SlideShare a Scribd company logo
1 of 22
Presentation for
Technical Committee Meeting
Bangladesh Urban Resilience Project
Presentation by M&E Team / PCMU
May 25, 2021
Overview of URP
Bangladesh Urban Resilience Project Key Information
Name of the
project
Bangladesh Urban Resilience Project
Funding
information
Total Project Cost : US$ 182.00 million
The world Bank Part : US$ 173.00 million
GoB Part : US$ 9.00 million
Implementing
agency
 Department of Disaster Management (DDM)
 Dhaka North City Corporation (DNCC)
o Dhaka South City Corporation (DSCC)
o Sylhet City Corporation (SCC)
o Fire Service and Civil Defence (FSCD)
 Rajdhani Unnayan Kartipakkha (RAJUK)
 PCMU, Planning Commission
Duration of the
project
1st Phase : March 2015 to June 2020 (Completed)
Restructured phase : July 2020 to April 2022 (ongoing)
Total financial
progress
Total Approved cost : 151,300 Lac BDT
Expenditure up to Feb 2021 : 87,776.82 i.e., 57.35%
86,776.82
(57.35%)
Key Achievements
DDM’s Progress to Renovate NDMRTI and ERCC (A-1)
A-1: Renovate office space in DDM building for NDMRTI & ERCC
NDMRTI (National Disaster Management Research and Training Institute):
Renovation and Decoration completed for
7th floor : Office room and training center; 8th floor: 4 Training center (Sidr,
Aila, Foni & Amphan) and 2 computer lab
9th floor : Mujib corner (901), Multi purpose hall (902), Library (903) and
Auditorium (904)
ERCC (Emergency Response and Communication Centre): Renovation
Completed for ICT server room, media centre, ERCC observation room &
emergency exit.
Handover not yet done by the contractor due to pending approval of
additional work from the Ministry.
Procurement of ICT equipment on process to renovate ERCC & NDMRTI.
DDM’s Progress on Training, Exercise and Drill (A-5)
 Training postponed since 3rd week of March 2020. TED contract
ended with REM/DTCL in November 18, 2020
 Force Majeure claimed by REM/DTCL with significant amount of
contract value as compensation.
 Financial Settlement between DDM PIU and REM/DTCL is getting
delayed for long time;
 Early amicable settlement needed so that the left over amount if
available could be utilized.
 Potential High Risk for not achievement of PDO Indicator 3, IRI 6
& 7
DNCC Progress on A-2
For DNCC, DSCC & SCC - 30 Facilities
 8 Emergency Warehouses (DNCC-5, DSCC-3),
 3 EOC (DNCC, DSCC & SCC) associated with 1
URI (Sylhet),
 8 DRM Offices (DNCC, DSCC),
 10 Zonal Control Rooms (1 control room at
each zonal office) –
For FSCD- 28 Facilities
 2 Command & Control Rooms (Mirpur,
Dhaka and Sylhet),
 13 Emergency Management Warehouses (11
Dhaka, 2 Sylhet)
 13 Auxiliary Control Rooms
1. Gazipur
2. Narayanganj
3. Mymensingh
4. Chittagong
5. Comilla
6. Jashore
7. Rajshahi
8. Rangpur
9. Barisal
10. Sylhet
Tender floated for the Construction of Greenfield Tower (60m wireless tower) at
Eight (8) different location for DNCC, DSCC, SCC and Ten (10) following location
for FSCD.
A-2 Target: Construction of Emergency Response Facilities
DNCC Progress on A-3
A-3: Emergency Communication Technology (ECT)
equipment
 Purchase ongoing for ICT equipment of EOC and CoC (1.18 & 1.19-
waiting for contract sign), EOC-DSCC, SCC & COC-FSCD (Dhaka &
Sylhet)
 Purchase ongoing for ICT equipment for NDMRTI & ERCC of DDM; (Pk
1.15- Tender Eval on-gong).
 ICT Equipment for FSCD Expected Delivery (Pk-1.8), May 30, 2021
(already in the port)
DNCC Progress
A-4: Procurement of Search and Rescue (SAR) equipment
 Following SAR equipment purchased
 22 SAR Equipment (vehicle),
 5 Water rescue vehicles,
 6 Breathing apparatus,
 950 Rescue suits,
 30 Chemical suits
 900 Searchlights,
 3 Drones,
 4 Mortuary Vans,
 6 Rescue carrying vehicles
 SAR equipment for warehouse
(Drill machine, generator, torchlight etc..)
 3 Cranes,
 3 Wheel type excavators,
 3 Chain type excavators,
 3 Bulldozers.
 3 Ladders (64-meter)
 10 Ambulances
 5 Hazmat Materials
3 rescue boat remaining for purchase (tentative delivery July 30, 2021)
RAJUK Progress on B1
 Status of B1 -Vulnerability Assessment of Critical and Essential
Facilities
 Approval done of “Comprehensive Situation Analysis Report” (CSAR)-
(MD-1); - January 12, 2020.
 Approval done of Individual reports for structures assessed (2 million
Sqm) of 1st Level Rapid Visual Assessment (RVA) -(MD-02); - March 7, 20.
 Field work of 5 million sqm Rapid Visual Assessment (RVA) completed;
(Submission for 1 million RVA report pending out of remaining 3 million
sqm).
 Preliminary Engineering assessment Report–PEA (MD-4&5) on-going;
(0.59 million sqm out of 1 million sqm PEA done. (tentative completion:
May-21).
 Detailed Engineering Assessment work already started.
Progress on B2
Status of B2- RSLUP (Risk Sensitive Land use planning)
 Approval done of Final SEA Report (MD-01); - September 13, 2020
 Approval done of Final Consultation Report and Comprehensive
Situational Analysis and Diagnosis Report (MD-2);-June 12, 2020.
 Approval done of Preliminary Risk Assessment, Strategic
Framework and Geological Survey Plan (MD-3); April 12 2020.
 Geotechnical Tests are on-going for:
 Microtremor Test (MT)- (GD-1); Standard Penetration Test (SPT)-
(GD-2); Cone Penetration Test (CPT)-(GD-3); Seismic Downhole
Test (SDHT)-(GD-4); Seismic Cone Penetration Test (SCPT)-(GD-5);
Tentative Completion-Apr-21.
 Geo Analysis and Modeling as well as Development of Risk Sensitive
Land Use Strategy of Dhaka City (MD-4); is On-going.
C-1: Establishment of URU Building
Approval done of Architectural, Structural and MEP, BoQ,
Bidding document and Design Report (S-11); December, 2019.
Contract signed for URU building (W-1) October 20, 2020. Physical
works started. Shore pile work & Load test are completed while
service pile work and earth excavation are going on.
Lab and Field equipment Delivered so far…:
Seismic Lab Equipment for URU (G-12) (Aug-2020)
Seismic Field Equipment for URU (G-13) (Aug-2020)
Field Equipment for Vulnerability Assessment Aspect of Structures & Geo-
physics (G-15) (Mar-2020)
PA System, Telecommunication, Access Control & Security and General
Electrical Equipment for PIU Office (G-18) (Jul-2020).
RAJUK Progress on C-1
URU Operationalization (S-6 with RTI)
Approval done of Situation Analysis and Feasibility Report (SAFR);
Mar-2019.
Approval done of Institutional Design & Organizational Study
(IDOS) Report; Oct-2019.
Approval done of Community Outreach Campaign Report ; Jun-
2020.
Submitted training documents for the URU Training Materials and
Documentation delivered; All related Training completed.
RAJUK Progress on C-1
C-2: Electronic Construction Permitting System (S-7 with RTI)
Approved Electronic Construction Permitting Assessment Report (CPAR);
done in Oct 2019.
Approval done of Strategic Plan Report with E-Permit Implementation
Action Plan, done in June 2020.
Approval done of Business Rules Specification (BRS) Report in April 2020.
 In-House Testing (IHT) done (ECP v2 Alpha Testing & Beta testing –Sept
22, 2020); User Acceptance Test (UAT) and Operational Acceptance Test
(OAT) done by April 11, 2021.
RAJUK Progress on C-2 & C-3
C-3: Professional Accreditation Program
After long waiting for designing the package and approval from ministry
contract has been signed with ICC on March 1, 2021. The Consultant has
submitted the draft Inception report and yet to validate it.
C-4: Improved Building Code Enforcement (S-9 with ICC)
 Approval done of Situation Analysis Report; on December 2019.
 Approval done of Concept Note Report (CNR) for URU; on April,
2020 after validation.
 Proposed Program for Building Codes and Construction Code
Enforcement Report submitted on April and Approved on Jun-
2020. Validation meeting done Nov-30, 2020
 Training and Capacity Building Report targeted to submit it
within May 2021 (Major upcoming milestone)
RAJUK Progress on C-4
PCMU Progress (Component-D)- Cont.
Component D: Projects Coordination, Monitoring and Evaluation
PCMU Organized: 1 TC Meeting, 1 PSC Meeting, 1 Coordination meeting
M&E Team meet with the Implementing Agencies
Meeting with DNCC on January 6, 12 and March 14, 15 (FSCD)
Meeting with DDM on February 14, March 24
Field visit to monitor SPT, West Paikpara, Mirpur on December 22,
Field visit to monitor Seismic Downhole Test (SDHT), Biruia, Savar
on February 10, 2021
Field visit to monitor RVA and PEA, Mirpur Ideal Girls College on
March 4, 2021
Field visit to monitor URU Construction progress (March 3, 7, 11, 15,
2021)
Project Approved cost and financial progress
Sl. No
Implementing
Agency Name
Total Approved
Cost (RDPP)
(in lac Tk.)
Expenditure for FY
20-21 Vs ADP All..
Total Expenditure
(Up to Feb 2021)
1
URP: DNCC 80,590
4,528.77
(87%)
59,859.51
(74.3%)
2
URP: RAJUK 53,665
3,727.49
(134%)
19,851.36
(37%)
3
URP: DDM 12,515
467.34
(11%)
4,887.50
(39%)
4
URP: PCMU 4,530
652.66
(53%)
2,178.45
(48%)
Total
151,300 9,376.3
(69.6%)
86,776.82
(57.35%)
Total project cost US $182 million. (US $173 million IDA Credit, US $9 million from GoB as operating costs.
Project Duration: March 2015 to April 2022;
Challenges
Due to postponement of Training, Exercise and Drill (TED), the
achievement of PDOI -3, IRI-6 & 7 are at high risk;
Due to delayed financial settlement with REM/DTCL the financial
restructuring (if needed for Rajuk) could be delayed
Completion of URU Construction within the project duration is tight
and could be delayed; specially the service pile work might not be
completed within the scheduled period before the rainy season starts;
URU Operationalization -- within the project duration (April 2022) is
challenging due to shortage of fund and the timeframe.
Operation & Maintenance (O&M) of purchased Goods & equipment
and overall Sustainability of URP;
Less Follow up mechanism and attention to address the PSC and
Technical committee decision.
Recommendations & Conclusions (long Term)
 Following issues need t0 be anlysed and reviewed
critically.
1. Essentialness of TED; that is very crucial to achieve PDIO 3, IRI 6
&7. We have facilities and equipment, now we need trained
staff to utilize the facilities and equipment. We must have to
restart TED.
2. Vulnerability Assessment (B1)- If the RVA (5m-sqm) --->PEA (1m
sqm)---->DEA (.4m sqm). What will be the aftermath of rest 4m
PEA and subsequent DEA and its implementation? Besides,
Vulnerability Assessment shouldn’t be confined only within
Dhaka city.
Recommendations & Conclusions (long Term)-cont..
3. URU construction & Operationalization– Package S-6 will be
ended in June 2021. Package S-6 needs to be redefined to
increase its scope of work with a view to fully operationalize the
URU. This is a comprehensive task.
4. Comprehensive plan & budget for Operation & Maintenance
(O&M) of purchased Goods & equipment is a persistent issue that
needs to be addressed for overall Sustainability of URP;
Considering the progress affected for COVID pandemic &
understanding the above critical and essential requirements; those
aren’t possible to be completed within April, 2022. We
recommend to initiate URP-II (decision time now??) with additional
budget to complete the mentioned tasks among others.
Recommendations & Conclusions (Short term)
 TED is essential to achieve PDIO 3, IRI 6 &7. There is no
alternative of TED to achieve these indicators. Considering the
short duration of the project G2G system to hire
trainers/mentors and conduct training would serve the purpose.
 DDM is recommended to complete the financial settlement
with REM/DTCL asap so that the left over amount could be
utilized.
 A financial restructuring is needed end of this FY 2020-2021. The
unutilized fund of DNCC, DDM and PCMU could be contributed
to completed the additional requirement of Rajuk
Recommendations & Conclusions (Short term)
 Construction of two basement (Mat foundation) for URU is
very critical to complete before rainy reason.
 Considering from the project Evaluation point of view, it is
essential either to complete TED to achieve the mentioned
indicators or Restructure the Results Framework and Readjust
the scope of Indicators those are related to Training, Exercise
and Drills.
 We strongly recommend a follow up mechanism to implement
the PSC meeting decision more effectively. PCMU could play
the most vital role to look into this matter.
Thank you very much

More Related Content

Similar to TC Presentation_M&E Team_May25.pptx

Performance Audit of GBPWD.pptx
Performance Audit of GBPWD.pptxPerformance Audit of GBPWD.pptx
Performance Audit of GBPWD.pptxsheikhInayat5
 
Government recognized new advance material for sustainable construction of ro...
Government recognized new advance material for sustainable construction of ro...Government recognized new advance material for sustainable construction of ro...
Government recognized new advance material for sustainable construction of ro...Jogani Reinforcement
 
Circular letter-no-2022-5 workshop on the guidelines in fy 2023 tagging of go...
Circular letter-no-2022-5 workshop on the guidelines in fy 2023 tagging of go...Circular letter-no-2022-5 workshop on the guidelines in fy 2023 tagging of go...
Circular letter-no-2022-5 workshop on the guidelines in fy 2023 tagging of go...Mabelle Gaytano
 
1st APR-URP Presentation
1st APR-URP Presentation 1st APR-URP Presentation
1st APR-URP Presentation ShamsulArefin75
 
Construction Planning of an Offshore Petroleum Platform
Construction Planning of an Offshore Petroleum PlatformConstruction Planning of an Offshore Petroleum Platform
Construction Planning of an Offshore Petroleum PlatformProfessor Kabir Sadeghi
 
Civil_Geotech Engg Proposal of new and details of existing PG programmes afte...
Civil_Geotech Engg Proposal of new and details of existing PG programmes afte...Civil_Geotech Engg Proposal of new and details of existing PG programmes afte...
Civil_Geotech Engg Proposal of new and details of existing PG programmes afte...nitrrfie
 
Departmental Briefing to Secretary Works on 08-02-2023.pptx
Departmental Briefing to Secretary Works on 08-02-2023.pptxDepartmental Briefing to Secretary Works on 08-02-2023.pptx
Departmental Briefing to Secretary Works on 08-02-2023.pptxsheikhInayat5
 
Update on Implementation of the EIA Process and Remaining Challenges in Oil a...
Update on Implementation of the EIA Process and Remaining Challenges in Oil a...Update on Implementation of the EIA Process and Remaining Challenges in Oil a...
Update on Implementation of the EIA Process and Remaining Challenges in Oil a...Ethical Sector
 
Construction management
Construction managementConstruction management
Construction managementvhjadhav
 
Circular letter-no-2022-5-dated-february-16-2022
Circular letter-no-2022-5-dated-february-16-2022Circular letter-no-2022-5-dated-february-16-2022
Circular letter-no-2022-5-dated-february-16-2022Mabelle Gaytano
 
Aem 606 eia eac-b9-2
Aem 606 eia eac-b9-2Aem 606 eia eac-b9-2
Aem 606 eia eac-b9-2B. BHASKAR
 
Report No.11 of 2021 - Performance Audit on Implementation of Phase-III, Delh...
Report No.11 of 2021 - Performance Audit on Implementation of Phase-III, Delh...Report No.11 of 2021 - Performance Audit on Implementation of Phase-III, Delh...
Report No.11 of 2021 - Performance Audit on Implementation of Phase-III, Delh...Life of A Public Auditor
 
PMDP Presentation Sep-22_Final dt 27.10.2022.pptx
PMDP Presentation Sep-22_Final  dt 27.10.2022.pptxPMDP Presentation Sep-22_Final  dt 27.10.2022.pptx
PMDP Presentation Sep-22_Final dt 27.10.2022.pptxssuserea04ef1
 
Sadeeq Khan_Senior Planning Engineer- Delay Analyst
Sadeeq Khan_Senior Planning Engineer- Delay AnalystSadeeq Khan_Senior Planning Engineer- Delay Analyst
Sadeeq Khan_Senior Planning Engineer- Delay AnalystSadeeq Ullah Khan
 

Similar to TC Presentation_M&E Team_May25.pptx (20)

Performance Audit of GBPWD.pptx
Performance Audit of GBPWD.pptxPerformance Audit of GBPWD.pptx
Performance Audit of GBPWD.pptx
 
Gujarat surface water
Gujarat surface waterGujarat surface water
Gujarat surface water
 
Norhtern Power Distribution Project
Norhtern Power Distribution ProjectNorhtern Power Distribution Project
Norhtern Power Distribution Project
 
Government recognized new advance material for sustainable construction of ro...
Government recognized new advance material for sustainable construction of ro...Government recognized new advance material for sustainable construction of ro...
Government recognized new advance material for sustainable construction of ro...
 
Circular letter-no-2022-5 workshop on the guidelines in fy 2023 tagging of go...
Circular letter-no-2022-5 workshop on the guidelines in fy 2023 tagging of go...Circular letter-no-2022-5 workshop on the guidelines in fy 2023 tagging of go...
Circular letter-no-2022-5 workshop on the guidelines in fy 2023 tagging of go...
 
1st APR-URP Presentation
1st APR-URP Presentation 1st APR-URP Presentation
1st APR-URP Presentation
 
Construction Planning of an Offshore Petroleum Platform
Construction Planning of an Offshore Petroleum PlatformConstruction Planning of an Offshore Petroleum Platform
Construction Planning of an Offshore Petroleum Platform
 
Civil_Geotech Engg Proposal of new and details of existing PG programmes afte...
Civil_Geotech Engg Proposal of new and details of existing PG programmes afte...Civil_Geotech Engg Proposal of new and details of existing PG programmes afte...
Civil_Geotech Engg Proposal of new and details of existing PG programmes afte...
 
Departmental Briefing to Secretary Works on 08-02-2023.pptx
Departmental Briefing to Secretary Works on 08-02-2023.pptxDepartmental Briefing to Secretary Works on 08-02-2023.pptx
Departmental Briefing to Secretary Works on 08-02-2023.pptx
 
Update on Implementation of the EIA Process and Remaining Challenges in Oil a...
Update on Implementation of the EIA Process and Remaining Challenges in Oil a...Update on Implementation of the EIA Process and Remaining Challenges in Oil a...
Update on Implementation of the EIA Process and Remaining Challenges in Oil a...
 
Construction management
Construction managementConstruction management
Construction management
 
Circular letter-no-2022-5-dated-february-16-2022
Circular letter-no-2022-5-dated-february-16-2022Circular letter-no-2022-5-dated-february-16-2022
Circular letter-no-2022-5-dated-february-16-2022
 
EDC3_Action_Plan_2016-01-01 rev 1
EDC3_Action_Plan_2016-01-01 rev 1EDC3_Action_Plan_2016-01-01 rev 1
EDC3_Action_Plan_2016-01-01 rev 1
 
Amrut ppt
Amrut pptAmrut ppt
Amrut ppt
 
Aem 606 eia eac-b9-2
Aem 606 eia eac-b9-2Aem 606 eia eac-b9-2
Aem 606 eia eac-b9-2
 
Report No.11 of 2021 - Performance Audit on Implementation of Phase-III, Delh...
Report No.11 of 2021 - Performance Audit on Implementation of Phase-III, Delh...Report No.11 of 2021 - Performance Audit on Implementation of Phase-III, Delh...
Report No.11 of 2021 - Performance Audit on Implementation of Phase-III, Delh...
 
PMDP Presentation Sep-22_Final dt 27.10.2022.pptx
PMDP Presentation Sep-22_Final  dt 27.10.2022.pptxPMDP Presentation Sep-22_Final  dt 27.10.2022.pptx
PMDP Presentation Sep-22_Final dt 27.10.2022.pptx
 
Sadeeq Khan_Senior Planning Engineer- Delay Analyst
Sadeeq Khan_Senior Planning Engineer- Delay AnalystSadeeq Khan_Senior Planning Engineer- Delay Analyst
Sadeeq Khan_Senior Planning Engineer- Delay Analyst
 
TEC Presentation.pptx
TEC Presentation.pptxTEC Presentation.pptx
TEC Presentation.pptx
 
Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012
 

More from Morshed Denar Alam Manna

More from Morshed Denar Alam Manna (6)

(SL Rev-2) 12 QPR PP Presentation_SL_Env_M&E Team_25 May 2021.pptx
(SL Rev-2) 12 QPR PP Presentation_SL_Env_M&E Team_25 May 2021.pptx(SL Rev-2) 12 QPR PP Presentation_SL_Env_M&E Team_25 May 2021.pptx
(SL Rev-2) 12 QPR PP Presentation_SL_Env_M&E Team_25 May 2021.pptx
 
AGENCY-WISE PHY.pptx
AGENCY-WISE PHY.pptxAGENCY-WISE PHY.pptx
AGENCY-WISE PHY.pptx
 
Arsenic a natural threat
Arsenic   a natural threatArsenic   a natural threat
Arsenic a natural threat
 
Canal revitalization
Canal revitalizationCanal revitalization
Canal revitalization
 
Limits to-growth-digital-scan-version
Limits to-growth-digital-scan-versionLimits to-growth-digital-scan-version
Limits to-growth-digital-scan-version
 
Jamuna bridge denar_final_19_feb20
Jamuna bridge denar_final_19_feb20Jamuna bridge denar_final_19_feb20
Jamuna bridge denar_final_19_feb20
 

Recently uploaded

Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIkoyaldeepu123
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 

Recently uploaded (20)

Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AI
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 

TC Presentation_M&E Team_May25.pptx

  • 1. Presentation for Technical Committee Meeting Bangladesh Urban Resilience Project Presentation by M&E Team / PCMU May 25, 2021
  • 2. Overview of URP Bangladesh Urban Resilience Project Key Information Name of the project Bangladesh Urban Resilience Project Funding information Total Project Cost : US$ 182.00 million The world Bank Part : US$ 173.00 million GoB Part : US$ 9.00 million Implementing agency  Department of Disaster Management (DDM)  Dhaka North City Corporation (DNCC) o Dhaka South City Corporation (DSCC) o Sylhet City Corporation (SCC) o Fire Service and Civil Defence (FSCD)  Rajdhani Unnayan Kartipakkha (RAJUK)  PCMU, Planning Commission Duration of the project 1st Phase : March 2015 to June 2020 (Completed) Restructured phase : July 2020 to April 2022 (ongoing) Total financial progress Total Approved cost : 151,300 Lac BDT Expenditure up to Feb 2021 : 87,776.82 i.e., 57.35% 86,776.82 (57.35%)
  • 4. DDM’s Progress to Renovate NDMRTI and ERCC (A-1) A-1: Renovate office space in DDM building for NDMRTI & ERCC NDMRTI (National Disaster Management Research and Training Institute): Renovation and Decoration completed for 7th floor : Office room and training center; 8th floor: 4 Training center (Sidr, Aila, Foni & Amphan) and 2 computer lab 9th floor : Mujib corner (901), Multi purpose hall (902), Library (903) and Auditorium (904) ERCC (Emergency Response and Communication Centre): Renovation Completed for ICT server room, media centre, ERCC observation room & emergency exit. Handover not yet done by the contractor due to pending approval of additional work from the Ministry. Procurement of ICT equipment on process to renovate ERCC & NDMRTI.
  • 5. DDM’s Progress on Training, Exercise and Drill (A-5)  Training postponed since 3rd week of March 2020. TED contract ended with REM/DTCL in November 18, 2020  Force Majeure claimed by REM/DTCL with significant amount of contract value as compensation.  Financial Settlement between DDM PIU and REM/DTCL is getting delayed for long time;  Early amicable settlement needed so that the left over amount if available could be utilized.  Potential High Risk for not achievement of PDO Indicator 3, IRI 6 & 7
  • 6. DNCC Progress on A-2 For DNCC, DSCC & SCC - 30 Facilities  8 Emergency Warehouses (DNCC-5, DSCC-3),  3 EOC (DNCC, DSCC & SCC) associated with 1 URI (Sylhet),  8 DRM Offices (DNCC, DSCC),  10 Zonal Control Rooms (1 control room at each zonal office) – For FSCD- 28 Facilities  2 Command & Control Rooms (Mirpur, Dhaka and Sylhet),  13 Emergency Management Warehouses (11 Dhaka, 2 Sylhet)  13 Auxiliary Control Rooms 1. Gazipur 2. Narayanganj 3. Mymensingh 4. Chittagong 5. Comilla 6. Jashore 7. Rajshahi 8. Rangpur 9. Barisal 10. Sylhet Tender floated for the Construction of Greenfield Tower (60m wireless tower) at Eight (8) different location for DNCC, DSCC, SCC and Ten (10) following location for FSCD. A-2 Target: Construction of Emergency Response Facilities
  • 7. DNCC Progress on A-3 A-3: Emergency Communication Technology (ECT) equipment  Purchase ongoing for ICT equipment of EOC and CoC (1.18 & 1.19- waiting for contract sign), EOC-DSCC, SCC & COC-FSCD (Dhaka & Sylhet)  Purchase ongoing for ICT equipment for NDMRTI & ERCC of DDM; (Pk 1.15- Tender Eval on-gong).  ICT Equipment for FSCD Expected Delivery (Pk-1.8), May 30, 2021 (already in the port)
  • 8. DNCC Progress A-4: Procurement of Search and Rescue (SAR) equipment  Following SAR equipment purchased  22 SAR Equipment (vehicle),  5 Water rescue vehicles,  6 Breathing apparatus,  950 Rescue suits,  30 Chemical suits  900 Searchlights,  3 Drones,  4 Mortuary Vans,  6 Rescue carrying vehicles  SAR equipment for warehouse (Drill machine, generator, torchlight etc..)  3 Cranes,  3 Wheel type excavators,  3 Chain type excavators,  3 Bulldozers.  3 Ladders (64-meter)  10 Ambulances  5 Hazmat Materials 3 rescue boat remaining for purchase (tentative delivery July 30, 2021)
  • 9. RAJUK Progress on B1  Status of B1 -Vulnerability Assessment of Critical and Essential Facilities  Approval done of “Comprehensive Situation Analysis Report” (CSAR)- (MD-1); - January 12, 2020.  Approval done of Individual reports for structures assessed (2 million Sqm) of 1st Level Rapid Visual Assessment (RVA) -(MD-02); - March 7, 20.  Field work of 5 million sqm Rapid Visual Assessment (RVA) completed; (Submission for 1 million RVA report pending out of remaining 3 million sqm).  Preliminary Engineering assessment Report–PEA (MD-4&5) on-going; (0.59 million sqm out of 1 million sqm PEA done. (tentative completion: May-21).  Detailed Engineering Assessment work already started.
  • 10. Progress on B2 Status of B2- RSLUP (Risk Sensitive Land use planning)  Approval done of Final SEA Report (MD-01); - September 13, 2020  Approval done of Final Consultation Report and Comprehensive Situational Analysis and Diagnosis Report (MD-2);-June 12, 2020.  Approval done of Preliminary Risk Assessment, Strategic Framework and Geological Survey Plan (MD-3); April 12 2020.  Geotechnical Tests are on-going for:  Microtremor Test (MT)- (GD-1); Standard Penetration Test (SPT)- (GD-2); Cone Penetration Test (CPT)-(GD-3); Seismic Downhole Test (SDHT)-(GD-4); Seismic Cone Penetration Test (SCPT)-(GD-5); Tentative Completion-Apr-21.  Geo Analysis and Modeling as well as Development of Risk Sensitive Land Use Strategy of Dhaka City (MD-4); is On-going.
  • 11. C-1: Establishment of URU Building Approval done of Architectural, Structural and MEP, BoQ, Bidding document and Design Report (S-11); December, 2019. Contract signed for URU building (W-1) October 20, 2020. Physical works started. Shore pile work & Load test are completed while service pile work and earth excavation are going on. Lab and Field equipment Delivered so far…: Seismic Lab Equipment for URU (G-12) (Aug-2020) Seismic Field Equipment for URU (G-13) (Aug-2020) Field Equipment for Vulnerability Assessment Aspect of Structures & Geo- physics (G-15) (Mar-2020) PA System, Telecommunication, Access Control & Security and General Electrical Equipment for PIU Office (G-18) (Jul-2020). RAJUK Progress on C-1
  • 12. URU Operationalization (S-6 with RTI) Approval done of Situation Analysis and Feasibility Report (SAFR); Mar-2019. Approval done of Institutional Design & Organizational Study (IDOS) Report; Oct-2019. Approval done of Community Outreach Campaign Report ; Jun- 2020. Submitted training documents for the URU Training Materials and Documentation delivered; All related Training completed. RAJUK Progress on C-1
  • 13. C-2: Electronic Construction Permitting System (S-7 with RTI) Approved Electronic Construction Permitting Assessment Report (CPAR); done in Oct 2019. Approval done of Strategic Plan Report with E-Permit Implementation Action Plan, done in June 2020. Approval done of Business Rules Specification (BRS) Report in April 2020.  In-House Testing (IHT) done (ECP v2 Alpha Testing & Beta testing –Sept 22, 2020); User Acceptance Test (UAT) and Operational Acceptance Test (OAT) done by April 11, 2021. RAJUK Progress on C-2 & C-3 C-3: Professional Accreditation Program After long waiting for designing the package and approval from ministry contract has been signed with ICC on March 1, 2021. The Consultant has submitted the draft Inception report and yet to validate it.
  • 14. C-4: Improved Building Code Enforcement (S-9 with ICC)  Approval done of Situation Analysis Report; on December 2019.  Approval done of Concept Note Report (CNR) for URU; on April, 2020 after validation.  Proposed Program for Building Codes and Construction Code Enforcement Report submitted on April and Approved on Jun- 2020. Validation meeting done Nov-30, 2020  Training and Capacity Building Report targeted to submit it within May 2021 (Major upcoming milestone) RAJUK Progress on C-4
  • 15. PCMU Progress (Component-D)- Cont. Component D: Projects Coordination, Monitoring and Evaluation PCMU Organized: 1 TC Meeting, 1 PSC Meeting, 1 Coordination meeting M&E Team meet with the Implementing Agencies Meeting with DNCC on January 6, 12 and March 14, 15 (FSCD) Meeting with DDM on February 14, March 24 Field visit to monitor SPT, West Paikpara, Mirpur on December 22, Field visit to monitor Seismic Downhole Test (SDHT), Biruia, Savar on February 10, 2021 Field visit to monitor RVA and PEA, Mirpur Ideal Girls College on March 4, 2021 Field visit to monitor URU Construction progress (March 3, 7, 11, 15, 2021)
  • 16. Project Approved cost and financial progress Sl. No Implementing Agency Name Total Approved Cost (RDPP) (in lac Tk.) Expenditure for FY 20-21 Vs ADP All.. Total Expenditure (Up to Feb 2021) 1 URP: DNCC 80,590 4,528.77 (87%) 59,859.51 (74.3%) 2 URP: RAJUK 53,665 3,727.49 (134%) 19,851.36 (37%) 3 URP: DDM 12,515 467.34 (11%) 4,887.50 (39%) 4 URP: PCMU 4,530 652.66 (53%) 2,178.45 (48%) Total 151,300 9,376.3 (69.6%) 86,776.82 (57.35%) Total project cost US $182 million. (US $173 million IDA Credit, US $9 million from GoB as operating costs. Project Duration: March 2015 to April 2022;
  • 17. Challenges Due to postponement of Training, Exercise and Drill (TED), the achievement of PDOI -3, IRI-6 & 7 are at high risk; Due to delayed financial settlement with REM/DTCL the financial restructuring (if needed for Rajuk) could be delayed Completion of URU Construction within the project duration is tight and could be delayed; specially the service pile work might not be completed within the scheduled period before the rainy season starts; URU Operationalization -- within the project duration (April 2022) is challenging due to shortage of fund and the timeframe. Operation & Maintenance (O&M) of purchased Goods & equipment and overall Sustainability of URP; Less Follow up mechanism and attention to address the PSC and Technical committee decision.
  • 18. Recommendations & Conclusions (long Term)  Following issues need t0 be anlysed and reviewed critically. 1. Essentialness of TED; that is very crucial to achieve PDIO 3, IRI 6 &7. We have facilities and equipment, now we need trained staff to utilize the facilities and equipment. We must have to restart TED. 2. Vulnerability Assessment (B1)- If the RVA (5m-sqm) --->PEA (1m sqm)---->DEA (.4m sqm). What will be the aftermath of rest 4m PEA and subsequent DEA and its implementation? Besides, Vulnerability Assessment shouldn’t be confined only within Dhaka city.
  • 19. Recommendations & Conclusions (long Term)-cont.. 3. URU construction & Operationalization– Package S-6 will be ended in June 2021. Package S-6 needs to be redefined to increase its scope of work with a view to fully operationalize the URU. This is a comprehensive task. 4. Comprehensive plan & budget for Operation & Maintenance (O&M) of purchased Goods & equipment is a persistent issue that needs to be addressed for overall Sustainability of URP; Considering the progress affected for COVID pandemic & understanding the above critical and essential requirements; those aren’t possible to be completed within April, 2022. We recommend to initiate URP-II (decision time now??) with additional budget to complete the mentioned tasks among others.
  • 20. Recommendations & Conclusions (Short term)  TED is essential to achieve PDIO 3, IRI 6 &7. There is no alternative of TED to achieve these indicators. Considering the short duration of the project G2G system to hire trainers/mentors and conduct training would serve the purpose.  DDM is recommended to complete the financial settlement with REM/DTCL asap so that the left over amount could be utilized.  A financial restructuring is needed end of this FY 2020-2021. The unutilized fund of DNCC, DDM and PCMU could be contributed to completed the additional requirement of Rajuk
  • 21. Recommendations & Conclusions (Short term)  Construction of two basement (Mat foundation) for URU is very critical to complete before rainy reason.  Considering from the project Evaluation point of view, it is essential either to complete TED to achieve the mentioned indicators or Restructure the Results Framework and Readjust the scope of Indicators those are related to Training, Exercise and Drills.  We strongly recommend a follow up mechanism to implement the PSC meeting decision more effectively. PCMU could play the most vital role to look into this matter.