SlideShare a Scribd company logo
(2) Business Administrator BA
(Email notification from Sharepoint)
(1) Material Requirement MR
Raised by Project Manager/ Project
Engineer / Site Engineer
Verifies :
- Material Code
- Material costs
After verification PR Purchase Requisition is
prepared by BA
(3) If Material Code doesn’t
exist: Material Creation
Approval
PM & CPM
(4) Purchase Order PO
is created by Procurement Controller
Initiating digital signature on the SharePoint
(6) OC
Order Confirmation
received in 3 days
OC not received:
Reminder sent/Call supplier
by Procurement
(7) Logistic takes over
Weekly Report:
Pending PO status on
Sharepoint
BA informs
Procurement
Procurement gets all
the relevant data
from the supplier
Procurement creates
Material in SAP &
informs BA with the
material number
Delivery done– QA/QC to be notified
in case of critical
deliveries/installation
Third Party Material Procurement
Overview
(5) PO sent to the supplier
by Procurement Controller (involve quality
department for critical deliveries/works)
Logistic takes over
Delivery done– QA/QC to be
notified in case of critical
deliveries/installation
Verifies :
- Material
status
PTO
PTSStatus alert
triggers to
Engineer
and PM
PM to
sign the PO
digitally
CPM to
sign the PO
digitally
Notification from SharePoint
Notification from SharePoint
Notification from SharePoint
Notification from SharePoint
PuM to
verify the
PO digitally
January 29, 2015 Third Party Material Procurement Overview NH
(1) Subject
Operator
Material Requirement
Project Manager, Project Engineer, Site
Manager
The procurement process commences with the need of material, initiator is the project manager, project engineer or site manager.
The basis of this is the project procurement plan which has the Bill of Quantities (BOQ) prepared by the project manager during the
PM stage “Acquisition phase”.
A Material Requisition (MR) is raised using a standard material requisition template.
The initiator is responsible for the content of the MR. All MRs
shall contain the following information:
- Description of the requested item, part no.
- Quantity
- Estimated price from price list / biding offer
- Cost Centre of the requesting BU / Corporate
Department (in case of framework order)
- WBS number / Project name
- BID Tabulation (Price Comparison Sheet) or Single
Source Justification (MR Value > 15’000 AED)
- Quotation attached
- JTS costs
MR is not valid without
proper JTS costs designation
Upload MR to SharePoint
Update SharePoint with the following informations:
- Division
- Category
- JTS costs
- Engineer
- Business Administrator
- Project Manager
- Commercial Manager
- Delivery instructions
(for direct deliveries to customer)
Standard Material Requisition Template [1.1]
See BID Tab [1.2] and SSJ [1.3] in attachments
Screenshot SharePoint: Update initiator
 BA Pool
Material Requirement MR
Raised by Project Manager/ Project Engineer /
Site Engineer
January 29, 2015 Third Party Material Procurement Overview NH
(2)
Subject
Operator
Purchase Requisition
Business Administrator
The Business Administrator has to check the content in the MR.
BA checks if the material number is existing.
In case the material is missing, BA will inform Procurement for Material Creation (3).
The MR gets converted into a SAP Purchase Requisition (PR).
Update the SharePoint with the PR number.
Put remarks if necessary.
Screenshot SharePoint: Business Administrator
 PM Pool for approval  CM Pool for approval  Procurement Pool
(3)
Subject
Operator
Material Creation
Procurement Controller
(Manual)
BA provides sheet “Create New Material in MM in Sales Org
2513”
BA provides sheet “Request for product specific data”, which
they receive from the supplier
Attachment 3.1: Create New Material in MM in Sales Org 2513
See Request for product specific data [3.2] in attachments
No Material Name Material Type Plant
Distr.
Channel
Unit of
Measure
Material
Group
Business
Unit
Product Hierarchy Profit Center
Purchasing
Group
Valuation Class
Price
AED
Sales Text
ECCN
CODES
DE US HS Code
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Prepared By : Tel:Date: Signature
to be send to Ms Rathi Manjunath
Create New Material in MM in Sales Org 2513
Business Administrator BA
(Email notification from Sharepoint)
After verification PR Purchase Requisition is
prepared by BA
If Material doesn’t exist:
Material Creation
January 29, 2015 Third Party Material Procurement Overview NH
Create a new Material: SAP - /nmm01
- Industry sector: Siemens International
- Material Type: Trading Goods
- Organizational levels: 9913, 2513, O1
Find required informations in sheet “Create New Material
in MM in Sales Org 2513”:
- Basic data 1
· Material
· Base Unit of Measure
· Material Group
- Sales: Sales Org 1
· Tax classification [default: 0]
- Sales: Sales Org 2
· Matl statisticsgrp [default: 1]
· Product hierarchy
- General Sales
· Trans. Grp [default: 0001]
· LoadingGrp [default: 0000]
· Profit Center
- Purchasing
· Purchaising Group
- Accounting 1
· Valuation class
· Moving price [default: 1]
- MRP 1
· MRP Type [default: ND]
- Foreign trade: Import data
· ECCN Code
 Material number
Screenshot SAP /nmm01: Initial Screen
Screenshot SAP /nmm01: Organizational levels
Screenshot SAP /nmm01: Input
Screenshot SAP example: /nmm01
 Send to Business Administrator
January 29, 2015 Third Party Material Procurement Overview NH
(4)
Subject:
Operator
Purchase Order
Procurement Controller
(Manual)
Creating a new Purchase Order:
SAP
1. /nme21n
2. /nme9f
3. /nme23n
MR
1. MR excel template
2. Bid Tab or SSJ
3. Quotation
SharePoint
1. Email notification that PR is awaiting for action
2. Open MR
3. Check JTS costs on SharePoint
4. Compare Quotation with MR
(Is MR value > 5’000 AED than check BID or SSJ)
5. SAP /nm21n
(a) Copy PR number which is mentioned
in the SharePoint, past in ‘Purchase
Requisition Number’ and execute.
(b) change to layout “shajeem” to see which
are the required materials
(c) Open MR and compare, pull the items
in the shopping card
6. Enter vendor name right on top
7. Enter store location (item overview) / Check in
register Org. Data (header) for Purchasing Group:
Purchasing Group / Store Location
U47 = 0024 – IBT-BAU
U48 = 0025 – CPS
U50 = 0026 – LCM_SER
Screenshot SharePoint: 2. PO request example
Screenshot SAP /nm21n: 5. Pull line items
Purchase Order PO
is created by Procurement Controller
a b
c
Screenshot SAP: Structure
- Header
- Item Overview
- Item Detail
Screenshot SAP: Register
example
January 29, 2015 Third Party Material Procurement Overview NH
8. Check for price, currency and quantity in MR and
quotation (item overview)
9. Put delivery date as per usual for the vendor (item
overview)
10. Put the right item text (item overview) :
Item text
Standard Purchase Order: Supply of _ _ _
Framework Order: Hire of _ _ _
11. Material PO text (item detail, register: texts)
Add additional item text
12. Header register: Delivery / Invoices
Fill in Payment Terms & Incoterms
13. Header, register Texts:
Add Standard header text
Add Shipping instructions for oversea supplier
Add Remarks
In case of framework order, add a reference to the
service agreement with this supplier. WBS number
and project name are mentioned in the MR.
Screenshot SAP: Item overview example
Standard additional text for Framework Orders:
[Period]
which is re-measurable.
Scope of Works:
1. [description of work]
2. [description of work]
…
----------------------------------------------
- Purchase Order (P.O.) number shall be
referred
on all Invoices.
- All hand tools shall be
provided by [company Name].
- Invoices shall be submitted along with signed
time sheets of responsible Siemens
Projectmanager along with WBS element.
----------------------------------------------
The above PARTICUALR CONDIONS shall apply in
addition to Siemens LLC General Terms and
Conditions of Purchase & agreed Conditions
within Manpower Provider Agreement with
Ref.No [reference number] including
annexure 1-5 duly signed on [date]
between [company name]
and Siemens LLC BT.
Standard Header Text for Purchase Orders:
Material which is delivered directly to RSA
Logistics requires to be delivered with 2copies
of the invoice which is mandatory. Kindly
inform a day in advance to Ms. Alta with the
Vehicle & Name of the Person no to arrange for
the gate pass before delivery of material.
Standard Shipping Instructions for Purchase Orders:
Mode of Dispatch: by UPS A/C# W8786E
if <40kgs, by Agility if >40Kgs
Standard Remarks for Purchase Orders:
[WBS number] – [Project name] **Please find
attached our General Terms and Conditions of
Purchase which forms an integral part of this
Purchase Order.
January 29, 2015 Third Party Material Procurement Overview NH
14. Header, Register: Communication
Sales Person: Person who submitted the quotation
Your reference: Quotation number
Our reference: ID number from SharePoint
15. Register: Partners
ZU: Signature Technical
ZV: Signature Commercial
(a) Search for names
16. Recheck everything, especially net price and quantity
17. Save PO in SAP, go to /nme9f and save as .pdf
Check printer options
(PDF-XChange Printer 2012)
18. Update SharePoint by the help of /nme23n:
- Project
- Vendor
- Proc Actions
- PO number
- PO created date
- PO currency
- PO value
- Delivery Date
19. Upload PO .pdf-File to SharePoint
Screenshot SAP: Communication example
Screenshot SAP: Partners example
Signature regulations
Screenshot SAP: PO created
See PO example [4.1] in attachments
Screenshot SAP /nme9f
Screenshot SharePoint: Update SharePoint
a
≤ 25’000 AED
Technical Level 4
Commercial Level 4
≤ 150’000 AED
Technical Level 3
Commercial Level 3
≤ 500’000 AED
Technical Level 2
Commercial Level 2
> 500’000 AED& CC
Technical Level 1
Commercial Level 1
January 29, 2015 Third Party Material Procurement Overview NH
 Approval by commercial signatory  Approval by technical signatory  Procurement Pool
(5)
Subject
Operator
Sending Purchase Order
Procurement Controller
(Manual)
Receiving notification from SharePoint: PO is signed.
1. Check Signatures
2. Prepare e-mail to current supplier
- Addressee:
TO: Supplier
CC: Logistic, Procurement Team, (for critical
deliveries/works, quality management)
- Attachments:
- PO
- New Code Of Conduct
- Standard T&C_UAE_Dec2014
- Text
3. Update SharePoint
- Proc Actions
- PO sent to the supplier date
4. Upload sent e-mail to SharePoint, via “PO Link”, “View
PO”
Text example “email to supplier”:
Good evening ,
Please find attached Purchase Orders for your
immediate processing.
Kindly acknowledge the receipt of the same &
advice the delivery date.
Thanks & Best regards
Nils Hass
Procurement Team
IC Building Technologies
SIEMENS LLC
9/F, The Galleries - Building 2
Downtown Jebel Ali
P.O. Box 2154
Dubai, United Arab Emirates
Screenshot SAP: Update SharePoint
Screenshot SAP: Uploading sent emails
 Order Confirmation (Supplier)
PO sent to the supplier
by Procurement Controller
(involve quality department for critical deliveries/works)
January 29, 2015 Third Party Material Procurement Overview NH
(6)
Subject
Operator
Order Confirmation
Procurement Controller
(Manual)
1. Received OC - sent e-mail to logistic in case they are
not in the CC
2. Upload OC to SharePoint via “PO Acknolegment
Link”, “View OA”
After 3 days, send reminder with ultimatum or call supplier
Screenshot SAP: Uploading Order Confirmation
 Logistic takes over
(7)
Subject
Operator
GRN
Logistic Team
The acceptances of the delivery and the receipt goods or
services (GR) are to be carried out by the Logistic Team.
To process GRN, the acceptance of the goods or services must
be validated by the original requestor (stamping / signature of
invoices)
 Delivery done
OC
Order Confirmation
received in 3 days
Logistic takes over
January 29, 2015 Third Party Material Procurement Overview NH
Attachment 1.1: Standard Material Requisition Template
January 29, 2015 Third Party Material Procurement Overview NH
Attachment 1.2: BID Tab
BID
Tabulation
ESN Code
S.No. Unit / Qty. Supplier 1 Supplier 2 Supplier 3 Supplier 4 Unit / Qty.
1 1.00
2
3
4
5
6
7
0 0 0 0
0 0 0 0
0
0 0 0 0
S.No. Response Response Response Response Response
1
2
3
4
5
6
7
8
9
10
11
12
13
14
PROCUREME
NT MGR
TECH
DIRECTOR
Tech.
Director
Exhange
Rates
1 Eur = 4.76 AED AED
1 GBP = 5.88 AED AED
1 USD = 3.68 AED AED
Negotiations
Description
Warranty
Delivery Time in weeks
Signed Code of Conduct, NDA & CR
Second Round Discount
Third Round Discount
Budget
CNI (AED)/Nett Savings
First Discounted Offer
REMARKS : As per Selection Criteria
The Bid tab is issued for the issuance of LOA, all MR1
and MR2 criteria to be fulfilled prior to issuance of
Purchase Order.
Selected Supplier :
c4s easy registration
DAMEX, BPC check
Suppleir Approved with Client
Selection Criteria :
ISO 9001 or equivalent certified
Manufacturing Country (GVS)
PROJECT MGR
Supplier Audit
Supplier from FPL
COMM DIRECTOR
COMMERCIAL
MGR
Risk Evaluation
Quote Comp. on ToCo
GVS Challenger
Frame Agreement
MR2 Criteria
Project Name
Description
Customs Duty ( If
applicable)
Total Cost of Ownershiop
( ToCo)
Project Description
Transport
Installation
CRSA for high risk country
DOR
ISO or equivalent certifications
Validity of offer
Sub Total:
Performance Bank Guarantee
Terms of Payment
Delivery Basis
Local Agent/Representative
Manufacture & Country of Origin
Commercial Compliance on complete Terms and Conditions
Technical Compliance on submitted documents
Code of Conduct, NDA & CR
MR1 Criteria
Liquidated Damages
January 29, 2015 Third Party Material Procurement Overview NH
Attachment 1.3: SSJ
Single Source
Justification
Building Technologies, LGR
SCM-BT
Date Dept Location
File references
Proposed Supplier
Description of product/services:
Order value :
Project Name (if applicable):
Reasons for not following 3 quotes / tender process
Quotation received from Supplier known to have required unique capability,
proprietary products or other intellectual property rights.
Insufficient time to obtain three written quotes. (Unforeseeable)
The need for security restricts the number of Suppliers selected to quote.
External customer specified
Item/Service is required to be compatible with installed equipment.
Supplementary or additional to previous competitively sourced requirement
Date of last sourcing :
No responses obtained from other invited suppliers
Framework Supplier / Preferred Supplier agreement in place
One-off advantageous opportunity for short lenght of time
Note: Please provide supporting documents wherever applicable (for e.g, document proof showing that Customer has
specified the product/ supplier)
Remarks/ Comments
Measures taken to mitigate risk
Please describe measures taken to ensure sole supplier source is comforming to market conditions
(such as : benchmark, cost calculation, other quotes,
comparison with references, with existing price, …)
Recommendation agreed by
Project Mgr Name Signature
Commerical Head Name Signature
Procurement / Supply Chain Mgr Name Signature
Requested by
January 29, 2015 Third Party Material Procurement Overview NH
Attachment 3.1: Create New Material in MM in Sales Org 2513
NoMaterialNameMaterialTypePlant
Distr.
Channel
Unitof
Measure
Material
Group
Business
Unit
ProductHierarchyProfitCenter
Purchasing
Group
ValuationClass
Price
AED
SalesText
ECCN
CODES
DEUSHSCode
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
PreparedBy:Tel:Date:Signature
tobesendtoMsRathiManjunath
CreateNewMaterialinMMinSalesOrg2513
January 29, 2015 Third Party Material Procurement Overview NH
Attachment 3.2: Request for product specific data (1)
Template for Supplier Declaration Form
(Use letter layout for external correspondence)
Request for product specific data
Ladies and Gentlemen,
. In order to comply with foreign trade and customs legislation we require various product-specific details for the
products you sell.
Could you please therefore let us know
 The classification according to the U.S. Export Administration Regulations the case of US products
(ECCN according to the U.S. Commerce Control List)
 The HS code
 The country of consignment/origin (LKZ) of the goods requested/ordered
Without this information it is not possible to ensure full compliance with the relevant legal requirements. The
information forms part of the commercial terms.
Please enter the code in the boxes provided for each item specified (see enclosure). Please return the
completed list to the
( ) address
( ) fax number
( ) e-mail address shown in
the header. Many thanks.
..............................................................................
Signature, company stamp
January 29, 2015 Third Party Material Procurement Overview NH
Attachment 3.2: Request for product specific data (2)
Siemens LLC Address of supplier:
Supplier number:
Transaction/order No.:
Item Productdescription Product code
Supplier
Internal
Siemens No.
HS Code or
statistical
commodity code
(8 digits)
ECCN
as per U.S.
CCL *
1
Country of
origin(country
code *
2
)
1
2
(Please use additional sheet if required)
In case above table is empty, we confirm the following regarding the items supplied by us to Siemens.
1. contains US origin, (Yes / No) or
2. any visible indication that item contains US hardware e.g. label „made in USA“ on product or attending
papers; (Yes / No) or
3. any functional indication, insinuating to US content, e.g. US operation software, US application software, etc.
(Yes / No) or
4. item purchased from a US company or US affiliated company? (Yes / No)
*
1)
Details
 If the product is not subject to U.S. Export Administration Regulations (not a U.S. product / no U.S. content
/ no U.S. manufacture under license) = No
 If the product is subject to U.S. Export Administration Regulations = Specify the relevant ECCN (Export
Control Classification Number if possible, with sub-number (Example: 5D992b2))
*2)
Country of origin (ISO Alpha2 Code – Example Germany=DE)
Company stamp, signature:
.......................................................
Place Date
Request form for export data, Date:
January 29, 2015 Third Party Material Procurement Overview NH
Attachment 4.1: PO example (1)
January 29, 2015 Third Party Material Procurement Overview NH
Attachment 4.1: PO example (2)
January 29, 2015 Third Party Material Procurement Overview NH
Attachment 4.1: PO example (3)

More Related Content

What's hot

Malhotra11
Malhotra11Malhotra11
Vendor managed consignment process SAP MM
Vendor managed consignment process SAP MMVendor managed consignment process SAP MM
Vendor managed consignment process SAP MM
Mohammed Azhad
 
The Relationship between Competition and Innovation – Álvaro Parra – June 202...
The Relationship between Competition and Innovation – Álvaro Parra – June 202...The Relationship between Competition and Innovation – Álvaro Parra – June 202...
The Relationship between Competition and Innovation – Álvaro Parra – June 202...
OECD Directorate for Financial and Enterprise Affairs
 
Lpm004 Canada Goose Presentation-Mia Tracy Riki
Lpm004 Canada Goose Presentation-Mia Tracy RikiLpm004 Canada Goose Presentation-Mia Tracy Riki
Lpm004 Canada Goose Presentation-Mia Tracy Riki
Riki Yao
 
Marketing research ch 4_malhotra
Marketing research ch 4_malhotraMarketing research ch 4_malhotra
Marketing research ch 4_malhotra
Jamil Ahmed AKASH
 
Chapter 1 Marketing Research Malhotra
Chapter 1 Marketing Research MalhotraChapter 1 Marketing Research Malhotra
Chapter 1 Marketing Research MalhotraAADITYA TANTIA
 
Porters 5 forces class presentation
Porters 5 forces class presentationPorters 5 forces class presentation
Porters 5 forces class presentation
annesunita
 
SAP SD third party process
SAP SD third party processSAP SD third party process
SAP SD third party process
SD Tutorial
 
The Marketing Plan
The Marketing PlanThe Marketing Plan
The Marketing Plan
gohar321
 
Schiffman cb10 ppt_04
Schiffman cb10 ppt_04Schiffman cb10 ppt_04
Schiffman cb10 ppt_04ftsutton
 
Chap008
Chap008Chap008
Chap008ays365
 
4retal instbyownrship
4retal instbyownrship4retal instbyownrship
4retal instbyownrship
Rishabh Sharma
 
#Sapmm #sap #mrp settings to automate the generation of #stock transfer #purc...
#Sapmm #sap #mrp settings to automate the generation of #stock transfer #purc...#Sapmm #sap #mrp settings to automate the generation of #stock transfer #purc...
#Sapmm #sap #mrp settings to automate the generation of #stock transfer #purc...
Rangabashyam S
 
Marketing management-by-philip-kotler-719-slides-1234238345990514-2 untitled9...
Marketing management-by-philip-kotler-719-slides-1234238345990514-2 untitled9...Marketing management-by-philip-kotler-719-slides-1234238345990514-2 untitled9...
Marketing management-by-philip-kotler-719-slides-1234238345990514-2 untitled9...Cibin Mathew
 
Case Study on Caterpillar Inc. (CAT)
Case Study on Caterpillar Inc. (CAT)Case Study on Caterpillar Inc. (CAT)
Case Study on Caterpillar Inc. (CAT)
Rishav Kar
 
Malhotra16
Malhotra16Malhotra16
Sap sd question
Sap sd questionSap sd question
Sap sd question
Amit Gupta
 

What's hot (20)

Malhotra11
Malhotra11Malhotra11
Malhotra11
 
Vendor managed consignment process SAP MM
Vendor managed consignment process SAP MMVendor managed consignment process SAP MM
Vendor managed consignment process SAP MM
 
The Relationship between Competition and Innovation – Álvaro Parra – June 202...
The Relationship between Competition and Innovation – Álvaro Parra – June 202...The Relationship between Competition and Innovation – Álvaro Parra – June 202...
The Relationship between Competition and Innovation – Álvaro Parra – June 202...
 
Chapter 1
Chapter   1Chapter   1
Chapter 1
 
Lpm004 Canada Goose Presentation-Mia Tracy Riki
Lpm004 Canada Goose Presentation-Mia Tracy RikiLpm004 Canada Goose Presentation-Mia Tracy Riki
Lpm004 Canada Goose Presentation-Mia Tracy Riki
 
Malhotra02
Malhotra02Malhotra02
Malhotra02
 
Marketing research ch 4_malhotra
Marketing research ch 4_malhotraMarketing research ch 4_malhotra
Marketing research ch 4_malhotra
 
Chapter 1 Marketing Research Malhotra
Chapter 1 Marketing Research MalhotraChapter 1 Marketing Research Malhotra
Chapter 1 Marketing Research Malhotra
 
Kotler mm 14e_12_ippt
Kotler mm 14e_12_ipptKotler mm 14e_12_ippt
Kotler mm 14e_12_ippt
 
Porters 5 forces class presentation
Porters 5 forces class presentationPorters 5 forces class presentation
Porters 5 forces class presentation
 
SAP SD third party process
SAP SD third party processSAP SD third party process
SAP SD third party process
 
The Marketing Plan
The Marketing PlanThe Marketing Plan
The Marketing Plan
 
Schiffman cb10 ppt_04
Schiffman cb10 ppt_04Schiffman cb10 ppt_04
Schiffman cb10 ppt_04
 
Chap008
Chap008Chap008
Chap008
 
4retal instbyownrship
4retal instbyownrship4retal instbyownrship
4retal instbyownrship
 
#Sapmm #sap #mrp settings to automate the generation of #stock transfer #purc...
#Sapmm #sap #mrp settings to automate the generation of #stock transfer #purc...#Sapmm #sap #mrp settings to automate the generation of #stock transfer #purc...
#Sapmm #sap #mrp settings to automate the generation of #stock transfer #purc...
 
Marketing management-by-philip-kotler-719-slides-1234238345990514-2 untitled9...
Marketing management-by-philip-kotler-719-slides-1234238345990514-2 untitled9...Marketing management-by-philip-kotler-719-slides-1234238345990514-2 untitled9...
Marketing management-by-philip-kotler-719-slides-1234238345990514-2 untitled9...
 
Case Study on Caterpillar Inc. (CAT)
Case Study on Caterpillar Inc. (CAT)Case Study on Caterpillar Inc. (CAT)
Case Study on Caterpillar Inc. (CAT)
 
Malhotra16
Malhotra16Malhotra16
Malhotra16
 
Sap sd question
Sap sd questionSap sd question
Sap sd question
 

Viewers also liked

MICHAELKAMAL 2015 CV
MICHAELKAMAL 2015 CVMICHAELKAMAL 2015 CV
MICHAELKAMAL 2015 CVmichael kamal
 
(14)danglers (2)
(14)danglers (2)(14)danglers (2)
(14)danglers (2)francpones
 
Manual zanussi campana zhc9131x
Manual zanussi   campana zhc9131xManual zanussi   campana zhc9131x
Manual zanussi campana zhc9131x
Alsako Electrodomésticos
 
Miscellaneous Survey
Miscellaneous SurveyMiscellaneous Survey
Miscellaneous Surveydrhulsey
 
HUB:BLE-2 09 short company pitches
HUB:BLE-2 09   short company pitchesHUB:BLE-2 09   short company pitches
HUB:BLE-2 09 short company pitches
Space IDEAS Hub
 
روش انقلاب (نجم آفندی) پارٹ نمبر 6
روش انقلاب (نجم آفندی) پارٹ نمبر 6روش انقلاب (نجم آفندی) پارٹ نمبر 6
روش انقلاب (نجم آفندی) پارٹ نمبر 6
سید محمد عمران نقوی
 
تاثیر ماتم
تاثیر ماتمتاثیر ماتم
HUB:BLE-2 08 reaching the world
HUB:BLE-2 08   reaching the worldHUB:BLE-2 08   reaching the world
HUB:BLE-2 08 reaching the world
Space IDEAS Hub
 
Cabazes de Natal 2013
Cabazes de Natal 2013Cabazes de Natal 2013
Cabazes de Natal 2013
Bísaro - Salsicharia Tradicional
 
Лекция 5 Элементарные структуры данных часть 3
Лекция 5 Элементарные структуры данных часть 3Лекция 5 Элементарные структуры данных часть 3
Лекция 5 Элементарные структуры данных часть 3
simple_people
 
Kazakhstan Investment Policy Framework 2017
Kazakhstan Investment Policy Framework 2017Kazakhstan Investment Policy Framework 2017
Kazakhstan Investment Policy Framework 2017
Embassy of Kazakhstan in the USA
 
Achieving a Successful Identity Management and Governance Deployment The Flor...
Achieving a Successful Identity Management and Governance Deployment The Flor...Achieving a Successful Identity Management and Governance Deployment The Flor...
Achieving a Successful Identity Management and Governance Deployment The Flor...
CA Technologies
 
Derecho del trabajo
Derecho del trabajoDerecho del trabajo
Derecho del trabajo
franciapalacios
 
Psicología penitenciaria
Psicología penitenciariaPsicología penitenciaria
Psicología penitenciaria
AnaNoiret
 
Електронна будова атома. Узагальнення
Електронна будова атома. УзагальненняЕлектронна будова атома. Узагальнення
Електронна будова атома. Узагальнення
Елена Мешкова
 

Viewers also liked (15)

MICHAELKAMAL 2015 CV
MICHAELKAMAL 2015 CVMICHAELKAMAL 2015 CV
MICHAELKAMAL 2015 CV
 
(14)danglers (2)
(14)danglers (2)(14)danglers (2)
(14)danglers (2)
 
Manual zanussi campana zhc9131x
Manual zanussi   campana zhc9131xManual zanussi   campana zhc9131x
Manual zanussi campana zhc9131x
 
Miscellaneous Survey
Miscellaneous SurveyMiscellaneous Survey
Miscellaneous Survey
 
HUB:BLE-2 09 short company pitches
HUB:BLE-2 09   short company pitchesHUB:BLE-2 09   short company pitches
HUB:BLE-2 09 short company pitches
 
روش انقلاب (نجم آفندی) پارٹ نمبر 6
روش انقلاب (نجم آفندی) پارٹ نمبر 6روش انقلاب (نجم آفندی) پارٹ نمبر 6
روش انقلاب (نجم آفندی) پارٹ نمبر 6
 
تاثیر ماتم
تاثیر ماتمتاثیر ماتم
تاثیر ماتم
 
HUB:BLE-2 08 reaching the world
HUB:BLE-2 08   reaching the worldHUB:BLE-2 08   reaching the world
HUB:BLE-2 08 reaching the world
 
Cabazes de Natal 2013
Cabazes de Natal 2013Cabazes de Natal 2013
Cabazes de Natal 2013
 
Лекция 5 Элементарные структуры данных часть 3
Лекция 5 Элементарные структуры данных часть 3Лекция 5 Элементарные структуры данных часть 3
Лекция 5 Элементарные структуры данных часть 3
 
Kazakhstan Investment Policy Framework 2017
Kazakhstan Investment Policy Framework 2017Kazakhstan Investment Policy Framework 2017
Kazakhstan Investment Policy Framework 2017
 
Achieving a Successful Identity Management and Governance Deployment The Flor...
Achieving a Successful Identity Management and Governance Deployment The Flor...Achieving a Successful Identity Management and Governance Deployment The Flor...
Achieving a Successful Identity Management and Governance Deployment The Flor...
 
Derecho del trabajo
Derecho del trabajoDerecho del trabajo
Derecho del trabajo
 
Psicología penitenciaria
Psicología penitenciariaPsicología penitenciaria
Psicología penitenciaria
 
Електронна будова атома. Узагальнення
Електронна будова атома. УзагальненняЕлектронна будова атома. Узагальнення
Електронна будова атома. Узагальнення
 

Similar to Third Party Material Procurement Overview-INSTRUCTIONS AMANUAL

MM Integración.pptx
MM Integración.pptxMM Integración.pptx
MM Integración.pptx
MarcoRico8
 
ERP System Process and Data Flow in Gane & Sarson Notation
ERP System Process and Data Flow in Gane & Sarson NotationERP System Process and Data Flow in Gane & Sarson Notation
ERP System Process and Data Flow in Gane & Sarson Notation
Glen Alleman
 
juh
juhjuh
Sapfinancialsintegration
SapfinancialsintegrationSapfinancialsintegration
Sapfinancialsintegration
Shobhnath Singh
 
SAP ATP check for Sales Order
SAP ATP check for Sales OrderSAP ATP check for Sales Order
SAP ATP check for Sales Order
Lee Scott
 
New Charts Architectures (2)
New Charts Architectures (2)New Charts Architectures (2)
New Charts Architectures (2)guestf73e68
 
Sap mm interview questions and answers
Sap mm interview questions and answersSap mm interview questions and answers
Sap mm interview questions and answers
Nancy Nelida
 
Dip configuration
Dip configurationDip configuration
Dip configuration
KamalRahangdale
 
Dynamics crm implementation for carbon provider
Dynamics crm implementation for carbon providerDynamics crm implementation for carbon provider
Dynamics crm implementation for carbon provider
varianceinfotech
 
Operations Management Material Requirements Planning (MRP)
Operations ManagementMaterial Requirements Planning (MRP)Operations ManagementMaterial Requirements Planning (MRP)
Operations Management Material Requirements Planning (MRP)Mostafa Ewees
 
Sap Mm
Sap   MmSap   Mm
Sap Mm
Ravi Jain
 
Stock transfer using stock transport order
Stock transfer using stock transport orderStock transfer using stock transport order
Stock transfer using stock transport order
Santhana Kishore
 
SAP Production Planning
SAP Production PlanningSAP Production Planning
SAP Production Planning
Rupesh Brahmankar
 
1260 Purchasing in Infor EAM.pdf
1260 Purchasing in Infor EAM.pdf1260 Purchasing in Infor EAM.pdf
1260 Purchasing in Infor EAM.pdf
ssuser623a0f
 
Training _ZK _Rev3_Final
Training _ZK _Rev3_FinalTraining _ZK _Rev3_Final
Training _ZK _Rev3_FinalZiad Khleif
 
SAP MM Purchasing .pptx
SAP MM  Purchasing .pptxSAP MM  Purchasing .pptx
SAP MM Purchasing .pptx
praveenRapeti3
 
Isu crm facts 01.doc
Isu crm facts 01.docIsu crm facts 01.doc
Isu crm facts 01.doc
Ripunjay Rathaur
 
Procurement Actual Process PART 1
Procurement Actual Process PART 1Procurement Actual Process PART 1
Procurement Actual Process PART 1Cumhur Sendoganer
 

Similar to Third Party Material Procurement Overview-INSTRUCTIONS AMANUAL (20)

MM Integración.pptx
MM Integración.pptxMM Integración.pptx
MM Integración.pptx
 
ERP System Process and Data Flow in Gane & Sarson Notation
ERP System Process and Data Flow in Gane & Sarson NotationERP System Process and Data Flow in Gane & Sarson Notation
ERP System Process and Data Flow in Gane & Sarson Notation
 
juh
juhjuh
juh
 
Sapfinancialsintegration
SapfinancialsintegrationSapfinancialsintegration
Sapfinancialsintegration
 
SAP ATP check for Sales Order
SAP ATP check for Sales OrderSAP ATP check for Sales Order
SAP ATP check for Sales Order
 
New Charts Architectures (2)
New Charts Architectures (2)New Charts Architectures (2)
New Charts Architectures (2)
 
Sap mm interview questions and answers
Sap mm interview questions and answersSap mm interview questions and answers
Sap mm interview questions and answers
 
Dip configuration
Dip configurationDip configuration
Dip configuration
 
Dynamics crm implementation for carbon provider
Dynamics crm implementation for carbon providerDynamics crm implementation for carbon provider
Dynamics crm implementation for carbon provider
 
Operations Management Material Requirements Planning (MRP)
Operations ManagementMaterial Requirements Planning (MRP)Operations ManagementMaterial Requirements Planning (MRP)
Operations Management Material Requirements Planning (MRP)
 
Sap Mm
Sap   MmSap   Mm
Sap Mm
 
Stock transfer using stock transport order
Stock transfer using stock transport orderStock transfer using stock transport order
Stock transfer using stock transport order
 
SAP Production Planning
SAP Production PlanningSAP Production Planning
SAP Production Planning
 
1260 Purchasing in Infor EAM.pdf
1260 Purchasing in Infor EAM.pdf1260 Purchasing in Infor EAM.pdf
1260 Purchasing in Infor EAM.pdf
 
Training _ZK _Rev3_Final
Training _ZK _Rev3_FinalTraining _ZK _Rev3_Final
Training _ZK _Rev3_Final
 
SAP MM Purchasing .pptx
SAP MM  Purchasing .pptxSAP MM  Purchasing .pptx
SAP MM Purchasing .pptx
 
IcSoft
IcSoftIcSoft
IcSoft
 
Mrp 1
Mrp 1Mrp 1
Mrp 1
 
Isu crm facts 01.doc
Isu crm facts 01.docIsu crm facts 01.doc
Isu crm facts 01.doc
 
Procurement Actual Process PART 1
Procurement Actual Process PART 1Procurement Actual Process PART 1
Procurement Actual Process PART 1
 

Third Party Material Procurement Overview-INSTRUCTIONS AMANUAL

  • 1. (2) Business Administrator BA (Email notification from Sharepoint) (1) Material Requirement MR Raised by Project Manager/ Project Engineer / Site Engineer Verifies : - Material Code - Material costs After verification PR Purchase Requisition is prepared by BA (3) If Material Code doesn’t exist: Material Creation Approval PM & CPM (4) Purchase Order PO is created by Procurement Controller Initiating digital signature on the SharePoint (6) OC Order Confirmation received in 3 days OC not received: Reminder sent/Call supplier by Procurement (7) Logistic takes over Weekly Report: Pending PO status on Sharepoint BA informs Procurement Procurement gets all the relevant data from the supplier Procurement creates Material in SAP & informs BA with the material number Delivery done– QA/QC to be notified in case of critical deliveries/installation Third Party Material Procurement Overview (5) PO sent to the supplier by Procurement Controller (involve quality department for critical deliveries/works) Logistic takes over Delivery done– QA/QC to be notified in case of critical deliveries/installation Verifies : - Material status PTO PTSStatus alert triggers to Engineer and PM PM to sign the PO digitally CPM to sign the PO digitally Notification from SharePoint Notification from SharePoint Notification from SharePoint Notification from SharePoint PuM to verify the PO digitally
  • 2. January 29, 2015 Third Party Material Procurement Overview NH (1) Subject Operator Material Requirement Project Manager, Project Engineer, Site Manager The procurement process commences with the need of material, initiator is the project manager, project engineer or site manager. The basis of this is the project procurement plan which has the Bill of Quantities (BOQ) prepared by the project manager during the PM stage “Acquisition phase”. A Material Requisition (MR) is raised using a standard material requisition template. The initiator is responsible for the content of the MR. All MRs shall contain the following information: - Description of the requested item, part no. - Quantity - Estimated price from price list / biding offer - Cost Centre of the requesting BU / Corporate Department (in case of framework order) - WBS number / Project name - BID Tabulation (Price Comparison Sheet) or Single Source Justification (MR Value > 15’000 AED) - Quotation attached - JTS costs MR is not valid without proper JTS costs designation Upload MR to SharePoint Update SharePoint with the following informations: - Division - Category - JTS costs - Engineer - Business Administrator - Project Manager - Commercial Manager - Delivery instructions (for direct deliveries to customer) Standard Material Requisition Template [1.1] See BID Tab [1.2] and SSJ [1.3] in attachments Screenshot SharePoint: Update initiator  BA Pool Material Requirement MR Raised by Project Manager/ Project Engineer / Site Engineer
  • 3. January 29, 2015 Third Party Material Procurement Overview NH (2) Subject Operator Purchase Requisition Business Administrator The Business Administrator has to check the content in the MR. BA checks if the material number is existing. In case the material is missing, BA will inform Procurement for Material Creation (3). The MR gets converted into a SAP Purchase Requisition (PR). Update the SharePoint with the PR number. Put remarks if necessary. Screenshot SharePoint: Business Administrator  PM Pool for approval  CM Pool for approval  Procurement Pool (3) Subject Operator Material Creation Procurement Controller (Manual) BA provides sheet “Create New Material in MM in Sales Org 2513” BA provides sheet “Request for product specific data”, which they receive from the supplier Attachment 3.1: Create New Material in MM in Sales Org 2513 See Request for product specific data [3.2] in attachments No Material Name Material Type Plant Distr. Channel Unit of Measure Material Group Business Unit Product Hierarchy Profit Center Purchasing Group Valuation Class Price AED Sales Text ECCN CODES DE US HS Code 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Prepared By : Tel:Date: Signature to be send to Ms Rathi Manjunath Create New Material in MM in Sales Org 2513 Business Administrator BA (Email notification from Sharepoint) After verification PR Purchase Requisition is prepared by BA If Material doesn’t exist: Material Creation
  • 4. January 29, 2015 Third Party Material Procurement Overview NH Create a new Material: SAP - /nmm01 - Industry sector: Siemens International - Material Type: Trading Goods - Organizational levels: 9913, 2513, O1 Find required informations in sheet “Create New Material in MM in Sales Org 2513”: - Basic data 1 · Material · Base Unit of Measure · Material Group - Sales: Sales Org 1 · Tax classification [default: 0] - Sales: Sales Org 2 · Matl statisticsgrp [default: 1] · Product hierarchy - General Sales · Trans. Grp [default: 0001] · LoadingGrp [default: 0000] · Profit Center - Purchasing · Purchaising Group - Accounting 1 · Valuation class · Moving price [default: 1] - MRP 1 · MRP Type [default: ND] - Foreign trade: Import data · ECCN Code  Material number Screenshot SAP /nmm01: Initial Screen Screenshot SAP /nmm01: Organizational levels Screenshot SAP /nmm01: Input Screenshot SAP example: /nmm01  Send to Business Administrator
  • 5. January 29, 2015 Third Party Material Procurement Overview NH (4) Subject: Operator Purchase Order Procurement Controller (Manual) Creating a new Purchase Order: SAP 1. /nme21n 2. /nme9f 3. /nme23n MR 1. MR excel template 2. Bid Tab or SSJ 3. Quotation SharePoint 1. Email notification that PR is awaiting for action 2. Open MR 3. Check JTS costs on SharePoint 4. Compare Quotation with MR (Is MR value > 5’000 AED than check BID or SSJ) 5. SAP /nm21n (a) Copy PR number which is mentioned in the SharePoint, past in ‘Purchase Requisition Number’ and execute. (b) change to layout “shajeem” to see which are the required materials (c) Open MR and compare, pull the items in the shopping card 6. Enter vendor name right on top 7. Enter store location (item overview) / Check in register Org. Data (header) for Purchasing Group: Purchasing Group / Store Location U47 = 0024 – IBT-BAU U48 = 0025 – CPS U50 = 0026 – LCM_SER Screenshot SharePoint: 2. PO request example Screenshot SAP /nm21n: 5. Pull line items Purchase Order PO is created by Procurement Controller a b c Screenshot SAP: Structure - Header - Item Overview - Item Detail Screenshot SAP: Register example
  • 6. January 29, 2015 Third Party Material Procurement Overview NH 8. Check for price, currency and quantity in MR and quotation (item overview) 9. Put delivery date as per usual for the vendor (item overview) 10. Put the right item text (item overview) : Item text Standard Purchase Order: Supply of _ _ _ Framework Order: Hire of _ _ _ 11. Material PO text (item detail, register: texts) Add additional item text 12. Header register: Delivery / Invoices Fill in Payment Terms & Incoterms 13. Header, register Texts: Add Standard header text Add Shipping instructions for oversea supplier Add Remarks In case of framework order, add a reference to the service agreement with this supplier. WBS number and project name are mentioned in the MR. Screenshot SAP: Item overview example Standard additional text for Framework Orders: [Period] which is re-measurable. Scope of Works: 1. [description of work] 2. [description of work] … ---------------------------------------------- - Purchase Order (P.O.) number shall be referred on all Invoices. - All hand tools shall be provided by [company Name]. - Invoices shall be submitted along with signed time sheets of responsible Siemens Projectmanager along with WBS element. ---------------------------------------------- The above PARTICUALR CONDIONS shall apply in addition to Siemens LLC General Terms and Conditions of Purchase & agreed Conditions within Manpower Provider Agreement with Ref.No [reference number] including annexure 1-5 duly signed on [date] between [company name] and Siemens LLC BT. Standard Header Text for Purchase Orders: Material which is delivered directly to RSA Logistics requires to be delivered with 2copies of the invoice which is mandatory. Kindly inform a day in advance to Ms. Alta with the Vehicle & Name of the Person no to arrange for the gate pass before delivery of material. Standard Shipping Instructions for Purchase Orders: Mode of Dispatch: by UPS A/C# W8786E if <40kgs, by Agility if >40Kgs Standard Remarks for Purchase Orders: [WBS number] – [Project name] **Please find attached our General Terms and Conditions of Purchase which forms an integral part of this Purchase Order.
  • 7. January 29, 2015 Third Party Material Procurement Overview NH 14. Header, Register: Communication Sales Person: Person who submitted the quotation Your reference: Quotation number Our reference: ID number from SharePoint 15. Register: Partners ZU: Signature Technical ZV: Signature Commercial (a) Search for names 16. Recheck everything, especially net price and quantity 17. Save PO in SAP, go to /nme9f and save as .pdf Check printer options (PDF-XChange Printer 2012) 18. Update SharePoint by the help of /nme23n: - Project - Vendor - Proc Actions - PO number - PO created date - PO currency - PO value - Delivery Date 19. Upload PO .pdf-File to SharePoint Screenshot SAP: Communication example Screenshot SAP: Partners example Signature regulations Screenshot SAP: PO created See PO example [4.1] in attachments Screenshot SAP /nme9f Screenshot SharePoint: Update SharePoint a ≤ 25’000 AED Technical Level 4 Commercial Level 4 ≤ 150’000 AED Technical Level 3 Commercial Level 3 ≤ 500’000 AED Technical Level 2 Commercial Level 2 > 500’000 AED& CC Technical Level 1 Commercial Level 1
  • 8. January 29, 2015 Third Party Material Procurement Overview NH  Approval by commercial signatory  Approval by technical signatory  Procurement Pool (5) Subject Operator Sending Purchase Order Procurement Controller (Manual) Receiving notification from SharePoint: PO is signed. 1. Check Signatures 2. Prepare e-mail to current supplier - Addressee: TO: Supplier CC: Logistic, Procurement Team, (for critical deliveries/works, quality management) - Attachments: - PO - New Code Of Conduct - Standard T&C_UAE_Dec2014 - Text 3. Update SharePoint - Proc Actions - PO sent to the supplier date 4. Upload sent e-mail to SharePoint, via “PO Link”, “View PO” Text example “email to supplier”: Good evening , Please find attached Purchase Orders for your immediate processing. Kindly acknowledge the receipt of the same & advice the delivery date. Thanks & Best regards Nils Hass Procurement Team IC Building Technologies SIEMENS LLC 9/F, The Galleries - Building 2 Downtown Jebel Ali P.O. Box 2154 Dubai, United Arab Emirates Screenshot SAP: Update SharePoint Screenshot SAP: Uploading sent emails  Order Confirmation (Supplier) PO sent to the supplier by Procurement Controller (involve quality department for critical deliveries/works)
  • 9. January 29, 2015 Third Party Material Procurement Overview NH (6) Subject Operator Order Confirmation Procurement Controller (Manual) 1. Received OC - sent e-mail to logistic in case they are not in the CC 2. Upload OC to SharePoint via “PO Acknolegment Link”, “View OA” After 3 days, send reminder with ultimatum or call supplier Screenshot SAP: Uploading Order Confirmation  Logistic takes over (7) Subject Operator GRN Logistic Team The acceptances of the delivery and the receipt goods or services (GR) are to be carried out by the Logistic Team. To process GRN, the acceptance of the goods or services must be validated by the original requestor (stamping / signature of invoices)  Delivery done OC Order Confirmation received in 3 days Logistic takes over
  • 10. January 29, 2015 Third Party Material Procurement Overview NH Attachment 1.1: Standard Material Requisition Template
  • 11. January 29, 2015 Third Party Material Procurement Overview NH Attachment 1.2: BID Tab BID Tabulation ESN Code S.No. Unit / Qty. Supplier 1 Supplier 2 Supplier 3 Supplier 4 Unit / Qty. 1 1.00 2 3 4 5 6 7 0 0 0 0 0 0 0 0 0 0 0 0 0 S.No. Response Response Response Response Response 1 2 3 4 5 6 7 8 9 10 11 12 13 14 PROCUREME NT MGR TECH DIRECTOR Tech. Director Exhange Rates 1 Eur = 4.76 AED AED 1 GBP = 5.88 AED AED 1 USD = 3.68 AED AED Negotiations Description Warranty Delivery Time in weeks Signed Code of Conduct, NDA & CR Second Round Discount Third Round Discount Budget CNI (AED)/Nett Savings First Discounted Offer REMARKS : As per Selection Criteria The Bid tab is issued for the issuance of LOA, all MR1 and MR2 criteria to be fulfilled prior to issuance of Purchase Order. Selected Supplier : c4s easy registration DAMEX, BPC check Suppleir Approved with Client Selection Criteria : ISO 9001 or equivalent certified Manufacturing Country (GVS) PROJECT MGR Supplier Audit Supplier from FPL COMM DIRECTOR COMMERCIAL MGR Risk Evaluation Quote Comp. on ToCo GVS Challenger Frame Agreement MR2 Criteria Project Name Description Customs Duty ( If applicable) Total Cost of Ownershiop ( ToCo) Project Description Transport Installation CRSA for high risk country DOR ISO or equivalent certifications Validity of offer Sub Total: Performance Bank Guarantee Terms of Payment Delivery Basis Local Agent/Representative Manufacture & Country of Origin Commercial Compliance on complete Terms and Conditions Technical Compliance on submitted documents Code of Conduct, NDA & CR MR1 Criteria Liquidated Damages
  • 12. January 29, 2015 Third Party Material Procurement Overview NH Attachment 1.3: SSJ Single Source Justification Building Technologies, LGR SCM-BT Date Dept Location File references Proposed Supplier Description of product/services: Order value : Project Name (if applicable): Reasons for not following 3 quotes / tender process Quotation received from Supplier known to have required unique capability, proprietary products or other intellectual property rights. Insufficient time to obtain three written quotes. (Unforeseeable) The need for security restricts the number of Suppliers selected to quote. External customer specified Item/Service is required to be compatible with installed equipment. Supplementary or additional to previous competitively sourced requirement Date of last sourcing : No responses obtained from other invited suppliers Framework Supplier / Preferred Supplier agreement in place One-off advantageous opportunity for short lenght of time Note: Please provide supporting documents wherever applicable (for e.g, document proof showing that Customer has specified the product/ supplier) Remarks/ Comments Measures taken to mitigate risk Please describe measures taken to ensure sole supplier source is comforming to market conditions (such as : benchmark, cost calculation, other quotes, comparison with references, with existing price, …) Recommendation agreed by Project Mgr Name Signature Commerical Head Name Signature Procurement / Supply Chain Mgr Name Signature Requested by
  • 13. January 29, 2015 Third Party Material Procurement Overview NH Attachment 3.1: Create New Material in MM in Sales Org 2513 NoMaterialNameMaterialTypePlant Distr. Channel Unitof Measure Material Group Business Unit ProductHierarchyProfitCenter Purchasing Group ValuationClass Price AED SalesText ECCN CODES DEUSHSCode 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 PreparedBy:Tel:Date:Signature tobesendtoMsRathiManjunath CreateNewMaterialinMMinSalesOrg2513
  • 14. January 29, 2015 Third Party Material Procurement Overview NH Attachment 3.2: Request for product specific data (1) Template for Supplier Declaration Form (Use letter layout for external correspondence) Request for product specific data Ladies and Gentlemen, . In order to comply with foreign trade and customs legislation we require various product-specific details for the products you sell. Could you please therefore let us know  The classification according to the U.S. Export Administration Regulations the case of US products (ECCN according to the U.S. Commerce Control List)  The HS code  The country of consignment/origin (LKZ) of the goods requested/ordered Without this information it is not possible to ensure full compliance with the relevant legal requirements. The information forms part of the commercial terms. Please enter the code in the boxes provided for each item specified (see enclosure). Please return the completed list to the ( ) address ( ) fax number ( ) e-mail address shown in the header. Many thanks. .............................................................................. Signature, company stamp
  • 15. January 29, 2015 Third Party Material Procurement Overview NH Attachment 3.2: Request for product specific data (2) Siemens LLC Address of supplier: Supplier number: Transaction/order No.: Item Productdescription Product code Supplier Internal Siemens No. HS Code or statistical commodity code (8 digits) ECCN as per U.S. CCL * 1 Country of origin(country code * 2 ) 1 2 (Please use additional sheet if required) In case above table is empty, we confirm the following regarding the items supplied by us to Siemens. 1. contains US origin, (Yes / No) or 2. any visible indication that item contains US hardware e.g. label „made in USA“ on product or attending papers; (Yes / No) or 3. any functional indication, insinuating to US content, e.g. US operation software, US application software, etc. (Yes / No) or 4. item purchased from a US company or US affiliated company? (Yes / No) * 1) Details  If the product is not subject to U.S. Export Administration Regulations (not a U.S. product / no U.S. content / no U.S. manufacture under license) = No  If the product is subject to U.S. Export Administration Regulations = Specify the relevant ECCN (Export Control Classification Number if possible, with sub-number (Example: 5D992b2)) *2) Country of origin (ISO Alpha2 Code – Example Germany=DE) Company stamp, signature: ....................................................... Place Date Request form for export data, Date:
  • 16. January 29, 2015 Third Party Material Procurement Overview NH Attachment 4.1: PO example (1)
  • 17. January 29, 2015 Third Party Material Procurement Overview NH Attachment 4.1: PO example (2)
  • 18. January 29, 2015 Third Party Material Procurement Overview NH Attachment 4.1: PO example (3)