1-2BROADGATE
PROJECTREVIEW
Xxx
FOREWORD
2
We have extensive experience of undertaking complex
projects where we have worked with occupiers to develop
their requirements and used our substantial project
management expertise to deliver their expectations,
resulting in buildings that positively enhance their business.
Many of our projects are undertaken in occupation and
we are adept at reviewing the strategy to advise on the
phasing of work to minimise disruption to the occupiers
while reducing costs and maintaining business continuity.
Peter Bicknell, Client Services Director (Head of Technical Services)
Peter Bicknell, Client Services Director
(Head of Technical Services)
Paul J Warrington, Engineering Manager
Foreword
CONTENTS
3
CONTENTS
3
1.0	Introduction 4
1.2 Project summary������������������������������������������������������������������������������������������������������������������������������������������������������������������ 6
2.0	 Phase 1 8
2.1 N+1 resilience system ��������������������������������������������������������������������������������������������������������������������������������������������������������� 9
2.2 Sixth floor chillers���������������������������������������������������������������������������������������������������������������������������������������������������������������10
2.3 Ground to second floor chillers �����������������������������������������������������������������������������������������������������������������������������������������11
2.4 Pumps���������������������������������������������������������������������������������������������������������������������������������������������������������������������������������12
2.5 Sprinkler heads�������������������������������������������������������������������������������������������������������������������������������������������������������������������13
2.6 Cooling towers �������������������������������������������������������������������������������������������������������������������������������������������������������������������14
2.7 Miscellaneous works����������������������������������������������������������������������������������������������������������������������������������������������������������16
3.0	 Phase 2 18
3.1 Generators �������������������������������������������������������������������������������������������������������������������������������������������������������������������������19
3.2 LV switchgear���������������������������������������������������������������������������������������������������������������������������������������������������������������������20
3.3 Loadbank����������������������������������������������������������������������������������������������������������������������������������������������������������������������������21
3.4 Building works���������������������������������������������������������������������������������������������������������������������������������������������������������������������22
3.5 Sprinkler systems���������������������������������������������������������������������������������������������������������������������������������������������������������������23
3.6 Pumps���������������������������������������������������������������������������������������������������������������������������������������������������������������������������������24
3.7 Chillers��������������������������������������������������������������������������������������������������������������������������������������������������������������������������������25
3.8 Cooling towers �������������������������������������������������������������������������������������������������������������������������������������������������������������������27
4.0	 Phase 3 28
4.1 Pumps���������������������������������������������������������������������������������������������������������������������������������������������������������������������������������29
4.2 Chillers��������������������������������������������������������������������������������������������������������������������������������������������������������������������������������30
4.3 Cooling towers �������������������������������������������������������������������������������������������������������������������������������������������������������������������31
5.0 	 Conclusion 32
44
1.0	Introduction
1.0INTRODUCTION
5
1-2 Broadgate consists of 305,272ft2
of floor area spread
across six levels occupied by a range of businesses
including ICAP, Royal Mail, KBW, Regus, Precise Media,
Brookfield Multiplex, ETX and GF Securities.
A four year comprehensive refurbishment programme
was carried out at the property restoring key elements
of the mechanical and electrical building infrastructure
with the aim of extending life to 2019. A key aim of
the project was to give confidence to the occupiers
ensuring their needs will be fulfilled in the future so they
can re-gear their lease and extend the duration of their
stay in the property.
The works were completed in three phases between
2012 and 2015, whilst the building was fully occupied.
Prior to the programme, the majority of systems and
equipment in the property had not undergone significant
upgrades from the systems installed during the initial
development of the property in 1986. An exception
being the transformation of the chilled water air
conditioning system in 2005 from a centralised system
to a quadrant chiller system with dedicated chillers and
AHUs housed on each floor. However the majority of
equipment in the building was approaching the end of its
serviceable life at the time of the programme.
In order to initiate the refurbishment project, Broadgate
Estates were invited by the landlord to summarise and
advise on the engineering systems within the property
with respect to suitability, reliability and obsolescence
of the equipment. Additionally any major equipment
or systems which had exceeded or were nearing their
service life were identified for replacement to ensure the
needs of the occupiers can be fulfilled until 2019.
A key aspect of the project initiation process was the
risk assessments carried out by Broadgate Estates on
all 386 engineering systems and assets in the building.
The assessments resulted in risk ratings being given
for the potential failure of all equipment and systems.
This was based on multiple factors such as condition,
compliance and service impact upon failure. Based on
the risk scores, equipment were prioritised within the
four year programme which resulted in the equipment
that was likely to pose the highest potential risk to the
occupiers’ business being addressed within the early
phases of the programme.
In order to transform these findings into specific work
items, Broadgate Estates commissioned several
specialists engineering service providers to propose
technical recommendations for the work required.
These proposals were utilised as guidance to produce
a detailed version of the phased refurbishment plan
spanning the four year period.
1.1 General
1.2 Project summary
The most significant and critical parts of the refurbishment
works were completed during phase 1 over an 18-month
period. The most notable of these works was the
replacement of the two dedicated chillers and cooling
tower which provide cooling to the occupiers’ UPS
facility on an N+1 configuration.
Further replacements were carried out of two chillers
located on the sixth floor whilst the floor was fully
occupied. Broadgate Estates ensured that occupiers’
cooling needs were continually satisfied by installing
and managing similar sized temporary chillers on the
roof for the duration of the works.
A complete refurbishment of the rest of the cooling
system in the building was undertaken during the three
phases. This included replacement or refurbishment of
78 primary and secondary chilled water and condenser
pumps, 22 chillers and 12 cooling towers in the building.
All of these works involved the contribution of multiple
contractors who worked on site simultaneously as
planned and coordinated by Broadgate Estates.
This ensured efficient and timely completion of work
packages with minimal downtime of systems.
Through meticulous planning and careful co-ordination
between the multiple parties, the cooling system
refurbishment works were completed without interruption
to occupiers’ air conditioning services.
The fire protection systems in the building were subjected
to overhaul to ensure these critical systems can continue
to perform at their optimum level. Key aspects of these
works were the change of all fire phones, sprinkler heads
and tanks and refurbishment of the main sprinkler pumps
in the building.
A number of important electrical upgrades formed a
substantial share of the phase 2 works in which the
two occupiers’ life safety generators were replaced
in their entirety and the four landlords’ generators
were fully reconditioned. Temporary generators
were installed and operated by Broadgate Estates
to maintain the level of backup power to occupiers
operations throughout the works.
Replacements to LV switchgear were undertaken where
ACBs (Air Circuit Breakers) had become obsolete and
unsupported with spare parts. Broadgate Estates also
managed the installation of a new load bank connection
facility as part of these works.
A number of temporary and permanent modifications
to the building were completed to enable the electrical
upgrades and to provide safe access routes for
occupiers during the works.
Several other restoration works were accomplished within
the programme including the replacement of all dry riser
landing valves and the refurbishment of passenger and
goods lifts and the two main AHUs. Upgrades were made
to the LTHW boiler system to transform the boiler burners
to flame controlled burners resulting in improved efficiency.
6
1.3 Project governance
The responsibility of overall project
delivery was held by an incumbent Project
Lead who also provided immediate
client oversight. A Project Engineering
Director and a Project Client Director was
also appointed to provide engineering
oversight and client oversight respectively
and to be jointly responsible for approving
works and contracts. Any significant
variations to costs and timescales
were scrutinised and approved by the
Project Directors. In the occurrence
of considerable technical variations,
the Project Engineering Director was
responsible for approving the changes.
Systems upgrades and IT and fabric
related works were managed by three
appointed project managers from the
respective departments within Broadgate
Estates. The project team also included
a Manager who ensured compliance of
the programme with CDM (Construction,
Design and Management) regulation.
A clear communication plan was vital
in carrying out works within timescales
and budgets with minimal interruption
to the multiple client operations in the
property. A building management meeting
and an occupiers’ meeting held on a
weekly basis and a landlord’s meeting
held every month were crucial elements
of the communication plan. A six weekly
programme which was updated on a
monthly basis was presented by Broadgate
Estates to stakeholders during these three
types of meetings.
1.0INTRODUCTION
7
WEEKLY MEETINGS MONTHLY MEETINGS
1.0INTRODUCTION
7
88
2.0	 Phase 1
2.0PHASE1
9
The most significant part of Phase 1 was to refurbish the
N+1 resilience cooling system which provides cooling to
the occupiers’ UPS facilities.
The refurbishment of this critical system was
carried out with the collaboration of three specialist
contractors working simultaneously whilst the building
was fully occupied.
The UPS cooling system consists of a Carrier 30HXC230
Chiller located within the basement and a ground floor
chiller which provides N+1 resilience. The system works
in conjunction with a dedicated cooling tower.
The most critical aspect of the works was the replacement
of the carrier chiller. Additionally the ground floor chiller
and the cooling tower were fully refurbished in order to
extend their service life.
Broadgate Estates ensured the work did not compromise
the cooling requirements and cooling system resilience
of the UPS system by installing and operating an equally
sized temporary AC plant with air cooled chillers housed
in the loading bay.
Furthermore the fan control strategy for the cooling
tower was upgraded from two speed control to fully
modulating control resulting in increased efficiency.
Changes were also made to the BMS to increase the
frequency of flushing to protect the tower should the
system not run for the preceding 12 hours.
Previous to the change, condenser flushing was
accommodated in a single time zone each day.
The set point temperature to enable the cooling tower
fan was also decreased from 24ºC to 18.5ºC.
2.1 N+1 resilience system
10
A complete replacement of the two chillers supplying
the sixth floor was carried out whilst the floor remained
fully occupied.
The new chillers were assembled on site within the plant
rooms whilst full cooling to the floor was maintained
using temporary chillers.
The temporary chillers were lifted by crane on to the
roof of the building and placed on a purpose built steel
structure for the duration of the works. These were
connected to the primary CHW circuit by temporary
flexible pipework which were fed through the roof and
seventh floor slabs.
Upon installation, the temporary system was tested
and commissioned before work started on the sixth
floor chillers.
One of the main challenges was the transportation of
the new chillers to the sixth floor plant rooms, which
was carried out by dismantling the units to manageable
sections and using the goods lift for transportation
between floors.
The old chillers were also transported from the sixth
floor to the ground floor using the same process.
The work was carefully co-ordinated and managed with
the contractor and the site M and E team to eliminate
the possibility of any disruption to the occupiers.
2.2 Sixth floor chillers
2.0PHASE1
11
A phased refurbishment programme was carried out for
all ten essential chillers on ground to second floor. This
included the replacement of all electronic monitoring
equipment, electronic switches, oil pumps and oil filters.
Furthermore the refrigerant volume and flow of the
systems were confirmed and the heat exchanger
internals were chemically cleaned using a flushing rig.
2.3 Ground to second floor chillers
The refurbishment process for each unit was concluded
by a comprehensive testing and commissioning
process. The chillers were refurbished to a carefully
planned schedule to ensure the cooling needs of the
occupiers were satisfied throughout the programme.
Broadgate Estates managed the refurbishment or replacement
of all 78 main pumps during the four-year programme to
ensure the units can perform effectively until 2019.
The pumps relate to all primary and secondary chilled water
and condenser pumps within the building. Each floor consists
of two primary chilled water pumps, eight condenser pumps
and eight secondary chilled water pumps.
Phase 1 addressed pumps on floors one to six with a particular
focus on third, fourth and fifth floors.
Some pumps were replaced in their entirety, whereas the
majority of pumps were refurbished.
Complete replacements were carried out for pumps that were
obsolete and unsupported by spares.
The pumps relating to refurbishment were initially assessed
to determine any components that required replacement.
Refurbishment consisted of replacement of seals, bearings,
O-rings, gaskets, motors and inverter drives.
Recognising the significant efficiency improvements that
can be realised, a number of bigger condenser pumps were
upgraded to inverter drives during the programme.
In order to minimise disruption and risk to the cooling
systems, the pump refurbishment programme was carefully
planned to match the cooling towers and chiller refurbishment
programmes that ran simultaneously.
Working in conjunction with the onsite M and E team, the
works were carried out successfully without any disruption to
the occupiers’ business.
12
2.4 Pumps
2.0PHASE1
13
2.5 Sprinkler heads
A substantial element of the renewal of the fire protection systems was
the replacement of all sprinkler heads in the property during the first
18 months of the programme. The key challenge was undertaking the
work in a property that was occupied with a number of floors housing
critical operations to occupiers’ businesses such as various trading
floors in the building.
Sprinkler replacements on occupied floors were carried out between
06.00pm and 03.00am to ensure no disruptions occurred and
sufficient time was available to prepare the floors ready for the
morning. An important aspect of the planning process was ensuring
all precautions were taken to eliminate the possibility of any impact on
occupiers’ property including highly sensitive and costly equipment.
The successful completion of the sprinkler replacement works
required careful planning and coordination and sound communication
between the site ME team and cleaning and fabric teams.
During the planning stage, each floor was divided into four quadrants
with work in each quadrant split further into multiple stages. Each
stage involved the replacement of around 30 sprinkler heads which
was typically completed within a single night shift.
Phase 1 of the programme incorporated the replacement of all 2,700
sprinkler heads from third floor to sixth floor which were fully occupied
during the works.
As Phase 1 was in progressions, the tenancy of ground, first and
second floors ended, which provided an opportunity to replace all the
sprinkler heads on these levels towards the latter part of phase 1.
Although not part of the initial plan for the programme, these works
were successfully incorporated to phase 1 works which resulted in the
renewal of all sprinkler heads in the building.
14
A key part for the refurbishment programme of the cooling system was the
reconditioning of all cooling towers.
Broadgate Estates also utilised this programme to upgrade the fan motors to IP65
inverter driven motors. The 12 cooling towers in the building feeding the quadrant
condenser system were reconditioned over three phases to an equal standard.
This resulted in prolonging life, improving efficiency and ensuring protection against
waterborne pathogens.
The SE1, NE1 and NW3 cooling towers were fully refurbished during Phase 1.
A complete restoration of the fan sections was undertaken which included the
replacement of fan motors, wheels, shafts, bearings and couplings.
The infrastructure was also modified to support the new control strategy where new
pumps and brominators were fitted and an IQ enclosure for monitoring and fault
finding was manufactured and installed.
New wiring infrastructure including new screened power supply, control wiring and
network wiring were also installed for each cooling tower.
As part of the programme, components such as drive sets and belts, drift eliminator
media, fill packs, access door gaskets and float valve assemblies were also replaced
for all cooling towers.
Electrical aspects of refurbishment included renewing of local isolators and flange
boxes and other localised lagging repairs.
The work was carried out during normal working hours, without any compromise on
occupiers’ cooling needs. This was achieved by refurbishing one cooling tower from
each quadrant condenser system at a time; ensuring two units were always online to
fulfil cooling needs of the occupiers.
In addition to the phased mechanical and electrical works, various other works were
undertaken as detailed below.
2.6 Cooling towers
2.0PHASE1
15
16
2.7 Miscellaneous works
In addition to the phased mechanical and electrical works,
various other works were undertaken as detailed below:
2.7.1	 Boiler Burners
In order to replace the obsolete burners for the two
LTHW boilers that provide underfloor heating for the
main atriums, the old burners were replaced in their
entirety with high efficiency flame controlled burners.
This was successfully carried out by the onsite M and E
maintenance team during the summer months to avoid
disruptions to occupiers’ heating.
2.7.2	AHUs
The on-site M and E service provider at 1-2 Broadgate carried out full
refurbishment of the two main AHUs located on the roof as part of
phase 1 of the programme to extend their life to 2019.
Works carried out on units include the overhaul of fans and fan drives,
replacement of filters, sensors, cleaning and lubrication of components
and treatment of corroded areas in the AHUs. A number of door hinges,
locks and seals were also renewed.
Units were then tested and commissioned and set back into operation.
2.0PHASE1
17
2.7.3	 Dry Riser Valves
In order to ensure the dry riser valves are in their optimum
condition to support the fire services in an event of a fire,
all 32 dry riser landing valves in the building were fully
replaced. Additionally four inlet breeching valves and four
air release valves were also replaced.
2.7.4	 Passenger and Goods Lifts
Broadgate Estates incorporated the refurbishment of
the lift motors and gearboxes of the four passenger lifts
and two goods lifts as part of the building infrastructure
works in Phase 2.
The lift motors in the passenger and goods lifts were
replaced due to their age which resulted in an extension
of life for the motors by 20 years.
Replacement of the gearboxes was a particularly
challenging aspect of these works as the original
and replacement gearbox assemblies had to be
disassembled for transport between floors due to
their size. The new gearboxes were reassembled
and commissioned in the lift plant rooms on the roof.
Arrangements were made by Broadgate Estates to
utilise a gearbox specialist from Germany to carry out
assembly and disassembly of gearbox units for each lift.
1818
3.0	 Phase 2
3.0PHASE2
19
The generator project aimed to renew and refurbish the
generator units to increase service life to 2019 and to
realise additional benefits of improved resilience, reliability
and maintainability.
The most significant part of the project was the
replacement of two life safety generators in their entirety
and the reconditioning of four occupiers’ generators.
These works also included a pressure test of the
occupiers’ generator flues and a full function test.
In order to increase the life of the generator switch panels
to 2019, generator sync panels, switch panels and
switchboard components in a number of generator and LV
rooms were replaced.
Additionally BMS devices, software, hardware and
graphics were also upgraded to support the new and
refurbished generators.
Careful co-ordination and planning was required between
Broadgate Estates, the site maintenance team and the
contractor who carried out the work, in order to minimise
disruption or loss of backup power to occupiers and
to ensure N+1 resilience of the generator systems was
always maintained.
Broadgate Estates also ensured the building works
programme was planned to have the necessary walls
demolished to create access to remove the old generators
and deliver the new generators.
3.1 Generators
20
Refurbishment of the LV switchgear included
the replacement of all Air circuit Breakers
(ACBs) and Moulded Case circuit Breakers
(MCCBs) within the old generator switch
boards.
The ACB and the MCCB ranges within the
old generator switch boards had become
obsolete and therefore replacements of
these units were carried out to ensure the
availability of spares beyond 2019.
Due to a number of incompatibilities
between the old and the new ACB ranges,
modification had to be made to the old
busbar connections to accommodate the
new units.
In order to eliminate any disruption to
occupiers’ operations, the ACB replacement
and load bank installation were completed
during weekend shutdowns.
3.2 LV switchgear
3.0PHASE2
21
A load bank connection facility was installed to facilitate
individual testing of the landlord’s generators. This panel
provides simulated loads to allow the landlord to test
each generator at any one time. In the event of a mains
failure during such a test, the load bank automatically
switches off to allow the generators to provide backup
power to the property.
3.3 Loadbank
22
The services of a specialist building works
company was needed to undertake
temporary and permanent modifications
to the building structure to satisfy access
requirements for the electrical works.
A number of walls and doorways of generator
rooms were demolished to remove old
generators from the building and to deliver
the new units.
Temporary walls and doorways were put
up to ensure access was permitted to
hazardous areas and safe walkways were
available for occupiers.
Additionally cladding was installed on
Finsbury Avenue which was painted and
illuminated to safely store the temporary
generators and load bank testing equipment.
Upon completion of the electrical upgrades, all
walls and doorways were rebuilt and the four
generator rooms were redecorated including
restoring walkways and floor markings.
Permanent changes to the building include
the holes formed through blockwork to
feed the loadbank busbar and cables,
modifications to the mesh cages to house
the new loadbank connection panels and
installation of fire cladding to all openings of
busbar and cables.
3.4 Building works
3.0PHASE2
23
3.5 Sprinkler systems
3.5.1	 Sprinkler Pumps
The two main sprinkler pumps and the associated
jockey pumps serving the building were subjected
to a full refurbishment programme with the aim to
ensure this critical system is able to perform at its
optimum level.
3.5.2	 Sprinkler Tanks
As part of the phase 1 works, all the sprinkler
tanks storing water in the basement were relined.
3.5.3	 Fire Phones
All fire phones within the building were replaced
with new units in Phase 1. It was crucial to carefully
plan and manage this element of the programme
to ensure the large quantity of fire phones located
throughout the building were renewed using an
efficient and methodical approach.
24
On continuation of the pump replacement and
refurbishment works, eighteen secondary chilled water
and condenser pumps on the ground to 5th floors were
addressed during phase 2.
The work done for each pump varied depending on
their condition.
Complete replacement was carried out for eight
pumps that were unsupported with spares with the
rest being refurbished.
New inverters were fitted for five of the refurbished
pumps and the remaining pumps were fitted with new
seals, gaskets and bearings. All pumps refurbished
were fitted with new motors.
Recognising the significant efficiency improvements that
can be realised, a number of bigger condenser pumps
were upgraded to inverter drives during the programme.
In order to minimise disruption and risk to the cooling
systems, the pump refurbishment programme was
carefully planned to match the cooling towers and chiller
refurbishment programmes that ran simultaneously.
Working in conjunction with the onsite M and E team,
the works were carried out successfully without any
disruption to the occupiers’ business.
3.6 Pumps
3.0PHASE2
25
During phase 2, four more chillers
were subjected to refurbishment.
This included the replacement of all
electronic monitoring equipment,
electronic switches, oil pumps and
oil filters.
Furthermore the refrigerant volume and
flow of the systems were confirmed
and the heat exchanger internals were
chemically cleaned using a flushing rig.
The refurbishment process for
each unit was concluded by
a comprehensive testing and
commissioning process. The chillers
were refurbished to a carefully
planned schedule to ensure the
cooling needs of the occupiers were
satisfied throughout the programme.
3.7 Chillers
26
3.0PHASE2
27
The refurbishment works for the cooling towers were
continued during phase 2 to fully restore three cooling
towers (i.e. SW1, NW1  NE3).
A complete restoration of the fan sections was
undertaken which included the replacement of fan
motors, wheels, shafts, bearings and couplings.
The infrastructure was also modified to support the new
control strategy where new pumps and brominators
were fitted.
New wiring infrastructure including new screened power
supply, control wiring and network wiring were also
installed for the cooling towers.
As part of the programme, components such as drive
sets and belts, drift eliminator media, fill packs, access
door gaskets and float valve assemblies were also
replaced.
Electrical aspects of refurbishment included renewing
of local isolators and flange boxes and other localised
lagging repairs.
The work was carried out during normal working hours,
without any compromise on occupiers’ cooling needs.
This was achieved by refurbishing one cooling tower
from each quadrant condenser system at a time;
ensuring two units were always online to fulfil cooling
needs of the occupiers.
3.8 Cooling towers
2828
4.0	 Phase 3
The pump replacement and refurbishment works were
completed during phase 3.
A similar approach to phase 1 and 2 was taken,
whereby each pump was assessed for replacement
requirements before replacing the required components.
Eight twinhead pumps on levels two, four and five
were addressed on this phase. Six of these pumps
were replaced and two were fitted with new seals and
O-rings. All pumps were fitted with new motors.
Recognising the significant efficiency improvements that
can be realised, a number of bigger condenser pumps
were upgraded to inverter drives during the programme.
In order to minimise disruption and risk to the cooling
systems, the pump refurbishment programme was
carefully planned to match the cooling towers and chiller
refurbishment programmes that ran simultaneously.
Working in conjunction with the onsite M and E team,
the works were carried out successfully without any
disruption to the occupiers’ business.
The refurbishment process for each unit was concluded
by a comprehensive testing and commissioning
process. The chillers were refurbished to a carefully
planned schedule to ensure the cooling needs of the
occupiers were satisfied throughout the programme.
4.1 Pumps
4.0PHASE3
29
In order to conclude the chiller refurbishment works, the
eight remaining chillers in the building were refurbished
using the same process used in the first two phases.
This included the replacement of all electronic monitoring
equipment, electronic switches, oil pumps and oil filters.
Furthermore the refrigerant volume and flow of the systems
were confirmed and the heat exchanger internals were
chemically cleaned using a flushing rig.
The refurbishment process for each unit was concluded by
a comprehensive testing and commissioning process. The
chillers were refurbished to a carefully planned schedule to
ensure the cooling needs of the occupiers were satisfied
throughout the programme.
4.2 Chillers
30
The final phase also involved the completion of the
cooling tower refurbishment works.
Six cooling towers (i.e. NE2, NW2, SW2, SW3, SE2 and
SE3) were fully refurbished in this phase.
A complete restoration of the fan sections was
undertaken which included the replacement of fan
motors, wheels, shafts, bearings and couplings.
The infrastructure was also modified to support the new
control strategy where new pumps and brominators
were fitted.
New wiring infrastructure including new screened power
supply, control wiring and network wiring were also
installed for the cooling towers.
As part of the programme, components such as drive sets
and belts, drift eliminator media, fill packs, access door
gaskets and float valve assemblies were also replaced.
Electrical aspects of refurbishment included renewing
of local isolators and flange boxes and other localised
lagging repairs.
The work was carried out during normal working hours,
without any compromise on occupiers’ cooling needs.
This was achieved by refurbishing one cooling tower
from each quadrant condenser system at a time;
ensuring two units were always online to fulfil cooling
needs of the occupiers.
Completion of these works ensured all the cooling
towers at 1 and 2 Broadgate are at an equal standard
with increased life, efficiency and protection against
waterborne pathogens.
4.3 Cooling towers
31
4.0PHASE3
31
32
5.0	Conclusion
CONCLUSION
33
Under the management of Broadgate Estates, the
refurbishment program of 1-2 Broadgate was delivered
before the scheduled completion date, significantly under
budget and without the occurrence of any safety incidents.
Though careful planning, coordination and a highly
client focussed approach, Broadgate Estates ensured
all building services to occupiers were maintained
throughout the program, without any compromise on
standards and resilience.
5.0 Conclusion
in partnership with

More Related Content

What's hot

Tim Rathsam Work History
Tim Rathsam Work HistoryTim Rathsam Work History
Tim Rathsam Work History
Tim Rathsam
 
West.Robert.resume.2016-02
West.Robert.resume.2016-02West.Robert.resume.2016-02
West.Robert.resume.2016-02
Robert West
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011
Jamal Nelson, CCM
 
Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland Resume'- June 20th 2015Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland
 
Mohammad Rehan Akbar Khan .P.M
Mohammad Rehan Akbar Khan .P.MMohammad Rehan Akbar Khan .P.M
Mohammad Rehan Akbar Khan .P.M
Rehan Khan
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completion
Ronie Chu
 
Resume for Kenneth Peartree (Full)
Resume for Kenneth Peartree (Full)Resume for Kenneth Peartree (Full)
Resume for Kenneth Peartree (Full)
Ken Peartree
 
Eng_1st Qtr 2014 Ops Meeting
Eng_1st Qtr 2014 Ops MeetingEng_1st Qtr 2014 Ops Meeting
Eng_1st Qtr 2014 Ops Meeting
Kurt Holobaugh
 
EdwardRueblingResume-7-20-16
EdwardRueblingResume-7-20-16EdwardRueblingResume-7-20-16
EdwardRueblingResume-7-20-16
Edward Ruebling
 
Dave Harrison CV December 2016
Dave Harrison CV December 2016Dave Harrison CV December 2016
Dave Harrison CV December 2016
David Harrison
 
last updat C.V SAYED
last updat C.V SAYEDlast updat C.V SAYED
last updat C.V SAYED
Sayed Rewesh
 
CV of Instrumentation Consultant_Rashesh Shah_32 years plus exp
CV of Instrumentation Consultant_Rashesh Shah_32 years plus expCV of Instrumentation Consultant_Rashesh Shah_32 years plus exp
CV of Instrumentation Consultant_Rashesh Shah_32 years plus exp
Rashesh Shah
 

What's hot (20)

Tim Rathsam Work History
Tim Rathsam Work HistoryTim Rathsam Work History
Tim Rathsam Work History
 
West.Robert.resume.2016-02
West.Robert.resume.2016-02West.Robert.resume.2016-02
West.Robert.resume.2016-02
 
MS CV May 2016
MS CV May 2016MS CV May 2016
MS CV May 2016
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011
 
Current Construction Projects, City of Chicago, August 21, 2008
Current Construction Projects, City of Chicago, August 21, 2008Current Construction Projects, City of Chicago, August 21, 2008
Current Construction Projects, City of Chicago, August 21, 2008
 
DAMAC Heights Project
DAMAC Heights ProjectDAMAC Heights Project
DAMAC Heights Project
 
Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland Resume'- June 20th 2015Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland Resume'- June 20th 2015
 
Anil Pachpande-CV2016
Anil Pachpande-CV2016Anil Pachpande-CV2016
Anil Pachpande-CV2016
 
The Commissioning Process
The Commissioning ProcessThe Commissioning Process
The Commissioning Process
 
Harshad Patel Resume- hkp-G15
Harshad Patel Resume- hkp-G15Harshad Patel Resume- hkp-G15
Harshad Patel Resume- hkp-G15
 
Mohammad Rehan Akbar Khan .P.M
Mohammad Rehan Akbar Khan .P.MMohammad Rehan Akbar Khan .P.M
Mohammad Rehan Akbar Khan .P.M
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completion
 
Resume for Kenneth Peartree (Full)
Resume for Kenneth Peartree (Full)Resume for Kenneth Peartree (Full)
Resume for Kenneth Peartree (Full)
 
Eng_1st Qtr 2014 Ops Meeting
Eng_1st Qtr 2014 Ops MeetingEng_1st Qtr 2014 Ops Meeting
Eng_1st Qtr 2014 Ops Meeting
 
EdwardRueblingResume-7-20-16
EdwardRueblingResume-7-20-16EdwardRueblingResume-7-20-16
EdwardRueblingResume-7-20-16
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 )
 
Dave Harrison CV December 2016
Dave Harrison CV December 2016Dave Harrison CV December 2016
Dave Harrison CV December 2016
 
last updat C.V SAYED
last updat C.V SAYEDlast updat C.V SAYED
last updat C.V SAYED
 
CV of Instrumentation Consultant_Rashesh Shah_32 years plus exp
CV of Instrumentation Consultant_Rashesh Shah_32 years plus expCV of Instrumentation Consultant_Rashesh Shah_32 years plus exp
CV of Instrumentation Consultant_Rashesh Shah_32 years plus exp
 
Baijan Savalan _ Avans High School lecture 27.10.16
Baijan Savalan _ Avans High School lecture 27.10.16Baijan Savalan _ Avans High School lecture 27.10.16
Baijan Savalan _ Avans High School lecture 27.10.16
 

Viewers also liked

Project 2 - Final Deck
Project 2 - Final DeckProject 2 - Final Deck
Project 2 - Final Deck
Philip Croft
 

Viewers also liked (10)

Abril 2016
Abril 2016Abril 2016
Abril 2016
 
Schema benefici del verde
Schema benefici del verdeSchema benefici del verde
Schema benefici del verde
 
Project 2 - Final Deck
Project 2 - Final DeckProject 2 - Final Deck
Project 2 - Final Deck
 
Actividad 2-vitacora-4
Actividad 2-vitacora-4Actividad 2-vitacora-4
Actividad 2-vitacora-4
 
Simple and Continuous Tenses
Simple and Continuous TensesSimple and Continuous Tenses
Simple and Continuous Tenses
 
Resume 2015-16
Resume 2015-16Resume 2015-16
Resume 2015-16
 
Linguistic markup and transclusion processing in XML documents
Linguistic markup and transclusion processing in XML documentsLinguistic markup and transclusion processing in XML documents
Linguistic markup and transclusion processing in XML documents
 
TRABAJO FINAL DE PSICOINFORMATICA
TRABAJO FINAL DE PSICOINFORMATICATRABAJO FINAL DE PSICOINFORMATICA
TRABAJO FINAL DE PSICOINFORMATICA
 
Caso faltante a la ética
Caso faltante a la éticaCaso faltante a la ética
Caso faltante a la ética
 
NeuroRegTBIDisc
NeuroRegTBIDiscNeuroRegTBIDisc
NeuroRegTBIDisc
 

Similar to 1-2 Broadgate Final Project Report

ProTec Recent Projects Brochure
ProTec Recent Projects BrochureProTec Recent Projects Brochure
ProTec Recent Projects Brochure
Steven MacDonald
 
Tony Greenfield CV 23 March 2015 pdf
Tony Greenfield CV 23 March 2015 pdfTony Greenfield CV 23 March 2015 pdf
Tony Greenfield CV 23 March 2015 pdf
Tony Greenfield
 
Leon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016RLeon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016R
Leon Chacon
 
Anthony_F_Vitola_Engineer_Resume
Anthony_F_Vitola_Engineer_ResumeAnthony_F_Vitola_Engineer_Resume
Anthony_F_Vitola_Engineer_Resume
Anthony Vitola
 
resume for john rhynold 2015 #2
resume for john rhynold 2015 #2resume for john rhynold 2015 #2
resume for john rhynold 2015 #2
john rhynold
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1
Dan Caouette
 

Similar to 1-2 Broadgate Final Project Report (20)

ProTec Recent Projects Brochure
ProTec Recent Projects BrochureProTec Recent Projects Brochure
ProTec Recent Projects Brochure
 
Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00
 
Tony Greenfield CV 23 March 2015 pdf
Tony Greenfield CV 23 March 2015 pdfTony Greenfield CV 23 March 2015 pdf
Tony Greenfield CV 23 March 2015 pdf
 
william-first-revision
william-first-revisionwilliam-first-revision
william-first-revision
 
Leon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016RLeon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016R
 
william-second-revision (3)
william-second-revision (3)william-second-revision (3)
william-second-revision (3)
 
CV_Ashu Bhatt
CV_Ashu BhattCV_Ashu Bhatt
CV_Ashu Bhatt
 
Projects presentation1
Projects presentation1Projects presentation1
Projects presentation1
 
Paul Southall's CP2 Presentation
Paul Southall's CP2 PresentationPaul Southall's CP2 Presentation
Paul Southall's CP2 Presentation
 
5.ve volume 1_ve_burton
5.ve volume 1_ve_burton5.ve volume 1_ve_burton
5.ve volume 1_ve_burton
 
Baf 2013 abc of jv3_ken thomson
Baf 2013 abc of jv3_ken thomsonBaf 2013 abc of jv3_ken thomson
Baf 2013 abc of jv3_ken thomson
 
Barangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact SheetBarangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact Sheet
 
Anthony_F_Vitola_Engineer_Resume
Anthony_F_Vitola_Engineer_ResumeAnthony_F_Vitola_Engineer_Resume
Anthony_F_Vitola_Engineer_Resume
 
report.docx
report.docxreport.docx
report.docx
 
resume for john rhynold 2015 #2
resume for john rhynold 2015 #2resume for john rhynold 2015 #2
resume for john rhynold 2015 #2
 
Mechanical Hvac INMA 3117
Mechanical Hvac INMA 3117Mechanical Hvac INMA 3117
Mechanical Hvac INMA 3117
 
Hvac chiller Engineer Tech
Hvac chiller Engineer Tech Hvac chiller Engineer Tech
Hvac chiller Engineer Tech
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1
 
Kandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _bKandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _b
 
Assignment (1)
Assignment (1)Assignment (1)
Assignment (1)
 

1-2 Broadgate Final Project Report

  • 2. Xxx FOREWORD 2 We have extensive experience of undertaking complex projects where we have worked with occupiers to develop their requirements and used our substantial project management expertise to deliver their expectations, resulting in buildings that positively enhance their business. Many of our projects are undertaken in occupation and we are adept at reviewing the strategy to advise on the phasing of work to minimise disruption to the occupiers while reducing costs and maintaining business continuity. Peter Bicknell, Client Services Director (Head of Technical Services) Peter Bicknell, Client Services Director (Head of Technical Services) Paul J Warrington, Engineering Manager Foreword
  • 3. CONTENTS 3 CONTENTS 3 1.0 Introduction 4 1.2 Project summary������������������������������������������������������������������������������������������������������������������������������������������������������������������ 6 2.0 Phase 1 8 2.1 N+1 resilience system ��������������������������������������������������������������������������������������������������������������������������������������������������������� 9 2.2 Sixth floor chillers���������������������������������������������������������������������������������������������������������������������������������������������������������������10 2.3 Ground to second floor chillers �����������������������������������������������������������������������������������������������������������������������������������������11 2.4 Pumps���������������������������������������������������������������������������������������������������������������������������������������������������������������������������������12 2.5 Sprinkler heads�������������������������������������������������������������������������������������������������������������������������������������������������������������������13 2.6 Cooling towers �������������������������������������������������������������������������������������������������������������������������������������������������������������������14 2.7 Miscellaneous works����������������������������������������������������������������������������������������������������������������������������������������������������������16 3.0 Phase 2 18 3.1 Generators �������������������������������������������������������������������������������������������������������������������������������������������������������������������������19 3.2 LV switchgear���������������������������������������������������������������������������������������������������������������������������������������������������������������������20 3.3 Loadbank����������������������������������������������������������������������������������������������������������������������������������������������������������������������������21 3.4 Building works���������������������������������������������������������������������������������������������������������������������������������������������������������������������22 3.5 Sprinkler systems���������������������������������������������������������������������������������������������������������������������������������������������������������������23 3.6 Pumps���������������������������������������������������������������������������������������������������������������������������������������������������������������������������������24 3.7 Chillers��������������������������������������������������������������������������������������������������������������������������������������������������������������������������������25 3.8 Cooling towers �������������������������������������������������������������������������������������������������������������������������������������������������������������������27 4.0 Phase 3 28 4.1 Pumps���������������������������������������������������������������������������������������������������������������������������������������������������������������������������������29 4.2 Chillers��������������������������������������������������������������������������������������������������������������������������������������������������������������������������������30 4.3 Cooling towers �������������������������������������������������������������������������������������������������������������������������������������������������������������������31 5.0 Conclusion 32
  • 5. 1.0INTRODUCTION 5 1-2 Broadgate consists of 305,272ft2 of floor area spread across six levels occupied by a range of businesses including ICAP, Royal Mail, KBW, Regus, Precise Media, Brookfield Multiplex, ETX and GF Securities. A four year comprehensive refurbishment programme was carried out at the property restoring key elements of the mechanical and electrical building infrastructure with the aim of extending life to 2019. A key aim of the project was to give confidence to the occupiers ensuring their needs will be fulfilled in the future so they can re-gear their lease and extend the duration of their stay in the property. The works were completed in three phases between 2012 and 2015, whilst the building was fully occupied. Prior to the programme, the majority of systems and equipment in the property had not undergone significant upgrades from the systems installed during the initial development of the property in 1986. An exception being the transformation of the chilled water air conditioning system in 2005 from a centralised system to a quadrant chiller system with dedicated chillers and AHUs housed on each floor. However the majority of equipment in the building was approaching the end of its serviceable life at the time of the programme. In order to initiate the refurbishment project, Broadgate Estates were invited by the landlord to summarise and advise on the engineering systems within the property with respect to suitability, reliability and obsolescence of the equipment. Additionally any major equipment or systems which had exceeded or were nearing their service life were identified for replacement to ensure the needs of the occupiers can be fulfilled until 2019. A key aspect of the project initiation process was the risk assessments carried out by Broadgate Estates on all 386 engineering systems and assets in the building. The assessments resulted in risk ratings being given for the potential failure of all equipment and systems. This was based on multiple factors such as condition, compliance and service impact upon failure. Based on the risk scores, equipment were prioritised within the four year programme which resulted in the equipment that was likely to pose the highest potential risk to the occupiers’ business being addressed within the early phases of the programme. In order to transform these findings into specific work items, Broadgate Estates commissioned several specialists engineering service providers to propose technical recommendations for the work required. These proposals were utilised as guidance to produce a detailed version of the phased refurbishment plan spanning the four year period. 1.1 General
  • 6. 1.2 Project summary The most significant and critical parts of the refurbishment works were completed during phase 1 over an 18-month period. The most notable of these works was the replacement of the two dedicated chillers and cooling tower which provide cooling to the occupiers’ UPS facility on an N+1 configuration. Further replacements were carried out of two chillers located on the sixth floor whilst the floor was fully occupied. Broadgate Estates ensured that occupiers’ cooling needs were continually satisfied by installing and managing similar sized temporary chillers on the roof for the duration of the works. A complete refurbishment of the rest of the cooling system in the building was undertaken during the three phases. This included replacement or refurbishment of 78 primary and secondary chilled water and condenser pumps, 22 chillers and 12 cooling towers in the building. All of these works involved the contribution of multiple contractors who worked on site simultaneously as planned and coordinated by Broadgate Estates. This ensured efficient and timely completion of work packages with minimal downtime of systems. Through meticulous planning and careful co-ordination between the multiple parties, the cooling system refurbishment works were completed without interruption to occupiers’ air conditioning services. The fire protection systems in the building were subjected to overhaul to ensure these critical systems can continue to perform at their optimum level. Key aspects of these works were the change of all fire phones, sprinkler heads and tanks and refurbishment of the main sprinkler pumps in the building. A number of important electrical upgrades formed a substantial share of the phase 2 works in which the two occupiers’ life safety generators were replaced in their entirety and the four landlords’ generators were fully reconditioned. Temporary generators were installed and operated by Broadgate Estates to maintain the level of backup power to occupiers operations throughout the works. Replacements to LV switchgear were undertaken where ACBs (Air Circuit Breakers) had become obsolete and unsupported with spare parts. Broadgate Estates also managed the installation of a new load bank connection facility as part of these works. A number of temporary and permanent modifications to the building were completed to enable the electrical upgrades and to provide safe access routes for occupiers during the works. Several other restoration works were accomplished within the programme including the replacement of all dry riser landing valves and the refurbishment of passenger and goods lifts and the two main AHUs. Upgrades were made to the LTHW boiler system to transform the boiler burners to flame controlled burners resulting in improved efficiency. 6
  • 7. 1.3 Project governance The responsibility of overall project delivery was held by an incumbent Project Lead who also provided immediate client oversight. A Project Engineering Director and a Project Client Director was also appointed to provide engineering oversight and client oversight respectively and to be jointly responsible for approving works and contracts. Any significant variations to costs and timescales were scrutinised and approved by the Project Directors. In the occurrence of considerable technical variations, the Project Engineering Director was responsible for approving the changes. Systems upgrades and IT and fabric related works were managed by three appointed project managers from the respective departments within Broadgate Estates. The project team also included a Manager who ensured compliance of the programme with CDM (Construction, Design and Management) regulation. A clear communication plan was vital in carrying out works within timescales and budgets with minimal interruption to the multiple client operations in the property. A building management meeting and an occupiers’ meeting held on a weekly basis and a landlord’s meeting held every month were crucial elements of the communication plan. A six weekly programme which was updated on a monthly basis was presented by Broadgate Estates to stakeholders during these three types of meetings. 1.0INTRODUCTION 7 WEEKLY MEETINGS MONTHLY MEETINGS 1.0INTRODUCTION 7
  • 9. 2.0PHASE1 9 The most significant part of Phase 1 was to refurbish the N+1 resilience cooling system which provides cooling to the occupiers’ UPS facilities. The refurbishment of this critical system was carried out with the collaboration of three specialist contractors working simultaneously whilst the building was fully occupied. The UPS cooling system consists of a Carrier 30HXC230 Chiller located within the basement and a ground floor chiller which provides N+1 resilience. The system works in conjunction with a dedicated cooling tower. The most critical aspect of the works was the replacement of the carrier chiller. Additionally the ground floor chiller and the cooling tower were fully refurbished in order to extend their service life. Broadgate Estates ensured the work did not compromise the cooling requirements and cooling system resilience of the UPS system by installing and operating an equally sized temporary AC plant with air cooled chillers housed in the loading bay. Furthermore the fan control strategy for the cooling tower was upgraded from two speed control to fully modulating control resulting in increased efficiency. Changes were also made to the BMS to increase the frequency of flushing to protect the tower should the system not run for the preceding 12 hours. Previous to the change, condenser flushing was accommodated in a single time zone each day. The set point temperature to enable the cooling tower fan was also decreased from 24ºC to 18.5ºC. 2.1 N+1 resilience system
  • 10. 10 A complete replacement of the two chillers supplying the sixth floor was carried out whilst the floor remained fully occupied. The new chillers were assembled on site within the plant rooms whilst full cooling to the floor was maintained using temporary chillers. The temporary chillers were lifted by crane on to the roof of the building and placed on a purpose built steel structure for the duration of the works. These were connected to the primary CHW circuit by temporary flexible pipework which were fed through the roof and seventh floor slabs. Upon installation, the temporary system was tested and commissioned before work started on the sixth floor chillers. One of the main challenges was the transportation of the new chillers to the sixth floor plant rooms, which was carried out by dismantling the units to manageable sections and using the goods lift for transportation between floors. The old chillers were also transported from the sixth floor to the ground floor using the same process. The work was carefully co-ordinated and managed with the contractor and the site M and E team to eliminate the possibility of any disruption to the occupiers. 2.2 Sixth floor chillers
  • 11. 2.0PHASE1 11 A phased refurbishment programme was carried out for all ten essential chillers on ground to second floor. This included the replacement of all electronic monitoring equipment, electronic switches, oil pumps and oil filters. Furthermore the refrigerant volume and flow of the systems were confirmed and the heat exchanger internals were chemically cleaned using a flushing rig. 2.3 Ground to second floor chillers The refurbishment process for each unit was concluded by a comprehensive testing and commissioning process. The chillers were refurbished to a carefully planned schedule to ensure the cooling needs of the occupiers were satisfied throughout the programme.
  • 12. Broadgate Estates managed the refurbishment or replacement of all 78 main pumps during the four-year programme to ensure the units can perform effectively until 2019. The pumps relate to all primary and secondary chilled water and condenser pumps within the building. Each floor consists of two primary chilled water pumps, eight condenser pumps and eight secondary chilled water pumps. Phase 1 addressed pumps on floors one to six with a particular focus on third, fourth and fifth floors. Some pumps were replaced in their entirety, whereas the majority of pumps were refurbished. Complete replacements were carried out for pumps that were obsolete and unsupported by spares. The pumps relating to refurbishment were initially assessed to determine any components that required replacement. Refurbishment consisted of replacement of seals, bearings, O-rings, gaskets, motors and inverter drives. Recognising the significant efficiency improvements that can be realised, a number of bigger condenser pumps were upgraded to inverter drives during the programme. In order to minimise disruption and risk to the cooling systems, the pump refurbishment programme was carefully planned to match the cooling towers and chiller refurbishment programmes that ran simultaneously. Working in conjunction with the onsite M and E team, the works were carried out successfully without any disruption to the occupiers’ business. 12 2.4 Pumps
  • 13. 2.0PHASE1 13 2.5 Sprinkler heads A substantial element of the renewal of the fire protection systems was the replacement of all sprinkler heads in the property during the first 18 months of the programme. The key challenge was undertaking the work in a property that was occupied with a number of floors housing critical operations to occupiers’ businesses such as various trading floors in the building. Sprinkler replacements on occupied floors were carried out between 06.00pm and 03.00am to ensure no disruptions occurred and sufficient time was available to prepare the floors ready for the morning. An important aspect of the planning process was ensuring all precautions were taken to eliminate the possibility of any impact on occupiers’ property including highly sensitive and costly equipment. The successful completion of the sprinkler replacement works required careful planning and coordination and sound communication between the site ME team and cleaning and fabric teams. During the planning stage, each floor was divided into four quadrants with work in each quadrant split further into multiple stages. Each stage involved the replacement of around 30 sprinkler heads which was typically completed within a single night shift. Phase 1 of the programme incorporated the replacement of all 2,700 sprinkler heads from third floor to sixth floor which were fully occupied during the works. As Phase 1 was in progressions, the tenancy of ground, first and second floors ended, which provided an opportunity to replace all the sprinkler heads on these levels towards the latter part of phase 1. Although not part of the initial plan for the programme, these works were successfully incorporated to phase 1 works which resulted in the renewal of all sprinkler heads in the building.
  • 14. 14 A key part for the refurbishment programme of the cooling system was the reconditioning of all cooling towers. Broadgate Estates also utilised this programme to upgrade the fan motors to IP65 inverter driven motors. The 12 cooling towers in the building feeding the quadrant condenser system were reconditioned over three phases to an equal standard. This resulted in prolonging life, improving efficiency and ensuring protection against waterborne pathogens. The SE1, NE1 and NW3 cooling towers were fully refurbished during Phase 1. A complete restoration of the fan sections was undertaken which included the replacement of fan motors, wheels, shafts, bearings and couplings. The infrastructure was also modified to support the new control strategy where new pumps and brominators were fitted and an IQ enclosure for monitoring and fault finding was manufactured and installed. New wiring infrastructure including new screened power supply, control wiring and network wiring were also installed for each cooling tower. As part of the programme, components such as drive sets and belts, drift eliminator media, fill packs, access door gaskets and float valve assemblies were also replaced for all cooling towers. Electrical aspects of refurbishment included renewing of local isolators and flange boxes and other localised lagging repairs. The work was carried out during normal working hours, without any compromise on occupiers’ cooling needs. This was achieved by refurbishing one cooling tower from each quadrant condenser system at a time; ensuring two units were always online to fulfil cooling needs of the occupiers. In addition to the phased mechanical and electrical works, various other works were undertaken as detailed below. 2.6 Cooling towers
  • 16. 16 2.7 Miscellaneous works In addition to the phased mechanical and electrical works, various other works were undertaken as detailed below: 2.7.1 Boiler Burners In order to replace the obsolete burners for the two LTHW boilers that provide underfloor heating for the main atriums, the old burners were replaced in their entirety with high efficiency flame controlled burners. This was successfully carried out by the onsite M and E maintenance team during the summer months to avoid disruptions to occupiers’ heating. 2.7.2 AHUs The on-site M and E service provider at 1-2 Broadgate carried out full refurbishment of the two main AHUs located on the roof as part of phase 1 of the programme to extend their life to 2019. Works carried out on units include the overhaul of fans and fan drives, replacement of filters, sensors, cleaning and lubrication of components and treatment of corroded areas in the AHUs. A number of door hinges, locks and seals were also renewed. Units were then tested and commissioned and set back into operation.
  • 17. 2.0PHASE1 17 2.7.3 Dry Riser Valves In order to ensure the dry riser valves are in their optimum condition to support the fire services in an event of a fire, all 32 dry riser landing valves in the building were fully replaced. Additionally four inlet breeching valves and four air release valves were also replaced. 2.7.4 Passenger and Goods Lifts Broadgate Estates incorporated the refurbishment of the lift motors and gearboxes of the four passenger lifts and two goods lifts as part of the building infrastructure works in Phase 2. The lift motors in the passenger and goods lifts were replaced due to their age which resulted in an extension of life for the motors by 20 years. Replacement of the gearboxes was a particularly challenging aspect of these works as the original and replacement gearbox assemblies had to be disassembled for transport between floors due to their size. The new gearboxes were reassembled and commissioned in the lift plant rooms on the roof. Arrangements were made by Broadgate Estates to utilise a gearbox specialist from Germany to carry out assembly and disassembly of gearbox units for each lift.
  • 19. 3.0PHASE2 19 The generator project aimed to renew and refurbish the generator units to increase service life to 2019 and to realise additional benefits of improved resilience, reliability and maintainability. The most significant part of the project was the replacement of two life safety generators in their entirety and the reconditioning of four occupiers’ generators. These works also included a pressure test of the occupiers’ generator flues and a full function test. In order to increase the life of the generator switch panels to 2019, generator sync panels, switch panels and switchboard components in a number of generator and LV rooms were replaced. Additionally BMS devices, software, hardware and graphics were also upgraded to support the new and refurbished generators. Careful co-ordination and planning was required between Broadgate Estates, the site maintenance team and the contractor who carried out the work, in order to minimise disruption or loss of backup power to occupiers and to ensure N+1 resilience of the generator systems was always maintained. Broadgate Estates also ensured the building works programme was planned to have the necessary walls demolished to create access to remove the old generators and deliver the new generators. 3.1 Generators
  • 20. 20 Refurbishment of the LV switchgear included the replacement of all Air circuit Breakers (ACBs) and Moulded Case circuit Breakers (MCCBs) within the old generator switch boards. The ACB and the MCCB ranges within the old generator switch boards had become obsolete and therefore replacements of these units were carried out to ensure the availability of spares beyond 2019. Due to a number of incompatibilities between the old and the new ACB ranges, modification had to be made to the old busbar connections to accommodate the new units. In order to eliminate any disruption to occupiers’ operations, the ACB replacement and load bank installation were completed during weekend shutdowns. 3.2 LV switchgear
  • 21. 3.0PHASE2 21 A load bank connection facility was installed to facilitate individual testing of the landlord’s generators. This panel provides simulated loads to allow the landlord to test each generator at any one time. In the event of a mains failure during such a test, the load bank automatically switches off to allow the generators to provide backup power to the property. 3.3 Loadbank
  • 22. 22 The services of a specialist building works company was needed to undertake temporary and permanent modifications to the building structure to satisfy access requirements for the electrical works. A number of walls and doorways of generator rooms were demolished to remove old generators from the building and to deliver the new units. Temporary walls and doorways were put up to ensure access was permitted to hazardous areas and safe walkways were available for occupiers. Additionally cladding was installed on Finsbury Avenue which was painted and illuminated to safely store the temporary generators and load bank testing equipment. Upon completion of the electrical upgrades, all walls and doorways were rebuilt and the four generator rooms were redecorated including restoring walkways and floor markings. Permanent changes to the building include the holes formed through blockwork to feed the loadbank busbar and cables, modifications to the mesh cages to house the new loadbank connection panels and installation of fire cladding to all openings of busbar and cables. 3.4 Building works
  • 23. 3.0PHASE2 23 3.5 Sprinkler systems 3.5.1 Sprinkler Pumps The two main sprinkler pumps and the associated jockey pumps serving the building were subjected to a full refurbishment programme with the aim to ensure this critical system is able to perform at its optimum level. 3.5.2 Sprinkler Tanks As part of the phase 1 works, all the sprinkler tanks storing water in the basement were relined. 3.5.3 Fire Phones All fire phones within the building were replaced with new units in Phase 1. It was crucial to carefully plan and manage this element of the programme to ensure the large quantity of fire phones located throughout the building were renewed using an efficient and methodical approach.
  • 24. 24 On continuation of the pump replacement and refurbishment works, eighteen secondary chilled water and condenser pumps on the ground to 5th floors were addressed during phase 2. The work done for each pump varied depending on their condition. Complete replacement was carried out for eight pumps that were unsupported with spares with the rest being refurbished. New inverters were fitted for five of the refurbished pumps and the remaining pumps were fitted with new seals, gaskets and bearings. All pumps refurbished were fitted with new motors. Recognising the significant efficiency improvements that can be realised, a number of bigger condenser pumps were upgraded to inverter drives during the programme. In order to minimise disruption and risk to the cooling systems, the pump refurbishment programme was carefully planned to match the cooling towers and chiller refurbishment programmes that ran simultaneously. Working in conjunction with the onsite M and E team, the works were carried out successfully without any disruption to the occupiers’ business. 3.6 Pumps
  • 25. 3.0PHASE2 25 During phase 2, four more chillers were subjected to refurbishment. This included the replacement of all electronic monitoring equipment, electronic switches, oil pumps and oil filters. Furthermore the refrigerant volume and flow of the systems were confirmed and the heat exchanger internals were chemically cleaned using a flushing rig. The refurbishment process for each unit was concluded by a comprehensive testing and commissioning process. The chillers were refurbished to a carefully planned schedule to ensure the cooling needs of the occupiers were satisfied throughout the programme. 3.7 Chillers
  • 26. 26
  • 27. 3.0PHASE2 27 The refurbishment works for the cooling towers were continued during phase 2 to fully restore three cooling towers (i.e. SW1, NW1 NE3). A complete restoration of the fan sections was undertaken which included the replacement of fan motors, wheels, shafts, bearings and couplings. The infrastructure was also modified to support the new control strategy where new pumps and brominators were fitted. New wiring infrastructure including new screened power supply, control wiring and network wiring were also installed for the cooling towers. As part of the programme, components such as drive sets and belts, drift eliminator media, fill packs, access door gaskets and float valve assemblies were also replaced. Electrical aspects of refurbishment included renewing of local isolators and flange boxes and other localised lagging repairs. The work was carried out during normal working hours, without any compromise on occupiers’ cooling needs. This was achieved by refurbishing one cooling tower from each quadrant condenser system at a time; ensuring two units were always online to fulfil cooling needs of the occupiers. 3.8 Cooling towers
  • 29. The pump replacement and refurbishment works were completed during phase 3. A similar approach to phase 1 and 2 was taken, whereby each pump was assessed for replacement requirements before replacing the required components. Eight twinhead pumps on levels two, four and five were addressed on this phase. Six of these pumps were replaced and two were fitted with new seals and O-rings. All pumps were fitted with new motors. Recognising the significant efficiency improvements that can be realised, a number of bigger condenser pumps were upgraded to inverter drives during the programme. In order to minimise disruption and risk to the cooling systems, the pump refurbishment programme was carefully planned to match the cooling towers and chiller refurbishment programmes that ran simultaneously. Working in conjunction with the onsite M and E team, the works were carried out successfully without any disruption to the occupiers’ business. The refurbishment process for each unit was concluded by a comprehensive testing and commissioning process. The chillers were refurbished to a carefully planned schedule to ensure the cooling needs of the occupiers were satisfied throughout the programme. 4.1 Pumps 4.0PHASE3 29
  • 30. In order to conclude the chiller refurbishment works, the eight remaining chillers in the building were refurbished using the same process used in the first two phases. This included the replacement of all electronic monitoring equipment, electronic switches, oil pumps and oil filters. Furthermore the refrigerant volume and flow of the systems were confirmed and the heat exchanger internals were chemically cleaned using a flushing rig. The refurbishment process for each unit was concluded by a comprehensive testing and commissioning process. The chillers were refurbished to a carefully planned schedule to ensure the cooling needs of the occupiers were satisfied throughout the programme. 4.2 Chillers 30
  • 31. The final phase also involved the completion of the cooling tower refurbishment works. Six cooling towers (i.e. NE2, NW2, SW2, SW3, SE2 and SE3) were fully refurbished in this phase. A complete restoration of the fan sections was undertaken which included the replacement of fan motors, wheels, shafts, bearings and couplings. The infrastructure was also modified to support the new control strategy where new pumps and brominators were fitted. New wiring infrastructure including new screened power supply, control wiring and network wiring were also installed for the cooling towers. As part of the programme, components such as drive sets and belts, drift eliminator media, fill packs, access door gaskets and float valve assemblies were also replaced. Electrical aspects of refurbishment included renewing of local isolators and flange boxes and other localised lagging repairs. The work was carried out during normal working hours, without any compromise on occupiers’ cooling needs. This was achieved by refurbishing one cooling tower from each quadrant condenser system at a time; ensuring two units were always online to fulfil cooling needs of the occupiers. Completion of these works ensured all the cooling towers at 1 and 2 Broadgate are at an equal standard with increased life, efficiency and protection against waterborne pathogens. 4.3 Cooling towers 31 4.0PHASE3 31
  • 33. CONCLUSION 33 Under the management of Broadgate Estates, the refurbishment program of 1-2 Broadgate was delivered before the scheduled completion date, significantly under budget and without the occurrence of any safety incidents. Though careful planning, coordination and a highly client focussed approach, Broadgate Estates ensured all building services to occupiers were maintained throughout the program, without any compromise on standards and resilience. 5.0 Conclusion