2. Introduction & Advantages Of PS Module
Project Creation
Creation Of Service PR & Material PR Via PS
Cost Planning
Budgeting
Release Budget
Display Release Budget
Make PO with reference to PR
3. Introduction to PS Module
Project can be broken in to sub parts viz WBS (Work Breakdown Structure),
Network & Activity.
WBS is known as Cost Collector.
A WBS can have several Network.
A Network can have several Activity
This shows
the flow and
sequence of
the project
for WBS ,
Network &
Activity.
4. Advantages Of PS Module
Complete Project Structure can be viewed and monitored in terms of Sub Parts
ie as WBS/Network/Activity, Project Progress can be monitored, Project
Scheduling can be done and monitored , Project Profitability can be viewed.
Materials that needs to be processed for the project can be attached to the
project as Components under Activity.
PR can be created from the PS Module immediately after attaching materials to
the project.
Project specific PR & PO can be viewed in a project specific list for PR & PO.
Project Stock can be monitored and handled properly in terms of Inventory.
Project Budget can be controlled.
Good reports are available to see the comparison between Actual & Budgeted,
costs.
And Lot More…………..
20. CJ20N PROJECT CREATION
SCREEN 11 ( Second Method To Create Activity )
First select
the Network
and then
Click on
Activity
Overview to
create
Activity
25. CJ20N PROJECT CREATION
SCREEN 16 ( Add Component )
Select
Activity, Click
on
Component
Overview to
get this
following
screen to add
Materials to
Activity.
26. CJ20N PROJECT CREATION
SCREEN 17 ( Add Component )
Enter all details in following tabs ,
Material , Requirement Quantity ,
Procurement , Item Category ,
Res. / Pur. Req.
34. CJ20N CREATION OF SERVICE PR VIA PROJECT OR
FROM PS MODULE
Open the pre
created project for
which you need to
create the service
PR or even you can
create a new
project as explained
above as per
requirement.
35. CJ20N CREATION OF SERVICE PR VIA PROJECT OR
FROM PS MODULE
Select Network
After that click
on Activity.
36. CJ20N CREATION OF SERVICE PR VIA PROJECT OR
FROM PS MODULE
In the next
screen click on
“Ext.
Processing”
Tab under
activity.
37. CJ20N CREATION OF SERVICE PR VIA PROJECT OR
FROM PS MODULE
Enter Service
description ,
Click on the
check box and
press enter
38. CJ20N CREATION OF SERVICE PR VIA PROJECT OR
FROM PS MODULE
Enter Service
description ,
Click on the
check box and
press enter
39. CJ20N CREATION OF SERVICE PR VIA PROJECT OR
FROM PS MODULE
After pressing
enter you will
get this
following
screen to enter
details.
40. CJ20N CREATION OF SERVICE PR VIA PROJECT OR
FROM PS MODULE
Enter details
for Material
Group And
Purchase
Group. Press
Enter.
41. CJ20N CREATION OF SERVICE PR VIA PROJECT OR
FROM PS MODULE
After pressing
enter you will
get the
following
screen.
42. CJ20N CREATION OF SERVICE PR VIA PROJECT OR
FROM PS MODULE
Fill these
details as per
requirement
and press
enter.
After that click on
back green arrow to
go to the next
screen
43. CJ20N CREATION OF SERVICE PR VIA PROJECT OR
FROM PS MODULE
In this screen click
on the new created
service activity.
Click on “Extnl
Tab”
This is the Service PR
Number that has been
generated.
44. CJ20N CREATION OF SERVICE PR VIA PROJECT OR
FROM PS MODULE
Click on Save Button
to save the project.
51. CJ40 Cost Planning
This is Planned
Total Value , this
value we are
getting from
Network Cost ie
from the materials
we are attaching to
the activity as
components.
66. CJ32 Budget Release
Click here to select
the row
After selecting row , Go
to edit and click on
Copy View
67. CJ32 Budget Release
This new Pop Up
Window comes up,
here select Current
Budget option
Before selecting an
option see if value
in current budget
column is there,
since you will be
releasing amount
from this current
budget for usage in
the project.
After selecting Current
Budget option click on
this green tick or press
enter.
68. CJ32 Budget Release
After selecting Current
Budget option you get a
next Pop Up Window.
Here you can release
the percentage of
Budget as per your
requirement ie you can
release the complete
100% of budget or X%
of budget as per your
need of the project.
Click on this green tick
or press enter.
69. CJ32 Budget Release
Check this value in
release column , it
should be equal to
your X% value of
your Current
Budget Column
Value.
70. CJ32 Budget Release
Click here to select
the complete row
After selecting row go
to Edit Option and
click on Total Up .
71. CJ32 Budget Release
After that you
will get this Pop
Up window ,
click on this
green tick or
press enter.
75. CJ31 Display Released Budget
Check the values of two columns
Budget and Release. The values
should be as per your calculations.
Budget column should have value
that you have entered as budgeted
value and Release column should
have that X% value that you have
released in CJ32.
88. ME21N Create PO
Click on this check icon
to verify that all details
have been filled
properly then save the
document and get PO
number.
Press this to save
the document.
90. Proposed Project Structure Explanation
We can sub divide the complete project as below in PS :-
WBS For Structure
WBS For Coldform ,
Revenue WBS ( For capturing Invoice Value)
New WBS Structure (Amendments In Quantity & BOQ List)
New WBS Coldform (Amendments In Quantity & BOQ List)
Click to see the Project Structure Hierarchy
92. Additional List Of T-Codes
S_ALR_87013558 – Budget/Actual/Commitment/Assigned Cost
ME5J – List Of Project Related PR
ME2J – List Of Project Related PO
ME21N – Create PO
ME29N – Release PO
MIGO – Do GR
ML81N – Service Entry Against PO
MMBE – Stock Overview
MM60 – Material List
93. Lets Work Out Together And Make Efforts To
Get PS Module Working And Active So That We
Can Cross Many Of Our Hurdles And
Challenges In Our Projects And Its Reports !!!!!