THE CONSTRUCTION LABOUR SHORTAGE IN JOHOR BAHRU,
MALAYSIA
Abdul Rahim Abdul Hamid1
, Bachan Singh Besawa Jagar Singh 2
, Muhammad Shahrom Mazlan3
1,2
Senior Lecturer, 3
Project Engineer, Department of Structures and Materials, Faculty of Civil Engineering, Universiti
Teknologi Malaysia, 81310 UTM Johor Bahru, Johor Darul Ta’zim, Malaysia.
rahimfka@gmail.com, bachan19@yahoo.com, matshah_125@yahoo.com.my
Abstract
Construction industry is one of the sectors that require the Labor intensive to fulfill the work site. However, we always hear the
problems related to the shortage of the construction workers. Therefore, the purpose of this study are to estimate the current shortage
composition of construction labor, to evaluate the problem faced by contractor when hired labor, to examine contractor method of
acquiring construction labor, and to investigate the strategies taken by contractor to overcome shortage of labor. The questionnaire
will be distributed to the 35 of construction site which targeting project representative that involved with construction site in Johor
Bahru district, Malaysia, in order to obtain their feedback related to this topic. The Johor Bahru district is located in the southern
part of Johor in the Malay Peninsula, separated from Singapore by Straits of Johor. The district covers an area of 1,871 km² and has
a population of over 2 million. The data will be analyzed using SPSS 16 in order to obtain average index, frequencies and percentage
calculation. The result obtained from analysis will be represent in data table, bar and pie chart. The result of this study indicates that
the current shortage and demand of the current construction are about 12.14% from the total labor workforce which is about 360
workers for 35 projects sites.
Keywords: Construction, Foreign Workers, Shortage, Strategies
----------------------------------------------------------------------***------------------------------------------------------------------------
1. INTRODUCTION
The construction industry is among the most important
industries in the country that closely related to other economic
sectors. It is the capital goods industry to provide
infrastructure for other industries operation. The construction
industry also is a sector becomes the engine of economic
growth and most resources are used for national development
(Zakaria, M.Y, 2006)[1]. The construction project depends on
project resources. Among the most important resources is the
source of workers. Shortage of labor resources in Malaysia
resulting, the country depends on the labor workforce from
outside, especially from Indonesia [2, 3]. Scenarios for the
recruitment of foreign workers in the construction sector in
Malaysia not a new issue. Malaysia has started taking foreign
workers since the reign of the British. Malaysia is the biggest
net importer of labor in Asia with a migrant labor force of
around 2 million (21 percent of 9.5 million of the total work
force) as of 2010 (Migration News, 2011)[4]. Construction
was among the sectors which came to rely heavily on foreign
workers owing to a confluence of factors: Malaysian youth’s
aversion to low status work, an expanding manufacturing
sector which was offering much better employment
conditions, labor attrition, widening opportunities for tertiary
education, a lower birth rate and the emigration of Malaysian
workers to high-wage countries such as Japan and Singapore
(Abdul-Aziz, 1995)[5,6]. Datuk Ir. Hamzah Hasan, Chief
Executive, CIDB revealed that there are about 300,000 legal
foreign construction workers in addition to 391,006 local
workforce (43% of the total construction workers)( Malaysian
Construction Summit 2008)[7].
From the statistic show that the foreign workers involved in
construction sector is around 361,000 workers. From the
study conducted by CIDB about the status construction
workers and local which covered the skilled workers, semi
skilled workers and unskilled workers at construction site,
revealed that 52% (361,000 workers) are from foreigner
workers contributing to total workforce construction industry,
while 48% (333,000 workers) are local workers (CIDB &
CREAM, 2010)[8]. From the total foreign construction
workers (361,000 workers), (59%) from Indonesia, (13%)
Bangladesh and (28%) are from others country Nepal,
Myammar, India, Vietnam and Sri Langka. Through the study,
the more foreign workers employed in the private projects,
compared with projects under government tender.
2. LITERATURE REVIEW
The project under 10th
Malaysian Plan (10 MP) and Economic
Transformation Programmed including Mass Rapid Transit
(MRT) which costing over RM40 billion with required about
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 02 Issue: 10 | Oct-2013, Available @ http://www.ijret.org 509
130,000 construction skilled workers of various manpower of
various trade both local and foreign workers to ensure
successful completion (CIDB News, 2011)[9].The Malaysian
construction industry has been experiencing a critical shortage
of workforce. Nowadays the local workers unable to fulfill the
demand of construction market from time being. This reason
caused the contractor willing to import foreign workers from
outside to meet the needs and requirement labor market in
construction sector. According to Kwan Foh Kwai the
President of MBAM (Master Builder Association of Malaysia)
mentioned that, shortage of skilled construction workers is
very crucial issues in construction industry (MBAM Online
News)[10]. Besides that, MBAM also stated that, the acute
shortage of skilled workers in the construction industry will
give negative impact towards the projects under Malaysian
Plan (10MP) and Economic Transformation Programmed (The
Star Online) [11].
Current topical issues relevant to the Malaysia construction
industry are the quality of workmanship. According to
REHDA (Real Estate Housing Developers’ Association
Malaysia quality of product including housing and building
are related directly to manpower and skilled. It seems that the
construction workers is failed to attract workers in skilled and
semi-skilled trades. The 3D perception has discouraged skilled
local workers in joining, resulting in a lot of job being
executed by the untrained construction workers. The important
issue from REHDA stated that, the skilled labor shortage is the
one of factor contributing of the increasing property price (The
Stars Newspaper, 2011)[12].
The aim of this master project is to study the current
construction labor shortage at construction projects in the
district of Johor Baharu, Malaysia. In order to achieve this
aim, four objectives are developed. The objectives are as
follow to estimate the current labor shortage at construction
sites, to evaluate the problem faced by contractor when hired
labor, to examine contractor method of acquiring construction
labor and to investigate the strategies taken by contractor to
overcome shortage of labor.
3. METHODOLOGY
The main reason of the study is to fulfill earlier stated
objectives though the collection of data using survey
questionnaire forms. The methodology is set in order to gather
the data to achieved the outlined of objectives.
The first step of study is to rationalize the issue to set up the
topic of study. After that the statement of problems, aims and
objectives were developed. This study required several
methods of data collections for the purpose of objectives
achievements. For the knowledge improvement phase, the
literature review is carried out. The literature sources that
connection with study including journal, books, conference
papers, magazines and websites will be used in the literature
review part. From that information, a set of questionnaire form
that related to objectives will be developed. The question that
develops in the questionnaire was in the form of multiple
choice or open ended questions or Likert Scale. The
respondents are among the contractors parties that involved in
construction projects. The result obtained from questionnaire
will be represent in data table, bar and pie chart, and radar
plot. The data will be analyzed using statistical method that is
mean or average index, frequencies and percentage
calculation. The final phase of this study is to define the
conclusion and recommendation with reference to the
objective, subsequent to the analysis from the questionnaire.
The feedbacks provided by respondents are categorized into
five options, Strongly Agree, Agree, Moderate/slightly agree,
Disagree and Strongly Agree[13]. The Multiple-choice
questions require the anticipation of the whole range of likely
answers, which would be given, and formulating the options.
The multiple-choice questions are based on Likert scale of five
ordinal measures of agreement towards each statement (from 1
to 5).
4. RESULTS AND DISCUSSIONS
This study was conducted to study current construction labor
shortage at construction projects in Johor Baharu. This chapter
will discussed the analysis data of questionnaire that were
obtain from respondent which is consist project representative
that is project manager from the 35 construction sites in
Johore Bahru.
The data analysis section is divided into four part according
objectives. For the first objective that consists of demographic
background or data which is consist of the number of shortage
of workers in 35 construction sites. Meanwhile, for the others
objective consist of Likert scale analysis consists of questions
regarding to the problems facing by contractor when hired
labor, contractor method of acquiring construction labor and
the strategies taken by contractor to overcome shortage of
labor.
4.1 Objective 1
Table 1 tabulates the current shortage of 35 construction
project in area Johor Bahru. From the table indicates the
shortages among project site survey are range from 4.17%
until 44.44%.Besides that, the percentage shortage for overall
project is about 12.14% which is about 360 workers from the
total existing labor workforce.
Beside that Chart 1 represent shortage of labor by category of
labor. From the 360 numbers of workers shortage, the
contractors needs 54% of skilled workers, 28% semi skilled
and 18% unskilled workers in their construction projects.
Others than that, from 360 workers, the contractors more
considers to hired 80% of foreign construction workers and
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 02 Issue: 10 | Oct-2013, Available @ http://www.ijret.org 510
only 20% of local workforces. The types of labor are
illustrated in the Chart 2.
Table - 1: Current Shortage of workers for Overall Project
Chart - 1: Shortage by Category of Labor
Chart - 2: Shortage by Type of Labor
4.2 Objective 2
The data analysis for the research objective no 2 which is
“Evaluating Problem Faced by Contractor When Hired
Labor”, were conducted to evaluated the common problem
faced by contractor when hired labor workforce. The research
question/objective is represented by 12 items. The attainment
for this section is by questionnaire survey. The research result
findings are shown in Chart 3 and Table 2 as follow.
Chart - 3: Mean/Average Index and Problem Facing by
Contractor when Hired Labor
Table – 2: Classification of Problem Face by Contractor
Chart 3 represent bar chart mean/average index on the
problem facing by contractor start from item problem no 1
until problem no 12. From the chart show that the highest
index is belonging to item problem no 5 which is problem on
recruitment and delivery cost of labor. While the smallest
mean index is on problem Registration with job Malaysia
agency that is 3.71 averages/ means index. The higher value
represent the priority or critical of that problem and vice versa.
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 02 Issue: 10 | Oct-2013, Available @ http://www.ijret.org 511
4.3 Objective 3
The data analysis of the objective number 3 which is
“Examine Contractor Method of Acquiring Construction
Labor”, were conducted to confirm what the common
contractor method of acquiring construction labor. The
research objective is represented by 7 items. The attainment
for this section is by questionnaire survey. The research result
findings are shown in Chart 4 and Table 3 as follow.
Chart - 4: Mean/Average Index and Contractor Method
Acquiring Construction Labor
Table - 3: Code for Contractor Method in Acquiring
Construction Labor
Chart 4 illustrated bar chart of the mean/average index on
contractor method acquiring construction labor start from item
method no 1 until method no 12. From the chart above
describing that the highest index is subjected towards item
method no 2 which is acquiring labor through subcontractors
and average mean index is 4.23. Whereas the smallest mean
index is reflected on method by applies from department of
labor forces that is 3.34 averages/ means index. The higher
value represents the popular or common method used by
contractors while the smallest values indicate the less popular
method applies by contractor in acquiring the labor
workforces.
4.4 Objective 4
The data analysis for the objective number 4 which is
“Strategies Taken by Contractors to Overcome Shortage of
Labor”, were conducted to investigate what the common
approach taken by contractors to overcome shortage of labors.
The research objective is represented by 10 items. The
attainment for this section is by questionnaire survey. The
research result findings are shown in Chart 5 and Table 4 as
follow.
Chart - 5: Mean/Average Index of Strategies Taken by
Contractor to Overcome Shortage of Labor
Table – 4: Code for Strategies Taken by Contractor
Chart 5 tabulated bar chart of the mean/average index on
strategies taken by contractor to overcome shortage of labor
start from item strategies no 1 until strategies no 10. From the
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 02 Issue: 10 | Oct-2013, Available @ http://www.ijret.org 512
chart above describing that the highest index is subjected
towards item strategy item no 9 which is maximize/fully
optimize used of labors available while the average mean
index is 4.23. Whereas the smallest mean index is reflected on
strategy by introduce multiple shifts work system that is 3.2
averages/ means index. The higher value represents the
popular or common strategy applied by contractors while the
smallest values indicate the less popular strategy applies by
contractor in to overcome shortage of the labor workforces.
CONCLUSIONS
From the result analysis and discussion, some of conclusion
can be came out based on objectives of this study as follow the
first objectives were to study the current shortage composition
of construction labor. From the data analysis the current
shortage composition for every project site surveyed is range
from 4.17% until 44.44%. Others than that, for overall project
on the average is about 12.14% from total labor workforces.
The second objective was to evaluate the problem faced by
contractor when hired labor. From the findings the
average/min index of problem face by contractor were ranging
from 3.71-4.29. Therefore as conclusion the critical problem
facing by contractors when hired labor is recruitment and
delivery cost of labor. The third objective is to examine
contractor method of acquiring construction labor. From the
analysis indicates the average/min index of contractor method
of acquiring construction labor was ranging from 3.34-4.23.
Therefore as conclusion the common practice contractor
method of acquiring construction labors is through
subcontractor’s method The final objective is to investigate
the strategies taken by contractor to overcome shortage of
labor. From the analysis highlighted the average/min index
strategies taken by contractor to overcome shortage was
ranging from 3.20-4.23. Therefore as conclusion the popular
strategy practice by contractor to overcome shortage of labors
is fully maximized or optimized used of labors available in
construction projects.
ACKNOWLEDGEMENTS
We would like to thank our sponsor, Ministry of Higher
Education (MOHE) and Universiti Teknologi Malaysia
(UTM) for the financial support of Research University Grant
(Vote No. Q.J130000.7122.03J11) which enable us to carry
out this research project Thank you also to UTM Research
Management Centre (RMC) and those who had contributed
towards the completion of this research.
REFERENCES
[1] Zakaria, M.Y (2006) “Challenges in Providing Local
Skilled Construction Workers” Universiti Teknologi Malaysia.
[2] Berita Harian “ABM Help in Reducing Dependance on
foreign Workers” by Aivizanoorwani Shah Shahroni on 8th
July 2010
[3] Bernama, (2011) “Reduction of Foreign Workers
Dependency Through IBS” website www.Bernama.com
[4] Migration News online (2 April 2011) “Southern Asia”
logged www.migration.ucdavyis.edu.my asscess on 26 July
2011.
[5] Abdul Aziz (1995). Foreign Labour in the Malaysian
Construction Industry (Geneva, International Labour Office.
[6] The Malaysian Insider online “Foreign Workers Levy Hike
in 2011” 20th
May 2010 by Asrul Hadi Abdullah Sani, logged
on www.malaysianinsider.com
[7] Malaysian Construction Summit 2008 – 6th June 2008,
Paper presented by Datuk Ir. Hamzah Hasan, Chief Executive,
CIDB.
[8] CIDB & Cream (2010), “Latest Research on Construction
Foreign Workers 2010” can be access though
http://ibsresearch.blogspot.com/2010/09/kajian-status-terkini-
perkerja-asing-di.html
[9] CIDB News, (2011). “Moving Forward” by Sazali Che
mat.
[10] MBAM Online News “Skilled Manpower Shortage Need
Urgent Attention” by Siti Sakinah Abdul Latiff on 4 august
2010, can be acess on www.MBAM.org.my
[11] The Star Online “Workers Shortage Could Hit ETP Plan”
by Wong Pek Mei on 16 march 2011, can be access in
www.Thestar.my
[12] The Star Newspaper on Star Biz Week “Your 10
Questions with Datuk Seri Michael Yam REHDA President”.
25 June 2011
[13] Abd. Majid M.Z. and Ronald McCaffer, M.ASCE
(1997), .Factors of Non Excusable Delays That Influence
Contractor’s Performance., Journal of Construction
Engineering and Management, ASCE
BIOGRAPHIES
Abdul Rahim Abdul Hamid is a Senior
Lecturer in Department of Structures and
Materials, Faculty of Civil Engineering at
Universiti Teknologi Malaysia, Skudai
Johor, Malaysia since 1994. He holds a
Master in Construction Engineering and BSc.
in Civil Engineering Washington University, USA
Bachan Singh a/l Besawa Jagar Singh is a
Senior Lecturer in Department of Structures
and Materials, Faculty of Civil Engineering
at Universiti Teknologi Malaysia, Skudai
Johor, Malaysia.
Muhammad Shahrom Mazlan is a Project
Engineer working with a Piling Company.
He was a post-graduate student of
Construction Management in Faculty of
Civil Engineering at Universiti Teknologi
Malaysia, Skudai Johor, Malaysia.

More Related Content

What's hot

Klibel5 bus 23
Klibel5 bus 23Klibel5 bus 23
Klibel5 bus 23
KLIBEL
 
Klibel5 acc 38_
Klibel5 acc 38_Klibel5 acc 38_
Klibel5 acc 38_
KLIBEL
 
Klibel5 econ 22_
Klibel5 econ 22_Klibel5 econ 22_
Klibel5 econ 22_
KLIBEL
 
Klibel5 bus 42
Klibel5 bus 42Klibel5 bus 42
Klibel5 bus 42
KLIBEL
 
Klibel5 acc 36_
Klibel5 acc 36_Klibel5 acc 36_
Klibel5 acc 36_
KLIBEL
 
Klibel5 bus 19
Klibel5 bus 19Klibel5 bus 19
Klibel5 bus 19
KLIBEL
 
Klibel5 acc 37_
Klibel5 acc 37_Klibel5 acc 37_
Klibel5 acc 37_
KLIBEL
 
The Effects of Organizational Changes Towards Students' Emotion
The Effects of Organizational Changes Towards Students' EmotionThe Effects of Organizational Changes Towards Students' Emotion
The Effects of Organizational Changes Towards Students' Emotion
Nada Rahmah Majied
 
Klibel5 bus 44
Klibel5 bus 44Klibel5 bus 44
Klibel5 bus 44
KLIBEL
 
Klibel5 bus 37
Klibel5 bus 37Klibel5 bus 37
Klibel5 bus 37
KLIBEL
 
The causality relationship between management in supply chain collaboration w...
The causality relationship between management in supply chain collaboration w...The causality relationship between management in supply chain collaboration w...
The causality relationship between management in supply chain collaboration w...
Alexander Decker
 
WHY KNOWLEDGE MANAGEMENT SYSTEM FAILED by DANIEL DONI SUNDJOJO
WHY KNOWLEDGE MANAGEMENT SYSTEM FAILED by DANIEL DONI SUNDJOJOWHY KNOWLEDGE MANAGEMENT SYSTEM FAILED by DANIEL DONI SUNDJOJO
WHY KNOWLEDGE MANAGEMENT SYSTEM FAILED by DANIEL DONI SUNDJOJODaniel Doni
 
Klibel5 bus 15
Klibel5 bus 15Klibel5 bus 15
Klibel5 bus 15
KLIBEL
 
Klibel5 acc 53_
Klibel5 acc 53_Klibel5 acc 53_
Klibel5 acc 53_
KLIBEL
 
A410106
A410106A410106
A410106
aijbm
 
B421220
B421220B421220
B421220
aijbm
 
The Effect of Non-Statutory Welfare Schemes on the Motivation Levels of Non-A...
The Effect of Non-Statutory Welfare Schemes on the Motivation Levels of Non-A...The Effect of Non-Statutory Welfare Schemes on the Motivation Levels of Non-A...
The Effect of Non-Statutory Welfare Schemes on the Motivation Levels of Non-A...
International Journal of Business Marketing and Management (IJBMM)
 
Impact of capacity building & employee
Impact of capacity building & employeeImpact of capacity building & employee
Impact of capacity building & employeeprjpublications
 
The influence of information technology capability, organizational learning, ...
The influence of information technology capability, organizational learning, ...The influence of information technology capability, organizational learning, ...
The influence of information technology capability, organizational learning, ...
Alexander Decker
 
B460817.pdf
B460817.pdfB460817.pdf
B460817.pdf
aijbm
 

What's hot (20)

Klibel5 bus 23
Klibel5 bus 23Klibel5 bus 23
Klibel5 bus 23
 
Klibel5 acc 38_
Klibel5 acc 38_Klibel5 acc 38_
Klibel5 acc 38_
 
Klibel5 econ 22_
Klibel5 econ 22_Klibel5 econ 22_
Klibel5 econ 22_
 
Klibel5 bus 42
Klibel5 bus 42Klibel5 bus 42
Klibel5 bus 42
 
Klibel5 acc 36_
Klibel5 acc 36_Klibel5 acc 36_
Klibel5 acc 36_
 
Klibel5 bus 19
Klibel5 bus 19Klibel5 bus 19
Klibel5 bus 19
 
Klibel5 acc 37_
Klibel5 acc 37_Klibel5 acc 37_
Klibel5 acc 37_
 
The Effects of Organizational Changes Towards Students' Emotion
The Effects of Organizational Changes Towards Students' EmotionThe Effects of Organizational Changes Towards Students' Emotion
The Effects of Organizational Changes Towards Students' Emotion
 
Klibel5 bus 44
Klibel5 bus 44Klibel5 bus 44
Klibel5 bus 44
 
Klibel5 bus 37
Klibel5 bus 37Klibel5 bus 37
Klibel5 bus 37
 
The causality relationship between management in supply chain collaboration w...
The causality relationship between management in supply chain collaboration w...The causality relationship between management in supply chain collaboration w...
The causality relationship between management in supply chain collaboration w...
 
WHY KNOWLEDGE MANAGEMENT SYSTEM FAILED by DANIEL DONI SUNDJOJO
WHY KNOWLEDGE MANAGEMENT SYSTEM FAILED by DANIEL DONI SUNDJOJOWHY KNOWLEDGE MANAGEMENT SYSTEM FAILED by DANIEL DONI SUNDJOJO
WHY KNOWLEDGE MANAGEMENT SYSTEM FAILED by DANIEL DONI SUNDJOJO
 
Klibel5 bus 15
Klibel5 bus 15Klibel5 bus 15
Klibel5 bus 15
 
Klibel5 acc 53_
Klibel5 acc 53_Klibel5 acc 53_
Klibel5 acc 53_
 
A410106
A410106A410106
A410106
 
B421220
B421220B421220
B421220
 
The Effect of Non-Statutory Welfare Schemes on the Motivation Levels of Non-A...
The Effect of Non-Statutory Welfare Schemes on the Motivation Levels of Non-A...The Effect of Non-Statutory Welfare Schemes on the Motivation Levels of Non-A...
The Effect of Non-Statutory Welfare Schemes on the Motivation Levels of Non-A...
 
Impact of capacity building & employee
Impact of capacity building & employeeImpact of capacity building & employee
Impact of capacity building & employee
 
The influence of information technology capability, organizational learning, ...
The influence of information technology capability, organizational learning, ...The influence of information technology capability, organizational learning, ...
The influence of information technology capability, organizational learning, ...
 
B460817.pdf
B460817.pdfB460817.pdf
B460817.pdf
 

Viewers also liked

foreign workers in Malaysia
foreign workers in Malaysiaforeign workers in Malaysia
foreign workers in Malaysia
Zakinan Nawaz
 
Malaysian property market
Malaysian property marketMalaysian property market
Malaysian property market
OneStop Idea
 
Study of bad block management and wear leveling in
Study of bad block management and wear leveling inStudy of bad block management and wear leveling in
Study of bad block management and wear leveling in
eSAT Publishing House
 
“Remedies over the obstacles in implementing automation in indian infrastruct...
“Remedies over the obstacles in implementing automation in indian infrastruct...“Remedies over the obstacles in implementing automation in indian infrastruct...
“Remedies over the obstacles in implementing automation in indian infrastruct...
eSAT Publishing House
 
Stability and surface free energy analysis of a liquid drop on a horizontal c...
Stability and surface free energy analysis of a liquid drop on a horizontal c...Stability and surface free energy analysis of a liquid drop on a horizontal c...
Stability and surface free energy analysis of a liquid drop on a horizontal c...
eSAT Publishing House
 
A novel tool for stereo matching of images
A novel tool for stereo matching of imagesA novel tool for stereo matching of images
A novel tool for stereo matching of imageseSAT Publishing House
 
An innovative way for computerized smith chart generation and transmission li...
An innovative way for computerized smith chart generation and transmission li...An innovative way for computerized smith chart generation and transmission li...
An innovative way for computerized smith chart generation and transmission li...
eSAT Publishing House
 
Quality of service (qos) in wi max
Quality of service (qos) in wi maxQuality of service (qos) in wi max
Quality of service (qos) in wi max
eSAT Publishing House
 
Mathematical model for an area source and the point
Mathematical model for an area source and the pointMathematical model for an area source and the point
Mathematical model for an area source and the point
eSAT Publishing House
 
Online social network mining current trends and research issues
Online social network mining current trends and research issuesOnline social network mining current trends and research issues
Online social network mining current trends and research issues
eSAT Publishing House
 
Blood flow through stenosed inclined tubes with
Blood flow through stenosed inclined tubes withBlood flow through stenosed inclined tubes with
Blood flow through stenosed inclined tubes with
eSAT Publishing House
 
Enhancement of power quality by unified power quality conditioner with fuzzy ...
Enhancement of power quality by unified power quality conditioner with fuzzy ...Enhancement of power quality by unified power quality conditioner with fuzzy ...
Enhancement of power quality by unified power quality conditioner with fuzzy ...
eSAT Publishing House
 
Detection of chlorpyrifos pesticide in various water
Detection of chlorpyrifos pesticide in various waterDetection of chlorpyrifos pesticide in various water
Detection of chlorpyrifos pesticide in various water
eSAT Publishing House
 
Effect of fiber distance on various sac ocdma detection techniques
Effect of fiber distance on various sac ocdma detection techniquesEffect of fiber distance on various sac ocdma detection techniques
Effect of fiber distance on various sac ocdma detection techniques
eSAT Publishing House
 
Analysis of zone routing protocol in manet
Analysis of zone routing protocol in manetAnalysis of zone routing protocol in manet
Analysis of zone routing protocol in manet
eSAT Publishing House
 
Analysis of grading techniques in xlpe cable insulation by fem
Analysis of grading techniques in xlpe cable insulation by femAnalysis of grading techniques in xlpe cable insulation by fem
Analysis of grading techniques in xlpe cable insulation by fem
eSAT Publishing House
 
Design features of a 5 tonne day multi – stage, intermittent drainage, conti...
Design features of a 5 tonne  day multi – stage, intermittent drainage, conti...Design features of a 5 tonne  day multi – stage, intermittent drainage, conti...
Design features of a 5 tonne day multi – stage, intermittent drainage, conti...
eSAT Publishing House
 
Behaviour of mine waste as reinforced soil
Behaviour of mine waste as reinforced soilBehaviour of mine waste as reinforced soil
Behaviour of mine waste as reinforced soil
eSAT Publishing House
 
An overview on data mining designed for imbalanced datasets
An overview on data mining designed for imbalanced datasetsAn overview on data mining designed for imbalanced datasets
An overview on data mining designed for imbalanced datasets
eSAT Publishing House
 
Emergency preparedness plan in educational institution
Emergency preparedness plan in educational institutionEmergency preparedness plan in educational institution
Emergency preparedness plan in educational institution
eSAT Publishing House
 

Viewers also liked (20)

foreign workers in Malaysia
foreign workers in Malaysiaforeign workers in Malaysia
foreign workers in Malaysia
 
Malaysian property market
Malaysian property marketMalaysian property market
Malaysian property market
 
Study of bad block management and wear leveling in
Study of bad block management and wear leveling inStudy of bad block management and wear leveling in
Study of bad block management and wear leveling in
 
“Remedies over the obstacles in implementing automation in indian infrastruct...
“Remedies over the obstacles in implementing automation in indian infrastruct...“Remedies over the obstacles in implementing automation in indian infrastruct...
“Remedies over the obstacles in implementing automation in indian infrastruct...
 
Stability and surface free energy analysis of a liquid drop on a horizontal c...
Stability and surface free energy analysis of a liquid drop on a horizontal c...Stability and surface free energy analysis of a liquid drop on a horizontal c...
Stability and surface free energy analysis of a liquid drop on a horizontal c...
 
A novel tool for stereo matching of images
A novel tool for stereo matching of imagesA novel tool for stereo matching of images
A novel tool for stereo matching of images
 
An innovative way for computerized smith chart generation and transmission li...
An innovative way for computerized smith chart generation and transmission li...An innovative way for computerized smith chart generation and transmission li...
An innovative way for computerized smith chart generation and transmission li...
 
Quality of service (qos) in wi max
Quality of service (qos) in wi maxQuality of service (qos) in wi max
Quality of service (qos) in wi max
 
Mathematical model for an area source and the point
Mathematical model for an area source and the pointMathematical model for an area source and the point
Mathematical model for an area source and the point
 
Online social network mining current trends and research issues
Online social network mining current trends and research issuesOnline social network mining current trends and research issues
Online social network mining current trends and research issues
 
Blood flow through stenosed inclined tubes with
Blood flow through stenosed inclined tubes withBlood flow through stenosed inclined tubes with
Blood flow through stenosed inclined tubes with
 
Enhancement of power quality by unified power quality conditioner with fuzzy ...
Enhancement of power quality by unified power quality conditioner with fuzzy ...Enhancement of power quality by unified power quality conditioner with fuzzy ...
Enhancement of power quality by unified power quality conditioner with fuzzy ...
 
Detection of chlorpyrifos pesticide in various water
Detection of chlorpyrifos pesticide in various waterDetection of chlorpyrifos pesticide in various water
Detection of chlorpyrifos pesticide in various water
 
Effect of fiber distance on various sac ocdma detection techniques
Effect of fiber distance on various sac ocdma detection techniquesEffect of fiber distance on various sac ocdma detection techniques
Effect of fiber distance on various sac ocdma detection techniques
 
Analysis of zone routing protocol in manet
Analysis of zone routing protocol in manetAnalysis of zone routing protocol in manet
Analysis of zone routing protocol in manet
 
Analysis of grading techniques in xlpe cable insulation by fem
Analysis of grading techniques in xlpe cable insulation by femAnalysis of grading techniques in xlpe cable insulation by fem
Analysis of grading techniques in xlpe cable insulation by fem
 
Design features of a 5 tonne day multi – stage, intermittent drainage, conti...
Design features of a 5 tonne  day multi – stage, intermittent drainage, conti...Design features of a 5 tonne  day multi – stage, intermittent drainage, conti...
Design features of a 5 tonne day multi – stage, intermittent drainage, conti...
 
Behaviour of mine waste as reinforced soil
Behaviour of mine waste as reinforced soilBehaviour of mine waste as reinforced soil
Behaviour of mine waste as reinforced soil
 
An overview on data mining designed for imbalanced datasets
An overview on data mining designed for imbalanced datasetsAn overview on data mining designed for imbalanced datasets
An overview on data mining designed for imbalanced datasets
 
Emergency preparedness plan in educational institution
Emergency preparedness plan in educational institutionEmergency preparedness plan in educational institution
Emergency preparedness plan in educational institution
 

Similar to The construction labour shortage in johor bahru,

The measurement model for outsourcing worker
The measurement model for outsourcing workerThe measurement model for outsourcing worker
The measurement model for outsourcing worker
eSAT Publishing House
 
The measurement model for outsourcing worker performance by middle and big cl...
The measurement model for outsourcing worker performance by middle and big cl...The measurement model for outsourcing worker performance by middle and big cl...
The measurement model for outsourcing worker performance by middle and big cl...
eSAT Journals
 
A STUDY ON THE APPLICABILITY OF QUALITY CIRCLES TO CONSTRUCTION PROJECTS
A STUDY ON THE APPLICABILITY OF QUALITY CIRCLES TO CONSTRUCTION PROJECTSA STUDY ON THE APPLICABILITY OF QUALITY CIRCLES TO CONSTRUCTION PROJECTS
A STUDY ON THE APPLICABILITY OF QUALITY CIRCLES TO CONSTRUCTION PROJECTS
Amy Roman
 
A study on the applicability of quality circles to construction projects
A study on the applicability of quality circles to construction projectsA study on the applicability of quality circles to construction projects
A study on the applicability of quality circles to construction projects
eSAT Journals
 
A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...
eSAT Journals
 
Improvement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal regionImprovement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal region
eSAT Publishing House
 
Improvement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal regionImprovement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal region
eSAT Journals
 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportation
eSAT Publishing House
 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projects
eSAT Journals
 
Success factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementSuccess factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementIAEME Publication
 
Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of  engineering procurement  c...Success factors enhancing business performance of  engineering procurement  c...
Success factors enhancing business performance of engineering procurement c...IAEME Publication
 
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET Journal
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- Review
IRJET Journal
 
Application of ict benefits for building project management using ism model
Application of ict benefits for building project management using ism modelApplication of ict benefits for building project management using ism model
Application of ict benefits for building project management using ism model
eSAT Publishing House
 
Evaluate the effective resource management through pert analysis
Evaluate the effective resource management through pert analysisEvaluate the effective resource management through pert analysis
Evaluate the effective resource management through pert analysis
eSAT Publishing House
 
A Review on Efficiency of Migrated Labours in Construction Industry
A Review on Efficiency of Migrated Labours in Construction IndustryA Review on Efficiency of Migrated Labours in Construction Industry
A Review on Efficiency of Migrated Labours in Construction Industry
IRJET Journal
 
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
IRJET- 	  Review: Factors Affecting Scheduling of Multiple ProjectsIRJET- 	  Review: Factors Affecting Scheduling of Multiple Projects
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
IRJET Journal
 
Evaluation of public procurement mechanism for sustainable development in ban...
Evaluation of public procurement mechanism for sustainable development in ban...Evaluation of public procurement mechanism for sustainable development in ban...
Evaluation of public procurement mechanism for sustainable development in ban...
eSAT Journals
 
Evaluation of public procurement mechanism for
Evaluation of public procurement mechanism forEvaluation of public procurement mechanism for
Evaluation of public procurement mechanism for
eSAT Publishing House
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
IRJET Journal
 

Similar to The construction labour shortage in johor bahru, (20)

The measurement model for outsourcing worker
The measurement model for outsourcing workerThe measurement model for outsourcing worker
The measurement model for outsourcing worker
 
The measurement model for outsourcing worker performance by middle and big cl...
The measurement model for outsourcing worker performance by middle and big cl...The measurement model for outsourcing worker performance by middle and big cl...
The measurement model for outsourcing worker performance by middle and big cl...
 
A STUDY ON THE APPLICABILITY OF QUALITY CIRCLES TO CONSTRUCTION PROJECTS
A STUDY ON THE APPLICABILITY OF QUALITY CIRCLES TO CONSTRUCTION PROJECTSA STUDY ON THE APPLICABILITY OF QUALITY CIRCLES TO CONSTRUCTION PROJECTS
A STUDY ON THE APPLICABILITY OF QUALITY CIRCLES TO CONSTRUCTION PROJECTS
 
A study on the applicability of quality circles to construction projects
A study on the applicability of quality circles to construction projectsA study on the applicability of quality circles to construction projects
A study on the applicability of quality circles to construction projects
 
A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...
 
Improvement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal regionImprovement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal region
 
Improvement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal regionImprovement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal region
 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportation
 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projects
 
Success factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementSuccess factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurement
 
Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of  engineering procurement  c...Success factors enhancing business performance of  engineering procurement  c...
Success factors enhancing business performance of engineering procurement c...
 
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- Review
 
Application of ict benefits for building project management using ism model
Application of ict benefits for building project management using ism modelApplication of ict benefits for building project management using ism model
Application of ict benefits for building project management using ism model
 
Evaluate the effective resource management through pert analysis
Evaluate the effective resource management through pert analysisEvaluate the effective resource management through pert analysis
Evaluate the effective resource management through pert analysis
 
A Review on Efficiency of Migrated Labours in Construction Industry
A Review on Efficiency of Migrated Labours in Construction IndustryA Review on Efficiency of Migrated Labours in Construction Industry
A Review on Efficiency of Migrated Labours in Construction Industry
 
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
IRJET- 	  Review: Factors Affecting Scheduling of Multiple ProjectsIRJET- 	  Review: Factors Affecting Scheduling of Multiple Projects
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
 
Evaluation of public procurement mechanism for sustainable development in ban...
Evaluation of public procurement mechanism for sustainable development in ban...Evaluation of public procurement mechanism for sustainable development in ban...
Evaluation of public procurement mechanism for sustainable development in ban...
 
Evaluation of public procurement mechanism for
Evaluation of public procurement mechanism forEvaluation of public procurement mechanism for
Evaluation of public procurement mechanism for
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
 

More from eSAT Publishing House

Likely impacts of hudhud on the environment of visakhapatnam
Likely impacts of hudhud on the environment of visakhapatnamLikely impacts of hudhud on the environment of visakhapatnam
Likely impacts of hudhud on the environment of visakhapatnam
eSAT Publishing House
 
Impact of flood disaster in a drought prone area – case study of alampur vill...
Impact of flood disaster in a drought prone area – case study of alampur vill...Impact of flood disaster in a drought prone area – case study of alampur vill...
Impact of flood disaster in a drought prone area – case study of alampur vill...
eSAT Publishing House
 
Hudhud cyclone – a severe disaster in visakhapatnam
Hudhud cyclone – a severe disaster in visakhapatnamHudhud cyclone – a severe disaster in visakhapatnam
Hudhud cyclone – a severe disaster in visakhapatnam
eSAT Publishing House
 
Groundwater investigation using geophysical methods a case study of pydibhim...
Groundwater investigation using geophysical methods  a case study of pydibhim...Groundwater investigation using geophysical methods  a case study of pydibhim...
Groundwater investigation using geophysical methods a case study of pydibhim...
eSAT Publishing House
 
Flood related disasters concerned to urban flooding in bangalore, india
Flood related disasters concerned to urban flooding in bangalore, indiaFlood related disasters concerned to urban flooding in bangalore, india
Flood related disasters concerned to urban flooding in bangalore, india
eSAT Publishing House
 
Enhancing post disaster recovery by optimal infrastructure capacity building
Enhancing post disaster recovery by optimal infrastructure capacity buildingEnhancing post disaster recovery by optimal infrastructure capacity building
Enhancing post disaster recovery by optimal infrastructure capacity building
eSAT Publishing House
 
Effect of lintel and lintel band on the global performance of reinforced conc...
Effect of lintel and lintel band on the global performance of reinforced conc...Effect of lintel and lintel band on the global performance of reinforced conc...
Effect of lintel and lintel band on the global performance of reinforced conc...
eSAT Publishing House
 
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
eSAT Publishing House
 
Wind damage to buildings, infrastrucuture and landscape elements along the be...
Wind damage to buildings, infrastrucuture and landscape elements along the be...Wind damage to buildings, infrastrucuture and landscape elements along the be...
Wind damage to buildings, infrastrucuture and landscape elements along the be...
eSAT Publishing House
 
Shear strength of rc deep beam panels – a review
Shear strength of rc deep beam panels – a reviewShear strength of rc deep beam panels – a review
Shear strength of rc deep beam panels – a review
eSAT Publishing House
 
Role of voluntary teams of professional engineers in dissater management – ex...
Role of voluntary teams of professional engineers in dissater management – ex...Role of voluntary teams of professional engineers in dissater management – ex...
Role of voluntary teams of professional engineers in dissater management – ex...
eSAT Publishing House
 
Risk analysis and environmental hazard management
Risk analysis and environmental hazard managementRisk analysis and environmental hazard management
Risk analysis and environmental hazard management
eSAT Publishing House
 
Review study on performance of seismically tested repaired shear walls
Review study on performance of seismically tested repaired shear wallsReview study on performance of seismically tested repaired shear walls
Review study on performance of seismically tested repaired shear walls
eSAT Publishing House
 
Monitoring and assessment of air quality with reference to dust particles (pm...
Monitoring and assessment of air quality with reference to dust particles (pm...Monitoring and assessment of air quality with reference to dust particles (pm...
Monitoring and assessment of air quality with reference to dust particles (pm...
eSAT Publishing House
 
Low cost wireless sensor networks and smartphone applications for disaster ma...
Low cost wireless sensor networks and smartphone applications for disaster ma...Low cost wireless sensor networks and smartphone applications for disaster ma...
Low cost wireless sensor networks and smartphone applications for disaster ma...
eSAT Publishing House
 
Coastal zones – seismic vulnerability an analysis from east coast of india
Coastal zones – seismic vulnerability an analysis from east coast of indiaCoastal zones – seismic vulnerability an analysis from east coast of india
Coastal zones – seismic vulnerability an analysis from east coast of india
eSAT Publishing House
 
Can fracture mechanics predict damage due disaster of structures
Can fracture mechanics predict damage due disaster of structuresCan fracture mechanics predict damage due disaster of structures
Can fracture mechanics predict damage due disaster of structures
eSAT Publishing House
 
Assessment of seismic susceptibility of rc buildings
Assessment of seismic susceptibility of rc buildingsAssessment of seismic susceptibility of rc buildings
Assessment of seismic susceptibility of rc buildings
eSAT Publishing House
 
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
eSAT Publishing House
 
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
eSAT Publishing House
 

More from eSAT Publishing House (20)

Likely impacts of hudhud on the environment of visakhapatnam
Likely impacts of hudhud on the environment of visakhapatnamLikely impacts of hudhud on the environment of visakhapatnam
Likely impacts of hudhud on the environment of visakhapatnam
 
Impact of flood disaster in a drought prone area – case study of alampur vill...
Impact of flood disaster in a drought prone area – case study of alampur vill...Impact of flood disaster in a drought prone area – case study of alampur vill...
Impact of flood disaster in a drought prone area – case study of alampur vill...
 
Hudhud cyclone – a severe disaster in visakhapatnam
Hudhud cyclone – a severe disaster in visakhapatnamHudhud cyclone – a severe disaster in visakhapatnam
Hudhud cyclone – a severe disaster in visakhapatnam
 
Groundwater investigation using geophysical methods a case study of pydibhim...
Groundwater investigation using geophysical methods  a case study of pydibhim...Groundwater investigation using geophysical methods  a case study of pydibhim...
Groundwater investigation using geophysical methods a case study of pydibhim...
 
Flood related disasters concerned to urban flooding in bangalore, india
Flood related disasters concerned to urban flooding in bangalore, indiaFlood related disasters concerned to urban flooding in bangalore, india
Flood related disasters concerned to urban flooding in bangalore, india
 
Enhancing post disaster recovery by optimal infrastructure capacity building
Enhancing post disaster recovery by optimal infrastructure capacity buildingEnhancing post disaster recovery by optimal infrastructure capacity building
Enhancing post disaster recovery by optimal infrastructure capacity building
 
Effect of lintel and lintel band on the global performance of reinforced conc...
Effect of lintel and lintel band on the global performance of reinforced conc...Effect of lintel and lintel band on the global performance of reinforced conc...
Effect of lintel and lintel band on the global performance of reinforced conc...
 
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
 
Wind damage to buildings, infrastrucuture and landscape elements along the be...
Wind damage to buildings, infrastrucuture and landscape elements along the be...Wind damage to buildings, infrastrucuture and landscape elements along the be...
Wind damage to buildings, infrastrucuture and landscape elements along the be...
 
Shear strength of rc deep beam panels – a review
Shear strength of rc deep beam panels – a reviewShear strength of rc deep beam panels – a review
Shear strength of rc deep beam panels – a review
 
Role of voluntary teams of professional engineers in dissater management – ex...
Role of voluntary teams of professional engineers in dissater management – ex...Role of voluntary teams of professional engineers in dissater management – ex...
Role of voluntary teams of professional engineers in dissater management – ex...
 
Risk analysis and environmental hazard management
Risk analysis and environmental hazard managementRisk analysis and environmental hazard management
Risk analysis and environmental hazard management
 
Review study on performance of seismically tested repaired shear walls
Review study on performance of seismically tested repaired shear wallsReview study on performance of seismically tested repaired shear walls
Review study on performance of seismically tested repaired shear walls
 
Monitoring and assessment of air quality with reference to dust particles (pm...
Monitoring and assessment of air quality with reference to dust particles (pm...Monitoring and assessment of air quality with reference to dust particles (pm...
Monitoring and assessment of air quality with reference to dust particles (pm...
 
Low cost wireless sensor networks and smartphone applications for disaster ma...
Low cost wireless sensor networks and smartphone applications for disaster ma...Low cost wireless sensor networks and smartphone applications for disaster ma...
Low cost wireless sensor networks and smartphone applications for disaster ma...
 
Coastal zones – seismic vulnerability an analysis from east coast of india
Coastal zones – seismic vulnerability an analysis from east coast of indiaCoastal zones – seismic vulnerability an analysis from east coast of india
Coastal zones – seismic vulnerability an analysis from east coast of india
 
Can fracture mechanics predict damage due disaster of structures
Can fracture mechanics predict damage due disaster of structuresCan fracture mechanics predict damage due disaster of structures
Can fracture mechanics predict damage due disaster of structures
 
Assessment of seismic susceptibility of rc buildings
Assessment of seismic susceptibility of rc buildingsAssessment of seismic susceptibility of rc buildings
Assessment of seismic susceptibility of rc buildings
 
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
 
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
 

Recently uploaded

CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
veerababupersonal22
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 

Recently uploaded (20)

CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 

The construction labour shortage in johor bahru,

  • 1. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 02 Issue: 10 | Oct-2013, Available @ http://www.ijret.org 508 THE CONSTRUCTION LABOUR SHORTAGE IN JOHOR BAHRU, MALAYSIA Abdul Rahim Abdul Hamid1 , Bachan Singh Besawa Jagar Singh 2 , Muhammad Shahrom Mazlan3 1,2 Senior Lecturer, 3 Project Engineer, Department of Structures and Materials, Faculty of Civil Engineering, Universiti Teknologi Malaysia, 81310 UTM Johor Bahru, Johor Darul Ta’zim, Malaysia. rahimfka@gmail.com, bachan19@yahoo.com, matshah_125@yahoo.com.my Abstract Construction industry is one of the sectors that require the Labor intensive to fulfill the work site. However, we always hear the problems related to the shortage of the construction workers. Therefore, the purpose of this study are to estimate the current shortage composition of construction labor, to evaluate the problem faced by contractor when hired labor, to examine contractor method of acquiring construction labor, and to investigate the strategies taken by contractor to overcome shortage of labor. The questionnaire will be distributed to the 35 of construction site which targeting project representative that involved with construction site in Johor Bahru district, Malaysia, in order to obtain their feedback related to this topic. The Johor Bahru district is located in the southern part of Johor in the Malay Peninsula, separated from Singapore by Straits of Johor. The district covers an area of 1,871 km² and has a population of over 2 million. The data will be analyzed using SPSS 16 in order to obtain average index, frequencies and percentage calculation. The result obtained from analysis will be represent in data table, bar and pie chart. The result of this study indicates that the current shortage and demand of the current construction are about 12.14% from the total labor workforce which is about 360 workers for 35 projects sites. Keywords: Construction, Foreign Workers, Shortage, Strategies ----------------------------------------------------------------------***------------------------------------------------------------------------ 1. INTRODUCTION The construction industry is among the most important industries in the country that closely related to other economic sectors. It is the capital goods industry to provide infrastructure for other industries operation. The construction industry also is a sector becomes the engine of economic growth and most resources are used for national development (Zakaria, M.Y, 2006)[1]. The construction project depends on project resources. Among the most important resources is the source of workers. Shortage of labor resources in Malaysia resulting, the country depends on the labor workforce from outside, especially from Indonesia [2, 3]. Scenarios for the recruitment of foreign workers in the construction sector in Malaysia not a new issue. Malaysia has started taking foreign workers since the reign of the British. Malaysia is the biggest net importer of labor in Asia with a migrant labor force of around 2 million (21 percent of 9.5 million of the total work force) as of 2010 (Migration News, 2011)[4]. Construction was among the sectors which came to rely heavily on foreign workers owing to a confluence of factors: Malaysian youth’s aversion to low status work, an expanding manufacturing sector which was offering much better employment conditions, labor attrition, widening opportunities for tertiary education, a lower birth rate and the emigration of Malaysian workers to high-wage countries such as Japan and Singapore (Abdul-Aziz, 1995)[5,6]. Datuk Ir. Hamzah Hasan, Chief Executive, CIDB revealed that there are about 300,000 legal foreign construction workers in addition to 391,006 local workforce (43% of the total construction workers)( Malaysian Construction Summit 2008)[7]. From the statistic show that the foreign workers involved in construction sector is around 361,000 workers. From the study conducted by CIDB about the status construction workers and local which covered the skilled workers, semi skilled workers and unskilled workers at construction site, revealed that 52% (361,000 workers) are from foreigner workers contributing to total workforce construction industry, while 48% (333,000 workers) are local workers (CIDB & CREAM, 2010)[8]. From the total foreign construction workers (361,000 workers), (59%) from Indonesia, (13%) Bangladesh and (28%) are from others country Nepal, Myammar, India, Vietnam and Sri Langka. Through the study, the more foreign workers employed in the private projects, compared with projects under government tender. 2. LITERATURE REVIEW The project under 10th Malaysian Plan (10 MP) and Economic Transformation Programmed including Mass Rapid Transit (MRT) which costing over RM40 billion with required about
  • 2. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 02 Issue: 10 | Oct-2013, Available @ http://www.ijret.org 509 130,000 construction skilled workers of various manpower of various trade both local and foreign workers to ensure successful completion (CIDB News, 2011)[9].The Malaysian construction industry has been experiencing a critical shortage of workforce. Nowadays the local workers unable to fulfill the demand of construction market from time being. This reason caused the contractor willing to import foreign workers from outside to meet the needs and requirement labor market in construction sector. According to Kwan Foh Kwai the President of MBAM (Master Builder Association of Malaysia) mentioned that, shortage of skilled construction workers is very crucial issues in construction industry (MBAM Online News)[10]. Besides that, MBAM also stated that, the acute shortage of skilled workers in the construction industry will give negative impact towards the projects under Malaysian Plan (10MP) and Economic Transformation Programmed (The Star Online) [11]. Current topical issues relevant to the Malaysia construction industry are the quality of workmanship. According to REHDA (Real Estate Housing Developers’ Association Malaysia quality of product including housing and building are related directly to manpower and skilled. It seems that the construction workers is failed to attract workers in skilled and semi-skilled trades. The 3D perception has discouraged skilled local workers in joining, resulting in a lot of job being executed by the untrained construction workers. The important issue from REHDA stated that, the skilled labor shortage is the one of factor contributing of the increasing property price (The Stars Newspaper, 2011)[12]. The aim of this master project is to study the current construction labor shortage at construction projects in the district of Johor Baharu, Malaysia. In order to achieve this aim, four objectives are developed. The objectives are as follow to estimate the current labor shortage at construction sites, to evaluate the problem faced by contractor when hired labor, to examine contractor method of acquiring construction labor and to investigate the strategies taken by contractor to overcome shortage of labor. 3. METHODOLOGY The main reason of the study is to fulfill earlier stated objectives though the collection of data using survey questionnaire forms. The methodology is set in order to gather the data to achieved the outlined of objectives. The first step of study is to rationalize the issue to set up the topic of study. After that the statement of problems, aims and objectives were developed. This study required several methods of data collections for the purpose of objectives achievements. For the knowledge improvement phase, the literature review is carried out. The literature sources that connection with study including journal, books, conference papers, magazines and websites will be used in the literature review part. From that information, a set of questionnaire form that related to objectives will be developed. The question that develops in the questionnaire was in the form of multiple choice or open ended questions or Likert Scale. The respondents are among the contractors parties that involved in construction projects. The result obtained from questionnaire will be represent in data table, bar and pie chart, and radar plot. The data will be analyzed using statistical method that is mean or average index, frequencies and percentage calculation. The final phase of this study is to define the conclusion and recommendation with reference to the objective, subsequent to the analysis from the questionnaire. The feedbacks provided by respondents are categorized into five options, Strongly Agree, Agree, Moderate/slightly agree, Disagree and Strongly Agree[13]. The Multiple-choice questions require the anticipation of the whole range of likely answers, which would be given, and formulating the options. The multiple-choice questions are based on Likert scale of five ordinal measures of agreement towards each statement (from 1 to 5). 4. RESULTS AND DISCUSSIONS This study was conducted to study current construction labor shortage at construction projects in Johor Baharu. This chapter will discussed the analysis data of questionnaire that were obtain from respondent which is consist project representative that is project manager from the 35 construction sites in Johore Bahru. The data analysis section is divided into four part according objectives. For the first objective that consists of demographic background or data which is consist of the number of shortage of workers in 35 construction sites. Meanwhile, for the others objective consist of Likert scale analysis consists of questions regarding to the problems facing by contractor when hired labor, contractor method of acquiring construction labor and the strategies taken by contractor to overcome shortage of labor. 4.1 Objective 1 Table 1 tabulates the current shortage of 35 construction project in area Johor Bahru. From the table indicates the shortages among project site survey are range from 4.17% until 44.44%.Besides that, the percentage shortage for overall project is about 12.14% which is about 360 workers from the total existing labor workforce. Beside that Chart 1 represent shortage of labor by category of labor. From the 360 numbers of workers shortage, the contractors needs 54% of skilled workers, 28% semi skilled and 18% unskilled workers in their construction projects. Others than that, from 360 workers, the contractors more considers to hired 80% of foreign construction workers and
  • 3. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 02 Issue: 10 | Oct-2013, Available @ http://www.ijret.org 510 only 20% of local workforces. The types of labor are illustrated in the Chart 2. Table - 1: Current Shortage of workers for Overall Project Chart - 1: Shortage by Category of Labor Chart - 2: Shortage by Type of Labor 4.2 Objective 2 The data analysis for the research objective no 2 which is “Evaluating Problem Faced by Contractor When Hired Labor”, were conducted to evaluated the common problem faced by contractor when hired labor workforce. The research question/objective is represented by 12 items. The attainment for this section is by questionnaire survey. The research result findings are shown in Chart 3 and Table 2 as follow. Chart - 3: Mean/Average Index and Problem Facing by Contractor when Hired Labor Table – 2: Classification of Problem Face by Contractor Chart 3 represent bar chart mean/average index on the problem facing by contractor start from item problem no 1 until problem no 12. From the chart show that the highest index is belonging to item problem no 5 which is problem on recruitment and delivery cost of labor. While the smallest mean index is on problem Registration with job Malaysia agency that is 3.71 averages/ means index. The higher value represent the priority or critical of that problem and vice versa.
  • 4. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 02 Issue: 10 | Oct-2013, Available @ http://www.ijret.org 511 4.3 Objective 3 The data analysis of the objective number 3 which is “Examine Contractor Method of Acquiring Construction Labor”, were conducted to confirm what the common contractor method of acquiring construction labor. The research objective is represented by 7 items. The attainment for this section is by questionnaire survey. The research result findings are shown in Chart 4 and Table 3 as follow. Chart - 4: Mean/Average Index and Contractor Method Acquiring Construction Labor Table - 3: Code for Contractor Method in Acquiring Construction Labor Chart 4 illustrated bar chart of the mean/average index on contractor method acquiring construction labor start from item method no 1 until method no 12. From the chart above describing that the highest index is subjected towards item method no 2 which is acquiring labor through subcontractors and average mean index is 4.23. Whereas the smallest mean index is reflected on method by applies from department of labor forces that is 3.34 averages/ means index. The higher value represents the popular or common method used by contractors while the smallest values indicate the less popular method applies by contractor in acquiring the labor workforces. 4.4 Objective 4 The data analysis for the objective number 4 which is “Strategies Taken by Contractors to Overcome Shortage of Labor”, were conducted to investigate what the common approach taken by contractors to overcome shortage of labors. The research objective is represented by 10 items. The attainment for this section is by questionnaire survey. The research result findings are shown in Chart 5 and Table 4 as follow. Chart - 5: Mean/Average Index of Strategies Taken by Contractor to Overcome Shortage of Labor Table – 4: Code for Strategies Taken by Contractor Chart 5 tabulated bar chart of the mean/average index on strategies taken by contractor to overcome shortage of labor start from item strategies no 1 until strategies no 10. From the
  • 5. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 02 Issue: 10 | Oct-2013, Available @ http://www.ijret.org 512 chart above describing that the highest index is subjected towards item strategy item no 9 which is maximize/fully optimize used of labors available while the average mean index is 4.23. Whereas the smallest mean index is reflected on strategy by introduce multiple shifts work system that is 3.2 averages/ means index. The higher value represents the popular or common strategy applied by contractors while the smallest values indicate the less popular strategy applies by contractor in to overcome shortage of the labor workforces. CONCLUSIONS From the result analysis and discussion, some of conclusion can be came out based on objectives of this study as follow the first objectives were to study the current shortage composition of construction labor. From the data analysis the current shortage composition for every project site surveyed is range from 4.17% until 44.44%. Others than that, for overall project on the average is about 12.14% from total labor workforces. The second objective was to evaluate the problem faced by contractor when hired labor. From the findings the average/min index of problem face by contractor were ranging from 3.71-4.29. Therefore as conclusion the critical problem facing by contractors when hired labor is recruitment and delivery cost of labor. The third objective is to examine contractor method of acquiring construction labor. From the analysis indicates the average/min index of contractor method of acquiring construction labor was ranging from 3.34-4.23. Therefore as conclusion the common practice contractor method of acquiring construction labors is through subcontractor’s method The final objective is to investigate the strategies taken by contractor to overcome shortage of labor. From the analysis highlighted the average/min index strategies taken by contractor to overcome shortage was ranging from 3.20-4.23. Therefore as conclusion the popular strategy practice by contractor to overcome shortage of labors is fully maximized or optimized used of labors available in construction projects. ACKNOWLEDGEMENTS We would like to thank our sponsor, Ministry of Higher Education (MOHE) and Universiti Teknologi Malaysia (UTM) for the financial support of Research University Grant (Vote No. Q.J130000.7122.03J11) which enable us to carry out this research project Thank you also to UTM Research Management Centre (RMC) and those who had contributed towards the completion of this research. REFERENCES [1] Zakaria, M.Y (2006) “Challenges in Providing Local Skilled Construction Workers” Universiti Teknologi Malaysia. [2] Berita Harian “ABM Help in Reducing Dependance on foreign Workers” by Aivizanoorwani Shah Shahroni on 8th July 2010 [3] Bernama, (2011) “Reduction of Foreign Workers Dependency Through IBS” website www.Bernama.com [4] Migration News online (2 April 2011) “Southern Asia” logged www.migration.ucdavyis.edu.my asscess on 26 July 2011. [5] Abdul Aziz (1995). Foreign Labour in the Malaysian Construction Industry (Geneva, International Labour Office. [6] The Malaysian Insider online “Foreign Workers Levy Hike in 2011” 20th May 2010 by Asrul Hadi Abdullah Sani, logged on www.malaysianinsider.com [7] Malaysian Construction Summit 2008 – 6th June 2008, Paper presented by Datuk Ir. Hamzah Hasan, Chief Executive, CIDB. [8] CIDB & Cream (2010), “Latest Research on Construction Foreign Workers 2010” can be access though http://ibsresearch.blogspot.com/2010/09/kajian-status-terkini- perkerja-asing-di.html [9] CIDB News, (2011). “Moving Forward” by Sazali Che mat. [10] MBAM Online News “Skilled Manpower Shortage Need Urgent Attention” by Siti Sakinah Abdul Latiff on 4 august 2010, can be acess on www.MBAM.org.my [11] The Star Online “Workers Shortage Could Hit ETP Plan” by Wong Pek Mei on 16 march 2011, can be access in www.Thestar.my [12] The Star Newspaper on Star Biz Week “Your 10 Questions with Datuk Seri Michael Yam REHDA President”. 25 June 2011 [13] Abd. Majid M.Z. and Ronald McCaffer, M.ASCE (1997), .Factors of Non Excusable Delays That Influence Contractor’s Performance., Journal of Construction Engineering and Management, ASCE BIOGRAPHIES Abdul Rahim Abdul Hamid is a Senior Lecturer in Department of Structures and Materials, Faculty of Civil Engineering at Universiti Teknologi Malaysia, Skudai Johor, Malaysia since 1994. He holds a Master in Construction Engineering and BSc. in Civil Engineering Washington University, USA Bachan Singh a/l Besawa Jagar Singh is a Senior Lecturer in Department of Structures and Materials, Faculty of Civil Engineering at Universiti Teknologi Malaysia, Skudai Johor, Malaysia. Muhammad Shahrom Mazlan is a Project Engineer working with a Piling Company. He was a post-graduate student of Construction Management in Faculty of Civil Engineering at Universiti Teknologi Malaysia, Skudai Johor, Malaysia.