost Analysis
Performing A Life Cycle Cost Analysis
 
Cooling curve
Cooling curveCooling curve
Cooling curve
 
Chilled Water Plant Optimization
Chilled Water Plant OptimizationChilled Water Plant Optimization
Chilled Water Plant Optimization
 
Cooling load calculations and principles
Cooling load calculations and principlesCooling load calculations and principles
Cooling load calculations and principles
 
HVAC Cooling Load Calculation
HVAC Cooling Load CalculationHVAC Cooling Load Calculation
HVAC Cooling Load Calculation
 
12 Cooling Load Calculations
12 Cooling Load Calculations12 Cooling Load Calculations
12 Cooling Load Calculations
 

Similar to UW- Energy Audit Class Lowell Hall TeamB 080715

Energy efficient systems and audits
Energy efficient systems and auditsEnergy efficient systems and audits
Energy efficient systems and audits
MukulGarg69
 
March3 2009-workshop-slides
March3 2009-workshop-slidesMarch3 2009-workshop-slides
March3 2009-workshop-slides
SWITCHOntario
 
Stoney River Energy Analysis
Stoney River Energy AnalysisStoney River Energy Analysis
Stoney River Energy Analysis
scottthorpe
 
Combi Systems: Lessons Learned from the Field
Combi Systems: Lessons Learned from the FieldCombi Systems: Lessons Learned from the Field
Combi Systems: Lessons Learned from the Field
Center for Energy and Environment
 
Energy audit 1
Energy audit 1Energy audit 1
Energy audit 1
Batsaikhan Battsetseg
 
Energy Saver Presentation
Energy Saver PresentationEnergy Saver Presentation
Energy Saver Presentation
Mark Forester
 
House hold electrical gadgets
House hold electrical gadgetsHouse hold electrical gadgets
House hold electrical gadgets
Vish Tyagi
 
Green buildings : Challange in Operation and Maintenance
Green buildings : Challange in Operation and MaintenanceGreen buildings : Challange in Operation and Maintenance
Green buildings : Challange in Operation and Maintenance
Tejwant Navalkar
 
Case study -4 Mort Street
Case study -4 Mort StreetCase study -4 Mort Street
Case study -4 Mort Street
Shamitha Reddy
 
First Unitarian Society of Minneapolis saves over $16,000 a year with energy-...
First Unitarian Society of Minneapolis saves over $16,000 a year with energy-...First Unitarian Society of Minneapolis saves over $16,000 a year with energy-...
First Unitarian Society of Minneapolis saves over $16,000 a year with energy-...
University of Minnesota
 
4 ch1
4 ch14 ch1
Energy audits in action
Energy audits in action Energy audits in action
Energy audits in action
Lonnie Russell
 
M2G May 2015 GTI Presentation
M2G May 2015 GTI PresentationM2G May 2015 GTI Presentation
M2G May 2015 GTI Presentation
Charles Rice
 
Turbine Inlet Air Cooling (TIAC) - Case Studies - Economics - Performance - C...
Turbine Inlet Air Cooling (TIAC) - Case Studies - Economics - Performance - C...Turbine Inlet Air Cooling (TIAC) - Case Studies - Economics - Performance - C...
Turbine Inlet Air Cooling (TIAC) - Case Studies - Economics - Performance - C...
Salman Haider
 
Looking for Energy Savings In All The Right Places - Eric Oliver
Looking for Energy Savings In All The Right Places - Eric OliverLooking for Energy Savings In All The Right Places - Eric Oliver
Looking for Energy Savings In All The Right Places - Eric Oliver
Chris Cheatham
 
energy
energyenergy
Flexible operation and heat rate in thermal power plant.pptx
Flexible operation and heat rate in thermal power plant.pptxFlexible operation and heat rate in thermal power plant.pptx
Flexible operation and heat rate in thermal power plant.pptx
AbhishekVerma847053
 
Ilc Power Point
Ilc Power PointIlc Power Point
Energy audit
Energy auditEnergy audit
Energy audit
Saifullah Memon
 
Energy management and audit
Energy management and auditEnergy management and audit
Energy management and audit
Kaustubh Kshetrapal
 

Similar to UW- Energy Audit Class Lowell Hall TeamB 080715 (20)

Energy efficient systems and audits
Energy efficient systems and auditsEnergy efficient systems and audits
Energy efficient systems and audits
 
March3 2009-workshop-slides
March3 2009-workshop-slidesMarch3 2009-workshop-slides
March3 2009-workshop-slides
 
Stoney River Energy Analysis
Stoney River Energy AnalysisStoney River Energy Analysis
Stoney River Energy Analysis
 
Combi Systems: Lessons Learned from the Field
Combi Systems: Lessons Learned from the FieldCombi Systems: Lessons Learned from the Field
Combi Systems: Lessons Learned from the Field
 
Energy audit 1
Energy audit 1Energy audit 1
Energy audit 1
 
Energy Saver Presentation
Energy Saver PresentationEnergy Saver Presentation
Energy Saver Presentation
 
House hold electrical gadgets
House hold electrical gadgetsHouse hold electrical gadgets
House hold electrical gadgets
 
Green buildings : Challange in Operation and Maintenance
Green buildings : Challange in Operation and MaintenanceGreen buildings : Challange in Operation and Maintenance
Green buildings : Challange in Operation and Maintenance
 
Case study -4 Mort Street
Case study -4 Mort StreetCase study -4 Mort Street
Case study -4 Mort Street
 
First Unitarian Society of Minneapolis saves over $16,000 a year with energy-...
First Unitarian Society of Minneapolis saves over $16,000 a year with energy-...First Unitarian Society of Minneapolis saves over $16,000 a year with energy-...
First Unitarian Society of Minneapolis saves over $16,000 a year with energy-...
 
4 ch1
4 ch14 ch1
4 ch1
 
Energy audits in action
Energy audits in action Energy audits in action
Energy audits in action
 
M2G May 2015 GTI Presentation
M2G May 2015 GTI PresentationM2G May 2015 GTI Presentation
M2G May 2015 GTI Presentation
 
Turbine Inlet Air Cooling (TIAC) - Case Studies - Economics - Performance - C...
Turbine Inlet Air Cooling (TIAC) - Case Studies - Economics - Performance - C...Turbine Inlet Air Cooling (TIAC) - Case Studies - Economics - Performance - C...
Turbine Inlet Air Cooling (TIAC) - Case Studies - Economics - Performance - C...
 
Looking for Energy Savings In All The Right Places - Eric Oliver
Looking for Energy Savings In All The Right Places - Eric OliverLooking for Energy Savings In All The Right Places - Eric Oliver
Looking for Energy Savings In All The Right Places - Eric Oliver
 
energy
energyenergy
energy
 
Flexible operation and heat rate in thermal power plant.pptx
Flexible operation and heat rate in thermal power plant.pptxFlexible operation and heat rate in thermal power plant.pptx
Flexible operation and heat rate in thermal power plant.pptx
 
Ilc Power Point
Ilc Power PointIlc Power Point
Ilc Power Point
 
Energy audit
Energy auditEnergy audit
Energy audit
 
Energy management and audit
Energy management and auditEnergy management and audit
Energy management and audit
 

UW- Energy Audit Class Lowell Hall TeamB 080715

  • 1. UW- Energy Audit Class Energy Efficiency Measures (EEM) for Lowell Hall Sarah Maston, Ryan Meyers, Kevin Preuss & Paul White
  • 2. Executive Summary Over the 1st week of August, our team provided a Level 2 Energy Audit of the Lowell Hall Building on the University of Wisconsin’s Madison Campus. We looked for Energy Efficiency Measures (EEMs) for the building envelope, lighting, and HVAC systems. After some quick calculations, we found that: EUI = 119.2 kBtu/SF/yr (EnergyStar National Median EUI = 74) ECI = $1.66/SF/yr …which indicates a myriad of opportunities for improvement. We have included 5 EEMs for consideration. The first EEM for the building envelope, has a lengthy payback, but may want to be considered for other reasons. EEMs 2-4 have simple paybacks of under 4 years. EEM-5 addresses a code violation. We also listed other EEMs for consideration.
  • 3. Energy End Use Pie Charts (Gas & Electric)
  • 4. Annual Energy Use Building EUI: 119.2 kBtu/SF/yr Building ECI: $1.66/SF/yr
  • 6. EEM-1: Replace Inefficient Windows • By reviewing the background information on Lowell Hall, that was provided, we determined that some of the windows were less efficient than others. • We originally were going to propose replacing the 7700 SF of the old glass windows with high-performance glass, but the payback was too large. kBTU Savings Cost Savings (Annual) Cost to Install Windows Simple Payback 583,552 $3282 $80.75/ SF 191 years
  • 7. EEM-2: Add Time Clock to Dining Rm Lights • During our building walkthrough, we noted that the cove lighting in the Dining Room stayed on 24/7, which is very inefficient. • We propose adding two time clocks to the lighting circuits for the cove lighting in the Dining Room. This time clock will turn the lights off over night, when no one is using the space. kWh Savings Cost Savings (Annual) Cost to Install Time Clocks Simple Payback 2135 kWh $278 $910 39 months
  • 8. EEM-3: Reduce Redundant Lobby Lighting • During our building walkthrough, we thought that the lobby lighting was excessive. • We recommend reducing the cove lighting by ½ and wiring the ballasts in tandem. kWh Savings Cost Savings (Annual) Cost to Remove Lights/ Rewire Ballasts Simple Payback 8970 kWh $493 $904 1.83 years
  • 9. EEM-4: VFDs for CHW & HW Pumps • During our walk-through, we noted that the primary CHW pump and the duty/ standby HW pumps had their balancing valves throttled down to 60% open. • The VFDs for these pumps were operating in hand, at 100%. This is extremely inefficient, and there was no indication as to why this was done. • We recommend opening the balancing valves to 100% open and then adjusting the pump speed down until the control valves in the system at the furthest point from the pumps just start to close down. Estimated CHW Pump Power Savings Savings Cost Savings (Annual) Cost to Adjust System Simple Payback 3 HP 6,445 kWh $354 $300 10 months Estimated HW Pump Power Savings Savings Cost Savings (Annual) Cost to Adjust System Simple Payback 5 HP 32,674 kWh $1797 $300 2 months
  • 10. EEM-5: Add modulation to OA damper (HV-1) • During our walk-through, we noted that the outside air (OA) damper to HV-1, serving the conference room did not modulate to bring in OA when the room was occupied. • The OA damper had been linked with the return air damper with a 2-position switch, such that the OA damper was either 100% open or 100% closed. The default is 100% closed, which does not provide the code-required fresh air to the room. • We recommend adding controls, such that the OA damper can modulate to bring in OA to meet the code requirements. Current Difference with damper open Savings Cost Savings (Annual) Cost to Install Controls Simple Payback 2.3 A 2135 kW $35.11 $300 8.5 years
  • 11. Additional EEMs to be Considered • The following are other issues that we witnessed in the building. Some additional research is required to determine costs and paybacks: • Consider replacing the 2 oversized HW boilers with modular condensing boilers. • Consider replacing oversized chiller with smaller chiller to reduce cycling. • Investigate use of check valves on two condenser water pumps that are tied together, to eliminate risk of recirculating water without cooling. • If replacing boilers is not possible, investigate installation of controls on both Kewanee boilers to control boiler temperature based on outside temperature. • Investigate potential for shutting down chiller pumps PE-3 on inlet side, or P1 on outlet side, of new chiller. Pumps are rated for 678 gpm. System requires 555 gpm. Pump P1 is connected to VFD, but 40% closed. • Building automation system is not utilized effectively, nor is it installed completely. Consider bringing in vendor for training. • Replace roof section that was not replaced in the last renovation. Many guest rooms are very hot.
  • 12. Conclusions There are many opportunities to improve the efficiencies of the systems in this building, but we have only focused on five key EEMs. With more research and time, more opportunities can be explored. Best Wishes!