SUMMER
INTERNSHIP
by Tan Wen Quan
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Introduction
 Leading global Built Asset Consultancy
 ARCADIS company
 Goal: Generate the best possible outcomes
for our clients, people and the comminutes
in which we work
 Third year(3rd) undergraduate student from
The University of Hong Kong
 Mechanical Engineering (4-yrs curriculum)
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Internal Training Activities
 Induction activities
 Information Risk Awareness Training
 Safety, Health & Environment (SHE) Induction Pack
 ECH Harris Academy
 “Health and Safety Induction” Training
 “Performance Management Process” Training
 Construction Industry Safety Training Certificate (“Green Card”)
 Training with interns
 Young Talent Workshop
 Young Talent Monthly Meeting – July (MBTI)
 Communicating with impact
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Chiller Replacement Projects
 ARCADIS was appointed as Project Manager in the engagement of a design and
build contractor to provide a turnkey solution for the replacement of existing
chillers with high energy efficient oil-free chiller system of the correct
capacity to meet the current building use and cooling load with acceptable
payback period
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
No Type of Building Location Job Scope of Contractor
1 Commercial Building Tsim Sha Tsui Supply and replace 2nos. chillers & modify
existing BMS
2 Commercial Building Yuen Long Supply and replace 2nos. chillers & modify
existing BMS
3 Commercial Building Mong Kong Supply and replace 3nos. Chillers, 4nos. Of
pumps & modify existing BMS
Chiller Replacement Projects -
TST
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Inspection of
building defects
after installation
of chiller
Testing &
Commissioning
(T&C)
PMFM Project
Handover
Measurement &
Verification
(M&V)
Brief Description:
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
The contractor is required to supply and replace 2 sets of air-cooled chiller and
modify existing BMS. The design conditions are as below:
Item Chilled Water System
Normal Flow rate (L/s) 21.8
Return Water temperature (°C) 12
Supply Water temperature (°C) 7
Ambient Wet Bulb temperature (°C) 35
Plant COP Min 3.2
Chiller COP Min 3.5
Total Cooling Capacity 602.3kW x 2
Estimated Operating Hour 12 hrs./day
No of Chilled Water Pump 3 Nos
Building Defects Rectification:
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
New chillers were installed and old chillers were dismantled from the building.
Inspection on general defects caused by installation work was carried out.
Below are some examples of defects:
Anchor bolt holes to be filled with non-
shrink grout and roof strains be removed
and repainted.
Building Defects Rectification:
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Temporary equipment to
be removed.
Building Defects Rectification:
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Paint work of the railing
to be reinstated.
Building Defects Rectification:
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Surface disturbed after
removal of derrick to be
reinstated.
Testing & Commissioning (T&C):
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Project commissioning (T&C) is the process of assuring that all systems and
components of a building or industrial plant are designed, installed, tested,
operated and maintained according to the operational requirements of the
client.
Testing and Commissioning Record
Piping hydraulic test
Water analysis report for flushing
BMS system
Chiller unit
Chilled water pump
Chiller Testing and
Commissioning Record
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
The water-side circuit installation status, evaporator pressure, electrical data
are recorded. Conditions of compressor and condenser fan are also evaluated.
Safety tests is also carried in this T&C process.
Pump Commissioning Record
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Before measurement are taken, the condition of the pump is checked. Measured
values are then compared with designed values to determine whether it
functions properly.
BMS System Commissioning Record
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Before fault tests are carried out, the value of all set points (AI/AO/DI/DO) are
recorded from the BMS system are validated by the T&C engineer to determine
whether it is operating normally.
Fault test:
A1 When the System is in “Manual Mode”, DDC will stop the Chiller Plant Operation
A2 In “Auto Mode”, startup of the automatic Chiller Plant Operation will follow the BMS
time schedule
A3 Whenever the time schedule is “On”, one set of chiller/CHWP will always be running
A4 DDC Controller will switched on the lead equipment (chiller/CHWP) first unless fault is
detected in the equipment
A5 Each group of equipment has its own lead/lag rotation sequence which is independent
from each others
A6 Lead/lag rotations are changed daily
BMS System Commissioning Record
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
PMFM Project Handover List
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Project handover was carried to facilitate future smooth operation and
maintenance which will be carried out by the Facilities Management Team of TST.
Operations and Maintenance
(O&M) Manual
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
A manual is prepared by contractor which includes the
guidelines that Facilities Management (FM) Team of the
building must address to ensure that the operations and
maintenance of the installed chiller system is in good
condition. This extends beyond the in-house staff to any
contracted services as well.
Measurement & Verification
(M&V)
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
M&V is a term given to the process for quantifying savings delivered by an
Energy Conservation Measure (ECM), as well as the sub-sector of the energy
industry involved with this practice. Post-installation verification is carried
out by the contractor to determine whether the chiller actual performance
meets the contract’s design specifications.
0
5000
10000
15000
20000
25000
30000
35000
40000
0
20000
40000
60000
80000
100000
120000
140000
160000
July August September October November December
SavingEstimate(Kwh)
ChillerPlantBaseline(Kwh)
Axis Title
Energy Saving Estimate
EMC Saving Estimation
kWh
Post-Installation Saving Estimate kWh Chiller Plant Baseline
kWh
Energy Saving Estimate
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
A summary of the Energy Saving Estimation is shown as below:
*Graph shown only for illustration purpose.
Fine-tuning Strategies for M&V
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Based on the energy saving estimate illustrated, the performance of the new
chiller plant is acceptable. The accuracy of saving estimate will be further
determine by tracking and documenting of the saving estimate for the next five
months.
Fine-tuning strategies:
1. Validate installed equipment and control schemes meet specifications
2. Validate modelled expected building load calculations
3. Validate installed equipment and control schemes operate and perform as specified
4. Check metering performance periodically to ensure meter functions properly
5. Water temperature, differential pressure to be reset seasonally
6. Sequencing of chiller
Bollard Procurement
This project involved the installation of anti-ram bollards to enhance the security
of the building according to our client’s requirement. A total of 9 bollards (4
fixed, 5 removable) shall be installed. There are Anti-Ram Standards to comply
with. The fixed bollards have to meet UK PAS 68 2007 (7.5 tonne at 50kph) to
protect the perimeter of the building.
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Site Inspection
Site inspection is carried out to determine the
location of installation of bollards and its
constraints. Below is a photo of the bollard
installation site:
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Removable Bollard
Fixed Bollard
Procurement for anti-ram bollard
suppliers
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Area 1: Entrance to fire equipment rooms
 2 x removable bollards are needed
 Consider its strength to match appearance of fixed bollards as possible
Area 2: Space between two islands for road blocker equipment
 3 x fixed bollards
 1 x fixed bollard located near the planter
 Strength to meet UK PAS 68 2007
Area 3: People front entrance
 3 x removable bollards are needed
 Spacing in between the bollards need to meet standards
 Consider its strength to match appearance of fixed bollards as possible
Shallow Mounted SP400 Bollard
 Sit on existing RC slab (not to
bolt onto it)
 Foundation Depth required:
 Fixed:175mm
 Removable: 400mm
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
On-site Constraints
 Area 1: Entrance to fire equipment rooms
 Foundation depth available: 850mm
 Foundation depth requirement: 400mm
 Difference: 350mm
 Area 2: Space between two islands for road blocker equipment
 Foundation depth available: 150mm
 Foundation depth requirement: 175mm
 Difference: (25mm)
 Area 3: People front entrance
 Foundation depth available: 500mm
 Foundation depth requirement: 400mm
 Difference: 100mm
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Follow-up Strategies
 Alternative commercially available bollard
 Supplier/Contractor with related work experience
 Existing Supplier/Contractor for area 2 (road blocker)
 Installation work
 Proposed work cost
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Takeaway
# 01 - Integrate academic learning with applied experience
of internship
# 02 - Better outlook of the building service industry in Hong
Kong
# 03 - Develop soft skills at workplace
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away
Q & A
Others
Interesting Facts
# 01 – Health and Safety Moment during meetings
# 02 – Workshops and trainings provided
# 03 – Act Courageously
Introduction
Internal
Training
Activities
Chiller
Replacement
Projects
Bollard
Procurement Take Away

More Related Content

What's hot

Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 ) SAJJAD KHUDHUR ABBAS
 
The Commissioning Process
The Commissioning ProcessThe Commissioning Process
The Commissioning Processd_mackay
 
Episode 33 : Project Execution Part (4)
Episode 33 :  Project Execution Part (4)Episode 33 :  Project Execution Part (4)
Episode 33 : Project Execution Part (4)SAJJAD KHUDHUR ABBAS
 
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...GSE Systems, Inc.
 
Mind map the_9_key_elements_video_05_pre-commissioning
Mind map the_9_key_elements_video_05_pre-commissioningMind map the_9_key_elements_video_05_pre-commissioning
Mind map the_9_key_elements_video_05_pre-commissioningsakol kai
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completionRonie Chu
 
Building Commissioning, Ongoing Commissioning and quality management using BACS
Building Commissioning, Ongoing Commissioning and quality management using BACSBuilding Commissioning, Ongoing Commissioning and quality management using BACS
Building Commissioning, Ongoing Commissioning and quality management using BACSLeonardo ENERGY
 
Commissioning of Offshore Installations
Commissioning of Offshore InstallationsCommissioning of Offshore Installations
Commissioning of Offshore Installationswan saiful arini
 
Precommissioning and Commissioning
Precommissioning and CommissioningPrecommissioning and Commissioning
Precommissioning and CommissioningWendy Soerachman
 
PetroSync - Well Completion and Workover
PetroSync - Well Completion and WorkoverPetroSync - Well Completion and Workover
PetroSync - Well Completion and WorkoverPetroSync
 
Gabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentationGabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentationAmeya Margaj
 
Case study electronics industry
Case study   electronics industryCase study   electronics industry
Case study electronics industryGanesh TN
 
Episode 31 : Project Execution Part (2)
Episode 31 :  Project Execution Part (2)Episode 31 :  Project Execution Part (2)
Episode 31 : Project Execution Part (2)SAJJAD KHUDHUR ABBAS
 
Debottlenecking a bulk manufacturing plant
Debottlenecking a bulk manufacturing plantDebottlenecking a bulk manufacturing plant
Debottlenecking a bulk manufacturing plantGBX Summits
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installationslaithu2908
 

What's hot (20)

Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 )
 
Episode 7 : iCON Basic Training
Episode 7 :  iCON Basic Training Episode 7 :  iCON Basic Training
Episode 7 : iCON Basic Training
 
The Commissioning Process
The Commissioning ProcessThe Commissioning Process
The Commissioning Process
 
Episode 33 : Project Execution Part (4)
Episode 33 :  Project Execution Part (4)Episode 33 :  Project Execution Part (4)
Episode 33 : Project Execution Part (4)
 
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
 
The Value of Building Commissioning
The Value of Building CommissioningThe Value of Building Commissioning
The Value of Building Commissioning
 
Mind map the_9_key_elements_video_05_pre-commissioning
Mind map the_9_key_elements_video_05_pre-commissioningMind map the_9_key_elements_video_05_pre-commissioning
Mind map the_9_key_elements_video_05_pre-commissioning
 
Training program for_urea_engineers_july_by ukh
Training program for_urea_engineers_july_by ukhTraining program for_urea_engineers_july_by ukh
Training program for_urea_engineers_july_by ukh
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completion
 
Building Commissioning, Ongoing Commissioning and quality management using BACS
Building Commissioning, Ongoing Commissioning and quality management using BACSBuilding Commissioning, Ongoing Commissioning and quality management using BACS
Building Commissioning, Ongoing Commissioning and quality management using BACS
 
Commissioning of Offshore Installations
Commissioning of Offshore InstallationsCommissioning of Offshore Installations
Commissioning of Offshore Installations
 
Precommissioning and Commissioning
Precommissioning and CommissioningPrecommissioning and Commissioning
Precommissioning and Commissioning
 
Pre commissioning
Pre commissioningPre commissioning
Pre commissioning
 
Portfolio
PortfolioPortfolio
Portfolio
 
PetroSync - Well Completion and Workover
PetroSync - Well Completion and WorkoverPetroSync - Well Completion and Workover
PetroSync - Well Completion and Workover
 
Gabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentationGabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentation
 
Case study electronics industry
Case study   electronics industryCase study   electronics industry
Case study electronics industry
 
Episode 31 : Project Execution Part (2)
Episode 31 :  Project Execution Part (2)Episode 31 :  Project Execution Part (2)
Episode 31 : Project Execution Part (2)
 
Debottlenecking a bulk manufacturing plant
Debottlenecking a bulk manufacturing plantDebottlenecking a bulk manufacturing plant
Debottlenecking a bulk manufacturing plant
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installations
 

Viewers also liked

DRI Presentation Ashton Strickland
DRI Presentation Ashton StricklandDRI Presentation Ashton Strickland
DRI Presentation Ashton StricklandAshton Strickland
 
Spring 12 Internship Orientation
Spring 12 Internship OrientationSpring 12 Internship Orientation
Spring 12 Internship Orientationbenwyeth
 
2010 OCP Summer Internship Program
2010 OCP Summer Internship Program2010 OCP Summer Internship Program
2010 OCP Summer Internship Programjjichisholm
 
Intern oreintation kiva 101
Intern oreintation kiva 101Intern oreintation kiva 101
Intern oreintation kiva 101kivaspeakers
 
COIP Orientations 2010
COIP Orientations 2010COIP Orientations 2010
COIP Orientations 2010pamelalh
 
New Hire Orientation - Spring 2012
New Hire Orientation - Spring 2012New Hire Orientation - Spring 2012
New Hire Orientation - Spring 2012tesengineering
 
Intern Department Orientation (I DO TMS)
Intern Department Orientation (I DO TMS)Intern Department Orientation (I DO TMS)
Intern Department Orientation (I DO TMS)Justin Miller
 
New Hire Orientation
New Hire OrientationNew Hire Orientation
New Hire Orientationmmbrown
 
Get Them Engaged! At Their New Hire Orientation Presentation
Get Them Engaged! At Their New Hire Orientation PresentationGet Them Engaged! At Their New Hire Orientation Presentation
Get Them Engaged! At Their New Hire Orientation PresentationTom Newell
 
Medical education in india-current status
Medical education in india-current statusMedical education in india-current status
Medical education in india-current statusMitasha Singh
 
7 Tips to Straighten Out the Kinks in Your Employee Onboarding Process
7 Tips to Straighten Out the Kinks in Your Employee Onboarding Process7 Tips to Straighten Out the Kinks in Your Employee Onboarding Process
7 Tips to Straighten Out the Kinks in Your Employee Onboarding ProcessClearCompany
 
Clarke abbotsford rounds 2009-02-11
Clarke   abbotsford rounds 2009-02-11Clarke   abbotsford rounds 2009-02-11
Clarke abbotsford rounds 2009-02-11Ihsaan Peer
 
New Hire Orientation Icebreakers That Are Anything But Dull
New Hire Orientation Icebreakers That Are Anything But DullNew Hire Orientation Icebreakers That Are Anything But Dull
New Hire Orientation Icebreakers That Are Anything But DullLinkedIn Talent Solutions
 
10 Tips on New Hire Orientation & Onboarding
10 Tips on New Hire Orientation & Onboarding10 Tips on New Hire Orientation & Onboarding
10 Tips on New Hire Orientation & OnboardingEduson.tv
 

Viewers also liked (19)

DRI Presentation Ashton Strickland
DRI Presentation Ashton StricklandDRI Presentation Ashton Strickland
DRI Presentation Ashton Strickland
 
Spring 12 Internship Orientation
Spring 12 Internship OrientationSpring 12 Internship Orientation
Spring 12 Internship Orientation
 
2010 OCP Summer Internship Program
2010 OCP Summer Internship Program2010 OCP Summer Internship Program
2010 OCP Summer Internship Program
 
Intern oreintation kiva 101
Intern oreintation kiva 101Intern oreintation kiva 101
Intern oreintation kiva 101
 
COIP Orientations 2010
COIP Orientations 2010COIP Orientations 2010
COIP Orientations 2010
 
Beamonte internship Fall 2014
Beamonte internship Fall 2014Beamonte internship Fall 2014
Beamonte internship Fall 2014
 
WSUP Intern Orientation 2014.15
WSUP Intern Orientation 2014.15WSUP Intern Orientation 2014.15
WSUP Intern Orientation 2014.15
 
New Hire Orientation - Spring 2012
New Hire Orientation - Spring 2012New Hire Orientation - Spring 2012
New Hire Orientation - Spring 2012
 
Intern Department Orientation (I DO TMS)
Intern Department Orientation (I DO TMS)Intern Department Orientation (I DO TMS)
Intern Department Orientation (I DO TMS)
 
New Hire Orientation
New Hire OrientationNew Hire Orientation
New Hire Orientation
 
City Vision Intern Orientation
City Vision Intern OrientationCity Vision Intern Orientation
City Vision Intern Orientation
 
Get Them Engaged! At Their New Hire Orientation Presentation
Get Them Engaged! At Their New Hire Orientation PresentationGet Them Engaged! At Their New Hire Orientation Presentation
Get Them Engaged! At Their New Hire Orientation Presentation
 
Gentherm Internship Program
Gentherm Internship ProgramGentherm Internship Program
Gentherm Internship Program
 
Medical education in india-current status
Medical education in india-current statusMedical education in india-current status
Medical education in india-current status
 
7 Tips to Straighten Out the Kinks in Your Employee Onboarding Process
7 Tips to Straighten Out the Kinks in Your Employee Onboarding Process7 Tips to Straighten Out the Kinks in Your Employee Onboarding Process
7 Tips to Straighten Out the Kinks in Your Employee Onboarding Process
 
Clarke abbotsford rounds 2009-02-11
Clarke   abbotsford rounds 2009-02-11Clarke   abbotsford rounds 2009-02-11
Clarke abbotsford rounds 2009-02-11
 
New Hire Orientation Icebreakers That Are Anything But Dull
New Hire Orientation Icebreakers That Are Anything But DullNew Hire Orientation Icebreakers That Are Anything But Dull
New Hire Orientation Icebreakers That Are Anything But Dull
 
Chris outram 3
Chris outram 3Chris outram 3
Chris outram 3
 
10 Tips on New Hire Orientation & Onboarding
10 Tips on New Hire Orientation & Onboarding10 Tips on New Hire Orientation & Onboarding
10 Tips on New Hire Orientation & Onboarding
 

Similar to Summer Internship Presentation

Stress Analysis in District Cooling Projects
Stress Analysis in District Cooling ProjectsStress Analysis in District Cooling Projects
Stress Analysis in District Cooling ProjectsAmer Abdul Aziz
 
Tony Greenfield CV 23 March 2015 pdf
Tony Greenfield CV 23 March 2015 pdfTony Greenfield CV 23 March 2015 pdf
Tony Greenfield CV 23 March 2015 pdfTony Greenfield
 
CD 2016 March - Advisian Showcase
CD 2016 March - Advisian ShowcaseCD 2016 March - Advisian Showcase
CD 2016 March - Advisian ShowcaseComit Projects Ltd
 
SECS White Paper For Folders
SECS White Paper For FoldersSECS White Paper For Folders
SECS White Paper For FoldersJessica Rearick
 
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...yusuf699644
 
Blazemaster Cost Saving Report
Blazemaster Cost Saving ReportBlazemaster Cost Saving Report
Blazemaster Cost Saving ReportPoojaShetty87
 
Dounreay’s Nuclear Flask Loading Facility Project – A New Delivery Strategy, ...
Dounreay’s Nuclear Flask Loading Facility Project – A New Delivery Strategy, ...Dounreay’s Nuclear Flask Loading Facility Project – A New Delivery Strategy, ...
Dounreay’s Nuclear Flask Loading Facility Project – A New Delivery Strategy, ...Association for Project Management
 
3 in 1-1.pptx
3 in 1-1.pptx3 in 1-1.pptx
3 in 1-1.pptxMABR19
 
Strategic meet_Engineering.pptx
Strategic meet_Engineering.pptxStrategic meet_Engineering.pptx
Strategic meet_Engineering.pptxmukeshsingh71872
 
Implementation of Business Process Reengineering in Thermax Ltd.
Implementation of Business Process Reengineering in Thermax Ltd.Implementation of Business Process Reengineering in Thermax Ltd.
Implementation of Business Process Reengineering in Thermax Ltd.Pramod Patil
 
Contribution to the Business Awards
Contribution to the Business AwardsContribution to the Business Awards
Contribution to the Business AwardsAzam Ghaffar
 
1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report1-2 Broadgate Final Project Report
1-2 Broadgate Final Project ReportPaul Warrington
 
KinetIQ Solutions Capability Statement
KinetIQ Solutions Capability StatementKinetIQ Solutions Capability Statement
KinetIQ Solutions Capability StatementRay Salmons
 

Similar to Summer Internship Presentation (20)

Stress Analysis in District Cooling Projects
Stress Analysis in District Cooling ProjectsStress Analysis in District Cooling Projects
Stress Analysis in District Cooling Projects
 
API 610 pumps .pdf
API 610 pumps .pdfAPI 610 pumps .pdf
API 610 pumps .pdf
 
Tony Greenfield CV 23 March 2015 pdf
Tony Greenfield CV 23 March 2015 pdfTony Greenfield CV 23 March 2015 pdf
Tony Greenfield CV 23 March 2015 pdf
 
CD 2016 March - Advisian Showcase
CD 2016 March - Advisian ShowcaseCD 2016 March - Advisian Showcase
CD 2016 March - Advisian Showcase
 
SECS White Paper For Folders
SECS White Paper For FoldersSECS White Paper For Folders
SECS White Paper For Folders
 
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
 
Blazemaster Cost Saving Report
Blazemaster Cost Saving ReportBlazemaster Cost Saving Report
Blazemaster Cost Saving Report
 
abid1
abid1abid1
abid1
 
Dounreay’s Nuclear Flask Loading Facility Project – A New Delivery Strategy, ...
Dounreay’s Nuclear Flask Loading Facility Project – A New Delivery Strategy, ...Dounreay’s Nuclear Flask Loading Facility Project – A New Delivery Strategy, ...
Dounreay’s Nuclear Flask Loading Facility Project – A New Delivery Strategy, ...
 
3 in 1-1.pptx
3 in 1-1.pptx3 in 1-1.pptx
3 in 1-1.pptx
 
CV
CVCV
CV
 
Strategic meet_Engineering.pptx
Strategic meet_Engineering.pptxStrategic meet_Engineering.pptx
Strategic meet_Engineering.pptx
 
HVAC Design Course Content For Regular & Weekend Batch
HVAC Design Course Content For Regular & Weekend BatchHVAC Design Course Content For Regular & Weekend Batch
HVAC Design Course Content For Regular & Weekend Batch
 
CV
CVCV
CV
 
Implementation of Business Process Reengineering in Thermax Ltd.
Implementation of Business Process Reengineering in Thermax Ltd.Implementation of Business Process Reengineering in Thermax Ltd.
Implementation of Business Process Reengineering in Thermax Ltd.
 
Glow Plug
Glow PlugGlow Plug
Glow Plug
 
Contribution to the Business Awards
Contribution to the Business AwardsContribution to the Business Awards
Contribution to the Business Awards
 
1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report1-2 Broadgate Final Project Report
1-2 Broadgate Final Project Report
 
KinetIQ Solutions Capability Statement
KinetIQ Solutions Capability StatementKinetIQ Solutions Capability Statement
KinetIQ Solutions Capability Statement
 
O & C Refurb
O & C RefurbO & C Refurb
O & C Refurb
 

Summer Internship Presentation

  • 3. Introduction  Leading global Built Asset Consultancy  ARCADIS company  Goal: Generate the best possible outcomes for our clients, people and the comminutes in which we work  Third year(3rd) undergraduate student from The University of Hong Kong  Mechanical Engineering (4-yrs curriculum) Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away
  • 4. Internal Training Activities  Induction activities  Information Risk Awareness Training  Safety, Health & Environment (SHE) Induction Pack  ECH Harris Academy  “Health and Safety Induction” Training  “Performance Management Process” Training  Construction Industry Safety Training Certificate (“Green Card”)  Training with interns  Young Talent Workshop  Young Talent Monthly Meeting – July (MBTI)  Communicating with impact Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away
  • 5. Chiller Replacement Projects  ARCADIS was appointed as Project Manager in the engagement of a design and build contractor to provide a turnkey solution for the replacement of existing chillers with high energy efficient oil-free chiller system of the correct capacity to meet the current building use and cooling load with acceptable payback period Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away No Type of Building Location Job Scope of Contractor 1 Commercial Building Tsim Sha Tsui Supply and replace 2nos. chillers & modify existing BMS 2 Commercial Building Yuen Long Supply and replace 2nos. chillers & modify existing BMS 3 Commercial Building Mong Kong Supply and replace 3nos. Chillers, 4nos. Of pumps & modify existing BMS
  • 6. Chiller Replacement Projects - TST Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away Inspection of building defects after installation of chiller Testing & Commissioning (T&C) PMFM Project Handover Measurement & Verification (M&V)
  • 7. Brief Description: Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away The contractor is required to supply and replace 2 sets of air-cooled chiller and modify existing BMS. The design conditions are as below: Item Chilled Water System Normal Flow rate (L/s) 21.8 Return Water temperature (°C) 12 Supply Water temperature (°C) 7 Ambient Wet Bulb temperature (°C) 35 Plant COP Min 3.2 Chiller COP Min 3.5 Total Cooling Capacity 602.3kW x 2 Estimated Operating Hour 12 hrs./day No of Chilled Water Pump 3 Nos
  • 8. Building Defects Rectification: Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away New chillers were installed and old chillers were dismantled from the building. Inspection on general defects caused by installation work was carried out. Below are some examples of defects: Anchor bolt holes to be filled with non- shrink grout and roof strains be removed and repainted.
  • 12. Testing & Commissioning (T&C): Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away Project commissioning (T&C) is the process of assuring that all systems and components of a building or industrial plant are designed, installed, tested, operated and maintained according to the operational requirements of the client. Testing and Commissioning Record Piping hydraulic test Water analysis report for flushing BMS system Chiller unit Chilled water pump
  • 13. Chiller Testing and Commissioning Record Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away The water-side circuit installation status, evaporator pressure, electrical data are recorded. Conditions of compressor and condenser fan are also evaluated. Safety tests is also carried in this T&C process.
  • 14. Pump Commissioning Record Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away Before measurement are taken, the condition of the pump is checked. Measured values are then compared with designed values to determine whether it functions properly.
  • 15. BMS System Commissioning Record Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away Before fault tests are carried out, the value of all set points (AI/AO/DI/DO) are recorded from the BMS system are validated by the T&C engineer to determine whether it is operating normally. Fault test: A1 When the System is in “Manual Mode”, DDC will stop the Chiller Plant Operation A2 In “Auto Mode”, startup of the automatic Chiller Plant Operation will follow the BMS time schedule A3 Whenever the time schedule is “On”, one set of chiller/CHWP will always be running A4 DDC Controller will switched on the lead equipment (chiller/CHWP) first unless fault is detected in the equipment A5 Each group of equipment has its own lead/lag rotation sequence which is independent from each others A6 Lead/lag rotations are changed daily
  • 16. BMS System Commissioning Record Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away
  • 17. PMFM Project Handover List Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away Project handover was carried to facilitate future smooth operation and maintenance which will be carried out by the Facilities Management Team of TST.
  • 18. Operations and Maintenance (O&M) Manual Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away A manual is prepared by contractor which includes the guidelines that Facilities Management (FM) Team of the building must address to ensure that the operations and maintenance of the installed chiller system is in good condition. This extends beyond the in-house staff to any contracted services as well.
  • 19. Measurement & Verification (M&V) Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away M&V is a term given to the process for quantifying savings delivered by an Energy Conservation Measure (ECM), as well as the sub-sector of the energy industry involved with this practice. Post-installation verification is carried out by the contractor to determine whether the chiller actual performance meets the contract’s design specifications.
  • 20. 0 5000 10000 15000 20000 25000 30000 35000 40000 0 20000 40000 60000 80000 100000 120000 140000 160000 July August September October November December SavingEstimate(Kwh) ChillerPlantBaseline(Kwh) Axis Title Energy Saving Estimate EMC Saving Estimation kWh Post-Installation Saving Estimate kWh Chiller Plant Baseline kWh Energy Saving Estimate Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away A summary of the Energy Saving Estimation is shown as below: *Graph shown only for illustration purpose.
  • 21. Fine-tuning Strategies for M&V Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away Based on the energy saving estimate illustrated, the performance of the new chiller plant is acceptable. The accuracy of saving estimate will be further determine by tracking and documenting of the saving estimate for the next five months. Fine-tuning strategies: 1. Validate installed equipment and control schemes meet specifications 2. Validate modelled expected building load calculations 3. Validate installed equipment and control schemes operate and perform as specified 4. Check metering performance periodically to ensure meter functions properly 5. Water temperature, differential pressure to be reset seasonally 6. Sequencing of chiller
  • 22. Bollard Procurement This project involved the installation of anti-ram bollards to enhance the security of the building according to our client’s requirement. A total of 9 bollards (4 fixed, 5 removable) shall be installed. There are Anti-Ram Standards to comply with. The fixed bollards have to meet UK PAS 68 2007 (7.5 tonne at 50kph) to protect the perimeter of the building. Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away
  • 23. Site Inspection Site inspection is carried out to determine the location of installation of bollards and its constraints. Below is a photo of the bollard installation site: Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away Removable Bollard Fixed Bollard
  • 24. Procurement for anti-ram bollard suppliers Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away Area 1: Entrance to fire equipment rooms  2 x removable bollards are needed  Consider its strength to match appearance of fixed bollards as possible Area 2: Space between two islands for road blocker equipment  3 x fixed bollards  1 x fixed bollard located near the planter  Strength to meet UK PAS 68 2007 Area 3: People front entrance  3 x removable bollards are needed  Spacing in between the bollards need to meet standards  Consider its strength to match appearance of fixed bollards as possible
  • 25. Shallow Mounted SP400 Bollard  Sit on existing RC slab (not to bolt onto it)  Foundation Depth required:  Fixed:175mm  Removable: 400mm Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away
  • 26. On-site Constraints  Area 1: Entrance to fire equipment rooms  Foundation depth available: 850mm  Foundation depth requirement: 400mm  Difference: 350mm  Area 2: Space between two islands for road blocker equipment  Foundation depth available: 150mm  Foundation depth requirement: 175mm  Difference: (25mm)  Area 3: People front entrance  Foundation depth available: 500mm  Foundation depth requirement: 400mm  Difference: 100mm Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away
  • 27. Follow-up Strategies  Alternative commercially available bollard  Supplier/Contractor with related work experience  Existing Supplier/Contractor for area 2 (road blocker)  Installation work  Proposed work cost Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away
  • 28. Takeaway # 01 - Integrate academic learning with applied experience of internship # 02 - Better outlook of the building service industry in Hong Kong # 03 - Develop soft skills at workplace Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away
  • 29. Q & A
  • 30.
  • 32. Interesting Facts # 01 – Health and Safety Moment during meetings # 02 – Workshops and trainings provided # 03 – Act Courageously Introduction Internal Training Activities Chiller Replacement Projects Bollard Procurement Take Away

Editor's Notes

  1. Summer Internship Start & End Date: 23 June to 28 August.
  2. Presentation rundown: Introduction of the company profile Training activities within the company given to interns Chiller Replacement projects under my line manager Bollard procurement – another task I was assigned Takeaway – summarized my working experience in this company
  3. EC Harris – built asset consultancy firm. It is now an Arcadis company. Goal of the Company – Generate the best possible solution and outcome for our client.
  4. First week in this company – Induction program. Information Risk Awareness Training – a training provided to us regarding the P&C issues. Safety, Health & Environment – SHE. Risk assessment – Test our knowledge on some anticipated risk. ECH Harris Academy – Training in their academy which are compulsory. Some are modules provided for our own interest. “Green Card” – I obtain this certificate on 31/07/2015.
  5. Chiller replacement projects for commercial buildings. Our role – PM. Engage with the design and build contractor to provide turnkey solution for the replacement of existing chillers. Highlighted in orange – For that these projects under my Line Manager are similar, thus, I would only present the chiller replacement project for TST.
  6. By the time I join ARCADIS, this project is already at the stage with the dismantle of old chillers and installment of new chillers had been done. Involved in the inspection of building defects, T&C, Project Handover and M&V.
  7. Below presenting those process/task I was involved in, there is a brief description of the design condition of this project. Point out that COP, which is the performance of the chiller is important. It is an important aspect for this project.
  8. The table shown T&C Record that has to be done for this project. Piping hydraulic test Water analysis report for flushing BMS system Chiller unit Chilled water pump
  9. For example A2: There is a BMS time schedule where will show the operating time at different days. While the chiller plant is operating at “Auto” Mode, it has to follow the pre-set time schedule.
  10. An interphase of the BMS system which provide important parameters.
  11. Alternative commercially available bollard which fits our requirements? Supplier/Contractor with related work experience which could provide us a clue to resolve the on-site constraints. Solution for Area 2, contact existing supplier/contractor to check whether the electrical wires of the road blocker system are installed underground or there are conduits which are hanged at the basement. Installation work – How to carried out? Proposed work cost – whether it is reasonable and its quality are upmost important to deliver our companies’ goals.
  12. Theoretical knowledge would not be enough in the real life application of engineering works. There are lot of things to be considered to produce desired result. First taste of work experience in Hong Kong. Meet and network with so many people of different background.
  13. Elephant – 22 months to be exact. It has one of the longest gestation periods in the animal kingdom. Blue whale pregnant for about 1 year. It shows that the company emphasized a lot on the safety. It helps to create awareness. Workshops such as Yong Talent Meeting – MBTI, Training with interns – get important feedback from line manger, Communicating with impact – benefit me a lot How we can all contribute.