SlideShare a Scribd company logo
Public Consultation
1
F.G. Gardiner Expressway
Rehabilitation
Public Consultation
February 17, 2015
Public Consultation
427
Kipling
Islington
ParkLawn
Dufferin
Strachan
Bathurst
Spadina
York
Yonge
Jarvis
LakeShore
“Anatomy” of Gardiner Expressway
– “At-grade” section: Hwy. 427 to Dufferin Street (1955 to 1958)
– “Elevated” section: Dufferin Street to Logan Avenue (1959 to 1966)
“At Grade”
- 11 km
- 32 bridges/
structures
“Elevated”
- 7 km
- 335 spans
DonValley
2
Public Consultation
Rehabilitation Strategic Plan
3
 In 2013 the Strategic Plan for the rehabilitation of the
Gardiner Expressway (developed by McCormick Rankin ) the
plan:
o identified immediate, short and long term rehabilitation needs of Gardiner;
o developed an implementation schedule for the necessary rehabilitation works
to maintain the Gardiner in a safe and serviceable condition; and,
o Took into consideration:
• previous rehabilitation work;
• User impacts and associated costs;
• Capital costs, Life cycle costs, Cash Flow requirements; and
• Assumed traffic restrictions of no more than a single lane closure in each
direction.
Public Consultation
4
 In 2014, Staff presented the Strategic Rehabilitation plan to the
Public Works Committee and City Council.
 On April 2, 2014 City Council:
o approved the “Accelerated Construction” approach for Gardiner
Rehabilitation reducing the traffic impacts for the anticipated work from 20
years to 12 years
o directed to report back with analysis of project delivery models and
procurement options.
 On June 10, 2014, Council authorized retention of Infrastructure
Ontario for the purposes of preparing a procurement options
analysis in support of the implementation of the Strategic Plan
Rehabilitation Strategic Plan
Public Consultation
Accelerated Rehabilitation Approach
Placing Prefabricated Deck-Girder Section
Montreal: Jacques Cartier Bridge Rehabilitation
Prefabrication Facility
5
Public Consultation
Evaluating Project Delivery
Various methods of project delivery
including
o Traditional project delivery
 Multiple contracts with private sector for design
and construction of various project components
o Public private partnership (P3)
 One large contract with private sector consortium
for design, construction, operations and life cycle
maintenance.
Public Consultation
Federal Funding Requests
 P3 Canada Fund
o P3 Canada funding for projects delivered as P3s
o Business case must demonstrate positive Value for
Money for project delivery as P3 compared with
traditional delivery methods
 New Building Canada Fund
o Projects with capital costs >$100 million must be
screened for potential delivery as P3
o Business case and procurement options analysis
to be submitted
7
Public Consultation
Models of PPP in Canada
Degree of Private Sector Involvement
DegreeofPrivateSectorRisk
Design – Build
PPPModels
Operation & Maintenance
Build – Finance
Build – Finance – Maintain
Lease – Develop – Operate
Design – Build – Operate
Design – Build – Finance – Maintain
Design – Build – Finance – Operate
Design – Build – Finance – Operate - Maintain
Build – Own – Operate
Concession
Privatization
Public Consultation
Key Features of P3
 Risk Transfer from public sector to private sector,
including:
o Project Delivery on time and on budget
o Long term maintenance risk
 Innovation
o Project structured so as to promote innovation in design and construction
 Integrated Project Delivery
o Design, Construction undertaken by one consortium enhances asset
delivery meeting/exceeding expectations
 Life Cycle Accountability for the Work
o Maintenance of constructed work is responsibility of private sector, post
construction, over long-term concession period (eg 30 year)
o ensures that asset will be maintained in good condition, and handed back to the City in
good condition at end of contract
Public Consultation
P3 Risk Transference
Traditional: Design-Bid-Build
(DBB)
Owner’s Risks Bidder’s Risks
Design
Financing
Highway
Maintenance
Lifecycle
Highway
Availability,
Performance &
Asset Value
Construction
P3: Design-Build-Finance-Operate-Maintain
(DBFOM)
Bidder’s Risks
Output
Specifications
Design
Financing
Construction
Lifecycle
Highway
Availability,
Maintenance
Performance &
Asset Value
Owner’s Risks
Risks are transferred to the party best able to manage them.
Public Consultation
Defining Value for Money (VfM)
11
• Base Costs: Design, Construction,
Operations (summer and winter maintenance)
and Rehabilitation over the concession term
• Financing Costs: Costs associated with
funding the project
• Ancillary Costs: includes additional 3rd
party
advisory, legal, delivery costs etc
• Risk Retained: Risks best managed by Public
sector stay with Public sector
• The risk adjusted cost difference between
PSC and AFP is the estimated Value for
Money
• If the AFP costs are less than the PSC cost,
there is positive Value for Money by
procuring a project using AFP.
Value for Money assessment compares the
cost of delivering the same project under two
different delivery models, Traditional or Public
Sector Comparator (PSC) to Alternative
Financing and Procurement (AFP) to determine
which provides a lower estimated total project
cost.
Base Costs
(Lower under AFP as a result of Innovation
Factor set off by higher Lifecycle Costs)
Risks Retained
+ Value for Money
PSC AFP
Ancillary Costs
Financing Costs
Public Consultation
Other Canadian Transportation P3 Projects
• Winnipeg- Chief Peguis Trail
• Saskatoon North Commuter Parkway and Traffic Bridge
Replacement
• Alberta- Stoney Trail (various projects)
• Quebec- Autoroutes 25 and 30
• Montreal- Rebuild of Turcott Interchange
• Federal- Montreal- Champlain Bridge
• New Brunswick- Fredricton-Moncton Highway
• Federal- New Brunswick- Trans Canada Highway
12

More Related Content

What's hot

Six Points Reconfiguration - Community Update June, 2013 (Poster Boards)
Six Points Reconfiguration - Community Update June, 2013 (Poster Boards)Six Points Reconfiguration - Community Update June, 2013 (Poster Boards)
Six Points Reconfiguration - Community Update June, 2013 (Poster Boards)
Toronto Public Consultation Unit
 
Improve kpmb+big booklet
Improve kpmb+big bookletImprove kpmb+big booklet
Improve kpmb+big bookletGardinerEast
 
Urban Design and Street Typology: Do They Matter?
Urban Design and Street Typology: Do They Matter?Urban Design and Street Typology: Do They Matter?
Urban Design and Street Typology: Do They Matter?
William Riggs
 
Mosman Parks & Bushland Association objection to Sydney Harbour Trust privati...
Mosman Parks & Bushland Association objection to Sydney Harbour Trust privati...Mosman Parks & Bushland Association objection to Sydney Harbour Trust privati...
Mosman Parks & Bushland Association objection to Sydney Harbour Trust privati...
savemiddlehead
 
New York's Next Great Waterfront Park - Urban Design
New York's Next Great Waterfront Park - Urban DesignNew York's Next Great Waterfront Park - Urban Design
New York's Next Great Waterfront Park - Urban Design
The Municipal Art Society of New York
 
Remove jcfo boards
Remove jcfo boardsRemove jcfo boards
Remove jcfo boardsGardinerEast
 
What if 280 came down
What if 280 came downWhat if 280 came down
What if 280 came down
emilypeckenham
 
Replace as+gg boards
Replace as+gg boardsReplace as+gg boards
Replace as+gg boardsGardinerEast
 
Improve kpmb+big boards
Improve kpmb+big boardsImprove kpmb+big boards
Improve kpmb+big boardsGardinerEast
 
Remove jcfo booklet
Remove jcfo bookletRemove jcfo booklet
Remove jcfo bookletGardinerEast
 
Improve dsr+aa booklet
Improve dsr+aa bookletImprove dsr+aa booklet
Improve dsr+aa bookletGardinerEast
 
Sectors 2 & 3 Charrette Closing Presentation
Sectors 2 & 3 Charrette Closing PresentationSectors 2 & 3 Charrette Closing Presentation
Sectors 2 & 3 Charrette Closing Presentation
City of Beaufort Planning Department
 
Beaufort-Sector1-Charrette-FinalPresentation
Beaufort-Sector1-Charrette-FinalPresentationBeaufort-Sector1-Charrette-FinalPresentation
Beaufort-Sector1-Charrette-FinalPresentation
City of Beaufort Planning Department
 
Improve dsr+aa boards
Improve dsr+aa boardsImprove dsr+aa boards
Improve dsr+aa boardsGardinerEast
 
Splost Presentation 2008
Splost Presentation 2008Splost Presentation 2008
Splost Presentation 2008Brett Deaton
 
Planning Department Response to Primary Questions re: Johnwoods
Planning Department Response to Primary Questions re: JohnwoodsPlanning Department Response to Primary Questions re: Johnwoods
Planning Department Response to Primary Questions re: Johnwoods
StittsvilleCentral.ca
 
John Rahaim - Transit Center District Plan
John Rahaim - Transit Center District PlanJohn Rahaim - Transit Center District Plan
John Rahaim - Transit Center District Plan
Stanford Sustainable Urban Systems Initiative
 
Remove oma+amo booklet
Remove oma+amo bookletRemove oma+amo booklet
Remove oma+amo bookletGardinerEast
 

What's hot (20)

Six Points Reconfiguration - Community Update June, 2013 (Poster Boards)
Six Points Reconfiguration - Community Update June, 2013 (Poster Boards)Six Points Reconfiguration - Community Update June, 2013 (Poster Boards)
Six Points Reconfiguration - Community Update June, 2013 (Poster Boards)
 
Removing Toronto's Expressway One Piece at a Time
Removing Toronto's Expressway One Piece at a TimeRemoving Toronto's Expressway One Piece at a Time
Removing Toronto's Expressway One Piece at a Time
 
Improve kpmb+big booklet
Improve kpmb+big bookletImprove kpmb+big booklet
Improve kpmb+big booklet
 
Urban Design and Street Typology: Do They Matter?
Urban Design and Street Typology: Do They Matter?Urban Design and Street Typology: Do They Matter?
Urban Design and Street Typology: Do They Matter?
 
Mosman Parks & Bushland Association objection to Sydney Harbour Trust privati...
Mosman Parks & Bushland Association objection to Sydney Harbour Trust privati...Mosman Parks & Bushland Association objection to Sydney Harbour Trust privati...
Mosman Parks & Bushland Association objection to Sydney Harbour Trust privati...
 
New York's Next Great Waterfront Park - Urban Design
New York's Next Great Waterfront Park - Urban DesignNew York's Next Great Waterfront Park - Urban Design
New York's Next Great Waterfront Park - Urban Design
 
Remove jcfo boards
Remove jcfo boardsRemove jcfo boards
Remove jcfo boards
 
What if 280 came down
What if 280 came downWhat if 280 came down
What if 280 came down
 
Replace as+gg boards
Replace as+gg boardsReplace as+gg boards
Replace as+gg boards
 
Improve kpmb+big boards
Improve kpmb+big boardsImprove kpmb+big boards
Improve kpmb+big boards
 
Remove jcfo booklet
Remove jcfo bookletRemove jcfo booklet
Remove jcfo booklet
 
Improve dsr+aa booklet
Improve dsr+aa bookletImprove dsr+aa booklet
Improve dsr+aa booklet
 
Sectors 2 & 3 Charrette Closing Presentation
Sectors 2 & 3 Charrette Closing PresentationSectors 2 & 3 Charrette Closing Presentation
Sectors 2 & 3 Charrette Closing Presentation
 
Beaufort-Sector1-Charrette-FinalPresentation
Beaufort-Sector1-Charrette-FinalPresentationBeaufort-Sector1-Charrette-FinalPresentation
Beaufort-Sector1-Charrette-FinalPresentation
 
Improve dsr+aa boards
Improve dsr+aa boardsImprove dsr+aa boards
Improve dsr+aa boards
 
Splost Projects
Splost ProjectsSplost Projects
Splost Projects
 
Splost Presentation 2008
Splost Presentation 2008Splost Presentation 2008
Splost Presentation 2008
 
Planning Department Response to Primary Questions re: Johnwoods
Planning Department Response to Primary Questions re: JohnwoodsPlanning Department Response to Primary Questions re: Johnwoods
Planning Department Response to Primary Questions re: Johnwoods
 
John Rahaim - Transit Center District Plan
John Rahaim - Transit Center District PlanJohn Rahaim - Transit Center District Plan
John Rahaim - Transit Center District Plan
 
Remove oma+amo booklet
Remove oma+amo bookletRemove oma+amo booklet
Remove oma+amo booklet
 

Similar to Delivering the Rehabilitation of the F.G. Gardiner Expressway

Private and Public Partnerships Move Mainstream
Private and Public Partnerships Move MainstreamPrivate and Public Partnerships Move Mainstream
Private and Public Partnerships Move Mainstream
Kerry Carey
 
Public-Private Partnerships - Business & Legal Issues
Public-Private Partnerships - Business & Legal IssuesPublic-Private Partnerships - Business & Legal Issues
Public-Private Partnerships - Business & Legal Issues
Lou Milrad
 
Demystifying The Public Private Partnership
Demystifying The Public Private PartnershipDemystifying The Public Private Partnership
Demystifying The Public Private Partnershipphilippduffy
 
Lindgren Combined 18may10
Lindgren Combined 18may10Lindgren Combined 18may10
Lindgren Combined 18may10
Jaylindgren
 
Aurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedIn
Aurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedInAurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedIn
Aurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedInSteve Richards
 
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
marcus evans Network
 
projectfinancingandpublicprivatepartnershipppp-191120191032.pdf
projectfinancingandpublicprivatepartnershipppp-191120191032.pdfprojectfinancingandpublicprivatepartnershipppp-191120191032.pdf
projectfinancingandpublicprivatepartnershipppp-191120191032.pdf
Seshukumar53
 
Project financing and public private partnership (ppp)
Project financing and public private partnership (ppp)Project financing and public private partnership (ppp)
Project financing and public private partnership (ppp)
M. Asim U Khan
 
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27Roland_Nikles
 
Project finance ppt final
Project finance ppt finalProject finance ppt final
Project finance ppt final
Sagar Srivastava
 
Project Financing and Investment Planning - BORAQS Kenya
Project Financing and Investment Planning - BORAQS KenyaProject Financing and Investment Planning - BORAQS Kenya
Project Financing and Investment Planning - BORAQS Kenya
Millennium Challenge Account - MCA Senegal
 
Jamieson: Alternative Finance and Delivery for Water Projects
Jamieson: Alternative Finance and Delivery for Water ProjectsJamieson: Alternative Finance and Delivery for Water Projects
Jamieson: Alternative Finance and Delivery for Water Projects
Paul Blanchard
 
TPO FPC Overview of Project Delivery Approaches
TPO FPC Overview of Project Delivery ApproachesTPO FPC Overview of Project Delivery Approaches
TPO FPC Overview of Project Delivery Approaches
Miami-Dade Transportation Planning Organization
 
Upp scoping session presentation 4 4-2019
Upp scoping session presentation 4 4-2019Upp scoping session presentation 4 4-2019
Upp scoping session presentation 4 4-2019
E'ville Eye
 
CV_PhilMorris_2015
CV_PhilMorris_2015CV_PhilMorris_2015
CV_PhilMorris_2015Phil Morris
 
DOPWIC Program Year 2019 Applicant Workshop
DOPWIC Program Year 2019 Applicant WorkshopDOPWIC Program Year 2019 Applicant Workshop
DOPWIC Program Year 2019 Applicant Workshop
Cuyahoga County Planning Commission
 
Executive Summary: Schematic Design, Finance Strategy and Next Steps
Executive Summary: Schematic Design, Finance Strategy and Next StepsExecutive Summary: Schematic Design, Finance Strategy and Next Steps
Executive Summary: Schematic Design, Finance Strategy and Next Steps
RiverFirst Initiative
 
Devore vvcc feb 13 2013 final
Devore vvcc feb 13 2013 finalDevore vvcc feb 13 2013 final
Devore vvcc feb 13 2013 finalvvchamber123
 
feasibility study
 feasibility study feasibility study
feasibility study
Primum Nocere
 

Similar to Delivering the Rehabilitation of the F.G. Gardiner Expressway (20)

Private and Public Partnerships Move Mainstream
Private and Public Partnerships Move MainstreamPrivate and Public Partnerships Move Mainstream
Private and Public Partnerships Move Mainstream
 
Public-Private Partnerships - Business & Legal Issues
Public-Private Partnerships - Business & Legal IssuesPublic-Private Partnerships - Business & Legal Issues
Public-Private Partnerships - Business & Legal Issues
 
Demystifying The Public Private Partnership
Demystifying The Public Private PartnershipDemystifying The Public Private Partnership
Demystifying The Public Private Partnership
 
Lindgren Combined 18may10
Lindgren Combined 18may10Lindgren Combined 18may10
Lindgren Combined 18may10
 
Aurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedIn
Aurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedInAurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedIn
Aurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedIn
 
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
 
projectfinancingandpublicprivatepartnershipppp-191120191032.pdf
projectfinancingandpublicprivatepartnershipppp-191120191032.pdfprojectfinancingandpublicprivatepartnershipppp-191120191032.pdf
projectfinancingandpublicprivatepartnershipppp-191120191032.pdf
 
Project financing and public private partnership (ppp)
Project financing and public private partnership (ppp)Project financing and public private partnership (ppp)
Project financing and public private partnership (ppp)
 
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
 
Rafeek's CV
Rafeek's CV Rafeek's CV
Rafeek's CV
 
Project finance ppt final
Project finance ppt finalProject finance ppt final
Project finance ppt final
 
Project Financing and Investment Planning - BORAQS Kenya
Project Financing and Investment Planning - BORAQS KenyaProject Financing and Investment Planning - BORAQS Kenya
Project Financing and Investment Planning - BORAQS Kenya
 
Jamieson: Alternative Finance and Delivery for Water Projects
Jamieson: Alternative Finance and Delivery for Water ProjectsJamieson: Alternative Finance and Delivery for Water Projects
Jamieson: Alternative Finance and Delivery for Water Projects
 
TPO FPC Overview of Project Delivery Approaches
TPO FPC Overview of Project Delivery ApproachesTPO FPC Overview of Project Delivery Approaches
TPO FPC Overview of Project Delivery Approaches
 
Upp scoping session presentation 4 4-2019
Upp scoping session presentation 4 4-2019Upp scoping session presentation 4 4-2019
Upp scoping session presentation 4 4-2019
 
CV_PhilMorris_2015
CV_PhilMorris_2015CV_PhilMorris_2015
CV_PhilMorris_2015
 
DOPWIC Program Year 2019 Applicant Workshop
DOPWIC Program Year 2019 Applicant WorkshopDOPWIC Program Year 2019 Applicant Workshop
DOPWIC Program Year 2019 Applicant Workshop
 
Executive Summary: Schematic Design, Finance Strategy and Next Steps
Executive Summary: Schematic Design, Finance Strategy and Next StepsExecutive Summary: Schematic Design, Finance Strategy and Next Steps
Executive Summary: Schematic Design, Finance Strategy and Next Steps
 
Devore vvcc feb 13 2013 final
Devore vvcc feb 13 2013 finalDevore vvcc feb 13 2013 final
Devore vvcc feb 13 2013 final
 
feasibility study
 feasibility study feasibility study
feasibility study
 

More from Toronto Public Consultation Unit

Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Toronto Public Consultation Unit
 
SmartTrack Public Meeting Presentation
SmartTrack Public Meeting PresentationSmartTrack Public Meeting Presentation
SmartTrack Public Meeting Presentation
Toronto Public Consultation Unit
 
Waterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display PanelsWaterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display Panels
Toronto Public Consultation Unit
 
Waterfront Transit Reset Public Meeting Presentation
Waterfront Transit Reset Public Meeting Presentation Waterfront Transit Reset Public Meeting Presentation
Waterfront Transit Reset Public Meeting Presentation
Toronto Public Consultation Unit
 
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
Toronto Public Consultation Unit
 
Sewer Outfall Project
Sewer Outfall ProjectSewer Outfall Project
Sewer Outfall Project
Toronto Public Consultation Unit
 
General information
General informationGeneral information
Disinfection System
Disinfection SystemDisinfection System
2017 Sediment Basin construction updated information
2017 Sediment Basin construction updated information 2017 Sediment Basin construction updated information
2017 Sediment Basin construction updated information
Toronto Public Consultation Unit
 
Scarborough Subway TPAP Boards
Scarborough Subway TPAP Boards Scarborough Subway TPAP Boards
Scarborough Subway TPAP Boards
Toronto Public Consultation Unit
 
2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final
Toronto Public Consultation Unit
 
King Street Phase 2 Slide Deck
King Street Phase 2 Slide Deck King Street Phase 2 Slide Deck
King Street Phase 2 Slide Deck
Toronto Public Consultation Unit
 
Scarborough Subway TPAP PIC
Scarborough Subway TPAP PICScarborough Subway TPAP PIC
Scarborough Subway TPAP PIC
Toronto Public Consultation Unit
 
Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Toronto Public Consultation Unit
 
Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing
Toronto Public Consultation Unit
 
FG Gardiner New Simcoe Ramp - display boards
FG Gardiner   New Simcoe Ramp - display boardsFG Gardiner   New Simcoe Ramp - display boards
FG Gardiner New Simcoe Ramp - display boards
Toronto Public Consultation Unit
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
Toronto Public Consultation Unit
 
Swc public consultation_pres_170307_final
Swc public consultation_pres_170307_finalSwc public consultation_pres_170307_final
Swc public consultation_pres_170307_final
Toronto Public Consultation Unit
 
King Street Pilot Public Meeting
King Street Pilot Public MeetingKing Street Pilot Public Meeting
King Street Pilot Public Meeting
Toronto Public Consultation Unit
 
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
Toronto Public Consultation Unit
 

More from Toronto Public Consultation Unit (20)

Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
 
SmartTrack Public Meeting Presentation
SmartTrack Public Meeting PresentationSmartTrack Public Meeting Presentation
SmartTrack Public Meeting Presentation
 
Waterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display PanelsWaterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display Panels
 
Waterfront Transit Reset Public Meeting Presentation
Waterfront Transit Reset Public Meeting Presentation Waterfront Transit Reset Public Meeting Presentation
Waterfront Transit Reset Public Meeting Presentation
 
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
 
Sewer Outfall Project
Sewer Outfall ProjectSewer Outfall Project
Sewer Outfall Project
 
General information
General informationGeneral information
General information
 
Disinfection System
Disinfection SystemDisinfection System
Disinfection System
 
2017 Sediment Basin construction updated information
2017 Sediment Basin construction updated information 2017 Sediment Basin construction updated information
2017 Sediment Basin construction updated information
 
Scarborough Subway TPAP Boards
Scarborough Subway TPAP Boards Scarborough Subway TPAP Boards
Scarborough Subway TPAP Boards
 
2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final
 
King Street Phase 2 Slide Deck
King Street Phase 2 Slide Deck King Street Phase 2 Slide Deck
King Street Phase 2 Slide Deck
 
Scarborough Subway TPAP PIC
Scarborough Subway TPAP PICScarborough Subway TPAP PIC
Scarborough Subway TPAP PIC
 
Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017
 
Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing
 
FG Gardiner New Simcoe Ramp - display boards
FG Gardiner   New Simcoe Ramp - display boardsFG Gardiner   New Simcoe Ramp - display boards
FG Gardiner New Simcoe Ramp - display boards
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
 
Swc public consultation_pres_170307_final
Swc public consultation_pres_170307_finalSwc public consultation_pres_170307_final
Swc public consultation_pres_170307_final
 
King Street Pilot Public Meeting
King Street Pilot Public MeetingKing Street Pilot Public Meeting
King Street Pilot Public Meeting
 
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
 

Recently uploaded

ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
Saeed Al Dhaheri
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Congressional Budget Office
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
oklahomajudicialproc1
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
ClaudioTebaldi2
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
ahcitycouncil
 
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
evkovas
 
PPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930FPPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930F
ahcitycouncil
 
NHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdfNHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdf
AjayVejendla3
 
2024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 372024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 37
JSchaus & Associates
 
PPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933FPPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933F
ahcitycouncil
 
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptxMHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
ILC- UK
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
Get Government Grants
 
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptxPD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
RIDPRO11
 
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
ehbuaw
 
What is the point of small housing associations.pptx
What is the point of small housing associations.pptxWhat is the point of small housing associations.pptx
What is the point of small housing associations.pptx
Paul Smith
 
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
ehbuaw
 
Many ways to support street children.pptx
Many ways to support street children.pptxMany ways to support street children.pptx
Many ways to support street children.pptx
SERUDS INDIA
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
ehbuaw
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
JSchaus & Associates
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
Antti Rautiainen
 

Recently uploaded (20)

ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
 
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
 
PPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930FPPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930F
 
NHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdfNHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdf
 
2024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 372024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 37
 
PPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933FPPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933F
 
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptxMHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
 
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptxPD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
 
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
 
What is the point of small housing associations.pptx
What is the point of small housing associations.pptxWhat is the point of small housing associations.pptx
What is the point of small housing associations.pptx
 
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
一比一原版(UOW毕业证)伍伦贡大学毕业证成绩单
 
Many ways to support street children.pptx
Many ways to support street children.pptxMany ways to support street children.pptx
Many ways to support street children.pptx
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
 

Delivering the Rehabilitation of the F.G. Gardiner Expressway

  • 1. Public Consultation 1 F.G. Gardiner Expressway Rehabilitation Public Consultation February 17, 2015
  • 2. Public Consultation 427 Kipling Islington ParkLawn Dufferin Strachan Bathurst Spadina York Yonge Jarvis LakeShore “Anatomy” of Gardiner Expressway – “At-grade” section: Hwy. 427 to Dufferin Street (1955 to 1958) – “Elevated” section: Dufferin Street to Logan Avenue (1959 to 1966) “At Grade” - 11 km - 32 bridges/ structures “Elevated” - 7 km - 335 spans DonValley 2
  • 3. Public Consultation Rehabilitation Strategic Plan 3  In 2013 the Strategic Plan for the rehabilitation of the Gardiner Expressway (developed by McCormick Rankin ) the plan: o identified immediate, short and long term rehabilitation needs of Gardiner; o developed an implementation schedule for the necessary rehabilitation works to maintain the Gardiner in a safe and serviceable condition; and, o Took into consideration: • previous rehabilitation work; • User impacts and associated costs; • Capital costs, Life cycle costs, Cash Flow requirements; and • Assumed traffic restrictions of no more than a single lane closure in each direction.
  • 4. Public Consultation 4  In 2014, Staff presented the Strategic Rehabilitation plan to the Public Works Committee and City Council.  On April 2, 2014 City Council: o approved the “Accelerated Construction” approach for Gardiner Rehabilitation reducing the traffic impacts for the anticipated work from 20 years to 12 years o directed to report back with analysis of project delivery models and procurement options.  On June 10, 2014, Council authorized retention of Infrastructure Ontario for the purposes of preparing a procurement options analysis in support of the implementation of the Strategic Plan Rehabilitation Strategic Plan
  • 5. Public Consultation Accelerated Rehabilitation Approach Placing Prefabricated Deck-Girder Section Montreal: Jacques Cartier Bridge Rehabilitation Prefabrication Facility 5
  • 6. Public Consultation Evaluating Project Delivery Various methods of project delivery including o Traditional project delivery  Multiple contracts with private sector for design and construction of various project components o Public private partnership (P3)  One large contract with private sector consortium for design, construction, operations and life cycle maintenance.
  • 7. Public Consultation Federal Funding Requests  P3 Canada Fund o P3 Canada funding for projects delivered as P3s o Business case must demonstrate positive Value for Money for project delivery as P3 compared with traditional delivery methods  New Building Canada Fund o Projects with capital costs >$100 million must be screened for potential delivery as P3 o Business case and procurement options analysis to be submitted 7
  • 8. Public Consultation Models of PPP in Canada Degree of Private Sector Involvement DegreeofPrivateSectorRisk Design – Build PPPModels Operation & Maintenance Build – Finance Build – Finance – Maintain Lease – Develop – Operate Design – Build – Operate Design – Build – Finance – Maintain Design – Build – Finance – Operate Design – Build – Finance – Operate - Maintain Build – Own – Operate Concession Privatization
  • 9. Public Consultation Key Features of P3  Risk Transfer from public sector to private sector, including: o Project Delivery on time and on budget o Long term maintenance risk  Innovation o Project structured so as to promote innovation in design and construction  Integrated Project Delivery o Design, Construction undertaken by one consortium enhances asset delivery meeting/exceeding expectations  Life Cycle Accountability for the Work o Maintenance of constructed work is responsibility of private sector, post construction, over long-term concession period (eg 30 year) o ensures that asset will be maintained in good condition, and handed back to the City in good condition at end of contract
  • 10. Public Consultation P3 Risk Transference Traditional: Design-Bid-Build (DBB) Owner’s Risks Bidder’s Risks Design Financing Highway Maintenance Lifecycle Highway Availability, Performance & Asset Value Construction P3: Design-Build-Finance-Operate-Maintain (DBFOM) Bidder’s Risks Output Specifications Design Financing Construction Lifecycle Highway Availability, Maintenance Performance & Asset Value Owner’s Risks Risks are transferred to the party best able to manage them.
  • 11. Public Consultation Defining Value for Money (VfM) 11 • Base Costs: Design, Construction, Operations (summer and winter maintenance) and Rehabilitation over the concession term • Financing Costs: Costs associated with funding the project • Ancillary Costs: includes additional 3rd party advisory, legal, delivery costs etc • Risk Retained: Risks best managed by Public sector stay with Public sector • The risk adjusted cost difference between PSC and AFP is the estimated Value for Money • If the AFP costs are less than the PSC cost, there is positive Value for Money by procuring a project using AFP. Value for Money assessment compares the cost of delivering the same project under two different delivery models, Traditional or Public Sector Comparator (PSC) to Alternative Financing and Procurement (AFP) to determine which provides a lower estimated total project cost. Base Costs (Lower under AFP as a result of Innovation Factor set off by higher Lifecycle Costs) Risks Retained + Value for Money PSC AFP Ancillary Costs Financing Costs
  • 12. Public Consultation Other Canadian Transportation P3 Projects • Winnipeg- Chief Peguis Trail • Saskatoon North Commuter Parkway and Traffic Bridge Replacement • Alberta- Stoney Trail (various projects) • Quebec- Autoroutes 25 and 30 • Montreal- Rebuild of Turcott Interchange • Federal- Montreal- Champlain Bridge • New Brunswick- Fredricton-Moncton Highway • Federal- New Brunswick- Trans Canada Highway 12

Editor's Notes

  1. The Expressway is 18 km long extending from Highway 427 in the west to Logan Ave. in the east. The Expressway is divided into two sections: At-Grade & Elevated The “at-grade” section is 11 km long and extends from approximately from Highway 427 to 300m east of Dufferin Street. The at-grade section includes 32 structures consisting of bridges, retaining walls and culverts The “elevated” section is 7 km long and extends from east of Bathurst Street to the DVP ramp. The elevated section consists of 335 spans on top 334 bents. It also includes 17 ramps
  2. We are undertaking a detailed analysis of available project procurement models including: Traditional delivery- the way we have been undertaking projects to date P3- this is another method of project delivery, which we will discuss briefly in the slides that follow In Ontario, P3 is also knows as “AFP”, or “Alternative Financing and Procurement” Not all projects are suitable for delivery as P3s. A detailed analysis needs to be undertaken to determine the optimal project delivery method
  3. We are also required to investigate P3 procurement methods to receive financing under the above 2 federal funds. Funding under the P3 Canada Fund is provided only for projects that are delivered as P3s. This means not just any P3, but an in depth analysis must demonstrate that there is a positive “value for money” in undertaking a P3 for a particular project The New Building Canada fund also funds projects that are not P3s. All projects estimated at $100 million and more must undergo a P3 screen. If this screen indicates that a particular project may be suitable for delivery as a P3, then a further “procurement options analysis” must be prepared and submitted in order to be considered for funding
  4. There are various types of P3 models. You will note that we are not talking about privatization. That appears at the top of this chart, above the various P3 models. For this project, we are considering a model of a Design-Build-Finance-Operate-Maintain nature This means that a private sector partner would design, construct, and finance the construction of the asset. Post-construction, the private sector partner would be responsible for life cycle maintenance, and operations over a long-term concession contract
  5. This slide compares traditional project delivery, with a P3 On the left hand side, under a traditional method, the public sector partner keeps all of the risks shown in blue, transferring only the construction risk to the private sector. This means that the private sector partner is responsible only for construction of the asset In comparison, on the right hand side of the slide, under a P3, the risks shown in blue are transferred to the private sector partner. That is, project design, construction, financing (ie until the public sector provides payment), and life cycle maintenance as well as operations