Rob Halstead
Head of Risk Management, Crossrail
Risk and Assurance on Crossrail
What is Crossrail?
Risk Management Challenges
Risk and Assurance
Conclusions
Risk and Assurance on Crossrail
What is Crossrail?
A new railway for London
and the south east
Over 100 km from east to
west
24 trains per hour in each
direction
More than 200 million
passenger journey per
annum
Adds 10% to London’s rail
capacity
£14.8bn funding
38 stations served
9 new stations built
42 km new tunnels
8 million cubic metres of spoil
4300+ Parliamentary
commitments
Europe’s largest infrastructure project
14,000 employed
Why Crossrail?
24 trains per hour
200 million journeys per year
£42bn+ benefits
What is Crossrail?
Risk Management Challenges
Risk and Assurance
Conclusions
Risk and Assurance on Crossrail
Managing the project
Risk Management Challenges
Tunnelling
Integrating the Railway
Managing Europe’s Largest Construction Project
The Crossrail Route
Tier 1 Contractors
and others…
Industry Partners
Delivery Partners
Transcend PDP
An industry wide project
Sponsors
Construction on staggering scale
Paddington Bond Street Tottenham Court Road Farringdon Liverpool Street
Whitechapel Canary Wharf WoolwichCustom House
Programme Management
140 main works contracts
40 worksites
10,000 suppliers
1 million activity schedule
Extended to Reading
27 station upgrades
2 major structures
61km of track
179 switches & crossings
150 km OLE
Signalling upgrade
Network Rail surface works
Risk Management at Crossrail
“Managing risk and uncertainty is critical
to the successful delivery of Crossrail”
Andrew Wolstenholme OBE
Chief Executive of Crossrail Limited
Drivers of Risk Management
Delivery
Avoid nasty surprises
Identify opportunities to improve
Head off issues before they impact
Commercial
Ensure that commercial exposure
of the organisation is understood
and managed
Inform allocation of risk between
parties through contracts
Engineering
Monitor the mitigation of risk through
design
Ensure that works are delivered safely
and that output is fit for purpose
Finance
Understand true exposure to risk
and uncertainty
Support investment decisions
through assessment of risk impacts
Risk
Support Delivery : Provide Assurance : Inform Decision Making
RISK MANAGEMENT:
Risk Hierarchy
Risk Governance Risk Reporting
Crossrail
Limited Board
Executive
Committee
Risk Sub-
Committee
Programme
Risk Panel
Delivery
Reviews
Audit
Committee
1) Report
2) Escalate
3) AggregateContractor Risks
Project Risks
Strategic Risks
Programme Risks
Sector Risks
Keeping it simple
Identify Assess Respond
Prioritise by assessing
‘Probability’ and ‘Impact’  Terminate
 Transfer
 Treat
 Tolerate
Uncertainty that mattersRisk is:
Risk Management is:
Tunnelling
Running Tunnels
Running Tunnels
- Paddington to Stratford and
North Kent
- Bored Tunnels 7m diameter
- 30 - 40m depth
- 42km long
- 8 Tunnel Boring Machines
(TBMs)
Station Tunnels
Stations Tunnels
- Platform tunnels, circulation
areas, cross passages
- Sprayed Concrete Lining
(SCL)
- 16km tunnelling
Key Questions
How do we make sure that the
tunnels are safe?
How do we deal with ground
conditions and underground
obstructions?
How do we avoid damage to
buildings and services?
Tunnelling
Tunnelling
Risk Mitigations
Enabling works – diverting and
protecting utilities
Ground treatment
Monitoring
Risk management
(AIB Code of practice for risk
management in underground
construction)
People, process, culture
Tottenham Court Road
Liverpool Street
Tunnelling progress to date
Running tunnels:
Station tunnels:
43km 99% complete
17km 78% complete
Railway Integration
Station Fit Out
Under Platform Services Area
Station Structure
Track Systems
Traction Power &
Overhead Line
Equipment
Emergency
Walkway
Gravity Drainage
HV Power
LV Power
Tunnel Lighting
Communications
& Control
Radio Systems
Signalling
PlatformDoors
Tunnel Ventilation
Pumped
Drainage
Pump
Smoke Extract
Fire Detection
Station
Ventilation
Station Lighting Signage
Passenger
Information
CCTV
PA / VA
HelpPoint
Fire Main Station Cable
Management
System
Station Systems
Automatic Fare
Collection
Lifts & Escalators
Station
Management
System
Station Heating,
Cooling and Air
Conditioning
Route Wide Railway Infrastructure
Route Control
Centre
Back Up Control
Facility
Bulk Supply
Points
Auto Trans-
former Sites
Depots &
Stabling
Rolling Stock
Paddington
Railway and
Tunnel Systems
Railway Systems
Rolling Stock
200m long trains
1,500 seated and
standing passengers
per train at peak times
Regenerates energy
during braking (major
savings in energy and
CO2 emissions)
Railway Integration Components
Systems Integration
Railway Integration – Central Section
Railway Integration – end to end
Operator, Maintainer, Infrastructure
Manager Readiness
Testing and Commissioning
Handover
Technical Assurance
8323 Railway fails to perform as intended / required by Sponsors
Critical non performances by key players means Railway fails to perform as intended / required by Sponsors
Howard Smith
6151 Failure to integrate railway [with NR]
Chris Sexton
7851 An integrated railway is not delivered delaying Railway
opening
Chris Sexton
6153 Delayed
acceptance of
stations and
railway systems by
IM and other key
stakeholders
Chris Sexton
6827 Insufficient resilience
of the railway in
operational service.
Programme
Level
Provisionof technical
assurance evidence to
satisfy IMs
Management of handover
872 Failure to manage
Standards Baseline (Rail
Systems)
Failure to execute Trial
Operations successfully
Project
Level
Failure to capture
Operations and Maintenance
requirements in procured
works
Failure to integrate CTOC or
other TOCs
1809 The railway is not delivered for technical reasons (Stages 1 - 5)
“1. Failure to integrate the system”
Simon Wright
Strategic
Level
6923 Operators and
Infrastructure Managers
may not be ready to take
the railway into operation
resulting in delay to the
railway opening.
Howard Smith
11497 The railway service
cannot be operated effectively
at opening because of other
rail operator/ regulator issues
Howard Smith
Failure to deliver Requirements
Failure to exploit “smart
stations” / Digital Railway
opportunities
Operational integration with
NR
Management of technical
interfaces between
systems and contracts
Integration with Rolling
Stock
Failure to integrate with
LUL
Failure to execute or
integrate the test and
commissioning plan
Failure to manage the
governance /
relationships with other
parties
Failure to manage
Railway Safety risk
transfer and mitigation
with Operators
5980 (RI) Failure to
implement the
Signalling System
effectively
Chris Sexton
> Development of the
fringe with NR signalling
> Complexity of
integrating ATO/ATP
> Provision of a signalling
system compatible with
the Crossrail train in the
Heathrow Tunnel
> Integration into a single
Driver DMI
> Development required
to chosen signalling
system to integrate with
NR control centres
> Signalling principles
require further
unforeseen development
6826 Failure to meet
Operators requirements
(Operational, Maintenance,
Safety, Performance)
Jeremy Bates
883 Unable to obtain safety
approval for the railway
7984 Comments/Objection
by ORR on the Construction
and Commissioning Rulebook
principles
11739 The testing and
commissioning strategy
may not be effectively
aligned with the planned
permanent and
temporary power
provision
12561 Operational Readiness –
being ready to put the output
from Crossrail delivery and the
RSD into full operational
service
Howard Smith
Currently owned by J Bates –
would need to be re-assigned and
promoted to Programme Risk
Promote to Strategic Level and assign
to Simon Wright or Andrew
Wolstenholme
Promote to Strategic
Level
Currently a
Programme Risk
TBD The railway service
cannot be operated
effectively because regulator
fails to approve Crossrail
Simon Wright
2611, 8395 RCC building
6957 Changes to NR
demarcation at PML
Lack of integration with NR’s
test and commissioning plan
Lack of integration with NR’s
test and commissioning plan
1000, 872, 13286
6135 On Network Works interface
with Network Rail projects
Matt White
14090 NR Interfacing project
to develop and deliver ETCS
may encounter technical,
operational and schedule
challenges
1994 Continuing evolution of NR
signalling
7622 Network Rail/TOC projects
conflict with CRL programme
commissioning requirements
5981 Provision of an ATP system
(ETCS) in the Heathrow Tunnels
14090 NR Interfacing project to
develop and deliver ETCS may
encounter technical, operational
and schedule challenges
GW works integration
South East Section works
integration
Eastern works
integration
Systems works
integration
7489 Platform heights on GE
routes are above standard and
CRL may not be able to satisfy
level-boarding gauge clearance
requirements.
8115 – Constraints of legacy
surface station platforms may
give rise to an inability to install
transmission systems for Driver
Only Operated CCTV
10296 Lack of interface control
between D&B for station fit-
out, MEP, architectural and
systemwide.
5900 Floating slab track
interaction with rolling stock.
10471 PSD Entrapment
13159 Integration of PED and
PES design solution
13159 Integration of PED and
PES design solution
8516 Definition and
coordination of interfaces:
Civils to Systemwide
7490, 6822 Insufficient time
for rolling stock testing
6305 Insufficient resources for
commissioning
9728 Signalling Integration /
Commissioning issues at
interface with national
network
7622 Commissioning of
railway systems at the
interfaces with the national
network.
7982 Delays to station
(systemwide) systems testing
11739 The testing and
commissioning strategy may
not be effectively aligned
with the planned permanent
and temporary power
provision
11473 Inadequacy of temp
power supply
1994 Signalling project delays
7829 CIS not integrated with NR
On Network Stations
2829, 5381 Western works –
integration
9098 Network Rail delivery /
interfaces at OOC
10826 Stage 2: Infrastructure
(including Depot, Heathrow
ETCS, Paddington platform
works) and integration with
GW signalling is not available
10725 Platform heights on GW
routes are above standard and
CRL may not be able to satisfy
level-boarding gauge clearance
requirements.
5758 NR interface at
Plumstead
14024 ICDs may be incomplete,
or out-of-date, leading to
scope gaps delaying
programme
2024 IMs lose confidence in the
CRL Technical Authority and set
up their own independent
assurance system
7459, 5090 Lack of clear safety
assurance documentation from
Crossrail to IM.
4547 Inefficient submission and
review procedures
7981 RIR CSM does not deliver
sufficient safety justification
evidence to provide safety
assurance
5957 Crossrail 3D design model
may not be kept updated
11039 Late mobilisation of IM
resources
CRL fails to provide adequate
evidence as part of handover
process
CRL fails to provide adequate
evidence as part of handover
process
6990 Failure to fulfil PDA
Requirements in relation to
Handover
6286 Failure to provide adequate
test & commissioning evidence
Failure to demonstrate
achievement of Substantial
Completion Criteria as defined in
PDA to Sponsors.
Failure to demonstrate
achievement of Substantial
Completion Criteria as defined in
PDA to Sponsors.
10471 Potential entrapment
issue
8115 DOO CCTV
7489, 10725 Level boarding,
stepping distances & Gauge
clearance – NR stations
7985 Impact of energisation on
neighbouring systems - EMC
2002 Integrated Station
Management Systems at LU
interchange stations (Stations
Ops Rooms)
CRL CIS not integrated with
existing LU CIS
CRL CIS not integrated with
existing LU CIS
9548 Maintenance support
services, spares and specialist
plant not procured on time.
Track access / maintenance
assumptions not aligned to 95%
PPM
Track access / maintenance
assumptions not aligned to 95%
PPM
Remote condition Monitoring
strategy
Remote condition Monitoring
strategy
3049, 6297, 1032, 10391 LUL /
CRL relationships
RfL Relationship risk?RfL Relationship risk?
13395 Lack of clarity of Urban
Realm/OSD design and
delivery
1008 Mismatch between RfL/LU
requirements and CRL design
1146 Customer Service is not
perceived as being world class.
10544 Timetable not produced in
time
1061 Performance Modelling
inadequate (PPM target not
achieved)
6471 Sponsors, TfL, IPs: Late or
unexpected changes in requirements
integration with NR control centresintegration with NR control centres
10021 Train Operators do not accept
NR Network Change
9290 Insufficient driver resources to
support staged opening of Crossrail
9624 Timing and performance
of Rolling Stock and Depot
could delay opening of
Crossrail
1156 Overrun on Trial Operations
Lack of Operational Readiness
(including Trial Operations and Staff
Training & Familiarisation)
Lack of Operational Readiness
(including Trial Operations and Staff
Training & Familiarisation)
13253 TransitiontoOperations
Martin Buck 11941 Trial operations are insufficient
to demonstrate agreed objectives.
13253 Transition into operations
Management of Asset
information
11838 Lack of clarity over the
approach to specification,
handover and use of Crossrail
Asset Information could delay
asset acceptance
Chris Sexton
Currently a
Programme Risk
2033 Delivery of design (and its
design assumptions) is not
accepted by IMs (NR, RfL and LUL)
Maintenance plan is incorrectMaintenance plan is incorrect
RAM outputs not aligned with
maintenance assumptions
RAM outputs not aligned with
maintenance assumptions
Signalling contingenciesSignalling contingencies
Insufficient timetable flexibility /
recovery time
Insufficient timetable flexibility /
recovery time
Power / Comms resiliencePower / Comms resilience
7622 Commissioning of railway
systems at the interfaces with the
national network.
Paddington OSDPaddington OSD
8089 HS2 interface
Matt White
5960 HS2 interchange station at Old
Oak Common causes change/delay
5960 External interfaces adversely impact the ability to
deliver and subsequently the operation of the railway.
(HS2, BAA, Ilford, OOC)
Howard Smith
CRL Regulatory Approval
8093 There is a risk that the NoBo and
DeBo identify further non compliances
which require derogations and the
developement of NNTRs
10739 Rail Regulator – failure to gain
regulatory consents by NR
CRL submissions to ORR not managedCRL submissions to ORR not managed
RfL Regulatory Approval
RfL submissions to ORR not managedRfL submissions to ORR not managed
Interfaces with other operators
e.g. Freight, First Great
Western
, Abellio Greater Anglia,
Heathrow Express, DLR
Promote from project to
strategic
14395 Ilford speed restrictions14395 Ilford speed restrictions
Demote from strategic
to programme
5981 Provision of ATP system
in Heathrow Tunnel
Header here max 30 characters2014 Effort…
Rolling Stock Programme
Stations Programme
Systemwide Programme
ONW Programme
Installation – Phase 2.1 Commissioning – Phase 2.2-2.3
NR/Railway Systems
Integration
Railway/Tunnel M&E
Systems Integration
Station Systems/LU
Systems Integration
Railway/Station Systems
Integration
System Integration – Phase 3
Station Comms – Precom
& Com
NR Systems – Precom &
Com
Railway Systems –
Precom & Com
Tunnel M&E Systems –
Precom & Com
Station Systems – Precom
& Com
LU Systems – Precom &
Com
NR Systems – Install &
Static Tests
Railway Systems – Install
& Static Tests
Tunnel M&E Systems –
Install & Static Tests
Station Comms – Install &
Static Tests
Station Systems – Install &
Static Tests
LU Systems – Install &
Static Tests
NR/Station Comms
Systems Integration
Station Comms Integration
Tunnel M&E/Station
Systems Integration
Tunnel M&E Systems
Integration
Railway/Station Comms
Systems Integration
Railway Systems
Integration
NR Systems Integration
Station Comms/Station
Systems Integration
Dynamic Testing – Phase 4 Trial Running – Phase 5
Dynamic Testing Trial Running
Station Systems
Integration
Station Comms/LU
Systems Integration
Integration Test
Complete - Milestones
Rolling Stock Fitout
Rolling Stock Proving GE
& GW
Rolling Stock/NR Systems
Integration (GE/GW)
Rolling Stock/Railway
Systems Integration (TT)
 Area of greatest
T&C/ Integration
risk
 Immediate area
of focus
Key Questions
How can we coordinate testing, commissioning
and handover activities across the Central Section?
How can we integrate Central and Outer sections?
How can we provide high levels of service from day
one?
Phased opening
2018201720162012
1
2013
2
2014
3
2015
4 5 6
Q1
Stage 5
2019
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Stage 4Stage 3Stage 2Stage 1
7 8 9 10
Stage 1: Liverpool St (mainline) to Shenfield (May 2017)
Stage 3: Paddington (Crossrail platforms) to Abbey Wood (Dec 2018)
Stage 2: Heathrow to Paddington (mainline platforms) (May 2018)
Stage 4: Paddington (Crossrail platforms) to Shenfield (May 2019)
Stage 5: Full through service (Dec 2019)
Systems Engineering
This phase of the works brings a new set
of challenges
Interfaces
Organisations
Collaborative working
Programme Management
Assurance
Risk Management is changing to support the work:
Definition of common goals and RACI for Risks
Bringing teams together through facilitation and joint
working
Focus on schedule and interdependencies
What is Crossrail?
Risk Management Challenges
Risk and Assurance
Conclusions
Risk and Assurance on Crossrail
Crossrail’s Programme Assurance Strategy describes an Assurance
Chain linking Sponsors, Crossrail Limited and its Supply Chain
AssuranceRequirements
AssuranceEvidence
Project
Sponsors
Infrastructure
Managers
Regulators
Tier 1 Contractors Industry Partners
Tier 2 Contractors
Crossrail
Delivery
Independent
Assurance
Robust Reporting
Assured Delivery
Crossrail: ‘Three Lines of Defence’
1st Line: Delivery Teams
Embedded risk management and controls
3rd Line: Independent Assurance
Independent challenge and assurance
Internal Audit, External Audit, Sponsors Rep
CIAG (Crossrail Integrated Assurance Group)
2nd Line: Oversight Functions
Set policy and procedure and provide functional oversight
Quality, Finance, Controls, Technical, Risk Management
CrossrailLimitedBoard,ExComandAuditCommitee
Risk Management Assurance
Report to Joint Sponsor Team
Aggregate risk information against COST and SCHEDULE forecasts (QRA)
Inform Audit Plan with high risk areas
Engage with Sponsors Representative
Work with Insurance (Joint Code of Practice for Tunnelling Projects)
Embed risk management into the organisation: set Policy, Plan and Procedure
We measure and monitor that it is happening (ARM Metrics) and that it is working (Key Risks)
We extend this to our supply chain and measure using performance assurance
Report to ExComm
Report to Audit Cttee
Report to Board
2nd Line: Oversight Functions
Set policy and procedure and provide functional oversight
Quality, Finance, Controls, Technical, Risk Management
What is Crossrail?
Risk Management Challenges
Risk and Assurance
Conclusions
Risk and Assurance on Crossrail
Conclusions
Risk management is a key part of our overall assurance framework
It is built on good engagement with Delivery
Provides assurance that Crossrail is delivering the right outputs
on time and to budget
Informs key decisions
Crossrail is still on target to open in December 2018
Rob Halstead
Head of Risk Management, Crossrail
Risk and Assurance on Crossrail

More Related Content

What's hot

Kotler mm 14e_02_ippt
Kotler mm 14e_02_ipptKotler mm 14e_02_ippt
Kotler mm 14e_02_ipptFahim Muntaha
 
Marketing plan project (final)
Marketing plan project (final)Marketing plan project (final)
Marketing plan project (final)Tagaris Cheikh Ali
 
Bmw x6 marketing
Bmw x6 marketingBmw x6 marketing
Bmw x6 marketingHarsh Shah
 
Kotler mm 14e 08 ippt
Kotler mm 14e 08 ipptKotler mm 14e 08 ippt
Kotler mm 14e 08 ipptEhab Yousry
 
Supply Chain for Management Consultants & Business Analysts
Supply Chain for Management Consultants & Business AnalystsSupply Chain for Management Consultants & Business Analysts
Supply Chain for Management Consultants & Business AnalystsAsen Gyczew
 
Role of new media in corporate communication
Role of new media in corporate communicationRole of new media in corporate communication
Role of new media in corporate communicationDr. Shalini Pandey
 
Define a Powerful Go-to-Market Strategy That Sets Your Product Apart
Define a Powerful Go-to-Market Strategy That Sets Your Product ApartDefine a Powerful Go-to-Market Strategy That Sets Your Product Apart
Define a Powerful Go-to-Market Strategy That Sets Your Product ApartCompellingPM
 
Foundations of business strategy - Lec 1.pdf
Foundations of business strategy - Lec 1.pdfFoundations of business strategy - Lec 1.pdf
Foundations of business strategy - Lec 1.pdfMohammed Ali Ahmed
 
Market Penetration Strategy PowerPoint Presentation Slides
Market Penetration Strategy PowerPoint Presentation Slides Market Penetration Strategy PowerPoint Presentation Slides
Market Penetration Strategy PowerPoint Presentation Slides SlideTeam
 
Kotler mm 14e 15 ippt
Kotler mm 14e 15 ipptKotler mm 14e 15 ippt
Kotler mm 14e 15 ipptEhab Yousry
 
Social Media: Chapter 1 (horizontal revolution)
Social Media: Chapter 1 (horizontal revolution)Social Media: Chapter 1 (horizontal revolution)
Social Media: Chapter 1 (horizontal revolution)Jawad Chaudhry
 
Marketing Management Book kotler(summary)
Marketing Management Book kotler(summary)Marketing Management Book kotler(summary)
Marketing Management Book kotler(summary)Kavery Gupta
 
Brand Awareness & Marketing Campaign using Digital Marketing
Brand Awareness & Marketing Campaign using Digital MarketingBrand Awareness & Marketing Campaign using Digital Marketing
Brand Awareness & Marketing Campaign using Digital MarketingAneela Ganisetti
 

What's hot (20)

Kotler mm 14e_02_ippt
Kotler mm 14e_02_ipptKotler mm 14e_02_ippt
Kotler mm 14e_02_ippt
 
Marketing plan project (final)
Marketing plan project (final)Marketing plan project (final)
Marketing plan project (final)
 
Media Plan Project
Media Plan ProjectMedia Plan Project
Media Plan Project
 
Bmw x6 marketing
Bmw x6 marketingBmw x6 marketing
Bmw x6 marketing
 
Kotler mm 14e 08 ippt
Kotler mm 14e 08 ipptKotler mm 14e 08 ippt
Kotler mm 14e 08 ippt
 
PR CaseStudies
PR CaseStudiesPR CaseStudies
PR CaseStudies
 
Marketing Plan in 5 Steps
Marketing Plan in 5 StepsMarketing Plan in 5 Steps
Marketing Plan in 5 Steps
 
Supply Chain for Management Consultants & Business Analysts
Supply Chain for Management Consultants & Business AnalystsSupply Chain for Management Consultants & Business Analysts
Supply Chain for Management Consultants & Business Analysts
 
Role of new media in corporate communication
Role of new media in corporate communicationRole of new media in corporate communication
Role of new media in corporate communication
 
Define a Powerful Go-to-Market Strategy That Sets Your Product Apart
Define a Powerful Go-to-Market Strategy That Sets Your Product ApartDefine a Powerful Go-to-Market Strategy That Sets Your Product Apart
Define a Powerful Go-to-Market Strategy That Sets Your Product Apart
 
Foundations of business strategy - Lec 1.pdf
Foundations of business strategy - Lec 1.pdfFoundations of business strategy - Lec 1.pdf
Foundations of business strategy - Lec 1.pdf
 
Chapter #4
Chapter #4Chapter #4
Chapter #4
 
Market Penetration Strategy PowerPoint Presentation Slides
Market Penetration Strategy PowerPoint Presentation Slides Market Penetration Strategy PowerPoint Presentation Slides
Market Penetration Strategy PowerPoint Presentation Slides
 
Channel Program
Channel ProgramChannel Program
Channel Program
 
Kotler mm 14e 15 ippt
Kotler mm 14e 15 ipptKotler mm 14e 15 ippt
Kotler mm 14e 15 ippt
 
Social Media: Chapter 1 (horizontal revolution)
Social Media: Chapter 1 (horizontal revolution)Social Media: Chapter 1 (horizontal revolution)
Social Media: Chapter 1 (horizontal revolution)
 
Marketing Management Book kotler(summary)
Marketing Management Book kotler(summary)Marketing Management Book kotler(summary)
Marketing Management Book kotler(summary)
 
Product roadmap 101
Product roadmap 101Product roadmap 101
Product roadmap 101
 
Kotler mm 14e_19_ippt
Kotler mm 14e_19_ipptKotler mm 14e_19_ippt
Kotler mm 14e_19_ippt
 
Brand Awareness & Marketing Campaign using Digital Marketing
Brand Awareness & Marketing Campaign using Digital MarketingBrand Awareness & Marketing Campaign using Digital Marketing
Brand Awareness & Marketing Campaign using Digital Marketing
 

Viewers also liked

3. Adrian Pyne - good agile governance (including case studies) GOV011015
3. Adrian Pyne - good agile governance (including case studies) GOV0110153. Adrian Pyne - good agile governance (including case studies) GOV011015
3. Adrian Pyne - good agile governance (including case studies) GOV011015Association for Project Management
 
Crossrail Governance - Simon Adams, United Kingdom
Crossrail Governance - Simon Adams, United KingdomCrossrail Governance - Simon Adams, United Kingdom
Crossrail Governance - Simon Adams, United KingdomOECD Governance
 
London's Crossrail Scheme - its evolution, governance, financing and challenges
London's Crossrail Scheme  - its evolution, governance, financing and challengesLondon's Crossrail Scheme  - its evolution, governance, financing and challenges
London's Crossrail Scheme - its evolution, governance, financing and challengesInstitute for Transport Studies (ITS)
 
3. Ross Garland - building governance capability - challenges facing good gov...
3. Ross Garland - building governance capability - challenges facing good gov...3. Ross Garland - building governance capability - challenges facing good gov...
3. Ross Garland - building governance capability - challenges facing good gov...Association for Project Management
 
6. Andy Murray - embedding governance (lessons from maturity models) GOV011015
6. Andy Murray - embedding governance (lessons from maturity models) GOV0110156. Andy Murray - embedding governance (lessons from maturity models) GOV011015
6. Andy Murray - embedding governance (lessons from maturity models) GOV011015Association for Project Management
 
Project Governance and Failure
Project Governance and FailureProject Governance and Failure
Project Governance and FailureMichael Krigsman
 
Program governance Structure
Program governance StructureProgram governance Structure
Program governance StructureSaurabh Sardesai
 

Viewers also liked (15)

3. Adrian Pyne - good agile governance (including case studies) GOV011015
3. Adrian Pyne - good agile governance (including case studies) GOV0110153. Adrian Pyne - good agile governance (including case studies) GOV011015
3. Adrian Pyne - good agile governance (including case studies) GOV011015
 
4. Ian Triplow - developing good governance... GOV011015
4. Ian Triplow - developing good governance... GOV0110154. Ian Triplow - developing good governance... GOV011015
4. Ian Triplow - developing good governance... GOV011015
 
1. Martin Samphire - introduction GOV011015
1. Martin Samphire - introduction GOV0110151. Martin Samphire - introduction GOV011015
1. Martin Samphire - introduction GOV011015
 
Crossrail Governance - Simon Adams, United Kingdom
Crossrail Governance - Simon Adams, United KingdomCrossrail Governance - Simon Adams, United Kingdom
Crossrail Governance - Simon Adams, United Kingdom
 
London's Crossrail Scheme - its evolution, governance, financing and challenges
London's Crossrail Scheme  - its evolution, governance, financing and challengesLondon's Crossrail Scheme  - its evolution, governance, financing and challenges
London's Crossrail Scheme - its evolution, governance, financing and challenges
 
3. Ross Garland - building governance capability - challenges facing good gov...
3. Ross Garland - building governance capability - challenges facing good gov...3. Ross Garland - building governance capability - challenges facing good gov...
3. Ross Garland - building governance capability - challenges facing good gov...
 
6. Andy Murray - embedding governance (lessons from maturity models) GOV011015
6. Andy Murray - embedding governance (lessons from maturity models) GOV0110156. Andy Murray - embedding governance (lessons from maturity models) GOV011015
6. Andy Murray - embedding governance (lessons from maturity models) GOV011015
 
Integrated Assurance and Audit at Crossrail, 17 may 2016
Integrated Assurance and Audit at Crossrail, 17 may 2016Integrated Assurance and Audit at Crossrail, 17 may 2016
Integrated Assurance and Audit at Crossrail, 17 may 2016
 
1. Roger Garrini - good governance guidance GOV011015
1. Roger Garrini - good governance guidance GOV0110151. Roger Garrini - good governance guidance GOV011015
1. Roger Garrini - good governance guidance GOV011015
 
4. Stuart Collins BBC - strategic governance of p3m GOV011015
4. Stuart Collins BBC - strategic governance of p3m GOV0110154. Stuart Collins BBC - strategic governance of p3m GOV011015
4. Stuart Collins BBC - strategic governance of p3m GOV011015
 
Project Governance and Failure
Project Governance and FailureProject Governance and Failure
Project Governance and Failure
 
Crossrail: lessons in governance
Crossrail: lessons in governanceCrossrail: lessons in governance
Crossrail: lessons in governance
 
5. Simon Adams - Crossrail governance GOV011015
5. Simon Adams - Crossrail governance GOV0110155. Simon Adams - Crossrail governance GOV011015
5. Simon Adams - Crossrail governance GOV011015
 
2. Amerjit Walia - delivering good governance for p3m GOV011015
2. Amerjit Walia - delivering good governance for p3m GOV0110152. Amerjit Walia - delivering good governance for p3m GOV011015
2. Amerjit Walia - delivering good governance for p3m GOV011015
 
Program governance Structure
Program governance StructureProgram governance Structure
Program governance Structure
 

Similar to Risk and assurance on crossrail - rob halstead

Moving London Forward - Crossrail
Moving London Forward - Crossrail Moving London Forward - Crossrail
Moving London Forward - Crossrail Ibrahim Al-Hudhaif
 
Communications Based Train Control Conference London March 12 2014
Communications Based Train Control Conference London March 12 2014 Communications Based Train Control Conference London March 12 2014
Communications Based Train Control Conference London March 12 2014 James Nesbitt
 
CBTC Communications Based Train Control conference March 12th 2014
CBTC Communications Based Train Control conference March 12th 2014 CBTC Communications Based Train Control conference March 12th 2014
CBTC Communications Based Train Control conference March 12th 2014 James Nesbitt
 
Jeddah metro full presentation - Briefing Day March, 30th
Jeddah metro full presentation - Briefing Day March, 30th Jeddah metro full presentation - Briefing Day March, 30th
Jeddah metro full presentation - Briefing Day March, 30th Ibrahim Al-Hudhaif
 
Jullian Valverde - the promotion and coordination of consortia for the provis...
Jullian Valverde - the promotion and coordination of consortia for the provis...Jullian Valverde - the promotion and coordination of consortia for the provis...
Jullian Valverde - the promotion and coordination of consortia for the provis...imadhammoud
 
Sro Project Brief
Sro Project BriefSro Project Brief
Sro Project Briefenergyvijay
 
06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultransConsultrans, S.A.
 
Strategic analysis of communications based train control systems in the weste...
Strategic analysis of communications based train control systems in the weste...Strategic analysis of communications based train control systems in the weste...
Strategic analysis of communications based train control systems in the weste...Shyam Raman
 
Crossrail Suppy Chain Engagement Seminar 2013 - Terry Morgan, Martin Rowark, ...
Crossrail Suppy Chain Engagement Seminar 2013 - Terry Morgan, Martin Rowark, ...Crossrail Suppy Chain Engagement Seminar 2013 - Terry Morgan, Martin Rowark, ...
Crossrail Suppy Chain Engagement Seminar 2013 - Terry Morgan, Martin Rowark, ...Invest Northern Ireland
 
19972 Informa Telecoms P15M16_v2
19972 Informa Telecoms P15M16_v219972 Informa Telecoms P15M16_v2
19972 Informa Telecoms P15M16_v2Niamh Horan
 
Global Rail _interactive_(c) Arup
Global Rail _interactive_(c) ArupGlobal Rail _interactive_(c) Arup
Global Rail _interactive_(c) ArupHeather Ceney
 
RPS CV of Simon Hua
RPS CV of Simon HuaRPS CV of Simon Hua
RPS CV of Simon HuaSimon Hua
 

Similar to Risk and assurance on crossrail - rob halstead (20)

Moving London Forward - Crossrail
Moving London Forward - Crossrail Moving London Forward - Crossrail
Moving London Forward - Crossrail
 
Communications Based Train Control Conference London March 12 2014
Communications Based Train Control Conference London March 12 2014 Communications Based Train Control Conference London March 12 2014
Communications Based Train Control Conference London March 12 2014
 
CBTC Communications Based Train Control conference March 12th 2014
CBTC Communications Based Train Control conference March 12th 2014 CBTC Communications Based Train Control conference March 12th 2014
CBTC Communications Based Train Control conference March 12th 2014
 
DML CV 17
DML CV 17DML CV 17
DML CV 17
 
Crossrail - Integrated Assurance, 17 May 2016,
Crossrail - Integrated Assurance, 17 May 2016, Crossrail - Integrated Assurance, 17 May 2016,
Crossrail - Integrated Assurance, 17 May 2016,
 
Jeddah metro full presentation - Briefing Day March, 30th
Jeddah metro full presentation - Briefing Day March, 30th Jeddah metro full presentation - Briefing Day March, 30th
Jeddah metro full presentation - Briefing Day March, 30th
 
Jullian Valverde - the promotion and coordination of consortia for the provis...
Jullian Valverde - the promotion and coordination of consortia for the provis...Jullian Valverde - the promotion and coordination of consortia for the provis...
Jullian Valverde - the promotion and coordination of consortia for the provis...
 
UK Rail_(c) Arup
UK Rail_(c) ArupUK Rail_(c) Arup
UK Rail_(c) Arup
 
Dubai metro paper in ASPECT Conference
Dubai metro paper in ASPECT Conference Dubai metro paper in ASPECT Conference
Dubai metro paper in ASPECT Conference
 
Sro Project Brief
Sro Project BriefSro Project Brief
Sro Project Brief
 
Presentation on Dhaka Metro Rail.pptx
Presentation on Dhaka Metro Rail.pptxPresentation on Dhaka Metro Rail.pptx
Presentation on Dhaka Metro Rail.pptx
 
CV_SIG_DES_MG_Dastagir 07_11_2016
CV_SIG_DES_MG_Dastagir 07_11_2016CV_SIG_DES_MG_Dastagir 07_11_2016
CV_SIG_DES_MG_Dastagir 07_11_2016
 
06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans06 presentation civil-engineering_consultrans
06 presentation civil-engineering_consultrans
 
eltracs res
eltracs reseltracs res
eltracs res
 
Strategic analysis of communications based train control systems in the weste...
Strategic analysis of communications based train control systems in the weste...Strategic analysis of communications based train control systems in the weste...
Strategic analysis of communications based train control systems in the weste...
 
Technologies Overview Feb 2014
Technologies Overview Feb 2014Technologies Overview Feb 2014
Technologies Overview Feb 2014
 
Crossrail Suppy Chain Engagement Seminar 2013 - Terry Morgan, Martin Rowark, ...
Crossrail Suppy Chain Engagement Seminar 2013 - Terry Morgan, Martin Rowark, ...Crossrail Suppy Chain Engagement Seminar 2013 - Terry Morgan, Martin Rowark, ...
Crossrail Suppy Chain Engagement Seminar 2013 - Terry Morgan, Martin Rowark, ...
 
19972 Informa Telecoms P15M16_v2
19972 Informa Telecoms P15M16_v219972 Informa Telecoms P15M16_v2
19972 Informa Telecoms P15M16_v2
 
Global Rail _interactive_(c) Arup
Global Rail _interactive_(c) ArupGlobal Rail _interactive_(c) Arup
Global Rail _interactive_(c) Arup
 
RPS CV of Simon Hua
RPS CV of Simon HuaRPS CV of Simon Hua
RPS CV of Simon Hua
 

More from Association for Project Management

Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Association for Project Management
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Association for Project Management
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...Association for Project Management
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Association for Project Management
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...Association for Project Management
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Association for Project Management
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Association for Project Management
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Association for Project Management
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Association for Project Management
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...Association for Project Management
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024Association for Project Management
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Association for Project Management
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...Association for Project Management
 

More from Association for Project Management (20)

Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
 

Recently uploaded

VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneCall girls in Ahmedabad High profile
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...noida100girls
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 

Recently uploaded (20)

VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 

Risk and assurance on crossrail - rob halstead

  • 1. Rob Halstead Head of Risk Management, Crossrail Risk and Assurance on Crossrail
  • 2.
  • 3.
  • 4. What is Crossrail? Risk Management Challenges Risk and Assurance Conclusions Risk and Assurance on Crossrail
  • 5. What is Crossrail? A new railway for London and the south east Over 100 km from east to west 24 trains per hour in each direction More than 200 million passenger journey per annum Adds 10% to London’s rail capacity
  • 6. £14.8bn funding 38 stations served 9 new stations built 42 km new tunnels 8 million cubic metres of spoil 4300+ Parliamentary commitments Europe’s largest infrastructure project
  • 7. 14,000 employed Why Crossrail? 24 trains per hour 200 million journeys per year £42bn+ benefits
  • 8. What is Crossrail? Risk Management Challenges Risk and Assurance Conclusions Risk and Assurance on Crossrail
  • 9. Managing the project Risk Management Challenges Tunnelling Integrating the Railway
  • 10. Managing Europe’s Largest Construction Project
  • 12. Tier 1 Contractors and others… Industry Partners Delivery Partners Transcend PDP An industry wide project Sponsors
  • 13. Construction on staggering scale Paddington Bond Street Tottenham Court Road Farringdon Liverpool Street Whitechapel Canary Wharf WoolwichCustom House
  • 14. Programme Management 140 main works contracts 40 worksites 10,000 suppliers 1 million activity schedule
  • 15. Extended to Reading 27 station upgrades 2 major structures 61km of track 179 switches & crossings 150 km OLE Signalling upgrade Network Rail surface works
  • 16. Risk Management at Crossrail “Managing risk and uncertainty is critical to the successful delivery of Crossrail” Andrew Wolstenholme OBE Chief Executive of Crossrail Limited
  • 17. Drivers of Risk Management Delivery Avoid nasty surprises Identify opportunities to improve Head off issues before they impact Commercial Ensure that commercial exposure of the organisation is understood and managed Inform allocation of risk between parties through contracts Engineering Monitor the mitigation of risk through design Ensure that works are delivered safely and that output is fit for purpose Finance Understand true exposure to risk and uncertainty Support investment decisions through assessment of risk impacts Risk Support Delivery : Provide Assurance : Inform Decision Making RISK MANAGEMENT:
  • 18. Risk Hierarchy Risk Governance Risk Reporting Crossrail Limited Board Executive Committee Risk Sub- Committee Programme Risk Panel Delivery Reviews Audit Committee 1) Report 2) Escalate 3) AggregateContractor Risks Project Risks Strategic Risks Programme Risks Sector Risks
  • 19. Keeping it simple Identify Assess Respond Prioritise by assessing ‘Probability’ and ‘Impact’  Terminate  Transfer  Treat  Tolerate Uncertainty that mattersRisk is: Risk Management is:
  • 21. Running Tunnels Running Tunnels - Paddington to Stratford and North Kent - Bored Tunnels 7m diameter - 30 - 40m depth - 42km long - 8 Tunnel Boring Machines (TBMs)
  • 22. Station Tunnels Stations Tunnels - Platform tunnels, circulation areas, cross passages - Sprayed Concrete Lining (SCL) - 16km tunnelling
  • 23. Key Questions How do we make sure that the tunnels are safe? How do we deal with ground conditions and underground obstructions? How do we avoid damage to buildings and services?
  • 25. Tunnelling Risk Mitigations Enabling works – diverting and protecting utilities Ground treatment Monitoring Risk management (AIB Code of practice for risk management in underground construction) People, process, culture
  • 28. Tunnelling progress to date Running tunnels: Station tunnels: 43km 99% complete 17km 78% complete
  • 31. Under Platform Services Area Station Structure Track Systems Traction Power & Overhead Line Equipment Emergency Walkway Gravity Drainage HV Power LV Power Tunnel Lighting Communications & Control Radio Systems Signalling PlatformDoors Tunnel Ventilation Pumped Drainage Pump Smoke Extract Fire Detection Station Ventilation Station Lighting Signage Passenger Information CCTV PA / VA HelpPoint Fire Main Station Cable Management System Station Systems Automatic Fare Collection Lifts & Escalators Station Management System Station Heating, Cooling and Air Conditioning Route Wide Railway Infrastructure Route Control Centre Back Up Control Facility Bulk Supply Points Auto Trans- former Sites Depots & Stabling Rolling Stock Paddington Railway and Tunnel Systems Railway Systems
  • 32. Rolling Stock 200m long trains 1,500 seated and standing passengers per train at peak times Regenerates energy during braking (major savings in energy and CO2 emissions)
  • 33. Railway Integration Components Systems Integration Railway Integration – Central Section Railway Integration – end to end Operator, Maintainer, Infrastructure Manager Readiness Testing and Commissioning Handover Technical Assurance 8323 Railway fails to perform as intended / required by Sponsors Critical non performances by key players means Railway fails to perform as intended / required by Sponsors Howard Smith 6151 Failure to integrate railway [with NR] Chris Sexton 7851 An integrated railway is not delivered delaying Railway opening Chris Sexton 6153 Delayed acceptance of stations and railway systems by IM and other key stakeholders Chris Sexton 6827 Insufficient resilience of the railway in operational service. Programme Level Provisionof technical assurance evidence to satisfy IMs Management of handover 872 Failure to manage Standards Baseline (Rail Systems) Failure to execute Trial Operations successfully Project Level Failure to capture Operations and Maintenance requirements in procured works Failure to integrate CTOC or other TOCs 1809 The railway is not delivered for technical reasons (Stages 1 - 5) “1. Failure to integrate the system” Simon Wright Strategic Level 6923 Operators and Infrastructure Managers may not be ready to take the railway into operation resulting in delay to the railway opening. Howard Smith 11497 The railway service cannot be operated effectively at opening because of other rail operator/ regulator issues Howard Smith Failure to deliver Requirements Failure to exploit “smart stations” / Digital Railway opportunities Operational integration with NR Management of technical interfaces between systems and contracts Integration with Rolling Stock Failure to integrate with LUL Failure to execute or integrate the test and commissioning plan Failure to manage the governance / relationships with other parties Failure to manage Railway Safety risk transfer and mitigation with Operators 5980 (RI) Failure to implement the Signalling System effectively Chris Sexton > Development of the fringe with NR signalling > Complexity of integrating ATO/ATP > Provision of a signalling system compatible with the Crossrail train in the Heathrow Tunnel > Integration into a single Driver DMI > Development required to chosen signalling system to integrate with NR control centres > Signalling principles require further unforeseen development 6826 Failure to meet Operators requirements (Operational, Maintenance, Safety, Performance) Jeremy Bates 883 Unable to obtain safety approval for the railway 7984 Comments/Objection by ORR on the Construction and Commissioning Rulebook principles 11739 The testing and commissioning strategy may not be effectively aligned with the planned permanent and temporary power provision 12561 Operational Readiness – being ready to put the output from Crossrail delivery and the RSD into full operational service Howard Smith Currently owned by J Bates – would need to be re-assigned and promoted to Programme Risk Promote to Strategic Level and assign to Simon Wright or Andrew Wolstenholme Promote to Strategic Level Currently a Programme Risk TBD The railway service cannot be operated effectively because regulator fails to approve Crossrail Simon Wright 2611, 8395 RCC building 6957 Changes to NR demarcation at PML Lack of integration with NR’s test and commissioning plan Lack of integration with NR’s test and commissioning plan 1000, 872, 13286 6135 On Network Works interface with Network Rail projects Matt White 14090 NR Interfacing project to develop and deliver ETCS may encounter technical, operational and schedule challenges 1994 Continuing evolution of NR signalling 7622 Network Rail/TOC projects conflict with CRL programme commissioning requirements 5981 Provision of an ATP system (ETCS) in the Heathrow Tunnels 14090 NR Interfacing project to develop and deliver ETCS may encounter technical, operational and schedule challenges GW works integration South East Section works integration Eastern works integration Systems works integration 7489 Platform heights on GE routes are above standard and CRL may not be able to satisfy level-boarding gauge clearance requirements. 8115 – Constraints of legacy surface station platforms may give rise to an inability to install transmission systems for Driver Only Operated CCTV 10296 Lack of interface control between D&B for station fit- out, MEP, architectural and systemwide. 5900 Floating slab track interaction with rolling stock. 10471 PSD Entrapment 13159 Integration of PED and PES design solution 13159 Integration of PED and PES design solution 8516 Definition and coordination of interfaces: Civils to Systemwide 7490, 6822 Insufficient time for rolling stock testing 6305 Insufficient resources for commissioning 9728 Signalling Integration / Commissioning issues at interface with national network 7622 Commissioning of railway systems at the interfaces with the national network. 7982 Delays to station (systemwide) systems testing 11739 The testing and commissioning strategy may not be effectively aligned with the planned permanent and temporary power provision 11473 Inadequacy of temp power supply 1994 Signalling project delays 7829 CIS not integrated with NR On Network Stations 2829, 5381 Western works – integration 9098 Network Rail delivery / interfaces at OOC 10826 Stage 2: Infrastructure (including Depot, Heathrow ETCS, Paddington platform works) and integration with GW signalling is not available 10725 Platform heights on GW routes are above standard and CRL may not be able to satisfy level-boarding gauge clearance requirements. 5758 NR interface at Plumstead 14024 ICDs may be incomplete, or out-of-date, leading to scope gaps delaying programme 2024 IMs lose confidence in the CRL Technical Authority and set up their own independent assurance system 7459, 5090 Lack of clear safety assurance documentation from Crossrail to IM. 4547 Inefficient submission and review procedures 7981 RIR CSM does not deliver sufficient safety justification evidence to provide safety assurance 5957 Crossrail 3D design model may not be kept updated 11039 Late mobilisation of IM resources CRL fails to provide adequate evidence as part of handover process CRL fails to provide adequate evidence as part of handover process 6990 Failure to fulfil PDA Requirements in relation to Handover 6286 Failure to provide adequate test & commissioning evidence Failure to demonstrate achievement of Substantial Completion Criteria as defined in PDA to Sponsors. Failure to demonstrate achievement of Substantial Completion Criteria as defined in PDA to Sponsors. 10471 Potential entrapment issue 8115 DOO CCTV 7489, 10725 Level boarding, stepping distances & Gauge clearance – NR stations 7985 Impact of energisation on neighbouring systems - EMC 2002 Integrated Station Management Systems at LU interchange stations (Stations Ops Rooms) CRL CIS not integrated with existing LU CIS CRL CIS not integrated with existing LU CIS 9548 Maintenance support services, spares and specialist plant not procured on time. Track access / maintenance assumptions not aligned to 95% PPM Track access / maintenance assumptions not aligned to 95% PPM Remote condition Monitoring strategy Remote condition Monitoring strategy 3049, 6297, 1032, 10391 LUL / CRL relationships RfL Relationship risk?RfL Relationship risk? 13395 Lack of clarity of Urban Realm/OSD design and delivery 1008 Mismatch between RfL/LU requirements and CRL design 1146 Customer Service is not perceived as being world class. 10544 Timetable not produced in time 1061 Performance Modelling inadequate (PPM target not achieved) 6471 Sponsors, TfL, IPs: Late or unexpected changes in requirements integration with NR control centresintegration with NR control centres 10021 Train Operators do not accept NR Network Change 9290 Insufficient driver resources to support staged opening of Crossrail 9624 Timing and performance of Rolling Stock and Depot could delay opening of Crossrail 1156 Overrun on Trial Operations Lack of Operational Readiness (including Trial Operations and Staff Training & Familiarisation) Lack of Operational Readiness (including Trial Operations and Staff Training & Familiarisation) 13253 TransitiontoOperations Martin Buck 11941 Trial operations are insufficient to demonstrate agreed objectives. 13253 Transition into operations Management of Asset information 11838 Lack of clarity over the approach to specification, handover and use of Crossrail Asset Information could delay asset acceptance Chris Sexton Currently a Programme Risk 2033 Delivery of design (and its design assumptions) is not accepted by IMs (NR, RfL and LUL) Maintenance plan is incorrectMaintenance plan is incorrect RAM outputs not aligned with maintenance assumptions RAM outputs not aligned with maintenance assumptions Signalling contingenciesSignalling contingencies Insufficient timetable flexibility / recovery time Insufficient timetable flexibility / recovery time Power / Comms resiliencePower / Comms resilience 7622 Commissioning of railway systems at the interfaces with the national network. Paddington OSDPaddington OSD 8089 HS2 interface Matt White 5960 HS2 interchange station at Old Oak Common causes change/delay 5960 External interfaces adversely impact the ability to deliver and subsequently the operation of the railway. (HS2, BAA, Ilford, OOC) Howard Smith CRL Regulatory Approval 8093 There is a risk that the NoBo and DeBo identify further non compliances which require derogations and the developement of NNTRs 10739 Rail Regulator – failure to gain regulatory consents by NR CRL submissions to ORR not managedCRL submissions to ORR not managed RfL Regulatory Approval RfL submissions to ORR not managedRfL submissions to ORR not managed Interfaces with other operators e.g. Freight, First Great Western , Abellio Greater Anglia, Heathrow Express, DLR Promote from project to strategic 14395 Ilford speed restrictions14395 Ilford speed restrictions Demote from strategic to programme 5981 Provision of ATP system in Heathrow Tunnel Header here max 30 characters2014 Effort… Rolling Stock Programme Stations Programme Systemwide Programme ONW Programme Installation – Phase 2.1 Commissioning – Phase 2.2-2.3 NR/Railway Systems Integration Railway/Tunnel M&E Systems Integration Station Systems/LU Systems Integration Railway/Station Systems Integration System Integration – Phase 3 Station Comms – Precom & Com NR Systems – Precom & Com Railway Systems – Precom & Com Tunnel M&E Systems – Precom & Com Station Systems – Precom & Com LU Systems – Precom & Com NR Systems – Install & Static Tests Railway Systems – Install & Static Tests Tunnel M&E Systems – Install & Static Tests Station Comms – Install & Static Tests Station Systems – Install & Static Tests LU Systems – Install & Static Tests NR/Station Comms Systems Integration Station Comms Integration Tunnel M&E/Station Systems Integration Tunnel M&E Systems Integration Railway/Station Comms Systems Integration Railway Systems Integration NR Systems Integration Station Comms/Station Systems Integration Dynamic Testing – Phase 4 Trial Running – Phase 5 Dynamic Testing Trial Running Station Systems Integration Station Comms/LU Systems Integration Integration Test Complete - Milestones Rolling Stock Fitout Rolling Stock Proving GE & GW Rolling Stock/NR Systems Integration (GE/GW) Rolling Stock/Railway Systems Integration (TT)  Area of greatest T&C/ Integration risk  Immediate area of focus
  • 34. Key Questions How can we coordinate testing, commissioning and handover activities across the Central Section? How can we integrate Central and Outer sections? How can we provide high levels of service from day one?
  • 35. Phased opening 2018201720162012 1 2013 2 2014 3 2015 4 5 6 Q1 Stage 5 2019 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Stage 4Stage 3Stage 2Stage 1 7 8 9 10 Stage 1: Liverpool St (mainline) to Shenfield (May 2017) Stage 3: Paddington (Crossrail platforms) to Abbey Wood (Dec 2018) Stage 2: Heathrow to Paddington (mainline platforms) (May 2018) Stage 4: Paddington (Crossrail platforms) to Shenfield (May 2019) Stage 5: Full through service (Dec 2019)
  • 37. This phase of the works brings a new set of challenges Interfaces Organisations Collaborative working Programme Management Assurance Risk Management is changing to support the work: Definition of common goals and RACI for Risks Bringing teams together through facilitation and joint working Focus on schedule and interdependencies
  • 38. What is Crossrail? Risk Management Challenges Risk and Assurance Conclusions Risk and Assurance on Crossrail
  • 39. Crossrail’s Programme Assurance Strategy describes an Assurance Chain linking Sponsors, Crossrail Limited and its Supply Chain AssuranceRequirements AssuranceEvidence Project Sponsors Infrastructure Managers Regulators Tier 1 Contractors Industry Partners Tier 2 Contractors Crossrail Delivery Independent Assurance Robust Reporting Assured Delivery
  • 40. Crossrail: ‘Three Lines of Defence’ 1st Line: Delivery Teams Embedded risk management and controls 3rd Line: Independent Assurance Independent challenge and assurance Internal Audit, External Audit, Sponsors Rep CIAG (Crossrail Integrated Assurance Group) 2nd Line: Oversight Functions Set policy and procedure and provide functional oversight Quality, Finance, Controls, Technical, Risk Management CrossrailLimitedBoard,ExComandAuditCommitee
  • 41. Risk Management Assurance Report to Joint Sponsor Team Aggregate risk information against COST and SCHEDULE forecasts (QRA) Inform Audit Plan with high risk areas Engage with Sponsors Representative Work with Insurance (Joint Code of Practice for Tunnelling Projects) Embed risk management into the organisation: set Policy, Plan and Procedure We measure and monitor that it is happening (ARM Metrics) and that it is working (Key Risks) We extend this to our supply chain and measure using performance assurance Report to ExComm Report to Audit Cttee Report to Board 2nd Line: Oversight Functions Set policy and procedure and provide functional oversight Quality, Finance, Controls, Technical, Risk Management
  • 42. What is Crossrail? Risk Management Challenges Risk and Assurance Conclusions Risk and Assurance on Crossrail
  • 43. Conclusions Risk management is a key part of our overall assurance framework It is built on good engagement with Delivery Provides assurance that Crossrail is delivering the right outputs on time and to budget Informs key decisions Crossrail is still on target to open in December 2018
  • 44. Rob Halstead Head of Risk Management, Crossrail Risk and Assurance on Crossrail