SlideShare a Scribd company logo
Slayton Hill Road Reconstruction

Lebanon, NH
February 12, 2014
Welcome and Introductions
• Greg Lewis – City Manager
Ground Rules

• Paula Maville – Deputy City Manager
Scenic Road Designation

• David McNamara – Fay, Spofford, & Thorndike
Design Update

Slayton Hill Road Reconstruction
City of Lebanon, NH
Scenic Road Designation
• Declaration of Purpose:
• Slayton Hill Designated Scenic on 12/15/93
• Impacts to Right-of-Way
88% of stone walls between Dulac & 78 Slayton
An additional 44% between 78 Slayton &
Dunsinaine
60% of trees (total length of project) will need to
be cleared
Slayton Hill Road Reconstruction
City of Lebanon, NH
Scenic Road Designation
• One of Two Processes to Undertake
§134-5 Effect of Designation as Scenic Road
Manager to obtain written consent of the Planning
Board after a Public Hearing

§134-8 Rescission of Designation of Scenic Road
Requires a petition of 10 Persons who are either voters
of the City or who own land which abuts the road
Reports Solicited from the Planning Board and
Conservation Commission
Public Hearing held by the City Council
Slayton Hill Road Reconstruction
City of Lebanon, NH
Meeting Objectives
• Update on status of project
Temporary repairs
Complete

Permanent reconstruction
Design Progress

Next Steps

• Solicit feedback
Scenic Road Designation
Present updated design progress
Discuss potential property and edge of road impacts
due to permanent improvements
Slayton Hill Road Reconstruction
City of Lebanon, NH
Existing Conditions
Slayton Hill Road was built into a hillside
Ledge and poorly drained soils
Slayton Hill Road – Reconstructed in 2001/2002 timeframe
Design was restricted by Scenic Road designation and
limiting property impacts
• Culverts generally replaced with new ADS pipe of the same
size
• Narrow/shallow swales and underdrains with limited armor
in place along uphill side of road
• New Standards
•
•
•
•

Precipitation Data
Storm Sizing
Slayton Hill Road Reconstruction
City of Lebanon, NH
Response – Short Term Repairs
• City forces
Immediate repairs following July 2nd Storm (July)
Temporary water main
Roadway repairs to allow traffic

Intermediate Term (Complete)
Repair buried water main
Widen road to allow minimum two lanes of traffic
Temporary pavement course for winter maintenance
Armor washed out ditches
Additional culvert to divert flows in lower section
Slayton Hill Road Reconstruction
City of Lebanon, NH
Design
• Design Storm
100 year minimum

• Culvert sizing
Slayton Hill Road
Total of 22 cross culverts
– 10 are adequately sized
– 11 are undersized
– 1 new Culvert

Dulac Street
Total of 3 cross culverts
– 2 are undersized
– 1 new culvert (twin pipes)
Slayton Hill Road Reconstruction
City of Lebanon, NH
Culvert Sizing – Slayton Hill Road
AREA

STATION

EXISTING CULVERT SIZE

PROPOSED CULVERT SIZE

AREA

STATION

EXISTING CULVERT SIZE

PROPOSED CULVERT SIZE

1

Intersection w/ Dulac St

18” HDPE

24” RCP

12

56+21

18” HDPE

24” RCP

2A

7+99

18” HDPE

24” RCP

13

56+89

24” HDPE

24” RCP

2B

11+84

-----

24” RCP
14

61+11

18” HDPE

30” RCP

15

63+11

18” HDPE

24” RCP

16

66+52

24” HDPE

36” RCP

17

75+26

48” HDPE

6-ft x 4-ft Concrete Box

18

82+53

18” HDPE

18” RCP
Replace CB with Headwall

19

85+99

18” HDPE

18” RCP
Replace CB with Headwall

30” HDPE

30” RCP

3

4

5

6

8

9

12+43

16+00

19+59

20+85

27+98

29+38

2.7-Ft x 2.6-Ft Concrete Box

4-Ft x 4-Ft Concrete Box

18” HDPE / 27.6

24” RCP

15” HDPE

15” RCP

15” HDPE

18” RCP

24” HDPE

18” HDPE

24” RCP

18” RCP
Replace CB with Headwall

20

10

33+82

30” HDPE

30” RCP

21

3+72

15” HDPE

15” RCP

11

42+31

24” HDPE

Twin 24” RCPs

22

89+18

15” HDPE

15” RCP

Slayton Hill Road Reconstruction
City of Lebanon, NH
Culvert Sizing – Dulac Street
AREA

STATION

EXISTING CULVERT SIZE

PROPOSED CULVERT SIZE

23A

202+50

12” HDPE

Twin 18” RCPs

23C

206+50

-----

Twin 18” RCPs

23B

209+50

12” HDPE

24” RCP

Slayton Hill Road Reconstruction
City of Lebanon, NH
Design
• Ditches
Most proposed are V shaped,
1.5’ to 2.0’ deep, 3:1
sideslopes off the road, 2:1
back slopes to match existing
ground
Lower portion includes a 2’
wide flat bottom
Slopes steeper than 10% will
be stone lined
Slopes flatter than 10% will
be grass, with reinforced
matting products
Underdrains
Slayton Hill Road Reconstruction
City of Lebanon, NH
Design - Tributary Drainage Areas

Slayton Hill Road Reconstruction
City of Lebanon, NH
Slayton Hill Road Typical Section

Slayton Hill Road Reconstruction
City of Lebanon, NH
Slayton Hill Road – Sta. 0+00 to 21+50
(Dulac to #53)

Slayton Hill Road Reconstruction
City of Lebanon, NH
Retaining Wall #1

Slayton Hill Road Reconstruction
City of Lebanon, NH
Slayton Hill Road – Sta. 21+50 to 43+50
(#53 to #121)

Slayton Hill Road Reconstruction
City of Lebanon, NH
Profile Change

Slayton Hill Road Reconstruction
City of Lebanon, NH
Slayton Hill Road – Sta. 43+50 to 64+50
(#121 to #141)

Slayton Hill Road Reconstruction
City of Lebanon, NH
Slayton Hill Road – Sta. 64+50 to 86+00
(#141 to #183)

Slayton Hill Road Reconstruction
City of Lebanon, NH
RetainingWall #3

Slayton Hill Road Reconstruction
City of Lebanon, NH
Slayton Hill Road – Sta. 86+00 to
Dunsinane (#183 to Dunsinane)

Slayton Hill Road Reconstruction
City of Lebanon, NH
Dulac Street

Slayton Hill Road Reconstruction
City of Lebanon, NH
Dulac Street

Slayton Hill Road Reconstruction
City of Lebanon, NH
Dulac Street Typical Section

Slayton Hill Road Reconstruction
City of Lebanon, NH
Next Steps
• Continue Design
Meet individually with abutters
Incorporate public comment

• Permitting
Coordination with relevant Local, State and Federal agencies
Dredge and Fill Permit, Shoreland Protection, Alteration of Terrain

Scenic Road Designation

• Final Design
Develop plans for bidding
Contract book and specifications

• Advertise
Accept Contractor bids

• Construction
Slayton Hill Road Reconstruction
City of Lebanon, NH
Individual Meetings
• Purpose
Discuss direct impacts to individual properties
Present ROW or easement acquisition offers

• Times
12 PM to 8 PM windows
Monday, March 3
Wednesday, March 5
Monday, March 10
Wednesday, March 12

20 minutes each
Sign up tonight with Tina
Slayton Hill Road Reconstruction
City of Lebanon, NH
ROW Process
• Follow NHDOT LPA/Federal Guidelines
• Permanent Impacts
Maintenance for drainage
Retaining walls

• Temporary Impacts
Slope and clearing work
Arborist

Driveway tie-ins

• City to assess property values
• Compensation offer
Monetary compensation
Slayton Hill Road Reconstruction
City of Lebanon, NH
Construction
• Duration
Major construction activities - one season, May to
November
Final overlay, clean up work – Spring of 2015

• Traffic Management
Full Access to houses, emergency vehicles at all times
Road closures allowable July and August
Minimum one-lane open during school year (7 AM to 9
AM and 3 PM to 5 PM)
Slayton Hill Road Reconstruction
City of Lebanon, NH
Timeline – Full Reconstruction
• Meet with Public, Walk-about, discuss impacts
September/October

• Final design
February - April

• Permitting
February - April

• Bid Project
May

• Construction
May - November 2014
Slayton Hill Road Reconstruction
City of Lebanon, NH
Individual Group Break Out
• Follow Up Questions
http://ask.lebnh.net/

• Contact Information
Greg Lewis, City Manager
greg.lewis@lebcity.com
Phone: 603-448-4220

Mike Lavalla, Director of Public Works
Mike.lavalla@lebcity.com
Phone: 603-448-3112

David McNamara, FST Project Manager
dmcnamara@fstinc.com
Phone: 603-669-2000
Slayton Hill Road Reconstruction
City of Lebanon, NH

More Related Content

What's hot

Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectCommunity Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
Fairfax County
 
Historic Jail Roof Replacement
Historic Jail Roof ReplacementHistoric Jail Roof Replacement
Historic Jail Roof Replacement
Fairfax County
 
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Fairfax County
 
CPAC Meeting 9-8-04
CPAC Meeting 9-8-04CPAC Meeting 9-8-04
CPAC Meeting 9-8-04HartTWI
 
Clairemont CPG Ad Hoc Subcommittee Meeting
Clairemont CPG Ad Hoc Subcommittee MeetingClairemont CPG Ad Hoc Subcommittee Meeting
Clairemont CPG Ad Hoc Subcommittee Meeting
CirculateSD
 
Gardiner East EA Public Forum 3 (Feb062014) - panels
Gardiner East EA Public Forum 3 (Feb062014) - panelsGardiner East EA Public Forum 3 (Feb062014) - panels
Gardiner East EA Public Forum 3 (Feb062014) - panelsGardinerEast
 
Retrofitting Trees in an Urban Corridor: Perspectives from a Designer, a Fore...
Retrofitting Trees in an Urban Corridor: Perspectives from a Designer, a Fore...Retrofitting Trees in an Urban Corridor: Perspectives from a Designer, a Fore...
Retrofitting Trees in an Urban Corridor: Perspectives from a Designer, a Fore...
Arbor Day Foundation
 
Alafaya presentation 3 3-11
Alafaya presentation 3 3-11Alafaya presentation 3 3-11
Alafaya presentation 3 3-11JennThomp
 
Tucker Avenue Neighborhood Stormwater Project Community Meeting Sept 19, 2019
Tucker Avenue Neighborhood Stormwater Project Community Meeting Sept 19, 2019Tucker Avenue Neighborhood Stormwater Project Community Meeting Sept 19, 2019
Tucker Avenue Neighborhood Stormwater Project Community Meeting Sept 19, 2019
Fairfax County
 
Balboa Avenue Station Presentation
Balboa Avenue Station PresentationBalboa Avenue Station Presentation
Balboa Avenue Station Presentation
CirculateSD
 
Pb Community Planning Group May 24
Pb Community Planning Group May 24Pb Community Planning Group May 24
Pb Community Planning Group May 24
CirculateSD
 
River Road Meeting 3-10-05
River Road Meeting 3-10-05River Road Meeting 3-10-05
River Road Meeting 3-10-05HartTWI
 
SASHTOSoutheastern Association of State Highway and Transportation Officials ...
SASHTOSoutheastern Association of State Highway and Transportation Officials ...SASHTOSoutheastern Association of State Highway and Transportation Officials ...
SASHTOSoutheastern Association of State Highway and Transportation Officials ...
James Gregg
 
City Council Feb. 5, 2013 river project update
City Council Feb. 5, 2013 river project updateCity Council Feb. 5, 2013 river project update
City Council Feb. 5, 2013 river project updateCity of San Angelo Texas
 
Clairemont subcommittee presentation 07.19.17
Clairemont subcommittee presentation  07.19.17Clairemont subcommittee presentation  07.19.17
Clairemont subcommittee presentation 07.19.17
CirculateSD
 
Glen Road Pedestrian Bridge - for Design Review Panel July 2017
Glen Road Pedestrian Bridge - for Design Review Panel July 2017Glen Road Pedestrian Bridge - for Design Review Panel July 2017
Glen Road Pedestrian Bridge - for Design Review Panel July 2017
Jason Diceman
 
Pacific Beach ad hoc subcommittee presentation 11/3/16
Pacific Beach ad hoc subcommittee presentation 11/3/16Pacific Beach ad hoc subcommittee presentation 11/3/16
Pacific Beach ad hoc subcommittee presentation 11/3/16
omedina91
 

What's hot (20)

City council 7 16-13 river project
City council 7 16-13 river projectCity council 7 16-13 river project
City council 7 16-13 river project
 
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectCommunity Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
 
Historic Jail Roof Replacement
Historic Jail Roof ReplacementHistoric Jail Roof Replacement
Historic Jail Roof Replacement
 
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
 
CPAC Meeting 9-8-04
CPAC Meeting 9-8-04CPAC Meeting 9-8-04
CPAC Meeting 9-8-04
 
Clairemont CPG Ad Hoc Subcommittee Meeting
Clairemont CPG Ad Hoc Subcommittee MeetingClairemont CPG Ad Hoc Subcommittee Meeting
Clairemont CPG Ad Hoc Subcommittee Meeting
 
Gardiner East EA Public Forum 3 (Feb062014) - panels
Gardiner East EA Public Forum 3 (Feb062014) - panelsGardiner East EA Public Forum 3 (Feb062014) - panels
Gardiner East EA Public Forum 3 (Feb062014) - panels
 
Retrofitting Trees in an Urban Corridor: Perspectives from a Designer, a Fore...
Retrofitting Trees in an Urban Corridor: Perspectives from a Designer, a Fore...Retrofitting Trees in an Urban Corridor: Perspectives from a Designer, a Fore...
Retrofitting Trees in an Urban Corridor: Perspectives from a Designer, a Fore...
 
Alafaya presentation 3 3-11
Alafaya presentation 3 3-11Alafaya presentation 3 3-11
Alafaya presentation 3 3-11
 
Tucker Avenue Neighborhood Stormwater Project Community Meeting Sept 19, 2019
Tucker Avenue Neighborhood Stormwater Project Community Meeting Sept 19, 2019Tucker Avenue Neighborhood Stormwater Project Community Meeting Sept 19, 2019
Tucker Avenue Neighborhood Stormwater Project Community Meeting Sept 19, 2019
 
Balboa Avenue Station Presentation
Balboa Avenue Station PresentationBalboa Avenue Station Presentation
Balboa Avenue Station Presentation
 
Pb Community Planning Group May 24
Pb Community Planning Group May 24Pb Community Planning Group May 24
Pb Community Planning Group May 24
 
River Road Meeting 3-10-05
River Road Meeting 3-10-05River Road Meeting 3-10-05
River Road Meeting 3-10-05
 
SASHTOSoutheastern Association of State Highway and Transportation Officials ...
SASHTOSoutheastern Association of State Highway and Transportation Officials ...SASHTOSoutheastern Association of State Highway and Transportation Officials ...
SASHTOSoutheastern Association of State Highway and Transportation Officials ...
 
City Council Feb. 5, 2013 river project update
City Council Feb. 5, 2013 river project updateCity Council Feb. 5, 2013 river project update
City Council Feb. 5, 2013 river project update
 
State of the City 2012
State of the City 2012State of the City 2012
State of the City 2012
 
CV Mirani Sb Color
CV Mirani Sb ColorCV Mirani Sb Color
CV Mirani Sb Color
 
Clairemont subcommittee presentation 07.19.17
Clairemont subcommittee presentation  07.19.17Clairemont subcommittee presentation  07.19.17
Clairemont subcommittee presentation 07.19.17
 
Glen Road Pedestrian Bridge - for Design Review Panel July 2017
Glen Road Pedestrian Bridge - for Design Review Panel July 2017Glen Road Pedestrian Bridge - for Design Review Panel July 2017
Glen Road Pedestrian Bridge - for Design Review Panel July 2017
 
Pacific Beach ad hoc subcommittee presentation 11/3/16
Pacific Beach ad hoc subcommittee presentation 11/3/16Pacific Beach ad hoc subcommittee presentation 11/3/16
Pacific Beach ad hoc subcommittee presentation 11/3/16
 

Viewers also liked

Clase enilsa acosta
Clase enilsa acostaClase enilsa acosta
Clase enilsa acosta
eniacosta2016
 
Beirut Mapping Party Presentation
Beirut Mapping Party PresentationBeirut Mapping Party Presentation
Beirut Mapping Party Presentation
bmichel2k
 
Jumps and Breaks: Reading the Grays of the Rental Market in Naba’a (Beirut)
Jumps and Breaks: Reading the Grays of the Rental Market in Naba’a (Beirut)Jumps and Breaks: Reading the Grays of the Rental Market in Naba’a (Beirut)
Jumps and Breaks: Reading the Grays of the Rental Market in Naba’a (Beirut)
Ayman Jalloul
 
Ordem De Eliminação A Fazenda 6
Ordem De Eliminação A Fazenda 6Ordem De Eliminação A Fazenda 6
Ordem De Eliminação A Fazenda 6
baruc100
 
Urban
UrbanUrban
Urban planning spring 2014
Urban planning spring 2014Urban planning spring 2014
Urban planning spring 2014
AUB
 
Mechanic Street Improvement Project Presentation
Mechanic Street Improvement Project PresentationMechanic Street Improvement Project Presentation
Mechanic Street Improvement Project Presentation
City of Lebanon
 
Final Year Project
Final Year ProjectFinal Year Project
Final Year ProjectK B
 
Effective research for civil & environmental engineering
Effective research for civil & environmental engineeringEffective research for civil & environmental engineering
Effective research for civil & environmental engineering
AUB
 

Viewers also liked (10)

Clase enilsa acosta
Clase enilsa acostaClase enilsa acosta
Clase enilsa acosta
 
Beirut Mapping Party Presentation
Beirut Mapping Party PresentationBeirut Mapping Party Presentation
Beirut Mapping Party Presentation
 
K4 products
K4 productsK4 products
K4 products
 
Jumps and Breaks: Reading the Grays of the Rental Market in Naba’a (Beirut)
Jumps and Breaks: Reading the Grays of the Rental Market in Naba’a (Beirut)Jumps and Breaks: Reading the Grays of the Rental Market in Naba’a (Beirut)
Jumps and Breaks: Reading the Grays of the Rental Market in Naba’a (Beirut)
 
Ordem De Eliminação A Fazenda 6
Ordem De Eliminação A Fazenda 6Ordem De Eliminação A Fazenda 6
Ordem De Eliminação A Fazenda 6
 
Urban
UrbanUrban
Urban
 
Urban planning spring 2014
Urban planning spring 2014Urban planning spring 2014
Urban planning spring 2014
 
Mechanic Street Improvement Project Presentation
Mechanic Street Improvement Project PresentationMechanic Street Improvement Project Presentation
Mechanic Street Improvement Project Presentation
 
Final Year Project
Final Year ProjectFinal Year Project
Final Year Project
 
Effective research for civil & environmental engineering
Effective research for civil & environmental engineeringEffective research for civil & environmental engineering
Effective research for civil & environmental engineering
 

Similar to Slayton Hill Road Reconstruction Presentation

Columbia Road/Randolph Court Stream Restoration July 2015
Columbia Road/Randolph Court Stream Restoration July 2015Columbia Road/Randolph Court Stream Restoration July 2015
Columbia Road/Randolph Court Stream Restoration July 2015
Fairfax County
 
Lebanon CSO 11 Public Meeting Presentation
Lebanon CSO 11 Public Meeting PresentationLebanon CSO 11 Public Meeting Presentation
Lebanon CSO 11 Public Meeting Presentation
City of Lebanon
 
Fairhill/MLK pre-construction public meeting 3-25-2015
Fairhill/MLK pre-construction public meeting 3-25-2015Fairhill/MLK pre-construction public meeting 3-25-2015
Fairhill/MLK pre-construction public meeting 3-25-2015
Northeast Ohio Regional Sewer District
 
Pic 2 panels june 23 2015
Pic 2 panels june 23 2015Pic 2 panels june 23 2015
Pic 2 panels june 23 2015
Toronto Public Consultation Unit
 
Public Meeting #2 Information Materials
Public Meeting #2 Information MaterialsPublic Meeting #2 Information Materials
Public Meeting #2 Information Materials
Toronto Public Consultation Unit
 
91 Design Build Update
91 Design Build Update91 Design Build Update
Nov. 18 Council Meeting: Local Project Updates
Nov. 18 Council Meeting:  Local Project UpdatesNov. 18 Council Meeting:  Local Project Updates
Nov. 18 Council Meeting: Local Project Updates
City of Corona
 
Okeechobee Road from Krome Avenue to NW 79 Avenue PD&E Study presentation, Ju...
Okeechobee Road from Krome Avenue to NW 79 Avenue PD&E Study presentation, Ju...Okeechobee Road from Krome Avenue to NW 79 Avenue PD&E Study presentation, Ju...
Okeechobee Road from Krome Avenue to NW 79 Avenue PD&E Study presentation, Ju...
Miami-Dade Transportation Planning Organization
 
Gardiner short briefing package
Gardiner   short briefing packageGardiner   short briefing package
Gardiner short briefing package
WaterfrontTO
 
Belmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingBelmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meeting
VDOT Northern Virginia
 
Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Tucker Avenue Neighborhood - Community Meeting 3-11-2020Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Fairfax County
 
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design Review
Tucker Avenue Neighborhood  Stormwater Improvement Preliminary Design ReviewTucker Avenue Neighborhood  Stormwater Improvement Preliminary Design Review
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design Review
Fairfax County
 
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
City of Corona
 
Suggested fine-tuning of bridge and park designs to best activate the Provide...
Suggested fine-tuning of bridge and park designs to best activate the Provide...Suggested fine-tuning of bridge and park designs to best activate the Provide...
Suggested fine-tuning of bridge and park designs to best activate the Provide...
Barnaby Evans
 
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...
Fairfax County
 
Bradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit ProjectBradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit Project
Fairfax County
 
Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017
Crosstown TO
 
Public Forum 3 - Presentation (Feb 6_2014)
Public Forum 3 - Presentation (Feb 6_2014)Public Forum 3 - Presentation (Feb 6_2014)
Public Forum 3 - Presentation (Feb 6_2014)GardinerEast
 
Campbellford Bridge Detailed Design Council Update.pdf
Campbellford Bridge Detailed Design Council Update.pdfCampbellford Bridge Detailed Design Council Update.pdf
Campbellford Bridge Detailed Design Council Update.pdf
KatrinaMcCullough2
 

Similar to Slayton Hill Road Reconstruction Presentation (20)

Columbia Road/Randolph Court Stream Restoration July 2015
Columbia Road/Randolph Court Stream Restoration July 2015Columbia Road/Randolph Court Stream Restoration July 2015
Columbia Road/Randolph Court Stream Restoration July 2015
 
Lebanon CSO 11 Public Meeting Presentation
Lebanon CSO 11 Public Meeting PresentationLebanon CSO 11 Public Meeting Presentation
Lebanon CSO 11 Public Meeting Presentation
 
Fairhill/MLK pre-construction public meeting 3-25-2015
Fairhill/MLK pre-construction public meeting 3-25-2015Fairhill/MLK pre-construction public meeting 3-25-2015
Fairhill/MLK pre-construction public meeting 3-25-2015
 
Pic 2 panels june 23 2015
Pic 2 panels june 23 2015Pic 2 panels june 23 2015
Pic 2 panels june 23 2015
 
Public Meeting #2 Information Materials
Public Meeting #2 Information MaterialsPublic Meeting #2 Information Materials
Public Meeting #2 Information Materials
 
91 Design Build Update
91 Design Build Update91 Design Build Update
91 Design Build Update
 
Nov. 18 Council Meeting: Local Project Updates
Nov. 18 Council Meeting:  Local Project UpdatesNov. 18 Council Meeting:  Local Project Updates
Nov. 18 Council Meeting: Local Project Updates
 
Okeechobee Road from Krome Avenue to NW 79 Avenue PD&E Study presentation, Ju...
Okeechobee Road from Krome Avenue to NW 79 Avenue PD&E Study presentation, Ju...Okeechobee Road from Krome Avenue to NW 79 Avenue PD&E Study presentation, Ju...
Okeechobee Road from Krome Avenue to NW 79 Avenue PD&E Study presentation, Ju...
 
Gardiner short briefing package
Gardiner   short briefing packageGardiner   short briefing package
Gardiner short briefing package
 
Belmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meetingBelmont Ridge Road Pardon Our Dust meeting
Belmont Ridge Road Pardon Our Dust meeting
 
Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Tucker Avenue Neighborhood - Community Meeting 3-11-2020Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Tucker Avenue Neighborhood - Community Meeting 3-11-2020
 
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design Review
Tucker Avenue Neighborhood  Stormwater Improvement Preliminary Design ReviewTucker Avenue Neighborhood  Stormwater Improvement Preliminary Design Review
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design Review
 
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
Jan. 21, 2015 City Council Presentation 2015 Capital Improvement Projects
 
Suggested fine-tuning of bridge and park designs to best activate the Provide...
Suggested fine-tuning of bridge and park designs to best activate the Provide...Suggested fine-tuning of bridge and park designs to best activate the Provide...
Suggested fine-tuning of bridge and park designs to best activate the Provide...
 
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...
 
Measure a foc 080713
Measure a foc 080713Measure a foc 080713
Measure a foc 080713
 
Bradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit ProjectBradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit Project
 
Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017
 
Public Forum 3 - Presentation (Feb 6_2014)
Public Forum 3 - Presentation (Feb 6_2014)Public Forum 3 - Presentation (Feb 6_2014)
Public Forum 3 - Presentation (Feb 6_2014)
 
Campbellford Bridge Detailed Design Council Update.pdf
Campbellford Bridge Detailed Design Council Update.pdfCampbellford Bridge Detailed Design Council Update.pdf
Campbellford Bridge Detailed Design Council Update.pdf
 

More from City of Lebanon

West Lebanon Village Charrette Presentation
West Lebanon Village Charrette PresentationWest Lebanon Village Charrette Presentation
West Lebanon Village Charrette Presentation
City of Lebanon
 
Franchise Agreement - Comcast Cable
Franchise Agreement - Comcast CableFranchise Agreement - Comcast Cable
Franchise Agreement - Comcast Cable
City of Lebanon
 
Draft Briefing Packages - Lebanon Airport Master Plan
Draft Briefing Packages - Lebanon Airport Master PlanDraft Briefing Packages - Lebanon Airport Master Plan
Draft Briefing Packages - Lebanon Airport Master Plan
City of Lebanon
 
City Manager Search - Lebanon, NH
City Manager Search - Lebanon, NHCity Manager Search - Lebanon, NH
City Manager Search - Lebanon, NH
City of Lebanon
 
Downtown Lebanon Visioning Study and Tunnel Project
Downtown Lebanon Visioning Study and Tunnel ProjectDowntown Lebanon Visioning Study and Tunnel Project
Downtown Lebanon Visioning Study and Tunnel Project
City of Lebanon
 
CSO 10 Public Meeting Presentation
CSO 10 Public Meeting PresentationCSO 10 Public Meeting Presentation
CSO 10 Public Meeting Presentation
City of Lebanon
 

More from City of Lebanon (6)

West Lebanon Village Charrette Presentation
West Lebanon Village Charrette PresentationWest Lebanon Village Charrette Presentation
West Lebanon Village Charrette Presentation
 
Franchise Agreement - Comcast Cable
Franchise Agreement - Comcast CableFranchise Agreement - Comcast Cable
Franchise Agreement - Comcast Cable
 
Draft Briefing Packages - Lebanon Airport Master Plan
Draft Briefing Packages - Lebanon Airport Master PlanDraft Briefing Packages - Lebanon Airport Master Plan
Draft Briefing Packages - Lebanon Airport Master Plan
 
City Manager Search - Lebanon, NH
City Manager Search - Lebanon, NHCity Manager Search - Lebanon, NH
City Manager Search - Lebanon, NH
 
Downtown Lebanon Visioning Study and Tunnel Project
Downtown Lebanon Visioning Study and Tunnel ProjectDowntown Lebanon Visioning Study and Tunnel Project
Downtown Lebanon Visioning Study and Tunnel Project
 
CSO 10 Public Meeting Presentation
CSO 10 Public Meeting PresentationCSO 10 Public Meeting Presentation
CSO 10 Public Meeting Presentation
 

Recently uploaded

Resolutions-Key-Interventions-28-May-2024.pdf
Resolutions-Key-Interventions-28-May-2024.pdfResolutions-Key-Interventions-28-May-2024.pdf
Resolutions-Key-Interventions-28-May-2024.pdf
bhavenpr
 
03062024_First India Newspaper Jaipur.pdf
03062024_First India Newspaper Jaipur.pdf03062024_First India Newspaper Jaipur.pdf
03062024_First India Newspaper Jaipur.pdf
FIRST INDIA
 
Preview of Court Document for Iseyin community
Preview of Court Document for Iseyin communityPreview of Court Document for Iseyin community
Preview of Court Document for Iseyin community
contact193699
 
What Ukraine Has Lost During Russia’s Invasion
What Ukraine Has Lost During Russia’s InvasionWhat Ukraine Has Lost During Russia’s Invasion
What Ukraine Has Lost During Russia’s Invasion
LUMINATIVE MEDIA/PROJECT COUNSEL MEDIA GROUP
 
Hindustan Insider 2nd edition release now
Hindustan Insider 2nd edition release nowHindustan Insider 2nd edition release now
Hindustan Insider 2nd edition release now
hindustaninsider22
 
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
CIkumparan
 
Letter-from-ECI-to-MeiTY-21st-march-2024.pdf
Letter-from-ECI-to-MeiTY-21st-march-2024.pdfLetter-from-ECI-to-MeiTY-21st-march-2024.pdf
Letter-from-ECI-to-MeiTY-21st-march-2024.pdf
bhavenpr
 
01062024_First India Newspaper Jaipur.pdf
01062024_First India Newspaper Jaipur.pdf01062024_First India Newspaper Jaipur.pdf
01062024_First India Newspaper Jaipur.pdf
FIRST INDIA
 
04062024_First India Newspaper Jaipur.pdf
04062024_First India Newspaper Jaipur.pdf04062024_First India Newspaper Jaipur.pdf
04062024_First India Newspaper Jaipur.pdf
FIRST INDIA
 
Hogan Comes Home: an MIA WWII crewman is returned
Hogan Comes Home: an MIA WWII crewman is returnedHogan Comes Home: an MIA WWII crewman is returned
Hogan Comes Home: an MIA WWII crewman is returned
rbakerj2
 
EED - The Container Port PERFORMANCE INDEX 2023
EED - The Container Port PERFORMANCE INDEX 2023EED - The Container Port PERFORMANCE INDEX 2023
EED - The Container Port PERFORMANCE INDEX 2023
El Estrecho Digital
 
Codes n Conventionss copy (1).paaaaaaptx
Codes n Conventionss copy (1).paaaaaaptxCodes n Conventionss copy (1).paaaaaaptx
Codes n Conventionss copy (1).paaaaaaptx
ZackSpencer3
 
Gabriel Whitley's Motion Summary Judgment
Gabriel Whitley's Motion Summary JudgmentGabriel Whitley's Motion Summary Judgment
Gabriel Whitley's Motion Summary Judgment
Abdul-Hakim Shabazz
 

Recently uploaded (13)

Resolutions-Key-Interventions-28-May-2024.pdf
Resolutions-Key-Interventions-28-May-2024.pdfResolutions-Key-Interventions-28-May-2024.pdf
Resolutions-Key-Interventions-28-May-2024.pdf
 
03062024_First India Newspaper Jaipur.pdf
03062024_First India Newspaper Jaipur.pdf03062024_First India Newspaper Jaipur.pdf
03062024_First India Newspaper Jaipur.pdf
 
Preview of Court Document for Iseyin community
Preview of Court Document for Iseyin communityPreview of Court Document for Iseyin community
Preview of Court Document for Iseyin community
 
What Ukraine Has Lost During Russia’s Invasion
What Ukraine Has Lost During Russia’s InvasionWhat Ukraine Has Lost During Russia’s Invasion
What Ukraine Has Lost During Russia’s Invasion
 
Hindustan Insider 2nd edition release now
Hindustan Insider 2nd edition release nowHindustan Insider 2nd edition release now
Hindustan Insider 2nd edition release now
 
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
 
Letter-from-ECI-to-MeiTY-21st-march-2024.pdf
Letter-from-ECI-to-MeiTY-21st-march-2024.pdfLetter-from-ECI-to-MeiTY-21st-march-2024.pdf
Letter-from-ECI-to-MeiTY-21st-march-2024.pdf
 
01062024_First India Newspaper Jaipur.pdf
01062024_First India Newspaper Jaipur.pdf01062024_First India Newspaper Jaipur.pdf
01062024_First India Newspaper Jaipur.pdf
 
04062024_First India Newspaper Jaipur.pdf
04062024_First India Newspaper Jaipur.pdf04062024_First India Newspaper Jaipur.pdf
04062024_First India Newspaper Jaipur.pdf
 
Hogan Comes Home: an MIA WWII crewman is returned
Hogan Comes Home: an MIA WWII crewman is returnedHogan Comes Home: an MIA WWII crewman is returned
Hogan Comes Home: an MIA WWII crewman is returned
 
EED - The Container Port PERFORMANCE INDEX 2023
EED - The Container Port PERFORMANCE INDEX 2023EED - The Container Port PERFORMANCE INDEX 2023
EED - The Container Port PERFORMANCE INDEX 2023
 
Codes n Conventionss copy (1).paaaaaaptx
Codes n Conventionss copy (1).paaaaaaptxCodes n Conventionss copy (1).paaaaaaptx
Codes n Conventionss copy (1).paaaaaaptx
 
Gabriel Whitley's Motion Summary Judgment
Gabriel Whitley's Motion Summary JudgmentGabriel Whitley's Motion Summary Judgment
Gabriel Whitley's Motion Summary Judgment
 

Slayton Hill Road Reconstruction Presentation

  • 1. Slayton Hill Road Reconstruction Lebanon, NH February 12, 2014
  • 2. Welcome and Introductions • Greg Lewis – City Manager Ground Rules • Paula Maville – Deputy City Manager Scenic Road Designation • David McNamara – Fay, Spofford, & Thorndike Design Update Slayton Hill Road Reconstruction City of Lebanon, NH
  • 3. Scenic Road Designation • Declaration of Purpose: • Slayton Hill Designated Scenic on 12/15/93 • Impacts to Right-of-Way 88% of stone walls between Dulac & 78 Slayton An additional 44% between 78 Slayton & Dunsinaine 60% of trees (total length of project) will need to be cleared Slayton Hill Road Reconstruction City of Lebanon, NH
  • 4. Scenic Road Designation • One of Two Processes to Undertake §134-5 Effect of Designation as Scenic Road Manager to obtain written consent of the Planning Board after a Public Hearing §134-8 Rescission of Designation of Scenic Road Requires a petition of 10 Persons who are either voters of the City or who own land which abuts the road Reports Solicited from the Planning Board and Conservation Commission Public Hearing held by the City Council Slayton Hill Road Reconstruction City of Lebanon, NH
  • 5. Meeting Objectives • Update on status of project Temporary repairs Complete Permanent reconstruction Design Progress Next Steps • Solicit feedback Scenic Road Designation Present updated design progress Discuss potential property and edge of road impacts due to permanent improvements Slayton Hill Road Reconstruction City of Lebanon, NH
  • 6. Existing Conditions Slayton Hill Road was built into a hillside Ledge and poorly drained soils Slayton Hill Road – Reconstructed in 2001/2002 timeframe Design was restricted by Scenic Road designation and limiting property impacts • Culverts generally replaced with new ADS pipe of the same size • Narrow/shallow swales and underdrains with limited armor in place along uphill side of road • New Standards • • • • Precipitation Data Storm Sizing Slayton Hill Road Reconstruction City of Lebanon, NH
  • 7. Response – Short Term Repairs • City forces Immediate repairs following July 2nd Storm (July) Temporary water main Roadway repairs to allow traffic Intermediate Term (Complete) Repair buried water main Widen road to allow minimum two lanes of traffic Temporary pavement course for winter maintenance Armor washed out ditches Additional culvert to divert flows in lower section Slayton Hill Road Reconstruction City of Lebanon, NH
  • 8. Design • Design Storm 100 year minimum • Culvert sizing Slayton Hill Road Total of 22 cross culverts – 10 are adequately sized – 11 are undersized – 1 new Culvert Dulac Street Total of 3 cross culverts – 2 are undersized – 1 new culvert (twin pipes) Slayton Hill Road Reconstruction City of Lebanon, NH
  • 9. Culvert Sizing – Slayton Hill Road AREA STATION EXISTING CULVERT SIZE PROPOSED CULVERT SIZE AREA STATION EXISTING CULVERT SIZE PROPOSED CULVERT SIZE 1 Intersection w/ Dulac St 18” HDPE 24” RCP 12 56+21 18” HDPE 24” RCP 2A 7+99 18” HDPE 24” RCP 13 56+89 24” HDPE 24” RCP 2B 11+84 ----- 24” RCP 14 61+11 18” HDPE 30” RCP 15 63+11 18” HDPE 24” RCP 16 66+52 24” HDPE 36” RCP 17 75+26 48” HDPE 6-ft x 4-ft Concrete Box 18 82+53 18” HDPE 18” RCP Replace CB with Headwall 19 85+99 18” HDPE 18” RCP Replace CB with Headwall 30” HDPE 30” RCP 3 4 5 6 8 9 12+43 16+00 19+59 20+85 27+98 29+38 2.7-Ft x 2.6-Ft Concrete Box 4-Ft x 4-Ft Concrete Box 18” HDPE / 27.6 24” RCP 15” HDPE 15” RCP 15” HDPE 18” RCP 24” HDPE 18” HDPE 24” RCP 18” RCP Replace CB with Headwall 20 10 33+82 30” HDPE 30” RCP 21 3+72 15” HDPE 15” RCP 11 42+31 24” HDPE Twin 24” RCPs 22 89+18 15” HDPE 15” RCP Slayton Hill Road Reconstruction City of Lebanon, NH
  • 10. Culvert Sizing – Dulac Street AREA STATION EXISTING CULVERT SIZE PROPOSED CULVERT SIZE 23A 202+50 12” HDPE Twin 18” RCPs 23C 206+50 ----- Twin 18” RCPs 23B 209+50 12” HDPE 24” RCP Slayton Hill Road Reconstruction City of Lebanon, NH
  • 11. Design • Ditches Most proposed are V shaped, 1.5’ to 2.0’ deep, 3:1 sideslopes off the road, 2:1 back slopes to match existing ground Lower portion includes a 2’ wide flat bottom Slopes steeper than 10% will be stone lined Slopes flatter than 10% will be grass, with reinforced matting products Underdrains Slayton Hill Road Reconstruction City of Lebanon, NH
  • 12. Design - Tributary Drainage Areas Slayton Hill Road Reconstruction City of Lebanon, NH
  • 13. Slayton Hill Road Typical Section Slayton Hill Road Reconstruction City of Lebanon, NH
  • 14. Slayton Hill Road – Sta. 0+00 to 21+50 (Dulac to #53) Slayton Hill Road Reconstruction City of Lebanon, NH
  • 15. Retaining Wall #1 Slayton Hill Road Reconstruction City of Lebanon, NH
  • 16. Slayton Hill Road – Sta. 21+50 to 43+50 (#53 to #121) Slayton Hill Road Reconstruction City of Lebanon, NH
  • 17. Profile Change Slayton Hill Road Reconstruction City of Lebanon, NH
  • 18. Slayton Hill Road – Sta. 43+50 to 64+50 (#121 to #141) Slayton Hill Road Reconstruction City of Lebanon, NH
  • 19. Slayton Hill Road – Sta. 64+50 to 86+00 (#141 to #183) Slayton Hill Road Reconstruction City of Lebanon, NH
  • 20. RetainingWall #3 Slayton Hill Road Reconstruction City of Lebanon, NH
  • 21. Slayton Hill Road – Sta. 86+00 to Dunsinane (#183 to Dunsinane) Slayton Hill Road Reconstruction City of Lebanon, NH
  • 22. Dulac Street Slayton Hill Road Reconstruction City of Lebanon, NH
  • 23. Dulac Street Slayton Hill Road Reconstruction City of Lebanon, NH
  • 24. Dulac Street Typical Section Slayton Hill Road Reconstruction City of Lebanon, NH
  • 25. Next Steps • Continue Design Meet individually with abutters Incorporate public comment • Permitting Coordination with relevant Local, State and Federal agencies Dredge and Fill Permit, Shoreland Protection, Alteration of Terrain Scenic Road Designation • Final Design Develop plans for bidding Contract book and specifications • Advertise Accept Contractor bids • Construction Slayton Hill Road Reconstruction City of Lebanon, NH
  • 26. Individual Meetings • Purpose Discuss direct impacts to individual properties Present ROW or easement acquisition offers • Times 12 PM to 8 PM windows Monday, March 3 Wednesday, March 5 Monday, March 10 Wednesday, March 12 20 minutes each Sign up tonight with Tina Slayton Hill Road Reconstruction City of Lebanon, NH
  • 27. ROW Process • Follow NHDOT LPA/Federal Guidelines • Permanent Impacts Maintenance for drainage Retaining walls • Temporary Impacts Slope and clearing work Arborist Driveway tie-ins • City to assess property values • Compensation offer Monetary compensation Slayton Hill Road Reconstruction City of Lebanon, NH
  • 28. Construction • Duration Major construction activities - one season, May to November Final overlay, clean up work – Spring of 2015 • Traffic Management Full Access to houses, emergency vehicles at all times Road closures allowable July and August Minimum one-lane open during school year (7 AM to 9 AM and 3 PM to 5 PM) Slayton Hill Road Reconstruction City of Lebanon, NH
  • 29. Timeline – Full Reconstruction • Meet with Public, Walk-about, discuss impacts September/October • Final design February - April • Permitting February - April • Bid Project May • Construction May - November 2014 Slayton Hill Road Reconstruction City of Lebanon, NH
  • 30. Individual Group Break Out • Follow Up Questions http://ask.lebnh.net/ • Contact Information Greg Lewis, City Manager greg.lewis@lebcity.com Phone: 603-448-4220 Mike Lavalla, Director of Public Works Mike.lavalla@lebcity.com Phone: 603-448-3112 David McNamara, FST Project Manager dmcnamara@fstinc.com Phone: 603-669-2000 Slayton Hill Road Reconstruction City of Lebanon, NH