SlideShare a Scribd company logo
Desain
Perkerasan
Jalan
Pilang Maharani Pramono
I0118116
Data Rencana Perkerasan Jalan
▰ Lokasi Trace Jalan
▰ Geometri Jalan Raya
▰ Tanah Dasar CBR
▰ Iklim
▰ Rencana LHR
2
Geometri Jalan
Lokasi Jalan : Cawas, Klaten
Fungsi Jalan : Kolektor
Kelas Jalan : III A
Jalan : 2 Lajur 2 Arah
CBR : 7%
Kecepatan Rencana (Vr) : 60-80 km/jam
Medan Jalan : Datar
Curah Hujan Rata-Rata : 1900-2500
mm/tahun
Zona Iklim :III (tropis,
lembab dengan musim hujan sedang)
3
Jalan yang direncanakan
berlokasi di Cawas dan
menghubungkan Desa
Candi dengan Desa
Nologaten
4
Peta Lokasi
Data Lintas Harian Rata-Rata
(LHR)
5
JENIS KENDARAAN LHR
5B 44
6B 95
7A1 8
7A2 27
1. Desain Perkerasan Lentur
Menentukan Umur Rencana
7
Berdasar Tabel 2.1
Umur Rencana
Perkerasan Jalan
Baru (UR),
diperoleh umur
rencana untuk
lapisan aspal dan
lapisan berbutir
adalah 20 tahun
Menghitung Faktor Pertumbuhan Kumulatif
8
𝑹 =
𝟏 + 𝟎, 𝟎𝟏𝒊 𝑼𝑹 − 𝟏
𝟎, 𝟎𝟏𝒊
Diketahui :
UR = 20 tahun
i = 3,50 %
R21-41 = 28,2797
R21-61 = 84,5503
Faktor Distribusi
9
Faktor Distribusi Arah (DD) Faktor Distribusi Lajur (DL)
Untuk jalan 2 arah,
faktor distribusi arah
(DD) umumnya diambil
0,50 kecuali pada
lokasi-lokasi yang
jumlah kendaraan niaga
cenderung lebih tinggi
pada satu arah tertentu
Menentukan VDF5
10
Berdasar Tabel 4.4,
Nilai VDF digunakan
dengan kriteria jenis
kendaraan Jawa
Normal VDF 5,
karena dengan
mempertimbangkan
pernyataan
pemerintah bahwa
mulai tahun 2020
tidak terdapat
kendaraan Overload
Menghitung Nilai ESA5
11
Jenis
Kendaraan
LHR (2 arah)
2021
VDF5
Normal
ESA5
(‘21-’41)
(1) (2) (3) (4)
5B 44 1 227085,845
6B 95 5,2 2500524,816
7A1 8 6,4 264245,3469
7A2 27 5,6 780349,54
Jumlah ESA5 3772205,547
CESA5 (‘21-’41) 3.772.205,547
Cara perhitungan ESA5
(‘21-’41)
ESA5 (‘21-’41) = 𝑳𝑯𝑹 × 𝑽𝑫𝑭 × 𝟑𝟔𝟓 × 𝑫𝑫 × 𝑫𝑳 × 𝑹
ESA5 (‘21-’41) = (2) × 𝟑 × 𝟑𝟔𝟓 × 𝟎, 𝟓𝟎 × 𝟏 ×
𝑹(𝟐𝟏 − 𝟒𝟏)
ESA5 (‘21-’41) = 3.772.205,547
* Sesuai hasil hitungan di Ms. Excel
Menentukan Jenis Perkerasan
12
Karena nilai
ESA5 sebesar
3.772.205,547,
maka dipilih
jenis perkerasan
lapis fondasi
soil cement
Menentukan Segmen Tanah Dasar
13
Dengan nilai CBR sebesar 7%, maka tidak diperlukan perbaikan
tanah
Lapis Perkerasan Lentur
14
Karena nilai ESA5
3.772.205,547 atau
> 0,5 – 4 juta ESA5,
maka dipilih desain
perkerasan lentur
dengan ketebalan
seperti yang tertera
di tabel
Lapis Perkerasan Lentur
15
Dengan
menggunakan
desain perkerasan
lentur dengan
ketebalan seperti
di tabel bagan
desain 6,
diperoleh lapis
perkerasan seperti
pada gambar di
samping
50 mm
300 mm
200 mm
260 mm Tanah Distabilisasi
LFA Kelas A
LFA Kelas A
AC WC
Menentukan Drainase
16
Nilai m untuk desain drainase perkerasan = 1,0
Menentukan Kebutuhan Daya Dukung Tepi
Perkerasan
17
Ketentuan
minimal daya
dukung tepi
perkerasan
sesuai seperti
gambar
disamping
Menentukan Kebutuhan Pelapisan (Sealing)
Bahu Jalan
18
• CBR tanah dasar : 7%
• Beban gandar kumulatif 20 tahun : 3 jt
ESA
• Beban rencana bahu jalan
= 10% x 3 jt ESA
= 300.000 ESA
• Struktur perkerasan lajur utama :
Lapisan Tebal (mm)
AC WC 50
LFA A 300
LFA A 200
Tanah distabilisasi 260
Kebutuhan Pelapisan (Sealing) Bahu Jalan
19
Jika dilihat dari grafik, dengan nilai CBR 7% dan beban
rencana bahu jalan 300.000 ESA, maka diperlukan
penutup sebesar 240 mm.
Tebal total perkerasan lajur utama : 810 mm > 240 mm
(tebal minimal perlu perkerasan bahu jalan)
Kebutuhan Pelapisan (Sealing) Bahu Jalan
20
Lapisan Tebal (mm)
LFA Kelas S 50
LFA Kelas A 760
Fondasi
(perbaikan tanah
dasar)
-
LFA Kelas S
LFA Kelas A
Fondasi
2. Desain Perkerasan Kaku
21
Menentukan Umur Rencana
22
Berdasar Tabel 2.1
Umur Rencana
Perkerasan Jalan
Baru (UR),
diperoleh umur
rencana untuk
lapisan aspal dan
lapisan berbutir
adalah 40 tahun
Menghitung Faktor Pertumbuhan Kumulatif
23
𝑹 =
𝟏 + 𝟎, 𝟎𝟏𝒊 𝑼𝑹 − 𝟏
𝟎, 𝟎𝟏𝒊
Diketahui :
UR = 40 tahun
i = 3,50 %
R21-41 = 28,2797
R21-61 = 84,5503
Nilai Distribusi
24
Nilai Distribusi Arah (DD)
Untuk jalan 2 arah,
faktor distribusi arah
(DD) umumnya diambil
0,50 kecuali pada
lokasi-lokasi yang
jumlah kendaraan niaga
cenderung lebih tinggi
pada satu arah tertentu
Menghitung Nilai ESA5
25
Jenis
Kendaraan
LHR (2 arah)
2021
VDF5
Normal
ESA5
(‘21-’41)
(1) (2) (3) (4)
5B 44 1 678938,7303
6B 95 5,2 7476041,246
7A1 8 6,4 290037,7953
7A2 27 5,6 2333080,364
Jumlah ESA5 11278098,14
CESA5 (‘21-’61) 11.278.098,14
Cara perhitungan ESA5
(‘21-’61)
ESA5 (‘21-’61) = 𝑳𝑯𝑹 × 𝑽𝑫𝑭 × 𝟑𝟔𝟓 × 𝑫𝑫 × 𝑫𝑳 × 𝑹
ESA5 (‘21-’61) = (2) × 𝟑 × 𝟑𝟔𝟓 × 𝟎, 𝟓𝟎 × 𝟏 ×
𝑹(𝟐𝟏 − 𝟔𝟏)
ESA5 (‘21-’61) = 11.278.098,14*
* Sesuai hasil hitungan di Ms. Excel
Menentukan Segmen Tanah Dasar
26
Dengan nilai CBR sebesar 7 %, maka tidak diperlukan perbaikan
tanah
Menentukan Daya Dukung Efektif Tanah Dasar
27
▰ Nilai CBR tanah dasar = 7% Solusi tanah dasar
▰ Tanah dasar normal secara umum mempunyai nilai
CBR > 2,5%
Menentukan Jenis Perkerasan
28
Karena nilai
ESA5 sebesar
11.278.098,14,
maka dipilih
jenis perkerasan
kaku dengan
lalu lintas berat
Lapis Perkerasan Kaku
29
Karena nilai
kelompok sumbu
kendaraan berat
sebesar 11,23 juta
atau < 25,8 juta,
maka dipilih desain
perkerasan kaku tipe
R3
Lapis Perkerasan Kaku
30
Dengan
menggunakan
desain
perkerasan kaku
diperoleh lapis
perkerasan
seperti gambar di
samping
285 mm
100 mm
150 mm
Perkerasan Beton
Lapis Fondasi Beton Kurus LMC
Lapis Drainase Agregat
Kelas A
300 mm Stabilisasi
Tanah
Dasar
Menentukan Bahu Jalan
31
▰ Menurut Bagan Desain 4 Perkerasan Kaku
untuk Jalan dengan Beban Lalu Lintas Berat
halaman 7-16, digunakan sambungan
dowel dan bahu beton
▰ Pada lampiran F-1, tebal bahu jalan diambil
500 mm
Menentukan Detail Desain
32
▰ Menentukan Tebal Pelat Beton Semen
▰ Umur rencana = 40 tahun
▰ CBR tanah dasar = 7%
▰ CBR tanah dasar efektif = 50% (Gambar 3)
▰ Kuat Tarik lentur = 4 Mpa
▰ Bahan pondasi bawah = Stabilitas
▰ Mutu baja tulangan = BJTU-39
▰ Koef. Gesek pada beton dengan pondasi = 1,3
▰ Bahu jalan = Beton
▰ Tie Bar = Baja ulir D16 mm BJTU-24
▰ Ruji = Ya (dowel), digunakan d = 36 mm
▰ Tebal pelat beton = 285 mm
▰ Lebar pelat = 2 x 3,5 m
▰ Panjang pelat = 6 m
Menentukan Daya Dukung Tepi Perkerasan
33
• Nilai CBR : 7%
• Maka ditentukan
tepi perkerasan
menggunakan
kemiringan 1V : 3H
Kesimpulan
34
▰ Perkerasan Lentur ▰ Perkerasan Kaku
50 mm
300 mm
200 mm
260 mm Tanah Distabilisasi
LFA Kelas A
LFA Kelas A
AC WC 285 mm
100 mm
150 mm
Perkerasan Beton
Lapis Fondasi Beton
Kurus LMC
Lapis Drainase
Agregat Kelas A
300 mm
Stabilisasi
Tanah
Dasar
Pelaksana : Kontraktor kecil – medium
Tebal Perkerasan : 810 mm
Tidak diperlukan perbaikan tanah dasar karena CBR = 7%
Pelaksana : Kontraktor besar dengan sumber daya yang memadai
Tebal Perkerasan : 535 mm
Beton bersambung tanpa tulangan (Tipe R3)
Lokasi : Cawas, Klaten
Fungsi Jalan : Kolektor
Kelas Jalan : III A
CBR : 7%
ESA5 (‘21-’41) = 3.772.205,547
ESA5 (‘21-’61) = 11.278.098,14
“
”
35
Dari hasil pendesainan perkerasan, jalan yang saya pilih adalah
jalan perkerasan lentur karena meninjau dari beban jalan yang
tidak terlalu berat seperti beban jalan pada perkerasan kaku. Jika
ada kerusakan kecil pada perkerasan lentur, mudah dilakukan
dalam perbaikannya. Untuk perkerasan lentur berwarna gelap
sehingga lebih nyaman untuk mata karena tidak menyilaukan.
Biaya konstruksi juga lebih murah dibandingkan perkerasan kaku.
Sehingga pekerjaan dilakukan oleh kontraktor kecil-medium.
Komentar dalam menggunakan panduan:
36
❑ Cukup mudah dipahami dalam menggunakan Manual Desain Perkerasan Jalan. Langkah-langkah
pengerjaan yang dijelaskan dalam Manual Desain Perkerasan Jalan sudah jelas, tapi dalam
penulisan Langkah-langkahnya belum tersusun secara urut dan terperinci. Menurut saya, Manual
Desain Perkerasan Jalan belum terlalu lengkap pada desain perkerasan kaku. Indonesia
menggunakan Manual Desain untuk memenuhi standar pemerataan konstruksi jalan di Indonesia
karena sulitnya mendapatkan data pendukung untuk desain perkerasan jalan karena kurang
terdokumentasikan dengan baik, maka didapatkan data yang tidak valid. Manual Desain
Perkerasan Jalan digunakan sebagai acuan dengan mengupgrade metode empiris menjadi metode
mekanistik sesuai dengan tipikal di Indonesia walaupun belum tentu sama pada setiap kondisi
atau tempat di seluruh Indonesia.
❑ Untuk penggunaan Pd T-14-2003 masih cukup bingung di bagian menentukan detail desain
perkerasan kaku dan membaca beberapa grafik. Pd T-14-2003 isinya lebih lengkap daripada
Manual Desain Perkerasan Jalan. Ada juga beberapa contoh perhitungan yang rinci dalam
menentukan desain perkerasan kaku yang masih cukup sulit dipahami karena jarang dibahas.
Agar dapat lebih memahami lagi, harus dipelajari lebih dalam lagi.
“
”
TERIMA KASIH
37

More Related Content

What's hot

Pd t 14-2003 - perencanaan perkerasan jalan beton semen
Pd t 14-2003 - perencanaan perkerasan jalan beton semenPd t 14-2003 - perencanaan perkerasan jalan beton semen
Pd t 14-2003 - perencanaan perkerasan jalan beton semen
Syukri Ghazali
 
Perhitungan Kapasitas Tampungan Waduk
Perhitungan Kapasitas Tampungan WadukPerhitungan Kapasitas Tampungan Waduk
Perhitungan Kapasitas Tampungan Waduk
21010115410004
 
Grafik nomogram
Grafik nomogramGrafik nomogram
87280501 perencanaan-sistem-drainase
87280501 perencanaan-sistem-drainase87280501 perencanaan-sistem-drainase
87280501 perencanaan-sistem-drainase
Miftakhul Yaqin
 
perhitungan jembatan
perhitungan jembatanperhitungan jembatan
perhitungan jembatanFarid Thahura
 
Sni 1725 2016 pembebanan untuk jembatan
Sni 1725 2016 pembebanan untuk jembatanSni 1725 2016 pembebanan untuk jembatan
Sni 1725 2016 pembebanan untuk jembatan
terbott
 
4. bagian bagian struktur konstruksi jembatan
4. bagian bagian struktur konstruksi jembatan4. bagian bagian struktur konstruksi jembatan
4. bagian bagian struktur konstruksi jembatan
Agus Tri
 
penulangan kolom, balok dan plat bangunan gedung
penulangan kolom, balok dan plat bangunan gedungpenulangan kolom, balok dan plat bangunan gedung
penulangan kolom, balok dan plat bangunan gedung
Agus Fitriyanto
 
AHS pekerjaan beton SNI 7394-2008
AHS pekerjaan beton SNI 7394-2008AHS pekerjaan beton SNI 7394-2008
AHS pekerjaan beton SNI 7394-2008
Vanny Wayongkere
 
Tabel baja-wf-lrfd
Tabel baja-wf-lrfdTabel baja-wf-lrfd
Tabel baja-wf-lrfd
Gunawan Sulistyo
 
Sni 2827 2008
Sni 2827 2008Sni 2827 2008
Sni 2827 2008
akkuanblog
 
Manual desain-perkerasan-jalan-2017
Manual desain-perkerasan-jalan-2017Manual desain-perkerasan-jalan-2017
Manual desain-perkerasan-jalan-2017
NUR SETIAJI
 
Kuliah minggu ke 9 struktur jembatan,06 nopb2012
Kuliah minggu ke 9 struktur jembatan,06 nopb2012Kuliah minggu ke 9 struktur jembatan,06 nopb2012
Kuliah minggu ke 9 struktur jembatan,06 nopb2012
فهرودين سفي
 
Mekanika tanah jilid 1 * braja m das *
Mekanika tanah jilid 1 * braja m das *Mekanika tanah jilid 1 * braja m das *
Mekanika tanah jilid 1 * braja m das *
speaklouder77
 
Bab 1 sondir
Bab 1 sondirBab 1 sondir
Bab 1 sondir
antonius giovanni
 
Tiang Pancang I
Tiang Pancang ITiang Pancang I
Tiang Pancang I
Nurul Angreliany
 
Studi Kasus Desain Perkerasan Jalan
Studi Kasus Desain Perkerasan JalanStudi Kasus Desain Perkerasan Jalan
Studi Kasus Desain Perkerasan Jalan
OryFebriayani
 
Sni 3407 2008 Cara uji sifat kekekalan agregat dengan cara perendaman menggun...
Sni 3407 2008 Cara uji sifat kekekalan agregat dengan cara perendaman menggun...Sni 3407 2008 Cara uji sifat kekekalan agregat dengan cara perendaman menggun...
Sni 3407 2008 Cara uji sifat kekekalan agregat dengan cara perendaman menggun...
Mira Pemayun
 
Spesifikasi penguatan tebing
Spesifikasi penguatan tebingSpesifikasi penguatan tebing
Spesifikasi penguatan tebingKetut Swandana
 

What's hot (20)

Pd t 14-2003 - perencanaan perkerasan jalan beton semen
Pd t 14-2003 - perencanaan perkerasan jalan beton semenPd t 14-2003 - perencanaan perkerasan jalan beton semen
Pd t 14-2003 - perencanaan perkerasan jalan beton semen
 
Perhitungan Kapasitas Tampungan Waduk
Perhitungan Kapasitas Tampungan WadukPerhitungan Kapasitas Tampungan Waduk
Perhitungan Kapasitas Tampungan Waduk
 
Grafik nomogram
Grafik nomogramGrafik nomogram
Grafik nomogram
 
87280501 perencanaan-sistem-drainase
87280501 perencanaan-sistem-drainase87280501 perencanaan-sistem-drainase
87280501 perencanaan-sistem-drainase
 
perhitungan jembatan
perhitungan jembatanperhitungan jembatan
perhitungan jembatan
 
Sni 1725 2016 pembebanan untuk jembatan
Sni 1725 2016 pembebanan untuk jembatanSni 1725 2016 pembebanan untuk jembatan
Sni 1725 2016 pembebanan untuk jembatan
 
4. bagian bagian struktur konstruksi jembatan
4. bagian bagian struktur konstruksi jembatan4. bagian bagian struktur konstruksi jembatan
4. bagian bagian struktur konstruksi jembatan
 
penulangan kolom, balok dan plat bangunan gedung
penulangan kolom, balok dan plat bangunan gedungpenulangan kolom, balok dan plat bangunan gedung
penulangan kolom, balok dan plat bangunan gedung
 
AHS pekerjaan beton SNI 7394-2008
AHS pekerjaan beton SNI 7394-2008AHS pekerjaan beton SNI 7394-2008
AHS pekerjaan beton SNI 7394-2008
 
Trial compaction (dahlia)
Trial compaction (dahlia)Trial compaction (dahlia)
Trial compaction (dahlia)
 
Tabel baja-wf-lrfd
Tabel baja-wf-lrfdTabel baja-wf-lrfd
Tabel baja-wf-lrfd
 
Sni 2827 2008
Sni 2827 2008Sni 2827 2008
Sni 2827 2008
 
Manual desain-perkerasan-jalan-2017
Manual desain-perkerasan-jalan-2017Manual desain-perkerasan-jalan-2017
Manual desain-perkerasan-jalan-2017
 
Kuliah minggu ke 9 struktur jembatan,06 nopb2012
Kuliah minggu ke 9 struktur jembatan,06 nopb2012Kuliah minggu ke 9 struktur jembatan,06 nopb2012
Kuliah minggu ke 9 struktur jembatan,06 nopb2012
 
Mekanika tanah jilid 1 * braja m das *
Mekanika tanah jilid 1 * braja m das *Mekanika tanah jilid 1 * braja m das *
Mekanika tanah jilid 1 * braja m das *
 
Bab 1 sondir
Bab 1 sondirBab 1 sondir
Bab 1 sondir
 
Tiang Pancang I
Tiang Pancang ITiang Pancang I
Tiang Pancang I
 
Studi Kasus Desain Perkerasan Jalan
Studi Kasus Desain Perkerasan JalanStudi Kasus Desain Perkerasan Jalan
Studi Kasus Desain Perkerasan Jalan
 
Sni 3407 2008 Cara uji sifat kekekalan agregat dengan cara perendaman menggun...
Sni 3407 2008 Cara uji sifat kekekalan agregat dengan cara perendaman menggun...Sni 3407 2008 Cara uji sifat kekekalan agregat dengan cara perendaman menggun...
Sni 3407 2008 Cara uji sifat kekekalan agregat dengan cara perendaman menggun...
 
Spesifikasi penguatan tebing
Spesifikasi penguatan tebingSpesifikasi penguatan tebing
Spesifikasi penguatan tebing
 

Similar to Studi Kasus Desain Perkerasan Jalan

Ppt rcc road design
Ppt rcc road designPpt rcc road design
Ppt rcc road design
Anjani Shukla
 
Analysis of Flexible Pavement Using IIT PAVE software
Analysis of Flexible Pavement Using IIT PAVE softwareAnalysis of Flexible Pavement Using IIT PAVE software
Analysis of Flexible Pavement Using IIT PAVE software
UnknownUser704294
 
Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)
Malyar Talash
 
ANALYSIS AND COMPARATIVE STUDY OF COMPOSITE BRIDGE GIRDERS
ANALYSIS AND COMPARATIVE STUDY OF COMPOSITE BRIDGE GIRDERSANALYSIS AND COMPARATIVE STUDY OF COMPOSITE BRIDGE GIRDERS
ANALYSIS AND COMPARATIVE STUDY OF COMPOSITE BRIDGE GIRDERS
IAEME Publication
 
Design Considerations for AASHTO Flexible pavement design
Design Considerations for AASHTO Flexible pavement designDesign Considerations for AASHTO Flexible pavement design
Design Considerations for AASHTO Flexible pavement design
Imran Nawaz
 
20.02 memoria-de-calculo-estructural-del-puente
20.02 memoria-de-calculo-estructural-del-puente20.02 memoria-de-calculo-estructural-del-puente
20.02 memoria-de-calculo-estructural-del-puente
Berny Lazarte Obregón
 
IRJET- Design and Comparision of Flexible and Rigid Pavements
IRJET-  	  Design and Comparision of Flexible and Rigid PavementsIRJET-  	  Design and Comparision of Flexible and Rigid Pavements
IRJET- Design and Comparision of Flexible and Rigid Pavements
IRJET Journal
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking ppt
Patel Tapan
 
Six week industrial training presentation BY GUPTA TARUN
Six week industrial training presentation BY GUPTA TARUNSix week industrial training presentation BY GUPTA TARUN
Six week industrial training presentation BY GUPTA TARUN
Tarun2222
 
Final year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement DesignFinal year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement Design
Riaz Zalil
 
Improving of Asphalt Pavement Performance using Steel wire Grid Reinforcement
Improving of Asphalt Pavement Performance using Steel wire Grid ReinforcementImproving of Asphalt Pavement Performance using Steel wire Grid Reinforcement
Improving of Asphalt Pavement Performance using Steel wire Grid Reinforcement
International Journal of Engineering Inventions www.ijeijournal.com
 
J012537580
J012537580J012537580
J012537580
IOSR Journals
 
Direct-Design-Method1.pdf
Direct-Design-Method1.pdfDirect-Design-Method1.pdf
Direct-Design-Method1.pdf
Wifin1
 
8th Semester (July-2016) Civil Engineering Question Paper
8th Semester (July-2016) Civil Engineering Question Paper8th Semester (July-2016) Civil Engineering Question Paper
8th Semester (July-2016) Civil Engineering Question Paper
BGS Institute of Technology, Adichunchanagiri University (ACU)
 
Road-design-standards-for-LGED.pptx
Road-design-standards-for-LGED.pptxRoad-design-standards-for-LGED.pptx
Road-design-standards-for-LGED.pptx
RagibShuvo1
 
Roadstab 2017
Roadstab 2017Roadstab 2017
8th Semester (June; July-2015) Civil Engineering Question Paper
8th Semester (June; July-2015) Civil Engineering Question Paper8th Semester (June; July-2015) Civil Engineering Question Paper
8th Semester (June; July-2015) Civil Engineering Question Paper
BGS Institute of Technology, Adichunchanagiri University (ACU)
 
PPT Estimate.pptx
PPT Estimate.pptxPPT Estimate.pptx
PPT Estimate.pptx
SantoshKapse9
 

Similar to Studi Kasus Desain Perkerasan Jalan (20)

Ppt rcc road design
Ppt rcc road designPpt rcc road design
Ppt rcc road design
 
Project 2b (1) (2)
Project 2b  (1) (2)Project 2b  (1) (2)
Project 2b (1) (2)
 
Analysis of Flexible Pavement Using IIT PAVE software
Analysis of Flexible Pavement Using IIT PAVE softwareAnalysis of Flexible Pavement Using IIT PAVE software
Analysis of Flexible Pavement Using IIT PAVE software
 
Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)
 
ANALYSIS AND COMPARATIVE STUDY OF COMPOSITE BRIDGE GIRDERS
ANALYSIS AND COMPARATIVE STUDY OF COMPOSITE BRIDGE GIRDERSANALYSIS AND COMPARATIVE STUDY OF COMPOSITE BRIDGE GIRDERS
ANALYSIS AND COMPARATIVE STUDY OF COMPOSITE BRIDGE GIRDERS
 
Design Considerations for AASHTO Flexible pavement design
Design Considerations for AASHTO Flexible pavement designDesign Considerations for AASHTO Flexible pavement design
Design Considerations for AASHTO Flexible pavement design
 
20.02 memoria-de-calculo-estructural-del-puente
20.02 memoria-de-calculo-estructural-del-puente20.02 memoria-de-calculo-estructural-del-puente
20.02 memoria-de-calculo-estructural-del-puente
 
IRJET- Design and Comparision of Flexible and Rigid Pavements
IRJET-  	  Design and Comparision of Flexible and Rigid PavementsIRJET-  	  Design and Comparision of Flexible and Rigid Pavements
IRJET- Design and Comparision of Flexible and Rigid Pavements
 
Pavement eng re
Pavement eng rePavement eng re
Pavement eng re
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking ppt
 
Six week industrial training presentation BY GUPTA TARUN
Six week industrial training presentation BY GUPTA TARUNSix week industrial training presentation BY GUPTA TARUN
Six week industrial training presentation BY GUPTA TARUN
 
Final year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement DesignFinal year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement Design
 
Improving of Asphalt Pavement Performance using Steel wire Grid Reinforcement
Improving of Asphalt Pavement Performance using Steel wire Grid ReinforcementImproving of Asphalt Pavement Performance using Steel wire Grid Reinforcement
Improving of Asphalt Pavement Performance using Steel wire Grid Reinforcement
 
J012537580
J012537580J012537580
J012537580
 
Direct-Design-Method1.pdf
Direct-Design-Method1.pdfDirect-Design-Method1.pdf
Direct-Design-Method1.pdf
 
8th Semester (July-2016) Civil Engineering Question Paper
8th Semester (July-2016) Civil Engineering Question Paper8th Semester (July-2016) Civil Engineering Question Paper
8th Semester (July-2016) Civil Engineering Question Paper
 
Road-design-standards-for-LGED.pptx
Road-design-standards-for-LGED.pptxRoad-design-standards-for-LGED.pptx
Road-design-standards-for-LGED.pptx
 
Roadstab 2017
Roadstab 2017Roadstab 2017
Roadstab 2017
 
8th Semester (June; July-2015) Civil Engineering Question Paper
8th Semester (June; July-2015) Civil Engineering Question Paper8th Semester (June; July-2015) Civil Engineering Question Paper
8th Semester (June; July-2015) Civil Engineering Question Paper
 
PPT Estimate.pptx
PPT Estimate.pptxPPT Estimate.pptx
PPT Estimate.pptx
 

Recently uploaded

Ethernet Routing and switching chapter 1.ppt
Ethernet Routing and switching chapter 1.pptEthernet Routing and switching chapter 1.ppt
Ethernet Routing and switching chapter 1.ppt
azkamurat
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
dxobcob
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
zwunae
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
obonagu
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
bhadouriyakaku
 

Recently uploaded (20)

Ethernet Routing and switching chapter 1.ppt
Ethernet Routing and switching chapter 1.pptEthernet Routing and switching chapter 1.ppt
Ethernet Routing and switching chapter 1.ppt
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
 

Studi Kasus Desain Perkerasan Jalan

  • 2. Data Rencana Perkerasan Jalan ▰ Lokasi Trace Jalan ▰ Geometri Jalan Raya ▰ Tanah Dasar CBR ▰ Iklim ▰ Rencana LHR 2
  • 3. Geometri Jalan Lokasi Jalan : Cawas, Klaten Fungsi Jalan : Kolektor Kelas Jalan : III A Jalan : 2 Lajur 2 Arah CBR : 7% Kecepatan Rencana (Vr) : 60-80 km/jam Medan Jalan : Datar Curah Hujan Rata-Rata : 1900-2500 mm/tahun Zona Iklim :III (tropis, lembab dengan musim hujan sedang) 3
  • 4. Jalan yang direncanakan berlokasi di Cawas dan menghubungkan Desa Candi dengan Desa Nologaten 4 Peta Lokasi
  • 5. Data Lintas Harian Rata-Rata (LHR) 5 JENIS KENDARAAN LHR 5B 44 6B 95 7A1 8 7A2 27
  • 7. Menentukan Umur Rencana 7 Berdasar Tabel 2.1 Umur Rencana Perkerasan Jalan Baru (UR), diperoleh umur rencana untuk lapisan aspal dan lapisan berbutir adalah 20 tahun
  • 8. Menghitung Faktor Pertumbuhan Kumulatif 8 𝑹 = 𝟏 + 𝟎, 𝟎𝟏𝒊 𝑼𝑹 − 𝟏 𝟎, 𝟎𝟏𝒊 Diketahui : UR = 20 tahun i = 3,50 % R21-41 = 28,2797 R21-61 = 84,5503
  • 9. Faktor Distribusi 9 Faktor Distribusi Arah (DD) Faktor Distribusi Lajur (DL) Untuk jalan 2 arah, faktor distribusi arah (DD) umumnya diambil 0,50 kecuali pada lokasi-lokasi yang jumlah kendaraan niaga cenderung lebih tinggi pada satu arah tertentu
  • 10. Menentukan VDF5 10 Berdasar Tabel 4.4, Nilai VDF digunakan dengan kriteria jenis kendaraan Jawa Normal VDF 5, karena dengan mempertimbangkan pernyataan pemerintah bahwa mulai tahun 2020 tidak terdapat kendaraan Overload
  • 11. Menghitung Nilai ESA5 11 Jenis Kendaraan LHR (2 arah) 2021 VDF5 Normal ESA5 (‘21-’41) (1) (2) (3) (4) 5B 44 1 227085,845 6B 95 5,2 2500524,816 7A1 8 6,4 264245,3469 7A2 27 5,6 780349,54 Jumlah ESA5 3772205,547 CESA5 (‘21-’41) 3.772.205,547 Cara perhitungan ESA5 (‘21-’41) ESA5 (‘21-’41) = 𝑳𝑯𝑹 × 𝑽𝑫𝑭 × 𝟑𝟔𝟓 × 𝑫𝑫 × 𝑫𝑳 × 𝑹 ESA5 (‘21-’41) = (2) × 𝟑 × 𝟑𝟔𝟓 × 𝟎, 𝟓𝟎 × 𝟏 × 𝑹(𝟐𝟏 − 𝟒𝟏) ESA5 (‘21-’41) = 3.772.205,547 * Sesuai hasil hitungan di Ms. Excel
  • 12. Menentukan Jenis Perkerasan 12 Karena nilai ESA5 sebesar 3.772.205,547, maka dipilih jenis perkerasan lapis fondasi soil cement
  • 13. Menentukan Segmen Tanah Dasar 13 Dengan nilai CBR sebesar 7%, maka tidak diperlukan perbaikan tanah
  • 14. Lapis Perkerasan Lentur 14 Karena nilai ESA5 3.772.205,547 atau > 0,5 – 4 juta ESA5, maka dipilih desain perkerasan lentur dengan ketebalan seperti yang tertera di tabel
  • 15. Lapis Perkerasan Lentur 15 Dengan menggunakan desain perkerasan lentur dengan ketebalan seperti di tabel bagan desain 6, diperoleh lapis perkerasan seperti pada gambar di samping 50 mm 300 mm 200 mm 260 mm Tanah Distabilisasi LFA Kelas A LFA Kelas A AC WC
  • 16. Menentukan Drainase 16 Nilai m untuk desain drainase perkerasan = 1,0
  • 17. Menentukan Kebutuhan Daya Dukung Tepi Perkerasan 17 Ketentuan minimal daya dukung tepi perkerasan sesuai seperti gambar disamping
  • 18. Menentukan Kebutuhan Pelapisan (Sealing) Bahu Jalan 18 • CBR tanah dasar : 7% • Beban gandar kumulatif 20 tahun : 3 jt ESA • Beban rencana bahu jalan = 10% x 3 jt ESA = 300.000 ESA • Struktur perkerasan lajur utama : Lapisan Tebal (mm) AC WC 50 LFA A 300 LFA A 200 Tanah distabilisasi 260
  • 19. Kebutuhan Pelapisan (Sealing) Bahu Jalan 19 Jika dilihat dari grafik, dengan nilai CBR 7% dan beban rencana bahu jalan 300.000 ESA, maka diperlukan penutup sebesar 240 mm. Tebal total perkerasan lajur utama : 810 mm > 240 mm (tebal minimal perlu perkerasan bahu jalan)
  • 20. Kebutuhan Pelapisan (Sealing) Bahu Jalan 20 Lapisan Tebal (mm) LFA Kelas S 50 LFA Kelas A 760 Fondasi (perbaikan tanah dasar) - LFA Kelas S LFA Kelas A Fondasi
  • 22. Menentukan Umur Rencana 22 Berdasar Tabel 2.1 Umur Rencana Perkerasan Jalan Baru (UR), diperoleh umur rencana untuk lapisan aspal dan lapisan berbutir adalah 40 tahun
  • 23. Menghitung Faktor Pertumbuhan Kumulatif 23 𝑹 = 𝟏 + 𝟎, 𝟎𝟏𝒊 𝑼𝑹 − 𝟏 𝟎, 𝟎𝟏𝒊 Diketahui : UR = 40 tahun i = 3,50 % R21-41 = 28,2797 R21-61 = 84,5503
  • 24. Nilai Distribusi 24 Nilai Distribusi Arah (DD) Untuk jalan 2 arah, faktor distribusi arah (DD) umumnya diambil 0,50 kecuali pada lokasi-lokasi yang jumlah kendaraan niaga cenderung lebih tinggi pada satu arah tertentu
  • 25. Menghitung Nilai ESA5 25 Jenis Kendaraan LHR (2 arah) 2021 VDF5 Normal ESA5 (‘21-’41) (1) (2) (3) (4) 5B 44 1 678938,7303 6B 95 5,2 7476041,246 7A1 8 6,4 290037,7953 7A2 27 5,6 2333080,364 Jumlah ESA5 11278098,14 CESA5 (‘21-’61) 11.278.098,14 Cara perhitungan ESA5 (‘21-’61) ESA5 (‘21-’61) = 𝑳𝑯𝑹 × 𝑽𝑫𝑭 × 𝟑𝟔𝟓 × 𝑫𝑫 × 𝑫𝑳 × 𝑹 ESA5 (‘21-’61) = (2) × 𝟑 × 𝟑𝟔𝟓 × 𝟎, 𝟓𝟎 × 𝟏 × 𝑹(𝟐𝟏 − 𝟔𝟏) ESA5 (‘21-’61) = 11.278.098,14* * Sesuai hasil hitungan di Ms. Excel
  • 26. Menentukan Segmen Tanah Dasar 26 Dengan nilai CBR sebesar 7 %, maka tidak diperlukan perbaikan tanah
  • 27. Menentukan Daya Dukung Efektif Tanah Dasar 27 ▰ Nilai CBR tanah dasar = 7% Solusi tanah dasar ▰ Tanah dasar normal secara umum mempunyai nilai CBR > 2,5%
  • 28. Menentukan Jenis Perkerasan 28 Karena nilai ESA5 sebesar 11.278.098,14, maka dipilih jenis perkerasan kaku dengan lalu lintas berat
  • 29. Lapis Perkerasan Kaku 29 Karena nilai kelompok sumbu kendaraan berat sebesar 11,23 juta atau < 25,8 juta, maka dipilih desain perkerasan kaku tipe R3
  • 30. Lapis Perkerasan Kaku 30 Dengan menggunakan desain perkerasan kaku diperoleh lapis perkerasan seperti gambar di samping 285 mm 100 mm 150 mm Perkerasan Beton Lapis Fondasi Beton Kurus LMC Lapis Drainase Agregat Kelas A 300 mm Stabilisasi Tanah Dasar
  • 31. Menentukan Bahu Jalan 31 ▰ Menurut Bagan Desain 4 Perkerasan Kaku untuk Jalan dengan Beban Lalu Lintas Berat halaman 7-16, digunakan sambungan dowel dan bahu beton ▰ Pada lampiran F-1, tebal bahu jalan diambil 500 mm
  • 32. Menentukan Detail Desain 32 ▰ Menentukan Tebal Pelat Beton Semen ▰ Umur rencana = 40 tahun ▰ CBR tanah dasar = 7% ▰ CBR tanah dasar efektif = 50% (Gambar 3) ▰ Kuat Tarik lentur = 4 Mpa ▰ Bahan pondasi bawah = Stabilitas ▰ Mutu baja tulangan = BJTU-39 ▰ Koef. Gesek pada beton dengan pondasi = 1,3 ▰ Bahu jalan = Beton ▰ Tie Bar = Baja ulir D16 mm BJTU-24 ▰ Ruji = Ya (dowel), digunakan d = 36 mm ▰ Tebal pelat beton = 285 mm ▰ Lebar pelat = 2 x 3,5 m ▰ Panjang pelat = 6 m
  • 33. Menentukan Daya Dukung Tepi Perkerasan 33 • Nilai CBR : 7% • Maka ditentukan tepi perkerasan menggunakan kemiringan 1V : 3H
  • 34. Kesimpulan 34 ▰ Perkerasan Lentur ▰ Perkerasan Kaku 50 mm 300 mm 200 mm 260 mm Tanah Distabilisasi LFA Kelas A LFA Kelas A AC WC 285 mm 100 mm 150 mm Perkerasan Beton Lapis Fondasi Beton Kurus LMC Lapis Drainase Agregat Kelas A 300 mm Stabilisasi Tanah Dasar Pelaksana : Kontraktor kecil – medium Tebal Perkerasan : 810 mm Tidak diperlukan perbaikan tanah dasar karena CBR = 7% Pelaksana : Kontraktor besar dengan sumber daya yang memadai Tebal Perkerasan : 535 mm Beton bersambung tanpa tulangan (Tipe R3) Lokasi : Cawas, Klaten Fungsi Jalan : Kolektor Kelas Jalan : III A CBR : 7% ESA5 (‘21-’41) = 3.772.205,547 ESA5 (‘21-’61) = 11.278.098,14
  • 35. “ ” 35 Dari hasil pendesainan perkerasan, jalan yang saya pilih adalah jalan perkerasan lentur karena meninjau dari beban jalan yang tidak terlalu berat seperti beban jalan pada perkerasan kaku. Jika ada kerusakan kecil pada perkerasan lentur, mudah dilakukan dalam perbaikannya. Untuk perkerasan lentur berwarna gelap sehingga lebih nyaman untuk mata karena tidak menyilaukan. Biaya konstruksi juga lebih murah dibandingkan perkerasan kaku. Sehingga pekerjaan dilakukan oleh kontraktor kecil-medium.
  • 36. Komentar dalam menggunakan panduan: 36 ❑ Cukup mudah dipahami dalam menggunakan Manual Desain Perkerasan Jalan. Langkah-langkah pengerjaan yang dijelaskan dalam Manual Desain Perkerasan Jalan sudah jelas, tapi dalam penulisan Langkah-langkahnya belum tersusun secara urut dan terperinci. Menurut saya, Manual Desain Perkerasan Jalan belum terlalu lengkap pada desain perkerasan kaku. Indonesia menggunakan Manual Desain untuk memenuhi standar pemerataan konstruksi jalan di Indonesia karena sulitnya mendapatkan data pendukung untuk desain perkerasan jalan karena kurang terdokumentasikan dengan baik, maka didapatkan data yang tidak valid. Manual Desain Perkerasan Jalan digunakan sebagai acuan dengan mengupgrade metode empiris menjadi metode mekanistik sesuai dengan tipikal di Indonesia walaupun belum tentu sama pada setiap kondisi atau tempat di seluruh Indonesia. ❑ Untuk penggunaan Pd T-14-2003 masih cukup bingung di bagian menentukan detail desain perkerasan kaku dan membaca beberapa grafik. Pd T-14-2003 isinya lebih lengkap daripada Manual Desain Perkerasan Jalan. Ada juga beberapa contoh perhitungan yang rinci dalam menentukan desain perkerasan kaku yang masih cukup sulit dipahami karena jarang dibahas. Agar dapat lebih memahami lagi, harus dipelajari lebih dalam lagi.