SlideShare a Scribd company logo
Rig Move Management & Logistics Plan
Introduction: This Rig Move Plan & Check List will address the personnel requirements, equipment requirements, responsibilities, specific procedures and contingency plans.
General Planning
 KERUI HSE will conduct a road and new location survey prior to the movement of any equipment – Map to be drawn, areas of concern will be identified.
 KERUI will provide senior personnel positioned at both the current Drilling Location and the New Drilling Location.
 KERUI radio and telephone contact will be ensured and between both locations
 KERUI will complete equipment Load List by priority. The equipment & materials load list will be on an as need - first required – last required basis.
 KERUI will identify equipment Load types by hazard or by weight i.e. heavy Loads – Wide Loads – Dangerous Goods.
 KERUI will ensure all Cranes have been properly certified by a recognized inspection organization
 KERUI will complete an inspection of all Cranes prior to acceptance – the inspection is to be recorded with all inspection items listed and checked
 KERUI will conduct Safety Meetings with all involved KERUI supervisory and general labor prior to rig down and load of vehicles.
 KERUI will conduct Safety Meetings with all Crane Operators & Truck Drivers prior to rig down and load of vehicles.
 KERUI will conduct Safety Meetings with all Truck Drivers and assigned Sub Contractor Truck Pushes prior to rig down and load of vehicles.
 KERUI will conduct Safety Meetings or Tool Box Talks as required.
 Daily KERUI Crew meetings will continue
 Daily Crew meetings will occur with KERUI Yemeni Subcontractor staff – translation for Arabic Speakers to be provided – Safety Forms to be signed.
Loading & Unloading Procedures
 Establish requirements and confirm competence and suitability of supervisors, labor and hardware.
 Gross weight to be known for each lift
 Certified slings and associated equipment identified and allocated for lift.
 All Lifting equipment to be inspected and suitable for each lift – non certified lifting equipment to be removed and destroyed.
 Banks man or signalman competent for the task dedicated for each lift
 Where possible Trucks will back under or out from under the lift to reduce crane movement - in particular for heavy and decidedly complicated lifts
 Conduct Pre Job Safety meeting prior to each days lifting and/or tool Box Talk prior to any Heavy or Tandem Lifts, or Lifts requiring a permit.
Establish Convoy Procedures
 Distance between trucks will average 10 meters
 Speed limits will be established at 40 KMPH maximum
 Conduct Pre Job Safety meeting – as required
Pre-departure Checks
 Loads in correct position on vehicles and properly secured. I.e. chain and boomers
 Trucks full fueled, drivers prepared drivers prepared with clear directions
 Convoy requirements understood
 Road hazards identified
 Contingencies in place and understood
 Conduct Pre Job Safety meeting – as required
Rig Move Management & Logistics Plan
Rig Equipment & Materials Logistics Register
New Location Offloading and Rig up Crew
Name Position Signature
1
2
3
4
5
6
7
8
9
10
11
12
13
14
14
Old Location Loading Crew
Name Position Signature
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
Rig Move Management & Logistics Plan
Pre-Job Safety Meeting – Rig Crews Groups # 1 & # 2
No. Name Position Signature
 Correct PPE – boots, coveralls, hardhat, gloves & hardhat.
 Safety Belts and Harness to be worn for working at heights.
 Signal man / Banks man identified and known.
 Proper communication with Load Master and Rig Manager
 No personnel to ride on loads.
 Use Tag Lines for all lifts.
 Do not stand or walk under suspended loads.
 Do not leave loads unattended at any time.
 Avoid sharp bends in slings – set loads on blocking and
never set loads directly on slings
 Check the SWL of all slings, chains, wire rope before using.
 Inspect all rigging equipment prior to use.
 Hand signals understood.
 Emergency Stop Signal understood
 Operator to obey only one rigger or signalman.
 Immediately discard defective lifting equipment
 Do not tie knots in sling chain, rope slings or wire rope
 Do not use rope for rigging or lifting loads
 At any time rig personnel can stop or suspend work if the
situation appears unsafe.
 Pre-job safety meeting or Tool Box Talks to be conducted on
an as need basis
 Stop Cards to be completed during rig moves
 All accidents and near misses t be reported
 Permits to be used for heavy lifts or tandem lifts.
1 Yu Xiang Dong R.M
2 Li Yanhao Electrician
4 Zhao Tinghai Mechanic
5 Shang Taigang Chief Motorman
6 You Shui Engineer
7 Xu Binhe HSE Officer
8 Lei Yong T.P
10 Tian Chao Driller
11 Liu Bo Driller
12 Ma Wenming Camp Boss
13 Moman Mansour Shakir Welder Man
14 Mohamed Jassem
Mohamed
F.L Op.
15 Mohammed Ali Wali F.L Op.
16 Ali Khalel Crane Op.
17 Latif Crane Op.
18 Sahar Kqdhim mouly A.D
19 Salah Derrickman
20 Hashim Derrickman
21 Hussin Floorman
22 Kadhum Kader Floorman
23 Hussin Abdul khalid Roustabout
24 Ali Naaim Roustabout
25 Msiar Muazi Roustabout
26 Waleed A.D
27 Ather Abdul Sanad Derrickman
28 Ali Mahdi Derrickman
Additional Items or Comments: H
Meeting Chairman Signature: Date:
Rig Move Management & Logistics Plan
Pre Rig Move Crane Safety Inspection Procedures
Purpose of the Guideline
The purpose of the guideline is to describe the extent to which contractor and subcontractor-operated cranes, including those which are owned, rented, or leased, shall be inspected
prior to the start of Rig Move activities. General inspections will occur at the beginning of each workday or shift.
Definition and Purpose of Inspections
The Pre-Rig Move safety inspection of sub-contractor-operated cranes comprises brief visual and operational examinations of specified accessible components to determine that
the cranes are safe to operate.
Recording Inspections
The Pre-Rig-Move and daily safety inspections of cranes shall be recorded on the KERUI Log of Daily Crane Safety Inspections.
Detection of any crane safety deficiency shall be recorded on the log, whether the deficiency is corrected immediately or at some other time during the workday or shift. The
deficiency shall be reported immediately to the KERUI Supervisor in charge, and subsequently to Presage Drilling.
Log entries in the date blocks shall be as provided on the form. If more than one deficiency must be noted in the block, place an asterisk in the block and one after Dated
Comments;
Retention and Distribution of Completed Logs
The current and last completed log shall be kept in an envelope in the crane cab.
Additional forms are should be available upon request from KERUI and the Crane Sub Contractor Company.
Original copies of completed logs are to be entered in the KERUI Safety Register - it is advisable to keep the original copies because due to critical entries such as first indication of
wire rope wear or subsequent further deterioration.
Classification and Correction of Deficiencies
Serious
 Definition: A deficiency which does not render any part of the crane unsafe, but does indicate the development of a more serious unsafe condition.
 Action: Required to be closely re-inspected during each daily safety inspection of the crane to the extent necessary to properly evaluate the deficiency.
Non-Serious
 Definition: A deficiency which, in the event the operation of the crane is continued, serious injury or damage is unlikely.
 Action: Prior to the end of the work day or shift, inform the responsible supervisor, who shall issue appropriate instructions for corrections of the deficiency.
Minor
 Definition: A deficiency which does not render any part of the crane unsafe, but does indicate the development of a more serious unsafe condition.
 Action: Required to be closely re-inspected during each daily safety inspection of the crane to the extent necessary to properly evaluate the deficiency.
Rig Move Management & Logistics Plan
Crane Safety Inspection Procedures
General Inspection Requirements
Structural:
 Inspect outriggers, main and jib boom for damage or malfunction.
 Operationally inspect outriggers for proper response to controls and for unhindered full extension and set.
 Visually inspect accessible areas of lattice booms of bent or broken members and for missing pin-keepers.
 Operationally inspect box-type booms for malfunctions in all movements and for evidence of binding and hydraulic system leaks.
 Wire rope and reeving running lines for damage or wear; reeving for correctness.
 Limit visual inspection to that portion required for the reeving on the crane. Un-inspected portions should be inspected when different reeving requires additional line.
 Running lines must be observed during regular operation to detect occurrences of any damage, excessive twisting, and incorrect reeling.
 Known minor deficiencies must be closely reexamined visually during each inspection to determine if further deterioration has occurred.
 Newly arrived cranes, and those which are last operated by others, must be visually examined to determine that the reeving is in accordance with the crane manufacturer’s
specifications.
 Hooks: Cracks or distortions. Blocks: Cracks in housing, binding swivel, broken or worn sheaves.
 Visually examine hooks for evidence or indication of cracks and distortions; if a hook has a visible twist, spread or crack, the responsible supervisor must be notified
immediately, and the hook shall not be used until approved or replaced.
 Visually examine all blocks for cracks, binding swivels, and broken or critically worn sheaves; evidence of any of these requires that the responsible supervisor be notified
immediately, and that block shall not be used until approved or replaced.
Electrical Systems: Malfunctions
 Visually inspect all readily accessible exposed wiring and switches for damage.
 Visually inspect all external headlamps, signal, and running lights for damaged or broken lenses; test all lights for operability.
 Actuate each manual electrical switch to determine that it operates as required by energizing the electrical device, light, or signal which it controls.
 Safety Devices and Indicators: Hook latch, boom angle indicator, backup alarm, etc., for correct operation.
 Visually examine each hook latch for operability, alignment, and proper contact of the latch with the inside face of the hook.
 Observe movements of the boom angle indicator to determine that it operates properly throughout its operational range as designed for the crane.
 Actuate backup alarms to determine operability and proper response to controls or movements of the crane.
 Air and Hydraulic Systems: Leaks, damage and deterioration. Visually inspect all readily accessible air and hydraulic lines, hoses, and fittings for evidence of leaks, damage
or deterioration.
 Air systems: Observe gauges for steady drop of pressure; listen for the sound of escaping air which could indicate damage or loose fittings; visually examine observable
abraded, dented, or cut lines and hoses.
 Hydraulic systems: Visually inspect accessible hoses for leaks through the hoses and fittings; visually inspect accessible hoses and fittings for cuts, abrasions, twists,
pinches, burrs, and abnormal enlargements.
Controls: Wear, lubrication, adjustments, and interference.
 Manipulate each control to detect malfunctions, and lack of proper response of equipment to control movements.
 Visually examine accessible control components for interference and lack of proper lubrication.
Miscellaneous:
 Tires for under inflation and severe cuts, steps and handholds for damage, critical dents in carrier, cracks or broken windows, etc. The malfunction or damage of any readily
visible or accessible component of the crane which is not included elsewhere in the log should be included in this section.
Rig Move Management & Logistics Plan
Crane Safety Pre-move Inspection Procedures
Inspection Protocols OK Minor-comments Non-Serious-comments Serious-comments
1 Outriggers – fully extended
2 Lattice booms
3 Box-type booms
4 Wire rope and reeving running lines
5 Running lines – while crane is active
6 Hooks: Cracks or distortions
7 Blocks: Cracks in housing, binding swivel, broken or worn
sheaves
8 Visually examine all blocks for cracks, binding swivels, and
broken or critically worn sheaves
9 Accessible exposed wiring and switches for damage
10 External headlamps, signal, and running lights
11 Manual electrical switches to determine that it operates as
required by energizing the electrical device, light, or signal
12 Safety Devices and Indicators: Hook latch, boom angle
indicator, backup alarm
13 Visually examine each hook latch for operability, alignment,
and proper contact of the latch
14 Observe movements of the boom angle indicator to
determine that it operates properly
15 Actuate backup alarms
16 Air and Hydraulic Systems: Leaks, damage and deterioration
17 Air systems: Observe gauges for steady drop of pressure;
listen for the sound of escaping air
18 Hydraulic systems: Visually inspect accessible hoses and
fittings.
19 Manipulate each control to detect malfunctions
20 Visually examine accessible control components
21 Tires for under inflation and severe cuts
22 Steps and handholds for damage
23 Critical dents in carrier
24 Cracks or broken windows
25 Malfunction or damage of any readily visible or accessible
component of the crane which is not included elsewhere in
the log
Inspected by: Signature: Date:
Rig Move Management & Logistics Plan
Lifting Equipment - Crane & Fork Lift List
Make and Model SWL DNV Inspection Outstanding Actions Safety Inspection
1
2
3
4
5
6
7
8
9
10
11
12
Comments:
Inspected by: Signature: Date:
Rig Move Management & Logistics Plan
Truck Safety Pre-move Inspection Procedures
Inspection Protocols OK Minor-comments Non-Serious-comments Serious-comments
1 Driver – current license and competent
2 Truck – general appearance & condition
3 Deck/bed condition
4 Retainer Pins available
5 Blocking Timbers available
6 Chain & Boomers – available & condition
7 Headlights, taillights, signal lights & horn
8 Reverse alarm installed
9 Tires for under inflation and severe cuts
10 Steps and handholds for damage
11 Cracks or broken windows
12 Fuel
13 Instructions/directions to next location known
14 Speed limit known and understood
15 Correct PPE
16
Malfunction or damage of any readily visible or
accessible component of the truck which is not
included elsewhere in the inspection
Comments:
Inspected by: Signature: Date:
Rig Move Management & Logistics Plan
Pre Job Safety Meeting –Truck Drivers
No. Name Company Signature
 Trucks are to be parked in order - off the Drilling Location
and in the lay down area beside the Rig. All vehicles are to
be in single rows.
 Drivers will conduct quick inspection of vehicle prior to - go
location and receive load.
 Trucks will come on location one at a time or as instructed
by the Truck Push.
 Drivers will move to clear area and secure load prior to
moving off the Drilling Location – all loads will be chained
with boomers and tie-downs.
 Loads will be backed under when possible to minimize
Crane movement of loads.
 With truck loaded and secured they will move off the Drilling
Location and assemble for Convoy.
 Drivers will conduct quick inspection of vehicle prior leaving
with Convoy.
 Concession Speed limit maximum is 60kph – Convoy speed
is 20 to 40kph maximum
 Distance between Trucks at 10 meters minimum.
 Escort vehicle is to be followed at all times.
 Drivers will not change oil and dump on ground – all waste
oils will be disposed of in waste barrels.
 There is to be no littering or throwing of garbage anywhere
in the TFE Concession.
 If an unsafe situation is apparent all truck drivers are
required to stop work and report the condition all accidents
are to be reported.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
Additional Items or Comments:
Meeting Chairman Signature: Date:
Rig Move Management & Logistics Plan
Pre-Job Safety Meeting – Crane Operators & Forklift Driver(s)
No. Name Company Signature
 Daily Safety Check completed by operator.
 Correct PPE – boots, coveralls, hardhat, gloves & hardhat.
 Operator aware of Safe Working Load – SWL.
 Outriggers to be fully extended – at all times.
 Load charts and boom angle indicators in Crane Cab.
 Hand signals understood.
 Emergency Stop Signal understood
 Operator to obey only one rigger or signalman.
 Signal man identified and known.
 Never start Crane movements until signalman is in sight.
 All hooks to be self-closing.
 No personnel to ride on loads.
 Crane operator not to move loads directly over personnel.
 Avoid sharp bends in slings – set loads on blocking and
never set loads directly on slings.
 Do not stand or walk under suspended loads.
 Do not leave loads unattended at any time.
 Use Tag Lines for all lifts.
 Check the SWL of all slings, chains, wire rope before using.
 Inspect all rigging equipment prior to use.
 Immediately discard defective lifting equipment
 Do not tie knots in sling chain, rope slings or wire rope
 Do not use rope for rigging or lifting loads
 At any time Crane Operators can stop or suspend work if the
situation appears unsafe.
1
2
3
4
5
6
7
8
9
10
11
12
Additional Items or Comments:
Meeting Chairman Signature: Date:

More Related Content

What's hot

Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)
TheSafetyGuru
 
Chemical handling.ppt
Chemical handling.pptChemical handling.ppt
Basic H2S training
Basic H2S training Basic H2S training
Basic H2S training
Tejpal Barnela
 
Powered Industrial Trucks Safety
Powered Industrial Trucks SafetyPowered Industrial Trucks Safety
Powered Industrial Trucks Safety
vtsiri
 
Compressed gas safety
Compressed gas safetyCompressed gas safety
Compressed gas safety
Reliance
 
Webbing Sling
Webbing SlingWebbing Sling
Webbing Sling
ANA ISABEL R.R.
 
Lifting tools
Lifting toolsLifting tools
Lifting tools
List Supplier
 
EIP
EIPEIP
Rig Safety Awareness
Rig Safety AwarenessRig Safety Awareness
Rig Safety Awareness
petroEDGE
 
Lifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptxLifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptx
DrValliammaishanmuga
 
Hse nitish
Hse nitishHse nitish
Hse nitish
Nitish Sharma
 
Introduction to oil & gas health safety environment
Introduction to oil & gas health safety environmentIntroduction to oil & gas health safety environment
Introduction to oil & gas health safety environment
Ir. Puput Risanto, IPM, PMP, PMI-RMP, ASEAN Eng
 
Process Safety Management
Process Safety ManagementProcess Safety Management
Process Safety Management
Triumvirate Environmental
 
Construction Safety Training
Construction Safety TrainingConstruction Safety Training
Construction Safety Training
Ali Kamal Mostofa Rubel
 
Work at height safety
Work at height safetyWork at height safety
Work at height safety
Chandrakant Singh
 
Health And Safety Induction Training
Health And Safety Induction TrainingHealth And Safety Induction Training
Health And Safety Induction Training
edale07
 
Work At Height
Work At HeightWork At Height
Work At Height
James McCann
 
Health & Safety For Water Treatment Plant Operators
Health & Safety For Water Treatment Plant OperatorsHealth & Safety For Water Treatment Plant Operators
Health & Safety For Water Treatment Plant Operators
David Horowitz
 
Crane Safety Training Presentation
Crane Safety Training PresentationCrane Safety Training Presentation
Crane Safety Training Presentation
FAIZ FAREED
 
scaffolding safety.pdf
scaffolding safety.pdfscaffolding safety.pdf
scaffolding safety.pdf
ShahzadaGull1
 

What's hot (20)

Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)
 
Chemical handling.ppt
Chemical handling.pptChemical handling.ppt
Chemical handling.ppt
 
Basic H2S training
Basic H2S training Basic H2S training
Basic H2S training
 
Powered Industrial Trucks Safety
Powered Industrial Trucks SafetyPowered Industrial Trucks Safety
Powered Industrial Trucks Safety
 
Compressed gas safety
Compressed gas safetyCompressed gas safety
Compressed gas safety
 
Webbing Sling
Webbing SlingWebbing Sling
Webbing Sling
 
Lifting tools
Lifting toolsLifting tools
Lifting tools
 
EIP
EIPEIP
EIP
 
Rig Safety Awareness
Rig Safety AwarenessRig Safety Awareness
Rig Safety Awareness
 
Lifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptxLifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptx
 
Hse nitish
Hse nitishHse nitish
Hse nitish
 
Introduction to oil & gas health safety environment
Introduction to oil & gas health safety environmentIntroduction to oil & gas health safety environment
Introduction to oil & gas health safety environment
 
Process Safety Management
Process Safety ManagementProcess Safety Management
Process Safety Management
 
Construction Safety Training
Construction Safety TrainingConstruction Safety Training
Construction Safety Training
 
Work at height safety
Work at height safetyWork at height safety
Work at height safety
 
Health And Safety Induction Training
Health And Safety Induction TrainingHealth And Safety Induction Training
Health And Safety Induction Training
 
Work At Height
Work At HeightWork At Height
Work At Height
 
Health & Safety For Water Treatment Plant Operators
Health & Safety For Water Treatment Plant OperatorsHealth & Safety For Water Treatment Plant Operators
Health & Safety For Water Treatment Plant Operators
 
Crane Safety Training Presentation
Crane Safety Training PresentationCrane Safety Training Presentation
Crane Safety Training Presentation
 
scaffolding safety.pdf
scaffolding safety.pdfscaffolding safety.pdf
scaffolding safety.pdf
 

Similar to Rig Move Management and Logistics Plan.doc

Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
VasudevaRajuDantulur1
 
Truck crane training bill brown
Truck crane training bill brownTruck crane training bill brown
Truck crane training bill brown
Bill Brown
 
Crane Operation - Lifting
Crane Operation -  LiftingCrane Operation -  Lifting
Crane Operation - Lifting
hafiz abdul majid
 
Lifting plan
Lifting planLifting plan
Lifting plan
tnsv22
 
Aerial Lift Safety Training by ANSV
Aerial Lift Safety Training by ANSVAerial Lift Safety Training by ANSV
Aerial Lift Safety Training by ANSV
Atlantic Training, LLC.
 
IZAJE DE CARGA EN MANIOBRAS PARA OPERADORES DE CARGA
IZAJE DE CARGA EN MANIOBRAS PARA OPERADORES DE CARGAIZAJE DE CARGA EN MANIOBRAS PARA OPERADORES DE CARGA
IZAJE DE CARGA EN MANIOBRAS PARA OPERADORES DE CARGA
ssuser9df777
 
Mechanical Handling updated.ppt
Mechanical Handling updated.pptMechanical Handling updated.ppt
Mechanical Handling updated.ppt
CheDillon1
 
update 20feb1
update 20feb1update 20feb1
Safe lifting practices
Safe lifting practicesSafe lifting practices
Safe lifting practices
Viktor Bily
 
1910.179 osha class
1910.179 osha class1910.179 osha class
1910.179 osha class
Bill Brown
 
Overhead Crane Safety Training purpose.pdf
Overhead Crane Safety Training purpose.pdfOverhead Crane Safety Training purpose.pdf
Overhead Crane Safety Training purpose.pdf
ssusere30a9a
 
Cranes and Derricks-2.PPT
Cranes and Derricks-2.PPTCranes and Derricks-2.PPT
Cranes and Derricks-2.PPT
HesamEsfandi
 
Overhead-Cranes safety training.ppt
Overhead-Cranes safety training.pptOverhead-Cranes safety training.ppt
Overhead-Cranes safety training.ppt
RazFazwan
 
Quality Control Operator Training &.pptx
Quality Control Operator Training &.pptxQuality Control Operator Training &.pptx
Quality Control Operator Training &.pptx
AizazFarhat3
 
construction macheinery Safety.pdf
construction macheinery Safety.pdfconstruction macheinery Safety.pdf
construction macheinery Safety.pdf
Bimal Chandra Das
 
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industry
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industryCrane & Lifting Safety.ppt Crane lifting safety useful for construction industry
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industry
Ramana Reddy G
 
Crane operator safety procedure
Crane operator safety procedureCrane operator safety procedure
Crane operator safety procedure
Abdul Shukur
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
UTA_AST-Rigging.pptx
UTA_AST-Rigging.pptxUTA_AST-Rigging.pptx
UTA_AST-Rigging.pptx
YazeedAlhafnawi2
 
HSE
HSEHSE

Similar to Rig Move Management and Logistics Plan.doc (20)

Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
 
Truck crane training bill brown
Truck crane training bill brownTruck crane training bill brown
Truck crane training bill brown
 
Crane Operation - Lifting
Crane Operation -  LiftingCrane Operation -  Lifting
Crane Operation - Lifting
 
Lifting plan
Lifting planLifting plan
Lifting plan
 
Aerial Lift Safety Training by ANSV
Aerial Lift Safety Training by ANSVAerial Lift Safety Training by ANSV
Aerial Lift Safety Training by ANSV
 
IZAJE DE CARGA EN MANIOBRAS PARA OPERADORES DE CARGA
IZAJE DE CARGA EN MANIOBRAS PARA OPERADORES DE CARGAIZAJE DE CARGA EN MANIOBRAS PARA OPERADORES DE CARGA
IZAJE DE CARGA EN MANIOBRAS PARA OPERADORES DE CARGA
 
Mechanical Handling updated.ppt
Mechanical Handling updated.pptMechanical Handling updated.ppt
Mechanical Handling updated.ppt
 
update 20feb1
update 20feb1update 20feb1
update 20feb1
 
Safe lifting practices
Safe lifting practicesSafe lifting practices
Safe lifting practices
 
1910.179 osha class
1910.179 osha class1910.179 osha class
1910.179 osha class
 
Overhead Crane Safety Training purpose.pdf
Overhead Crane Safety Training purpose.pdfOverhead Crane Safety Training purpose.pdf
Overhead Crane Safety Training purpose.pdf
 
Cranes and Derricks-2.PPT
Cranes and Derricks-2.PPTCranes and Derricks-2.PPT
Cranes and Derricks-2.PPT
 
Overhead-Cranes safety training.ppt
Overhead-Cranes safety training.pptOverhead-Cranes safety training.ppt
Overhead-Cranes safety training.ppt
 
Quality Control Operator Training &.pptx
Quality Control Operator Training &.pptxQuality Control Operator Training &.pptx
Quality Control Operator Training &.pptx
 
construction macheinery Safety.pdf
construction macheinery Safety.pdfconstruction macheinery Safety.pdf
construction macheinery Safety.pdf
 
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industry
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industryCrane & Lifting Safety.ppt Crane lifting safety useful for construction industry
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industry
 
Crane operator safety procedure
Crane operator safety procedureCrane operator safety procedure
Crane operator safety procedure
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
 
UTA_AST-Rigging.pptx
UTA_AST-Rigging.pptxUTA_AST-Rigging.pptx
UTA_AST-Rigging.pptx
 
HSE
HSEHSE
HSE
 

Recently uploaded

john krisinger-the science and history of the alcoholic beverage.pptx
john krisinger-the science and history of the alcoholic beverage.pptxjohn krisinger-the science and history of the alcoholic beverage.pptx
john krisinger-the science and history of the alcoholic beverage.pptx
Madan Karki
 
cnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classicationcnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classication
SakkaravarthiShanmug
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
AjmalKhan50578
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
Roger Rozario
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
gowrishankartb2005
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
artificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptxartificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptx
GauravCar
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
Nada Hikmah
 
BRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdfBRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdf
LAXMAREDDY22
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
Gino153088
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 

Recently uploaded (20)

john krisinger-the science and history of the alcoholic beverage.pptx
john krisinger-the science and history of the alcoholic beverage.pptxjohn krisinger-the science and history of the alcoholic beverage.pptx
john krisinger-the science and history of the alcoholic beverage.pptx
 
cnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classicationcnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classication
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
artificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptxartificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptx
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
 
BRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdfBRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdf
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 

Rig Move Management and Logistics Plan.doc

  • 1. Rig Move Management & Logistics Plan Introduction: This Rig Move Plan & Check List will address the personnel requirements, equipment requirements, responsibilities, specific procedures and contingency plans. General Planning  KERUI HSE will conduct a road and new location survey prior to the movement of any equipment – Map to be drawn, areas of concern will be identified.  KERUI will provide senior personnel positioned at both the current Drilling Location and the New Drilling Location.  KERUI radio and telephone contact will be ensured and between both locations  KERUI will complete equipment Load List by priority. The equipment & materials load list will be on an as need - first required – last required basis.  KERUI will identify equipment Load types by hazard or by weight i.e. heavy Loads – Wide Loads – Dangerous Goods.  KERUI will ensure all Cranes have been properly certified by a recognized inspection organization  KERUI will complete an inspection of all Cranes prior to acceptance – the inspection is to be recorded with all inspection items listed and checked  KERUI will conduct Safety Meetings with all involved KERUI supervisory and general labor prior to rig down and load of vehicles.  KERUI will conduct Safety Meetings with all Crane Operators & Truck Drivers prior to rig down and load of vehicles.  KERUI will conduct Safety Meetings with all Truck Drivers and assigned Sub Contractor Truck Pushes prior to rig down and load of vehicles.  KERUI will conduct Safety Meetings or Tool Box Talks as required.  Daily KERUI Crew meetings will continue  Daily Crew meetings will occur with KERUI Yemeni Subcontractor staff – translation for Arabic Speakers to be provided – Safety Forms to be signed. Loading & Unloading Procedures  Establish requirements and confirm competence and suitability of supervisors, labor and hardware.  Gross weight to be known for each lift  Certified slings and associated equipment identified and allocated for lift.  All Lifting equipment to be inspected and suitable for each lift – non certified lifting equipment to be removed and destroyed.  Banks man or signalman competent for the task dedicated for each lift  Where possible Trucks will back under or out from under the lift to reduce crane movement - in particular for heavy and decidedly complicated lifts  Conduct Pre Job Safety meeting prior to each days lifting and/or tool Box Talk prior to any Heavy or Tandem Lifts, or Lifts requiring a permit. Establish Convoy Procedures  Distance between trucks will average 10 meters  Speed limits will be established at 40 KMPH maximum  Conduct Pre Job Safety meeting – as required Pre-departure Checks  Loads in correct position on vehicles and properly secured. I.e. chain and boomers  Trucks full fueled, drivers prepared drivers prepared with clear directions  Convoy requirements understood  Road hazards identified  Contingencies in place and understood  Conduct Pre Job Safety meeting – as required
  • 2. Rig Move Management & Logistics Plan Rig Equipment & Materials Logistics Register New Location Offloading and Rig up Crew Name Position Signature 1 2 3 4 5 6 7 8 9 10 11 12 13 14 14 Old Location Loading Crew Name Position Signature 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
  • 3. Rig Move Management & Logistics Plan Pre-Job Safety Meeting – Rig Crews Groups # 1 & # 2 No. Name Position Signature  Correct PPE – boots, coveralls, hardhat, gloves & hardhat.  Safety Belts and Harness to be worn for working at heights.  Signal man / Banks man identified and known.  Proper communication with Load Master and Rig Manager  No personnel to ride on loads.  Use Tag Lines for all lifts.  Do not stand or walk under suspended loads.  Do not leave loads unattended at any time.  Avoid sharp bends in slings – set loads on blocking and never set loads directly on slings  Check the SWL of all slings, chains, wire rope before using.  Inspect all rigging equipment prior to use.  Hand signals understood.  Emergency Stop Signal understood  Operator to obey only one rigger or signalman.  Immediately discard defective lifting equipment  Do not tie knots in sling chain, rope slings or wire rope  Do not use rope for rigging or lifting loads  At any time rig personnel can stop or suspend work if the situation appears unsafe.  Pre-job safety meeting or Tool Box Talks to be conducted on an as need basis  Stop Cards to be completed during rig moves  All accidents and near misses t be reported  Permits to be used for heavy lifts or tandem lifts. 1 Yu Xiang Dong R.M 2 Li Yanhao Electrician 4 Zhao Tinghai Mechanic 5 Shang Taigang Chief Motorman 6 You Shui Engineer 7 Xu Binhe HSE Officer 8 Lei Yong T.P 10 Tian Chao Driller 11 Liu Bo Driller 12 Ma Wenming Camp Boss 13 Moman Mansour Shakir Welder Man 14 Mohamed Jassem Mohamed F.L Op. 15 Mohammed Ali Wali F.L Op. 16 Ali Khalel Crane Op. 17 Latif Crane Op. 18 Sahar Kqdhim mouly A.D 19 Salah Derrickman 20 Hashim Derrickman 21 Hussin Floorman 22 Kadhum Kader Floorman 23 Hussin Abdul khalid Roustabout 24 Ali Naaim Roustabout 25 Msiar Muazi Roustabout 26 Waleed A.D 27 Ather Abdul Sanad Derrickman 28 Ali Mahdi Derrickman Additional Items or Comments: H Meeting Chairman Signature: Date:
  • 4. Rig Move Management & Logistics Plan Pre Rig Move Crane Safety Inspection Procedures Purpose of the Guideline The purpose of the guideline is to describe the extent to which contractor and subcontractor-operated cranes, including those which are owned, rented, or leased, shall be inspected prior to the start of Rig Move activities. General inspections will occur at the beginning of each workday or shift. Definition and Purpose of Inspections The Pre-Rig Move safety inspection of sub-contractor-operated cranes comprises brief visual and operational examinations of specified accessible components to determine that the cranes are safe to operate. Recording Inspections The Pre-Rig-Move and daily safety inspections of cranes shall be recorded on the KERUI Log of Daily Crane Safety Inspections. Detection of any crane safety deficiency shall be recorded on the log, whether the deficiency is corrected immediately or at some other time during the workday or shift. The deficiency shall be reported immediately to the KERUI Supervisor in charge, and subsequently to Presage Drilling. Log entries in the date blocks shall be as provided on the form. If more than one deficiency must be noted in the block, place an asterisk in the block and one after Dated Comments; Retention and Distribution of Completed Logs The current and last completed log shall be kept in an envelope in the crane cab. Additional forms are should be available upon request from KERUI and the Crane Sub Contractor Company. Original copies of completed logs are to be entered in the KERUI Safety Register - it is advisable to keep the original copies because due to critical entries such as first indication of wire rope wear or subsequent further deterioration. Classification and Correction of Deficiencies Serious  Definition: A deficiency which does not render any part of the crane unsafe, but does indicate the development of a more serious unsafe condition.  Action: Required to be closely re-inspected during each daily safety inspection of the crane to the extent necessary to properly evaluate the deficiency. Non-Serious  Definition: A deficiency which, in the event the operation of the crane is continued, serious injury or damage is unlikely.  Action: Prior to the end of the work day or shift, inform the responsible supervisor, who shall issue appropriate instructions for corrections of the deficiency. Minor  Definition: A deficiency which does not render any part of the crane unsafe, but does indicate the development of a more serious unsafe condition.  Action: Required to be closely re-inspected during each daily safety inspection of the crane to the extent necessary to properly evaluate the deficiency.
  • 5. Rig Move Management & Logistics Plan Crane Safety Inspection Procedures General Inspection Requirements Structural:  Inspect outriggers, main and jib boom for damage or malfunction.  Operationally inspect outriggers for proper response to controls and for unhindered full extension and set.  Visually inspect accessible areas of lattice booms of bent or broken members and for missing pin-keepers.  Operationally inspect box-type booms for malfunctions in all movements and for evidence of binding and hydraulic system leaks.  Wire rope and reeving running lines for damage or wear; reeving for correctness.  Limit visual inspection to that portion required for the reeving on the crane. Un-inspected portions should be inspected when different reeving requires additional line.  Running lines must be observed during regular operation to detect occurrences of any damage, excessive twisting, and incorrect reeling.  Known minor deficiencies must be closely reexamined visually during each inspection to determine if further deterioration has occurred.  Newly arrived cranes, and those which are last operated by others, must be visually examined to determine that the reeving is in accordance with the crane manufacturer’s specifications.  Hooks: Cracks or distortions. Blocks: Cracks in housing, binding swivel, broken or worn sheaves.  Visually examine hooks for evidence or indication of cracks and distortions; if a hook has a visible twist, spread or crack, the responsible supervisor must be notified immediately, and the hook shall not be used until approved or replaced.  Visually examine all blocks for cracks, binding swivels, and broken or critically worn sheaves; evidence of any of these requires that the responsible supervisor be notified immediately, and that block shall not be used until approved or replaced. Electrical Systems: Malfunctions  Visually inspect all readily accessible exposed wiring and switches for damage.  Visually inspect all external headlamps, signal, and running lights for damaged or broken lenses; test all lights for operability.  Actuate each manual electrical switch to determine that it operates as required by energizing the electrical device, light, or signal which it controls.  Safety Devices and Indicators: Hook latch, boom angle indicator, backup alarm, etc., for correct operation.  Visually examine each hook latch for operability, alignment, and proper contact of the latch with the inside face of the hook.  Observe movements of the boom angle indicator to determine that it operates properly throughout its operational range as designed for the crane.  Actuate backup alarms to determine operability and proper response to controls or movements of the crane.  Air and Hydraulic Systems: Leaks, damage and deterioration. Visually inspect all readily accessible air and hydraulic lines, hoses, and fittings for evidence of leaks, damage or deterioration.  Air systems: Observe gauges for steady drop of pressure; listen for the sound of escaping air which could indicate damage or loose fittings; visually examine observable abraded, dented, or cut lines and hoses.  Hydraulic systems: Visually inspect accessible hoses for leaks through the hoses and fittings; visually inspect accessible hoses and fittings for cuts, abrasions, twists, pinches, burrs, and abnormal enlargements. Controls: Wear, lubrication, adjustments, and interference.  Manipulate each control to detect malfunctions, and lack of proper response of equipment to control movements.  Visually examine accessible control components for interference and lack of proper lubrication. Miscellaneous:  Tires for under inflation and severe cuts, steps and handholds for damage, critical dents in carrier, cracks or broken windows, etc. The malfunction or damage of any readily visible or accessible component of the crane which is not included elsewhere in the log should be included in this section.
  • 6. Rig Move Management & Logistics Plan Crane Safety Pre-move Inspection Procedures Inspection Protocols OK Minor-comments Non-Serious-comments Serious-comments 1 Outriggers – fully extended 2 Lattice booms 3 Box-type booms 4 Wire rope and reeving running lines 5 Running lines – while crane is active 6 Hooks: Cracks or distortions 7 Blocks: Cracks in housing, binding swivel, broken or worn sheaves 8 Visually examine all blocks for cracks, binding swivels, and broken or critically worn sheaves 9 Accessible exposed wiring and switches for damage 10 External headlamps, signal, and running lights 11 Manual electrical switches to determine that it operates as required by energizing the electrical device, light, or signal 12 Safety Devices and Indicators: Hook latch, boom angle indicator, backup alarm 13 Visually examine each hook latch for operability, alignment, and proper contact of the latch 14 Observe movements of the boom angle indicator to determine that it operates properly 15 Actuate backup alarms 16 Air and Hydraulic Systems: Leaks, damage and deterioration 17 Air systems: Observe gauges for steady drop of pressure; listen for the sound of escaping air 18 Hydraulic systems: Visually inspect accessible hoses and fittings. 19 Manipulate each control to detect malfunctions 20 Visually examine accessible control components 21 Tires for under inflation and severe cuts 22 Steps and handholds for damage 23 Critical dents in carrier 24 Cracks or broken windows 25 Malfunction or damage of any readily visible or accessible component of the crane which is not included elsewhere in the log Inspected by: Signature: Date:
  • 7. Rig Move Management & Logistics Plan Lifting Equipment - Crane & Fork Lift List Make and Model SWL DNV Inspection Outstanding Actions Safety Inspection 1 2 3 4 5 6 7 8 9 10 11 12 Comments: Inspected by: Signature: Date:
  • 8. Rig Move Management & Logistics Plan Truck Safety Pre-move Inspection Procedures Inspection Protocols OK Minor-comments Non-Serious-comments Serious-comments 1 Driver – current license and competent 2 Truck – general appearance & condition 3 Deck/bed condition 4 Retainer Pins available 5 Blocking Timbers available 6 Chain & Boomers – available & condition 7 Headlights, taillights, signal lights & horn 8 Reverse alarm installed 9 Tires for under inflation and severe cuts 10 Steps and handholds for damage 11 Cracks or broken windows 12 Fuel 13 Instructions/directions to next location known 14 Speed limit known and understood 15 Correct PPE 16 Malfunction or damage of any readily visible or accessible component of the truck which is not included elsewhere in the inspection Comments: Inspected by: Signature: Date:
  • 9. Rig Move Management & Logistics Plan Pre Job Safety Meeting –Truck Drivers No. Name Company Signature  Trucks are to be parked in order - off the Drilling Location and in the lay down area beside the Rig. All vehicles are to be in single rows.  Drivers will conduct quick inspection of vehicle prior to - go location and receive load.  Trucks will come on location one at a time or as instructed by the Truck Push.  Drivers will move to clear area and secure load prior to moving off the Drilling Location – all loads will be chained with boomers and tie-downs.  Loads will be backed under when possible to minimize Crane movement of loads.  With truck loaded and secured they will move off the Drilling Location and assemble for Convoy.  Drivers will conduct quick inspection of vehicle prior leaving with Convoy.  Concession Speed limit maximum is 60kph – Convoy speed is 20 to 40kph maximum  Distance between Trucks at 10 meters minimum.  Escort vehicle is to be followed at all times.  Drivers will not change oil and dump on ground – all waste oils will be disposed of in waste barrels.  There is to be no littering or throwing of garbage anywhere in the TFE Concession.  If an unsafe situation is apparent all truck drivers are required to stop work and report the condition all accidents are to be reported. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Additional Items or Comments: Meeting Chairman Signature: Date:
  • 10. Rig Move Management & Logistics Plan Pre-Job Safety Meeting – Crane Operators & Forklift Driver(s) No. Name Company Signature  Daily Safety Check completed by operator.  Correct PPE – boots, coveralls, hardhat, gloves & hardhat.  Operator aware of Safe Working Load – SWL.  Outriggers to be fully extended – at all times.  Load charts and boom angle indicators in Crane Cab.  Hand signals understood.  Emergency Stop Signal understood  Operator to obey only one rigger or signalman.  Signal man identified and known.  Never start Crane movements until signalman is in sight.  All hooks to be self-closing.  No personnel to ride on loads.  Crane operator not to move loads directly over personnel.  Avoid sharp bends in slings – set loads on blocking and never set loads directly on slings.  Do not stand or walk under suspended loads.  Do not leave loads unattended at any time.  Use Tag Lines for all lifts.  Check the SWL of all slings, chains, wire rope before using.  Inspect all rigging equipment prior to use.  Immediately discard defective lifting equipment  Do not tie knots in sling chain, rope slings or wire rope  Do not use rope for rigging or lifting loads  At any time Crane Operators can stop or suspend work if the situation appears unsafe. 1 2 3 4 5 6 7 8 9 10 11 12 Additional Items or Comments: Meeting Chairman Signature: Date: