3. Broader Context
URP is consistent with Higher Level Objectives
GoB’s 7th 5-year Plan & NSDS (Nat’l SD Strategy)
WB’s Country Partnership Framework with GoB
Objectives (PDO) of URP:
Strengthen GoB’s capacity to respond to emergency
events; and
Reduce vulnerability of future buildings to disasters in
Dhaka and Sylhet.
4. Structure of URP
4 Components
A: Reinforce Country’s EMR Capacity
B: Vulnerability Ass’t & Risk-based LUC
C: Improved Construction, Urban Planning and
Dev’t
D: URP Coordination and M&E
E: (contingency in case of disaster)
5. Purpose of 1st QPR
Provide “feedback” to IAs on Progress in
last quarter (4th Q FY2018)
Help M&E Team set up monitoring system
for KAAs
Build communication rapport with IAs
Identify Challenges & Opportunities
Make tentative Recommendations
6. Method of Tracking KAAs
M&E Team tracked progress made by each
IA on Key Agreed Actions (KAAs)
Created individual KAA Tracking Forms for
each IA (plus 3 “common” KAAs)
DDM: 4 KAAs
DNCC: 22
RAJUK: 20
PCMU: 6
Collected Info from IAs in July
7. Component A
A-1: DDM to renovate ERCC & NDMRTI
A-2: DNCC to renovate City Corp & FSCD
A-3: DNCC to supply ECT equipment
A-4: DNCC to supply SAR equipment
A-5: DDM to provide TED assistance
8. DDM – A1 & A5
A1: DDM renovate ERCC & NDMRTI
Waiting for design approval from MoDMR
Contract not signed yet
A5: TED Assistance Program
Waiting for NOL from WB
Pending approval from MoDMR
Verification by M&E Team pending
9. DNCC- A2, A3 & A4
A2: Renovate City Corp & FSCD facilities
Substantial progress made on most KAAs
Constructed 19/20 warehouses
A3: Supply ECT equipment
Delivery to FSCD expected by Nov.
A4: Provide SAR equipment
Substantial progress procuring equipment
10. Component B - RAJUK
B1: Vulnerability Assessment (VA)
NOL not received yet (S-4)
Evaluation not done yet for Earthquake &
Seismic equipment (G-9).
B2: Risk-Sensitive Land use Plan (RSLUP)
WB decision pending (S-5)
Re-tendering yet to start for Earthquake &
Seismic equipment for RSLUP (G-10)
11. Component C - RAJUK
C1: Establish URU in RAJUK
Most KAAs provide institutional “infrastructure”
Mixed progress (only 2/8 KAAs completed)
C2: e-permitting system for construction
Contract not signed (S-7); expected by Aug18.
C3: Professional Accreditation Program
Re-RPF not done (S-8); expected in Sept18
C4: Improve Building Code Enforcement
CCGP approval not received (S-9); in August18
12. Component D - PCMU
PCMU/URP
Coordination helpful in establishing
communication with IAs
Insufficient KAA reporting
M&E Team
Shall continue monitoring progress of IAs
Develop M&E Framework & Report
Develop PMIS prototype by end of 2018 &
final PMIS & website by 3rd Q FY19
13. Challenges
How to achieve greater implementation
efficiency & effectiveness?
Turning Activities & Outputs into Outcomes
Ensuring IA’s absorption of TA
Complex & confusing WB requirements
Lengthy & time-consuming staffing decisions
Maintaining M&E’s Independence/Credibility
Increase flow & ease of Info between IAs
Reach consensus on URP Scope & Duration
14. Opportunities
Greater “harmonization” of reporting forms
Use “results chains” to links outputs to outcomes
Improve IA’s Communication & Coordination
Make better use of information from other DRM
projects like CDMP, BUERP, ECRRP, etc…
Increase IA “absorptive capacity” (RAJUK)
Changes to Scope or Duration of URP?
15. Recommendations
“Harmonize” reporting formats to ease reporting
burden on IAs – M&E Team can help
Shift IA focus away from Activities & Outputs to
focus on Outcomes & PDO – results chains
Increase Capacity-building Assistance
Increase Communication and Coordination
among URP IAs
16. Recommendations
continued
Accelerate Staff Hiring & Approval
decisions –IA involvement in selection
Make greater use of Info from other recent
DRM projects in Bangladesh
Address fundamental question of the Best
Path Forward for URP at mid-point