6. Then save as shown below. Click on the highlighted button.
7.
8.
9.
10.
11.
12.
13.
14.
15. To supplement the Budget
Enter transaction code CJ36 highlighted in red.
16. Next Screen will come and we need to put the receiver year.
Receiver year: Current year or Year for which you need to upload budget.
Text name: -
Text: Supplement ENTER
17. Then next screen comes
Fill in receiver WBS element, the amount, the currency and the year.
24. Put the Project Definition: OR/1301. In the below I have selected project definition OR/1301 and Press
Enter
Then next screen comes and then go to edit and the select and select all
30. Process to Return Budget in SAP
Go to CJ 32 and De-release the project definition
Then, CJ 35 to return the budget
Then, again CJ 32 to Release the budget in SAP
CJ32 - Process to De-release Budget in SAP
Put CJ32 transaction code and Press Enter
37. Fill in sender WBS element.
Return → Post
NOTE: Rereleasing is required before posting the Return
DE release (sender) → Post Return → Release (both sender and receiver)
38. CJ32 - Again Release the Project Definition
Edit → Select→ Select All
Edit → Copy View → Current Budget → Overwrite → 100%
Release → Save
CJ32 - Process to Release the Budget in SAP
Put CJ32 transaction code and Press Enter
39. Edit → Select→ Select All
Edit → Copy View → Current Budget
42. Process to Transfer Budget in SAP
Go to CJ 32 and De-release the project definition
Then, CJ 34 to return the budget
Then, again CJ 32 to Release the budget in SAP
CJ32 - Process to De Release the Budget in SAP
Put CJ32 transaction code and Press Enter