10. Works on-going at URU site…
Re-bars fixing, Formworks in shear-wall at level-7 of main building.
Erection of Column, Beams, Decking Panel at level-7 of main building.
Civil works at different floor of main building (at B2, B1, level-2 too level-6):
Brick-works
Plastering
Fare-face works
Tiles works (pavement)
Grill works (Door/Windows fixing)
MEP works of main building
HVAC works (Ducting work, AC fixing)
Sanitary, Plumbing, Water Supply Works
Electrical System fixing works
Fire Detection and Protection works
Re-bars fixing, Column, Beams, Formworks in shear-wall and roof slab of Lab building.
Civil works (Plastering, Grill works)
Generator fixing
URU
main
building
URU
Lab
building
15. Achievement of package S-4: Vulnerability assessment of critical and essential facilities for FY 2022-2023
Feasibility report following DEA Long Term Invertment and Strategy Guideline
16. Achievement of package S-5: Development of a risk sensitive land use planning practices in Dhaka for FY 2022-23
RSLUP Guidebook Hazard, Vulnerability and Risk Assessment
and RSLUP Planning
17. Achievement of package S-5: Development of a risk sensitive land use planning practices in Dhaka for FY 2022-23
18. Achievement of package S-6: Operationalize the Urban Resilience Unit (URU) in RAJUK for FY 2022-23
A Progress Review Meeting for the URP-Rajuk part was held amongst key stakeholders under
directions of the minister of MoHPW on March 15, 2023,
19. Achievement of package S-7: Establish an Electronic Construction Permitting System for FY 2022-23
Home page of ECPS
Incoming file Screening window & Project Detail window
20. Achievement of package S-8A: Set up a Professional Accreditation Program for FY 2022-23
PAP Design Report Ceremony for awarding certificates of recognition
to 124 SEng registration exam candidates
21. Achievement of package S-9: Improved Building Code Enforcement in RAJUK Jurisdiction for FY 2022-23
Education and Outreach Campaign Report Monitoring and Evaluation Report
Editor's Notes
Since July 16, 2023, 72 applications have been received by ECPS. 70 of these are LUCs. 1 Construction Permitting and 1 Special Project. Out of 70 LUCs, 1 LUC was disqualified because it was located in a water body according to Detailed Area Plan (DAP).
(Contract S-8A Signing Date: March 1, 2021)
The package had a 17-month initial lifespan. However, S-8A has been extended for 7 months. It is currently 24 months long. As a result, the project is supposed be finished on March 30, 2023. But is not finished yet. To preare the pending deliverables (MD-6) and (MD-7), the consultant my need another two months (within October 2023).
ICC- conducted 48 training sessions of Structural Engineer – (SEng) Training Program as a part of Professional Accreditation Program Strengthening Component of the Urban Resilience Program (URP). A total of 2,942 individuals 1,100 individuals have attended each session. Only 336 candidates appeared in the exam hall from where 124 candidates eventually succeeded in passing the 12-hour SEng registration exam.
Finally, on 10 May 2023, the International Code Council (ICC) also awarded certificates of recognition to each of the 124 successful SEng applicants for their outstanding achievement in the exam.
Although, BPERB was supposed to organize the SEng Exam, due to their reluctance, IEB chose to conduct the SEng through ESCB. Considering the large number of applicants, ESCB reported that they would be unable to hold the exam and requested that BUET take over. BUET took the exam on November 10 and November 17, 2022, and delivered the score report to ESCB at the end of January 2023. In accordance with the decision of the 14th Coordination Meeting of the URP training program organized by Institution of Engineers, Bangladesh (IEB) held on March 9, 2023, the President of IEB called a meeting, formed a committee, named the Chairman of Bangladesh Professional Engineers Registration Board (BPERB) as its convenor, and declared that the committee would take control of the SEng registration process for the further decision regarding SEng registration.
Now BPERB along with IEB trying to stop the SEng program rather they started another program called “Registered Structural Engineers –RSE” which is contradictory with the objectives of Set up a Professional Accreditation Program and quite confusing also (the role of IEB) ???
(Contract Signing Date: October 30, 2018)
The package had a 36-month initial lifespan. However, S-9 has been extended for 18 months. It is currently 54 months long. As a result, the project is supposed be finished on April 30, 2023. But is not finished yet. To prepare the pending deliverable Annual Program Evaluation Report, the consultant my need another two months (within October 2023).