3. Introduction
Leading global Built Asset Consultancy
ARCADIS company
Goal: Generate the best possible outcomes
for our clients, people and the comminutes
in which we work
Third year(3rd) undergraduate student from
The University of Hong Kong
Mechanical Engineering (4-yrs curriculum)
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
4. Internal Training Activities
Induction activities
Information Risk Awareness Training
Safety, Health & Environment (SHE) Induction Pack
ECH Harris Academy
“Health and Safety Induction” Training
“Performance Management Process” Training
Construction Industry Safety Training Certificate (“Green Card”)
Training with interns
Young Talent Workshop
Young Talent Monthly Meeting – July (MBTI)
Communicating with impact
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
5. Chiller Replacement Projects
ARCADIS was appointed as Project Manager in the engagement of a design and
build contractor to provide a turnkey solution for the replacement of existing
chillers with high energy efficient oil-free chiller system of the correct
capacity to meet the current building use and cooling load with acceptable
payback period
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
No Type of Building Location Job Scope of Contractor
1 Commercial Building Tsim Sha Tsui Supply and replace 2nos. chillers & modify
existing BMS
2 Commercial Building Yuen Long Supply and replace 2nos. chillers & modify
existing BMS
3 Commercial Building Mong Kong Supply and replace 3nos. Chillers, 4nos. Of
pumps & modify existing BMS
6. Chiller Replacement Projects -
TST
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Inspection of
building defects
after installation
of chiller
Testing &
Commissioning
(T&C)
PMFM Project
Handover
Measurement &
Verification
(M&V)
7. Brief Description:
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
The contractor is required to supply and replace 2 sets of air-cooled chiller and
modify existing BMS. The design conditions are as below:
Item Chilled Water System
Normal Flow rate (L/s) 21.8
Return Water temperature (°C) 12
Supply Water temperature (°C) 7
Ambient Wet Bulb temperature (°C) 35
Plant COP Min 3.2
Chiller COP Min 3.5
Total Cooling Capacity 602.3kW x 2
Estimated Operating Hour 12 hrs./day
No of Chilled Water Pump 3 Nos
12. Testing & Commissioning (T&C):
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Project commissioning (T&C) is the process of assuring that all systems and
components of a building or industrial plant are designed, installed, tested,
operated and maintained according to the operational requirements of the
client.
Testing and Commissioning Record
Piping hydraulic test
Water analysis report for flushing
BMS system
Chiller unit
Chilled water pump
13. Chiller Testing and
Commissioning Record
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
The water-side circuit installation status, evaporator pressure, electrical data
are recorded. Conditions of compressor and condenser fan are also evaluated.
Safety tests is also carried in this T&C process.
15. BMS System Commissioning Record
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Before fault tests are carried out, the value of all set points (AI/AO/DI/DO) are
recorded from the BMS system are validated by the T&C engineer to determine
whether it is operating normally.
Fault test:
A1 When the System is in “Manual Mode”, DDC will stop the Chiller Plant Operation
A2 In “Auto Mode”, startup of the automatic Chiller Plant Operation will follow the BMS
time schedule
A3 Whenever the time schedule is “On”, one set of chiller/CHWP will always be running
A4 DDC Controller will switched on the lead equipment (chiller/CHWP) first unless fault is
detected in the equipment
A5 Each group of equipment has its own lead/lag rotation sequence which is independent
from each others
A6 Lead/lag rotations are changed daily
16. BMS System Commissioning Record
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
17. PMFM Project Handover List
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Project handover was carried to facilitate future smooth operation and
maintenance which will be carried out by the Facilities Management Team of TST.
18. Operations and Maintenance
(O&M) Manual
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
A manual is prepared by contractor which includes the
guidelines that Facilities Management (FM) Team of the
building must address to ensure that the operations and
maintenance of the installed chiller system is in good
condition. This extends beyond the in-house staff to any
contracted services as well.
20. 0
5000
10000
15000
20000
25000
30000
35000
40000
0
20000
40000
60000
80000
100000
120000
140000
160000
July August September October November December
SavingEstimate(Kwh)
ChillerPlantBaseline(Kwh)
Axis Title
Energy Saving Estimate
EMC Saving Estimation
kWh
Post-Installation Saving Estimate kWh Chiller Plant Baseline
kWh
Energy Saving Estimate
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
A summary of the Energy Saving Estimation is shown as below:
*Graph shown only for illustration purpose.
21. Fine-tuning Strategies for M&V
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Based on the energy saving estimate illustrated, the performance of the new
chiller plant is acceptable. The accuracy of saving estimate will be further
determine by tracking and documenting of the saving estimate for the next five
months.
Fine-tuning strategies:
1. Validate installed equipment and control schemes meet specifications
2. Validate modelled expected building load calculations
3. Validate installed equipment and control schemes operate and perform as specified
4. Check metering performance periodically to ensure meter functions properly
5. Water temperature, differential pressure to be reset seasonally
6. Sequencing of chiller
22. Bollard Procurement
This project involved the installation of anti-ram bollards to enhance the security
of the building according to our client’s requirement. A total of 9 bollards (4
fixed, 5 removable) shall be installed. There are Anti-Ram Standards to comply
with. The fixed bollards have to meet UK PAS 68 2007 (7.5 tonne at 50kph) to
protect the perimeter of the building.
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
23. Site Inspection
Site inspection is carried out to determine the
location of installation of bollards and its
constraints. Below is a photo of the bollard
installation site:
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Removable Bollard
Fixed Bollard
24. Procurement for anti-ram bollard
suppliers
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Area 1: Entrance to fire equipment rooms
2 x removable bollards are needed
Consider its strength to match appearance of fixed bollards as possible
Area 2: Space between two islands for road blocker equipment
3 x fixed bollards
1 x fixed bollard located near the planter
Strength to meet UK PAS 68 2007
Area 3: People front entrance
3 x removable bollards are needed
Spacing in between the bollards need to meet standards
Consider its strength to match appearance of fixed bollards as possible
25. Shallow Mounted SP400 Bollard
Sit on existing RC slab (not to
bolt onto it)
Foundation Depth required:
Fixed:175mm
Removable: 400mm
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
26. On-site Constraints
Area 1: Entrance to fire equipment rooms
Foundation depth available: 850mm
Foundation depth requirement: 400mm
Difference: 350mm
Area 2: Space between two islands for road blocker equipment
Foundation depth available: 150mm
Foundation depth requirement: 175mm
Difference: (25mm)
Area 3: People front entrance
Foundation depth available: 500mm
Foundation depth requirement: 400mm
Difference: 100mm
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
27. Follow-up Strategies
Alternative commercially available bollard
Supplier/Contractor with related work experience
Existing Supplier/Contractor for area 2 (road blocker)
Installation work
Proposed work cost
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
28. Takeaway
# 01 - Integrate academic learning with applied experience
of internship
# 02 - Better outlook of the building service industry in Hong
Kong
# 03 - Develop soft skills at workplace
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
32. Interesting Facts
# 01 – Health and Safety Moment during meetings
# 02 – Workshops and trainings provided
# 03 – Act Courageously
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Editor's Notes
Summer Internship Start & End Date: 23 June to 28 August.
Presentation rundown:
Introduction of the company profile
Training activities within the company given to interns
Chiller Replacement projects under my line manager
Bollard procurement – another task I was assigned
Takeaway – summarized my working experience in this company
EC Harris – built asset consultancy firm.
It is now an Arcadis company.
Goal of the Company – Generate the best possible solution and outcome for our client.
First week in this company – Induction program.
Information Risk Awareness Training – a training provided to us regarding the P&C issues.
Safety, Health & Environment – SHE.
Risk assessment – Test our knowledge on some anticipated risk.
ECH Harris Academy – Training in their academy which are compulsory. Some are modules provided for our own interest.
“Green Card” – I obtain this certificate on 31/07/2015.
Chiller replacement projects for commercial buildings.
Our role – PM.
Engage with the design and build contractor to provide turnkey solution for the replacement of existing chillers.
Highlighted in orange – For that these projects under my Line Manager are similar, thus, I would only present the chiller replacement project for TST.
By the time I join ARCADIS, this project is already at the stage with the dismantle of old chillers and installment of new chillers had been done.
Involved in the inspection of building defects, T&C, Project Handover and M&V.
Below presenting those process/task I was involved in, there is a brief description of the design condition of this project.
Point out that COP, which is the performance of the chiller is important.
It is an important aspect for this project.
The table shown T&C Record that has to be done for this project.
Piping hydraulic test
Water analysis report for flushing
BMS system
Chiller unit
Chilled water pump
For example A2:
There is a BMS time schedule where will show the operating time at different days. While the chiller plant is operating at “Auto” Mode, it has to follow the pre-set time schedule.
An interphase of the BMS system which provide important parameters.
Alternative commercially available bollard which fits our requirements?
Supplier/Contractor with related work experience which could provide us a clue to resolve the on-site constraints.
Solution for Area 2, contact existing supplier/contractor to check whether the electrical wires of the road blocker system are installed underground or there are conduits which are hanged at the basement.
Installation work – How to carried out?
Proposed work cost – whether it is reasonable and its quality are upmost important to deliver our companies’ goals.
Theoretical knowledge would not be enough in the real life application of engineering works. There are lot of things to be considered to produce desired result.
First taste of work experience in Hong Kong.
Meet and network with so many people of different background.
Elephant – 22 months to be exact. It has one of the longest gestation periods in the animal kingdom.
Blue whale pregnant for about 1 year.
It shows that the company emphasized a lot on the safety. It helps to create awareness.
Workshops such as Yong Talent Meeting – MBTI, Training with interns – get important feedback from line manger, Communicating with impact – benefit me a lot
How we can all contribute.