SlideShare a Scribd company logo
1 of 7
Download to read offline
T H E P R O J E C T F O R A S S E S S M E N T O F
E A R T H Q U A K E D I S A S T E R R I S K F O R
T H E K A T H M A N D U V A L L E Y I N N E P A L
JICA ProjectTeam
2nd Seminar
-Seismic Risk Assessment
for Kathmandu Valley-
Ryoji Takahashi
11th April 2017
Introduction of the Project and
Overall Progress
2
Background and Outline of Project
Main Activities and Progress
Towards Effective Utilization of Project
Outcomes
Contents
3
Background
In 2002, JICA conducted “The Study on
Earthquake Disaster Mitigation in the Kathmandu
Valley of Nepal”. Now, social environment has
greatly changed since then.
Government of Nepal submitted a request to
government of Japan for updating seismic risk
assessment and, agreed to implement the
project in January, 2015.
On 25 April 2015, Gorkha EQ occurred at the
time just about to commence this project and
caused severe damage both in and out of KV.
However, there is still possibility of earthquakes
around KV in the future and need to prepare.
JICA project team and counterparts discussed the
new needs after the earthquake and started the
project from May 2015 with modification on the
project components agreed in June 2015.
Seismic Gap Kathmandu
Possibility of devastating earthquake
Damage of Gorkha Earthquake
First JCC meeting
4
Study Area Hazard and Risk Assessment :
Kathmandu Valley
Pilot Activities:
Three Pilot Municipalities:
Lalitpur Metropolitan City,
Bhaktapur Municipality,
Budhanilkantha Municipality
Hazard and Risk Assessment :
Kathmandu Valley
Pilot Activities:
Three Pilot Municipalities:
Lalitpur Metropolitan City,
Bhaktapur Municipality,
Budhanilkantha Municipality
Kathmandu Valley
Kathmandu
District
Lalitpur
District
Bhaktapur
District
5
Study Area
The study area (KV) consists of 2 Metropolitan cities, 16 Municipalities and parts of 2 Rural
Municipalities.
Total wards: 232
BHAKTAPUR
Bhaktapur Municipality
Changunarayan
Madhyapur Thimi Municipality
Suryabinayak
KATHMANDU
Budhanilkantha
Chandragiri
Dakshinkali
Gokarneshwar
Kageshwori Manohara
Kathmandu Metropolitan
Kirtipur Municipality
Nagarjuna
Shankharapur
Tarkeshwar
Tokha
LALITPUR
Bagmati Rural Municipality
Godawari
Konjyosom Rural Municipality
Lalitpur Metropolitan
Mahalaxmi
6
Objectives and Outputs
Objectives: To assess seismic hazard and risk based on scenario earthquakes
with consideration of earthquake environment after the Gorkha Earthquake, and
to develop disaster risk reduction and management plan for concrete and effective
promotion of disaster risk reduction and management measures in the future.
Outputs:
Output 1: Seismic hazard assessment based on the latest knowledge and detail
ground model for Kathmandu Valley
Output 2: seismic risk assessment based on the results of seismic hazard assessment,
considering several earthquake occurrence scenes (date, time, etc.)
Output 3: Enhancement of knowledge for updating seismic risk assessment in
accordance with the social environment change in the future
Output 4: Formulation of build back better recovery and reconstruction plan and
disaster risk reduction and management plan making use of the seismic
hazard and risk assessment results for pilot municipalities
Understanding HazardUnderstanding Hazard
Understanding RiskUnderstanding Risk
Can be updated by Nepali SideCan be updated by Nepali Side
Plan and Implement to Reduce
Estimated Damages
Plan and Implement to Reduce
Estimated Damages
7
WG2: Risk
Assessment
WG3: Pilot ActivitiesWG1: Hazard Assessment
Main Activities
BBB Reconstruction Plan
for Pilot Municipalities
Disaster Risk Reduction
and Management Plan
Seismic Hazard
Assessment
Soil Investigation
Emergency
Response
Chronicle Survey
Standard Operation
Procedures
Building Damage and
Inventory Survey
Scenario Earthquake
Seismic Risk
Assessment
Evaluation of the
Results of 2002 Project
Construction of
Cut Model
Safe Kathmandu
Campaign
Original Components
Supplement components
8
Project Time Frame
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
13
14
16
16-1 Profile and damage survey
16-2 Vision on BBB plan
16-3 Policy on BBB plan
16-4 Action Plan on BBB plan
20
20-1 Determination of scenario earthquakes
20-2 Preliminary hazard analysis
20-3 Hazard analysis (intensity, landslide, etc.)
21
21-1 Building damage and building inventory
21-2 Development of building inventory GIS DB
21-3 Infrastructure and lifeline data
21-4 Population and social economic data
21-5 Investigation for risk assessment method
31
31-1 Earthquake occurrence occasion
31-2 Detail survey of typical buildings
31-3 Updating fragility curves of 2002
31-4 Damage assessment for buildings
31-5 Damage assessment for infrastructure
31-6 Human damage assessment
31-7 Economic damage assessment
32
32-1 Development of DRRMP
32-2 CB for local governmental officials
32-3 CB for community based DRR
33
Seismic risk assessment
Disaster risk reduction and management plan
Development of SOP
Construction of Model House
Urgent resilient and safe Kathmandu campaign
Recovery and reconstruction plan
Seismic hazard analysis
Data collection for seismic risk assessment
2nd Year
1st Year
Time Schedule
        Activities
2015 2016 2017 2018
1st Phase 2nd Phase
Implementation Period: May 2015 – April 2018
Seismic Risk Assessment: Feb. 2017Seismic Risk Assessment: Feb. 2017
Seismic Hazard Assessment: June 2016Seismic Hazard Assessment: June 2016
DRRM Plan: Dec 2017DRRM Plan: Dec 2017
SOP: September 2017SOP: September 2017
CBDRRM: Dec 2017CBDRRM: Dec 2017
Reconstruction Plan: May 2016Reconstruction Plan: May 2016
9
Main Activities and Progress
WG1: Seismic Hazard Assessment
WG2: Seismic Risk Assessment
WG3: Pilot Activities
Standard Operation Procedure (SOP)
Disaster Risk Reduction and Management Plan
Community-based Disaster Risk Reduction and
Management (CBDRRM) Activities
10
Seismic Hazard and Risk Assessment
Current Progress:
• All activities completed in February 2017
WG1 and WG2 Activity
Explain in Agenda No. 6Explain in Agenda No. 6
11
Approach of Seismic Hazard and Risk Assessment
Earthquake Source
Amplification
Attenuation
Total damage is mainly affected by intensity of ground motion,
vulnerability of structure and the number of vulnerable structure 12
Target Items for Seismic Risk Assessment
Building Road Bridge
Water & Sewage Power & Communication Human and Economic Loss
13
Pilot Activities
• Formulation of BBB RR Plans for 3 Pilot
Municipalities completed in May 2016
• Formulation of DRRMP, SOP and
implementation of CBDRRM Activities are on
going
WG3 Activity
Formulation of Standard Operation Procedures (SOP)
(Dec 2016 - Sep 2017)
Research existent materials in Nepal and Japan
Nepal
Japan
National Disaster Response
Framework (MoHA)
STANDARD OPERATING PROCEDURES (SOPs)
National Emergency Operation Center (NEOC)
Ministry of Home Affairs (MoHA)
Yokosuka City Fuchu City
Formulation of Standard Operation Procedures (SOP)
(Dec 2016 - Sep 2017)
Development First Draft SOP based on existent materials
First draft SOP was developed based on existent materials.
[Table of Contents]
1. General Description of Manual
2. Mobilization of officials
3. Establishment of Emergency Response Head Quarter (ERHQ)
4. Disaster Response Activities against Earthquake
[Appendix]
FORMAT A: Check List
FORMAT B: Disaster Information Format
FORMAT C: List of Evacuee at Evacuation Shelter
FORMAT D: Personal Data of Officials
Contents of SOP will be discussed and modified on
workshops in 3 municipalities.
Formulation of Standard Operation Procedures (SOP)
(Dec 2016 - Sep 2017)
Work Plan
2017
Mar Apr May Jun Jul Aug Sep
SOP
Guideline
Workshop
/ Meeting
Meetings
* MoHA, DAO
and 3
Municipals
Last Workshop
* Invite MoHA,
DAO and 3
Municipalities
Workshops in Lalitpur, Bhaktapur,
Budhanilkantha
*aim of this workshop is to discuss and modify
SOP for localization
First Draft
Modification and
localization
Modification and
localization
Localization for 3 municipalities
Second Draft
Finalized
Workshops in 3 municipalities will be
conducted in this period.
17
Testing stage
MoFALD Local Disaster Risk
Management Planning Guideline,
2011
Feedback
Implementation
Revision of Guideline
by Flagship 4 2. Upgrade of Annex : Template
(Table of Contents of Actual
LDRMP)
according to mainly Risk
Assessment and Sendai
Framework for DRR
3. Formulation of Technical
Guideline to support
formulation by Local Bodies
Approval of revised
Guideline by National
Steering Committee
4. Pilot Activities
(LDRMP Formulation
for 3 pilot muni.)
Finalization of Guideline
JICA Project
Activity
[Separate Document]
~May 2017
May~Dec 2017
~Apr 2017
Formulation of Disaster Risk Reduction and
Management (DRRM) Plan with Guideline
(Dec 2016 - Dec 2017)
1. Integration of Risk
Assessment part
18
Utilization image of Risk Assessment Results for DRR
(Summary)
Building
damage
Setting Target
Value for DRR
Setting Target
Value for DRR
Considering
Countermeasures
to achieve targets
Considering
Countermeasures
to achieve targets
Reduce the number of
100 50 or more fewer
Reduce the number of
Deaths
100 ⇒ 50 or more fewer
Reduce the number of
10,000 3,000
Reduce the number of
Evacuees
10,000 ⇒ 3,000
Reduce the number of
2,000 1,000
Reduce the number of
Heavy damage building
2,000 ⇒ 1,000
Seismic resistance of housing
Mason training
Building code implementation
Development of Evacuation sites
Securing Stockpiles
LDRMPLDRMP
Result of Risk AssessmentResult of Risk Assessment
Number of
death
Target year 2030
Image of the Plan
20162016 20302030
Infrastructure, Lifeline
Damage, Economic Loss
You can understand How much
seismic resistance of housings
are required
You can understand How much
stockpiles are required
Seismic resistance of Schools, etc.
You can understand Risk and
can consider the Priority
CBDRRM Activities
(Dec 2016 - Dec 2017, Implementation of BBB & DRRM Plan)
• CBDRRM Training for Municipality
Officers and Relevant Stakeholders
Step 1 (20-22 Feb 2017)
• CBDRRM Activities in a selected pilot
ward in each pilot municipality
Step 2 (Apr – Oct 2017)
• Feedback to the Local DRRM Plans
Step 3 (Nov – Dec 2017)
Flow of the Activities
1. Target Participants: 10 officers and relevant
stakeholders who relate to DRRM Activities in each
pilot municipality (Total 30)
2. Venue: Bhangeri Durbar Resort, Nagarkot
3. Program (3 days)
Know Earthquake mechanism and risks
Learn DRRM and CBDRRM incl. 9 Minimum
Characteristics of CBDRRM in Nepal
CBDRRM Mapping
CBDRRM Planning
Pilot Wards/Location
Lalitpur SMC Budhanilkantha Bhaktapur
Ward-8/ Gokul
Chaur
Ward-2
(former Ward 2
and 3)
Ward-3
(former Ward 13
and 16)
Targets of the Activities
(*due to restructuring of wards, the target areas were modified)
Step 1: Training for Municipality Officers
Details of the Activities
Step 2: CBDRRM Activities in Pilot Wards
1. Target Participants: 30 persons (members of CDMC,
and other relevant residents) in a ward
2. Venue: appropriate place in the selected pilot ward
3. Program (3 main events and follow-ups)
1st Workshop (2 days): Learning Risk and DRRM
System in Community
2nd Workshop (2 days): Formulation of CBDRRM
Map
3rd Workshop (1 day): Formulation of Action
Plan/ DRRM Plan for Community
CBDRRM Step 1: 3-day CBDRRM Training for Municipality Officers
and Relevant Stakeholders: 20-22 February 2017
1. Result
30 participants from three pilot municipalities
Enhanced capacities and ownerships of
municipality officers on promoting CBDRRM
activities in each municipality
Created a basis for sustainable CBDRRM
activities in each municipality with a sound
understanding of the importance and needs of
the activities of the municipality officers
Lecture by MoFALD Exercise for Community
DRR Mapping
Discussion on Action Plan for
Promoting CBDRRM
Certificate Distribution
by JS of MoFALD
1st Workshop (2 day)
Learning Risk and DRRM
System in Community
1) Learning Earthquake Hazard
and Risks
2) Learning Basics of Disaster
Risk Reduction and
Management
3) Review and Discussion on
Community's Current Situation
of DRRM and HVCA Assessment
+Follow-up Activities ** (Apr-Jun)
(Documentations, etc.)
2nd Workshop (2 days)
Formulation of Community-
based DRRM Map
1) DRRM Town Watching (Field
Survey by Community)
2) Community DRRM Mapping
3) Discussion on Evacuation Plan
+Follow-up Activities (Jul-Aug)
(Finalization of Map,
Documentations, etc.)
3rd Workshop (1 day)
Formulation of Action Plan/
DRRM Plan for Community
1) Disaster Response Plan for
Community (Information
Dissemination/ Response
Teams/ Equipment and Stocks)
2) Discussion on Action Plans for
Improving DRRM System and
Conditions in Community
3) Ward-level DM Planning
+Follow-up Activities (Sep-Oct)
(Finalization of Plans, Approval
procedure, etc.)
9 MCs: No. 2 & 3 9 MCs: No. 3, 4 & 9 9 MCs: No. 5, 6, 7 & 8
Risk Assessment Hazard & Risk Maps Local DRRM Plans
Pre-Coordination:
Coordination for Designation of the Participants
(CDMC Members + @)
9 MCs*: No. 1
Basic Information
*MCs: Minimum Characteristics
of NRRC Flagship 4
**Follow-up Activities will be
done by the selected members
Feedback
April (6-7: Lalitpur/ 9-10:
Budhanilkantha/tbd: Bhaktapur) June-July August- September
CBDRRM Step 2: CBDRRM Activities in Pilot Wards
March
A Community Activity based on
Action Plan (each pilot ward)
22
Effective Utilization of Project Outcomes
Who will utilize the results of the project
Stakeholders dealt with Disaster Risk Reduction
and Management such as Central and Local
Governments, Relevant Organizations including
NGOs/INGOs, Research Institutes, Private Sector,
Communities, and others are expected to make
effective utilization of the results of the Project to
reduce damages from the estimation results.
23
How to ensure to take actions by various
stakeholders to move forward to implement
prevention and mitigation measures
Needless to say but without implementation, the
same or the worse tragedy will occur by earthquakes.
How to ensure to take actions by various
stakeholders are the key. Not to scare people by the
result of risk assessment, realize the scale of
damages properly, and effective measures need to
be proposed having incentives to the implementers.
Dr. Nishikawa, special guest speaker will
talk more later!
Dr. Nishikawa, special guest speaker will
talk more later!
Effective Utilization of Project Outcomes
24
Remarks
Scenario Earthquakes are not the prediction
of next earthquake.
Based on the scenario earthquakes, hazard
and risk are assessed for KV to utilize for the
purpose of policy making and planning, and
others for effective Disaster Risk Reduction
and Management efforts.
Remarks
Scenario Earthquakes are not the prediction
of next earthquake.
Based on the scenario earthquakes, hazard
and risk are assessed for KV to utilize for the
purpose of policy making and planning, and
others for effective Disaster Risk Reduction
and Management efforts.
25
https://www.facebook.com/JICA-Earthquake-Risk-Assessment-PJ-in-KV-
Nepal-Community-690728411055174/
ERAKV Facebook PageERAKV Facebook Page

More Related Content

What's hot

The IPCC role, history and activities
The IPCC role, history and activitiesThe IPCC role, history and activities
The IPCC role, history and activitiesipcc-media
 
Activities of the Intergovernmental Panel on Climate Change (IPCC)
Activities of the Intergovernmental Panel on Climate Change (IPCC) Activities of the Intergovernmental Panel on Climate Change (IPCC)
Activities of the Intergovernmental Panel on Climate Change (IPCC) FAO
 
Role- IPCC: How it works and what it’s working on Getting more involved
Role- IPCC: How it works and what it’s working onGetting more involvedRole- IPCC: How it works and what it’s working onGetting more involved
Role- IPCC: How it works and what it’s working on Getting more involvedipcc-media
 
What is the IPCC?
What is the IPCC?What is the IPCC?
What is the IPCC?ipcc-media
 
Realising the Carbon Benefits of Sustainable Land Management Practices: Guide...
Realising the Carbon Benefits of Sustainable Land Management Practices: Guide...Realising the Carbon Benefits of Sustainable Land Management Practices: Guide...
Realising the Carbon Benefits of Sustainable Land Management Practices: Guide...Water, Land and Ecosystems (WLE)
 
IPCC History, mandate and the production of the Sixth Assessment Report
IPCC History, mandate and the production of the Sixth Assessment ReportIPCC History, mandate and the production of the Sixth Assessment Report
IPCC History, mandate and the production of the Sixth Assessment Reportipcc-media
 
IPCC Role and Activities
IPCC Role and ActivitiesIPCC Role and Activities
IPCC Role and Activitiesipcc-media
 
Overview of the IPCC, its role, mandate, history and the production of the IP...
Overview of the IPCC, its role, mandate, history and the production of the IP...Overview of the IPCC, its role, mandate, history and the production of the IP...
Overview of the IPCC, its role, mandate, history and the production of the IP...ipcc-media
 
Mitigation of Climate Change
 Mitigation of Climate Change Mitigation of Climate Change
Mitigation of Climate Changeipcc-media
 
The Sixth Assessment Cycle and how to be involved in the IPCC work
The Sixth Assessment Cycle and how to be involved in the IPCC workThe Sixth Assessment Cycle and how to be involved in the IPCC work
The Sixth Assessment Cycle and how to be involved in the IPCC workipcc-media
 
Media workshop - How does the IPCC work
Media workshop - How does the IPCC workMedia workshop - How does the IPCC work
Media workshop - How does the IPCC workipcc-media
 
Academia - SESSION 2: Updates on the preparation of Working Group (WG) I cont...
Academia - SESSION 2: Updates on the preparation of Working Group (WG) I cont...Academia - SESSION 2: Updates on the preparation of Working Group (WG) I cont...
Academia - SESSION 2: Updates on the preparation of Working Group (WG) I cont...ipcc-media
 
IPCC 6th Assessment Report Summary for Urban Policymakers - Introduction
IPCC 6th Assessment Report Summary for Urban Policymakers - Introduction IPCC 6th Assessment Report Summary for Urban Policymakers - Introduction
IPCC 6th Assessment Report Summary for Urban Policymakers - Introduction ipcc-media
 
Full Eecs Report Draft 11 05 2009
Full Eecs Report Draft 11 05 2009Full Eecs Report Draft 11 05 2009
Full Eecs Report Draft 11 05 2009Kim Mitchell
 
The AR6 process: How the IPCC produces reports
The AR6 process: How the IPCC produces reportsThe AR6 process: How the IPCC produces reports
The AR6 process: How the IPCC produces reportsipcc-media
 
IPCC role and activities and how does the IPCC work
IPCC role and activities and how does the IPCC workIPCC role and activities and how does the IPCC work
IPCC role and activities and how does the IPCC workipcc-media
 
Climate Change Impacts and Adaptation for Fiji
Climate Change Impacts and Adaptation for Fiji Climate Change Impacts and Adaptation for Fiji
Climate Change Impacts and Adaptation for Fiji ipcc-media
 

What's hot (20)

The IPCC role, history and activities
The IPCC role, history and activitiesThe IPCC role, history and activities
The IPCC role, history and activities
 
Activities of the Intergovernmental Panel on Climate Change (IPCC)
Activities of the Intergovernmental Panel on Climate Change (IPCC) Activities of the Intergovernmental Panel on Climate Change (IPCC)
Activities of the Intergovernmental Panel on Climate Change (IPCC)
 
Role- IPCC: How it works and what it’s working on Getting more involved
Role- IPCC: How it works and what it’s working onGetting more involvedRole- IPCC: How it works and what it’s working onGetting more involved
Role- IPCC: How it works and what it’s working on Getting more involved
 
What is the IPCC?
What is the IPCC?What is the IPCC?
What is the IPCC?
 
Realising the Carbon Benefits of Sustainable Land Management Practices: Guide...
Realising the Carbon Benefits of Sustainable Land Management Practices: Guide...Realising the Carbon Benefits of Sustainable Land Management Practices: Guide...
Realising the Carbon Benefits of Sustainable Land Management Practices: Guide...
 
IPCC History, mandate and the production of the Sixth Assessment Report
IPCC History, mandate and the production of the Sixth Assessment ReportIPCC History, mandate and the production of the Sixth Assessment Report
IPCC History, mandate and the production of the Sixth Assessment Report
 
IPCC Role and Activities
IPCC Role and ActivitiesIPCC Role and Activities
IPCC Role and Activities
 
Bur malaysia final
Bur malaysia finalBur malaysia final
Bur malaysia final
 
Overview of the IPCC, its role, mandate, history and the production of the IP...
Overview of the IPCC, its role, mandate, history and the production of the IP...Overview of the IPCC, its role, mandate, history and the production of the IP...
Overview of the IPCC, its role, mandate, history and the production of the IP...
 
Mitigation of Climate Change
 Mitigation of Climate Change Mitigation of Climate Change
Mitigation of Climate Change
 
The Sixth Assessment Cycle and how to be involved in the IPCC work
The Sixth Assessment Cycle and how to be involved in the IPCC workThe Sixth Assessment Cycle and how to be involved in the IPCC work
The Sixth Assessment Cycle and how to be involved in the IPCC work
 
Media workshop - How does the IPCC work
Media workshop - How does the IPCC workMedia workshop - How does the IPCC work
Media workshop - How does the IPCC work
 
Academia - SESSION 2: Updates on the preparation of Working Group (WG) I cont...
Academia - SESSION 2: Updates on the preparation of Working Group (WG) I cont...Academia - SESSION 2: Updates on the preparation of Working Group (WG) I cont...
Academia - SESSION 2: Updates on the preparation of Working Group (WG) I cont...
 
IPCC 6th Assessment Report Summary for Urban Policymakers - Introduction
IPCC 6th Assessment Report Summary for Urban Policymakers - Introduction IPCC 6th Assessment Report Summary for Urban Policymakers - Introduction
IPCC 6th Assessment Report Summary for Urban Policymakers - Introduction
 
Full Eecs Report Draft 11 05 2009
Full Eecs Report Draft 11 05 2009Full Eecs Report Draft 11 05 2009
Full Eecs Report Draft 11 05 2009
 
The AR6 process: How the IPCC produces reports
The AR6 process: How the IPCC produces reportsThe AR6 process: How the IPCC produces reports
The AR6 process: How the IPCC produces reports
 
IPCC role and activities and how does the IPCC work
IPCC role and activities and how does the IPCC workIPCC role and activities and how does the IPCC work
IPCC role and activities and how does the IPCC work
 
Final booklet
Final bookletFinal booklet
Final booklet
 
Climate Change Impacts and Adaptation for Fiji
Climate Change Impacts and Adaptation for Fiji Climate Change Impacts and Adaptation for Fiji
Climate Change Impacts and Adaptation for Fiji
 
TERI
TERI TERI
TERI
 

Similar to 1. Erakv 2nd seminar: Introduction of the project and its overall progress

Progress of Pilot Activities
Progress of Pilot ActivitiesProgress of Pilot Activities
Progress of Pilot ActivitiesYasuhiro Kawasoe
 
Item 7. Discussion on PWB 2023-24 work related to adaptation
Item 7. Discussion on PWB 2023-24 work related to adaptationItem 7. Discussion on PWB 2023-24 work related to adaptation
Item 7. Discussion on PWB 2023-24 work related to adaptationOECD Environment
 
TA-7779 Inception Workshop
TA-7779 Inception WorkshopTA-7779 Inception Workshop
TA-7779 Inception WorkshopSon Ha-Dang
 
Cv govind acharya for senior engineer
Cv  govind acharya for senior engineerCv  govind acharya for senior engineer
Cv govind acharya for senior engineerGovind Acharya
 
P carbono acre-vcs workshop_12_jun13
P carbono acre-vcs workshop_12_jun13P carbono acre-vcs workshop_12_jun13
P carbono acre-vcs workshop_12_jun13Idesam
 
Risk sensitive spatial planning in global south
Risk sensitive spatial planning in global south Risk sensitive spatial planning in global south
Risk sensitive spatial planning in global south Mwenje Emmanuel
 
Bunaken Island | Nov-15 | Bitung low carbon model town
Bunaken Island | Nov-15 | Bitung low carbon model townBunaken Island | Nov-15 | Bitung low carbon model town
Bunaken Island | Nov-15 | Bitung low carbon model townSmart Villages
 
Vietnam disaster risk prevention aid system for urban flooding
Vietnam disaster risk prevention aid system for urban floodingVietnam disaster risk prevention aid system for urban flooding
Vietnam disaster risk prevention aid system for urban floodingByoungjaeBJLee
 
2010-09-01-flagship-english(1)
2010-09-01-flagship-english(1)2010-09-01-flagship-english(1)
2010-09-01-flagship-english(1)Yuri Chakalall
 
IRJET- Construction Approach and Schedule Technical for Treatment Plant
IRJET- Construction Approach and Schedule Technical for Treatment PlantIRJET- Construction Approach and Schedule Technical for Treatment Plant
IRJET- Construction Approach and Schedule Technical for Treatment PlantIRJET Journal
 
Report on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeReport on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeKundan Sanap
 
Smp2 part c action plan final
Smp2 part c action plan finalSmp2 part c action plan final
Smp2 part c action plan finalSevern Estuary
 

Similar to 1. Erakv 2nd seminar: Introduction of the project and its overall progress (20)

Erakv news2
Erakv news2Erakv news2
Erakv news2
 
Erakv 3rd Newsletter
Erakv 3rd NewsletterErakv 3rd Newsletter
Erakv 3rd Newsletter
 
Progress of Pilot Activities
Progress of Pilot ActivitiesProgress of Pilot Activities
Progress of Pilot Activities
 
1. River Basin Planning - some key developments - Colin Byrne, DHPLG
1. River Basin Planning - some key developments - Colin Byrne, DHPLG1. River Basin Planning - some key developments - Colin Byrne, DHPLG
1. River Basin Planning - some key developments - Colin Byrne, DHPLG
 
Erakv 1st jcc 1
Erakv 1st jcc 1Erakv 1st jcc 1
Erakv 1st jcc 1
 
Item 7. Discussion on PWB 2023-24 work related to adaptation
Item 7. Discussion on PWB 2023-24 work related to adaptationItem 7. Discussion on PWB 2023-24 work related to adaptation
Item 7. Discussion on PWB 2023-24 work related to adaptation
 
Cv govind acharya
Cv  govind acharyaCv  govind acharya
Cv govind acharya
 
CV Govind Acharya
CV  Govind AcharyaCV  Govind Acharya
CV Govind Acharya
 
EDC3_Action_Plan_2016-01-01 rev 1
EDC3_Action_Plan_2016-01-01 rev 1EDC3_Action_Plan_2016-01-01 rev 1
EDC3_Action_Plan_2016-01-01 rev 1
 
TA-7779 Inception Workshop
TA-7779 Inception WorkshopTA-7779 Inception Workshop
TA-7779 Inception Workshop
 
Cv govind acharya for senior engineer
Cv  govind acharya for senior engineerCv  govind acharya for senior engineer
Cv govind acharya for senior engineer
 
P carbono acre-vcs workshop_12_jun13
P carbono acre-vcs workshop_12_jun13P carbono acre-vcs workshop_12_jun13
P carbono acre-vcs workshop_12_jun13
 
Japan’s efforts on mainstreaming climate change adaptation into vietnamese de...
Japan’s efforts on mainstreaming climate change adaptation into vietnamese de...Japan’s efforts on mainstreaming climate change adaptation into vietnamese de...
Japan’s efforts on mainstreaming climate change adaptation into vietnamese de...
 
Risk sensitive spatial planning in global south
Risk sensitive spatial planning in global south Risk sensitive spatial planning in global south
Risk sensitive spatial planning in global south
 
Bunaken Island | Nov-15 | Bitung low carbon model town
Bunaken Island | Nov-15 | Bitung low carbon model townBunaken Island | Nov-15 | Bitung low carbon model town
Bunaken Island | Nov-15 | Bitung low carbon model town
 
Vietnam disaster risk prevention aid system for urban flooding
Vietnam disaster risk prevention aid system for urban floodingVietnam disaster risk prevention aid system for urban flooding
Vietnam disaster risk prevention aid system for urban flooding
 
2010-09-01-flagship-english(1)
2010-09-01-flagship-english(1)2010-09-01-flagship-english(1)
2010-09-01-flagship-english(1)
 
IRJET- Construction Approach and Schedule Technical for Treatment Plant
IRJET- Construction Approach and Schedule Technical for Treatment PlantIRJET- Construction Approach and Schedule Technical for Treatment Plant
IRJET- Construction Approach and Schedule Technical for Treatment Plant
 
Report on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeReport on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridge
 
Smp2 part c action plan final
Smp2 part c action plan finalSmp2 part c action plan final
Smp2 part c action plan final
 

More from Subhechha Sharma

Erakv project pamphlet_english_version
Erakv project pamphlet_english_versionErakv project pamphlet_english_version
Erakv project pamphlet_english_versionSubhechha Sharma
 
Erakv project pamphlet_nepali_version
Erakv project pamphlet_nepali_versionErakv project pamphlet_nepali_version
Erakv project pamphlet_nepali_versionSubhechha Sharma
 
2 erakv final seminar_seismic hazard
2 erakv final seminar_seismic hazard2 erakv final seminar_seismic hazard
2 erakv final seminar_seismic hazardSubhechha Sharma
 
7 erakv 3rd seminar_building
7 erakv 3rd seminar_building7 erakv 3rd seminar_building
7 erakv 3rd seminar_buildingSubhechha Sharma
 
3. ERAKV 2nd Seminar-Investment
3. ERAKV 2nd Seminar-Investment 3. ERAKV 2nd Seminar-Investment
3. ERAKV 2nd Seminar-Investment Subhechha Sharma
 
2. ERAKV 2nd seminar- Risk Assessment
2. ERAKV 2nd seminar- Risk Assessment2. ERAKV 2nd seminar- Risk Assessment
2. ERAKV 2nd seminar- Risk AssessmentSubhechha Sharma
 
2. ERAKV- 2nd seminar: Risk Assessment
2. ERAKV- 2nd seminar: Risk Assessment2. ERAKV- 2nd seminar: Risk Assessment
2. ERAKV- 2nd seminar: Risk AssessmentSubhechha Sharma
 

More from Subhechha Sharma (9)

Erakv project pamphlet_english_version
Erakv project pamphlet_english_versionErakv project pamphlet_english_version
Erakv project pamphlet_english_version
 
Erakv project pamphlet_nepali_version
Erakv project pamphlet_nepali_versionErakv project pamphlet_nepali_version
Erakv project pamphlet_nepali_version
 
2 erakv final seminar_seismic hazard
2 erakv final seminar_seismic hazard2 erakv final seminar_seismic hazard
2 erakv final seminar_seismic hazard
 
8 erakv 3rd seminar_infra
8 erakv 3rd seminar_infra8 erakv 3rd seminar_infra
8 erakv 3rd seminar_infra
 
7 erakv 3rd seminar_building
7 erakv 3rd seminar_building7 erakv 3rd seminar_building
7 erakv 3rd seminar_building
 
6 disaster management act
6 disaster management act6 disaster management act
6 disaster management act
 
3. ERAKV 2nd Seminar-Investment
3. ERAKV 2nd Seminar-Investment 3. ERAKV 2nd Seminar-Investment
3. ERAKV 2nd Seminar-Investment
 
2. ERAKV 2nd seminar- Risk Assessment
2. ERAKV 2nd seminar- Risk Assessment2. ERAKV 2nd seminar- Risk Assessment
2. ERAKV 2nd seminar- Risk Assessment
 
2. ERAKV- 2nd seminar: Risk Assessment
2. ERAKV- 2nd seminar: Risk Assessment2. ERAKV- 2nd seminar: Risk Assessment
2. ERAKV- 2nd seminar: Risk Assessment
 

Recently uploaded

chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 

Recently uploaded (20)

chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 

1. Erakv 2nd seminar: Introduction of the project and its overall progress

  • 1. T H E P R O J E C T F O R A S S E S S M E N T O F E A R T H Q U A K E D I S A S T E R R I S K F O R T H E K A T H M A N D U V A L L E Y I N N E P A L JICA ProjectTeam 2nd Seminar -Seismic Risk Assessment for Kathmandu Valley- Ryoji Takahashi 11th April 2017 Introduction of the Project and Overall Progress 2 Background and Outline of Project Main Activities and Progress Towards Effective Utilization of Project Outcomes Contents 3 Background In 2002, JICA conducted “The Study on Earthquake Disaster Mitigation in the Kathmandu Valley of Nepal”. Now, social environment has greatly changed since then. Government of Nepal submitted a request to government of Japan for updating seismic risk assessment and, agreed to implement the project in January, 2015. On 25 April 2015, Gorkha EQ occurred at the time just about to commence this project and caused severe damage both in and out of KV. However, there is still possibility of earthquakes around KV in the future and need to prepare. JICA project team and counterparts discussed the new needs after the earthquake and started the project from May 2015 with modification on the project components agreed in June 2015. Seismic Gap Kathmandu Possibility of devastating earthquake Damage of Gorkha Earthquake First JCC meeting 4 Study Area Hazard and Risk Assessment : Kathmandu Valley Pilot Activities: Three Pilot Municipalities: Lalitpur Metropolitan City, Bhaktapur Municipality, Budhanilkantha Municipality Hazard and Risk Assessment : Kathmandu Valley Pilot Activities: Three Pilot Municipalities: Lalitpur Metropolitan City, Bhaktapur Municipality, Budhanilkantha Municipality Kathmandu Valley Kathmandu District Lalitpur District Bhaktapur District
  • 2. 5 Study Area The study area (KV) consists of 2 Metropolitan cities, 16 Municipalities and parts of 2 Rural Municipalities. Total wards: 232 BHAKTAPUR Bhaktapur Municipality Changunarayan Madhyapur Thimi Municipality Suryabinayak KATHMANDU Budhanilkantha Chandragiri Dakshinkali Gokarneshwar Kageshwori Manohara Kathmandu Metropolitan Kirtipur Municipality Nagarjuna Shankharapur Tarkeshwar Tokha LALITPUR Bagmati Rural Municipality Godawari Konjyosom Rural Municipality Lalitpur Metropolitan Mahalaxmi 6 Objectives and Outputs Objectives: To assess seismic hazard and risk based on scenario earthquakes with consideration of earthquake environment after the Gorkha Earthquake, and to develop disaster risk reduction and management plan for concrete and effective promotion of disaster risk reduction and management measures in the future. Outputs: Output 1: Seismic hazard assessment based on the latest knowledge and detail ground model for Kathmandu Valley Output 2: seismic risk assessment based on the results of seismic hazard assessment, considering several earthquake occurrence scenes (date, time, etc.) Output 3: Enhancement of knowledge for updating seismic risk assessment in accordance with the social environment change in the future Output 4: Formulation of build back better recovery and reconstruction plan and disaster risk reduction and management plan making use of the seismic hazard and risk assessment results for pilot municipalities Understanding HazardUnderstanding Hazard Understanding RiskUnderstanding Risk Can be updated by Nepali SideCan be updated by Nepali Side Plan and Implement to Reduce Estimated Damages Plan and Implement to Reduce Estimated Damages 7 WG2: Risk Assessment WG3: Pilot ActivitiesWG1: Hazard Assessment Main Activities BBB Reconstruction Plan for Pilot Municipalities Disaster Risk Reduction and Management Plan Seismic Hazard Assessment Soil Investigation Emergency Response Chronicle Survey Standard Operation Procedures Building Damage and Inventory Survey Scenario Earthquake Seismic Risk Assessment Evaluation of the Results of 2002 Project Construction of Cut Model Safe Kathmandu Campaign Original Components Supplement components 8 Project Time Frame May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar 13 14 16 16-1 Profile and damage survey 16-2 Vision on BBB plan 16-3 Policy on BBB plan 16-4 Action Plan on BBB plan 20 20-1 Determination of scenario earthquakes 20-2 Preliminary hazard analysis 20-3 Hazard analysis (intensity, landslide, etc.) 21 21-1 Building damage and building inventory 21-2 Development of building inventory GIS DB 21-3 Infrastructure and lifeline data 21-4 Population and social economic data 21-5 Investigation for risk assessment method 31 31-1 Earthquake occurrence occasion 31-2 Detail survey of typical buildings 31-3 Updating fragility curves of 2002 31-4 Damage assessment for buildings 31-5 Damage assessment for infrastructure 31-6 Human damage assessment 31-7 Economic damage assessment 32 32-1 Development of DRRMP 32-2 CB for local governmental officials 32-3 CB for community based DRR 33 Seismic risk assessment Disaster risk reduction and management plan Development of SOP Construction of Model House Urgent resilient and safe Kathmandu campaign Recovery and reconstruction plan Seismic hazard analysis Data collection for seismic risk assessment 2nd Year 1st Year Time Schedule         Activities 2015 2016 2017 2018 1st Phase 2nd Phase Implementation Period: May 2015 – April 2018 Seismic Risk Assessment: Feb. 2017Seismic Risk Assessment: Feb. 2017 Seismic Hazard Assessment: June 2016Seismic Hazard Assessment: June 2016 DRRM Plan: Dec 2017DRRM Plan: Dec 2017 SOP: September 2017SOP: September 2017 CBDRRM: Dec 2017CBDRRM: Dec 2017 Reconstruction Plan: May 2016Reconstruction Plan: May 2016
  • 3. 9 Main Activities and Progress WG1: Seismic Hazard Assessment WG2: Seismic Risk Assessment WG3: Pilot Activities Standard Operation Procedure (SOP) Disaster Risk Reduction and Management Plan Community-based Disaster Risk Reduction and Management (CBDRRM) Activities 10 Seismic Hazard and Risk Assessment Current Progress: • All activities completed in February 2017 WG1 and WG2 Activity Explain in Agenda No. 6Explain in Agenda No. 6 11 Approach of Seismic Hazard and Risk Assessment Earthquake Source Amplification Attenuation Total damage is mainly affected by intensity of ground motion, vulnerability of structure and the number of vulnerable structure 12 Target Items for Seismic Risk Assessment Building Road Bridge Water & Sewage Power & Communication Human and Economic Loss
  • 4. 13 Pilot Activities • Formulation of BBB RR Plans for 3 Pilot Municipalities completed in May 2016 • Formulation of DRRMP, SOP and implementation of CBDRRM Activities are on going WG3 Activity Formulation of Standard Operation Procedures (SOP) (Dec 2016 - Sep 2017) Research existent materials in Nepal and Japan Nepal Japan National Disaster Response Framework (MoHA) STANDARD OPERATING PROCEDURES (SOPs) National Emergency Operation Center (NEOC) Ministry of Home Affairs (MoHA) Yokosuka City Fuchu City Formulation of Standard Operation Procedures (SOP) (Dec 2016 - Sep 2017) Development First Draft SOP based on existent materials First draft SOP was developed based on existent materials. [Table of Contents] 1. General Description of Manual 2. Mobilization of officials 3. Establishment of Emergency Response Head Quarter (ERHQ) 4. Disaster Response Activities against Earthquake [Appendix] FORMAT A: Check List FORMAT B: Disaster Information Format FORMAT C: List of Evacuee at Evacuation Shelter FORMAT D: Personal Data of Officials Contents of SOP will be discussed and modified on workshops in 3 municipalities. Formulation of Standard Operation Procedures (SOP) (Dec 2016 - Sep 2017) Work Plan 2017 Mar Apr May Jun Jul Aug Sep SOP Guideline Workshop / Meeting Meetings * MoHA, DAO and 3 Municipals Last Workshop * Invite MoHA, DAO and 3 Municipalities Workshops in Lalitpur, Bhaktapur, Budhanilkantha *aim of this workshop is to discuss and modify SOP for localization First Draft Modification and localization Modification and localization Localization for 3 municipalities Second Draft Finalized Workshops in 3 municipalities will be conducted in this period.
  • 5. 17 Testing stage MoFALD Local Disaster Risk Management Planning Guideline, 2011 Feedback Implementation Revision of Guideline by Flagship 4 2. Upgrade of Annex : Template (Table of Contents of Actual LDRMP) according to mainly Risk Assessment and Sendai Framework for DRR 3. Formulation of Technical Guideline to support formulation by Local Bodies Approval of revised Guideline by National Steering Committee 4. Pilot Activities (LDRMP Formulation for 3 pilot muni.) Finalization of Guideline JICA Project Activity [Separate Document] ~May 2017 May~Dec 2017 ~Apr 2017 Formulation of Disaster Risk Reduction and Management (DRRM) Plan with Guideline (Dec 2016 - Dec 2017) 1. Integration of Risk Assessment part 18 Utilization image of Risk Assessment Results for DRR (Summary) Building damage Setting Target Value for DRR Setting Target Value for DRR Considering Countermeasures to achieve targets Considering Countermeasures to achieve targets Reduce the number of 100 50 or more fewer Reduce the number of Deaths 100 ⇒ 50 or more fewer Reduce the number of 10,000 3,000 Reduce the number of Evacuees 10,000 ⇒ 3,000 Reduce the number of 2,000 1,000 Reduce the number of Heavy damage building 2,000 ⇒ 1,000 Seismic resistance of housing Mason training Building code implementation Development of Evacuation sites Securing Stockpiles LDRMPLDRMP Result of Risk AssessmentResult of Risk Assessment Number of death Target year 2030 Image of the Plan 20162016 20302030 Infrastructure, Lifeline Damage, Economic Loss You can understand How much seismic resistance of housings are required You can understand How much stockpiles are required Seismic resistance of Schools, etc. You can understand Risk and can consider the Priority CBDRRM Activities (Dec 2016 - Dec 2017, Implementation of BBB & DRRM Plan) • CBDRRM Training for Municipality Officers and Relevant Stakeholders Step 1 (20-22 Feb 2017) • CBDRRM Activities in a selected pilot ward in each pilot municipality Step 2 (Apr – Oct 2017) • Feedback to the Local DRRM Plans Step 3 (Nov – Dec 2017) Flow of the Activities 1. Target Participants: 10 officers and relevant stakeholders who relate to DRRM Activities in each pilot municipality (Total 30) 2. Venue: Bhangeri Durbar Resort, Nagarkot 3. Program (3 days) Know Earthquake mechanism and risks Learn DRRM and CBDRRM incl. 9 Minimum Characteristics of CBDRRM in Nepal CBDRRM Mapping CBDRRM Planning Pilot Wards/Location Lalitpur SMC Budhanilkantha Bhaktapur Ward-8/ Gokul Chaur Ward-2 (former Ward 2 and 3) Ward-3 (former Ward 13 and 16) Targets of the Activities (*due to restructuring of wards, the target areas were modified) Step 1: Training for Municipality Officers Details of the Activities Step 2: CBDRRM Activities in Pilot Wards 1. Target Participants: 30 persons (members of CDMC, and other relevant residents) in a ward 2. Venue: appropriate place in the selected pilot ward 3. Program (3 main events and follow-ups) 1st Workshop (2 days): Learning Risk and DRRM System in Community 2nd Workshop (2 days): Formulation of CBDRRM Map 3rd Workshop (1 day): Formulation of Action Plan/ DRRM Plan for Community CBDRRM Step 1: 3-day CBDRRM Training for Municipality Officers and Relevant Stakeholders: 20-22 February 2017 1. Result 30 participants from three pilot municipalities Enhanced capacities and ownerships of municipality officers on promoting CBDRRM activities in each municipality Created a basis for sustainable CBDRRM activities in each municipality with a sound understanding of the importance and needs of the activities of the municipality officers Lecture by MoFALD Exercise for Community DRR Mapping Discussion on Action Plan for Promoting CBDRRM Certificate Distribution by JS of MoFALD
  • 6. 1st Workshop (2 day) Learning Risk and DRRM System in Community 1) Learning Earthquake Hazard and Risks 2) Learning Basics of Disaster Risk Reduction and Management 3) Review and Discussion on Community's Current Situation of DRRM and HVCA Assessment +Follow-up Activities ** (Apr-Jun) (Documentations, etc.) 2nd Workshop (2 days) Formulation of Community- based DRRM Map 1) DRRM Town Watching (Field Survey by Community) 2) Community DRRM Mapping 3) Discussion on Evacuation Plan +Follow-up Activities (Jul-Aug) (Finalization of Map, Documentations, etc.) 3rd Workshop (1 day) Formulation of Action Plan/ DRRM Plan for Community 1) Disaster Response Plan for Community (Information Dissemination/ Response Teams/ Equipment and Stocks) 2) Discussion on Action Plans for Improving DRRM System and Conditions in Community 3) Ward-level DM Planning +Follow-up Activities (Sep-Oct) (Finalization of Plans, Approval procedure, etc.) 9 MCs: No. 2 & 3 9 MCs: No. 3, 4 & 9 9 MCs: No. 5, 6, 7 & 8 Risk Assessment Hazard & Risk Maps Local DRRM Plans Pre-Coordination: Coordination for Designation of the Participants (CDMC Members + @) 9 MCs*: No. 1 Basic Information *MCs: Minimum Characteristics of NRRC Flagship 4 **Follow-up Activities will be done by the selected members Feedback April (6-7: Lalitpur/ 9-10: Budhanilkantha/tbd: Bhaktapur) June-July August- September CBDRRM Step 2: CBDRRM Activities in Pilot Wards March A Community Activity based on Action Plan (each pilot ward) 22 Effective Utilization of Project Outcomes Who will utilize the results of the project Stakeholders dealt with Disaster Risk Reduction and Management such as Central and Local Governments, Relevant Organizations including NGOs/INGOs, Research Institutes, Private Sector, Communities, and others are expected to make effective utilization of the results of the Project to reduce damages from the estimation results. 23 How to ensure to take actions by various stakeholders to move forward to implement prevention and mitigation measures Needless to say but without implementation, the same or the worse tragedy will occur by earthquakes. How to ensure to take actions by various stakeholders are the key. Not to scare people by the result of risk assessment, realize the scale of damages properly, and effective measures need to be proposed having incentives to the implementers. Dr. Nishikawa, special guest speaker will talk more later! Dr. Nishikawa, special guest speaker will talk more later! Effective Utilization of Project Outcomes 24 Remarks Scenario Earthquakes are not the prediction of next earthquake. Based on the scenario earthquakes, hazard and risk are assessed for KV to utilize for the purpose of policy making and planning, and others for effective Disaster Risk Reduction and Management efforts. Remarks Scenario Earthquakes are not the prediction of next earthquake. Based on the scenario earthquakes, hazard and risk are assessed for KV to utilize for the purpose of policy making and planning, and others for effective Disaster Risk Reduction and Management efforts.