6. Green River Widening Project
• Signs posted fines doubled
• Pavement widening by Christmas
• Two lanes each direction while
completing project
• Sidewalks done by Christmas
• Medians & Landscaping thru
March 2016
7. Letter to AWJV
• Letter to AWJV regarding
– No West Grand Boulevard Ramp Closures until other improvement s complete to accommodate traffic
– Main Street to be restriped from North Grand Boulevard to Fourth Street
– Main Street WB On-Ramp widened as discussed in MOT meeting last several weeks
– Lincoln Avenue widening traffic control be adjusted to work more efficiently
– MOT Sub-Task Force be set up to discuss specific issues of concern to the City
– Lane Closure Chart showing schedule of projected closures throughout limits of the Project
• AWJV has acknowledged our letter
– West Grand Boulevard WB On-Ramp will not be closed until completion of widening of Main Street
WB On-ramp
– Main Street will be restriped by the end of this week
– Lincoln Avenue traffic signal timing has been adjusted for efficient flow of traffic
– MOT Sub-Task Force first meeting was held Tuesday, November 17th, will meet twice each month
10. 1. Grand Boulevard ramps remain open
2. Re-stripe Main Street to 3 lanes prior to final configuration – Late Nov.
SR-91 Project
Local Street Sequencing
11. 1. Grand Boulevard ramps remain open
2. Re-stripe Main Street to 3 lanes prior to final configuration – Late Nov.
3. Restore Lincoln Avenue to all lanes – Early Dec.
SR-91 Project
Local Street Sequencing
12. 1. Grand Boulevard ramps remain open
2. Re-stripe Main Street to increase capacity – Late Nov.
3. Restore Lincoln Avenue to 3 lanes prior to final configuration – Early Dec.
4. New segment of Second Street to connect Vicentia Avenue to Lincoln Avenue-Early Dec.
SR-91 Project
Local Street Sequencing
13. 1. Grand Boulevard ramps remain open
2. Re-stripe Main Street to increase capacity – Late Nov.
3. Restore Lincoln Avenue to 3 lanes prior to final configuration – Early Dec.
4. New segment of Second Street to connect Vicentia Avenue to Lincoln Avenue - Early Dec.
5. Permanent closure of Grand Boulevard WB On-ramp – Mid Dec.
SR-91 Project
Local Street Sequencing
14. SR-91 Project
Modified Eastbound Off-Ramp at Maple Street
• EB Off-Ramp to Maple Street has been temporarily modified
• Still connects to Maple Street at same location, entrance from 91 adjusted
• Is separated by K-rail from Frontage Road
• David Thomas will explain more about upcoming work
Temporary Off-Ramp
Configuration