SlideShare a Scribd company logo
1 of 6
1
Review of Need for Grade-Separations
Five Locations
Statement of Work
Background:
On the morning of September 18, 2013, a VIA rail train and an OC Transpo
double-decker bus collided at the Transitway rail crossing just north of the
Fallowfield transit station. Six people sustained fatal injuries from the accident.
On December 2, 2015, the Transportation Safety Board made a series of
recommendations following its investigation into the accident, one of which is as
follows:
 TSB Recommendation R15-05: The Board recommends that the City of
Ottawa reconsider the need for grade separation at the Woodroffe Avenue,
Transitway and Fallowfield Road level crossings.
In the Barrhaven portion of the VIA Rail Smiths Falls Subdivision there exist
seven level crossings (Figure 1):
 Merivale Road (Mile 1.63)
 Woodroffe Avenue (Mile 3.28)
 Southwest Transitway (3.30)
 Fallowfield Road (Mile 3.88)
 Greenbank Road (Mile 5.1)
 Jockvale Road (Mile 5.73)
 Strandherd Drive (Mile 6.81)
2
Figure 1: At-Grade Crossing Locations
Of these seven level crossings, construction is underway at Greenbank Road for
a grade separation and along Strandherd Drive design has partially been
completed for a grade separation which is identified in the City’s Transportation
Master Plan (TMP) and tentatively planned to be constructed between 2020 and
2025. Therefore the focus of this study will be on the remaining five locations,
none of which are slated for modifications prior to 2031 as per the TMP roads
growth program.
Environmental Assessments have been completed at four of the five locations,
the exception being Jockvale Road.
A detailed safety assessment was completed on behalf of VIA Rail Canada and
the City of Ottawa in 2014. The report, entitled “Detailed Safety Assessment
Report” and dated December 2014, is available and shall serve as a background
document for this assignment.
3
Scope of Assignment:
Study Budget: $250K
Duration of Study: 10 months from award of contract to a consulting engineering
firm to undertake the work.
Objectives:
 To address the TSB’s recommendation regarding grade separation
 To review grade separation scenarios at Merivale and Jockvale Roads
Tasks:
(1) Information Review and Analysis
 Review and compile information for each of these crossing based on
previous City studies including EAs and preliminary design work, National
Capital Commission Greenbelt Master Plan, VIA safety audits, the TSB
report, and current and future VIA Rail service plans
 Where EAs exist summarize what were the identified issues, impacts,
benefits and risks associated with underpasses and overpasses at each
location. For Jockvale (where no EA exists), make best efforts to identify
issues, impacts, benefits and risks for underpass and overpass options.
 Research best practices and legislations in North America regarding
railway-roadway crossings to understand the triggers used to decide to
provide for grade separated crossings. Create a framework for such
triggers that could be used here in Ottawa. Identify what are the possible
applicable outcomes from current CTA rules and policies.
(2) Traffic Analysis
 Using updated City and VIA traffic data, assess the cross-product and
occupant product at each location. This is to include a presentation of
similarly produced analysis from the past (e.g. last 15 years) and new
projections for the future (e.g. next 15 years).
 Incorporate as part of this traffic analysis a review component that
examines the safety of all who cross at these locations including walking,
cycling, transit, automobile and truck
(3) Geotechnical Analysis
 Gather available geotechnical information
 If borehole and geotechnical information is lacking, particularly for the
Jockvale location, identify the need for such. [This additional field work
would be done by a separate party outside this study budget.]
4
 Identify and assess geotechnical issues that may be of concern for the
construction of grade-separations at the five locations.
(4) Grade-Separation Analysis
 Based on the research, information collected and analysis done for tasks
1, 2 and 3, review and reconfirm the previous recommended grade
separation options for the four locations
 For the Jockvale location, develop a conceptual grade separation
 Identify and reconfirm costing estimates (include all planning and design
efforts, property requirements, mitigation, traffic management, detouring
requirements, and appropriate contingencies) for these grade crossing
projects. The estimates shall allow the authorities to seek funding
assistance from senior levels of government.
(5) At-Grade Option
 Identify if there are any additional measures that might be done to improve
safety in the current condition.
(6) Go Forward Plan
 Identify the next steps for the City to move forward with grade-separations,
including any additional studies to address legislative requirements.
(7) Documentation/Deliverables
Monthly progress report identifying work performed, next month anticipated work,
any issue pending, updated schedule.
Draft and Final Study Reports will be prepared to document the entire study
process including the recommended option plans, costing, implementation and
staging plan, and commitments to future action, including external approvals
known to be required.
The Consultant shall assist the City Project Manager in the preparation of a Staff
report and a Microsoft PowerPoint presentation to relevant City Standing
Committees at the completion of the study.
The report shall be formatted in accordance with City guidelines and accessibility
policies.
5
The deliverables for this study include:
 Draft and Final Study Report;
 Project Recommended Plan incorporating concept design drawings of the
preferred design, and other information as identified elsewhere in this
document;
 Project Cost Estimate Report that will allow authorities to seek funding
assistance from senior levels of government for the grade- separated
crossings;
 Geotechnical Analysis Report;
 Maps for recommended cycling and pedestrian facilities shall identify tie-in
to existing and/or possible future network connections. Digital version of
all maps and plans must be in appropriate format conforming to City
CADD and GeoOttawa standards;
The Consultant will be responsible for preparing and distributing the agenda for
any meetings in connection with this Study at least two days before the meeting
date and prepare and distribute minutes of meetings within one week after the
meeting date.
All documentation produced during the course of the Study will be available to
the City both in hard copy and digital formats. Digital copies of written material
will be in MS Word and pdf format. Plans and maps for incorporation into the
Report and Study notices will be provided in jpg and/or pdf format. Conceptual/
functional design drawings will be provided in MicroStation dgn format in
accordance with City CADD standards. All final documents, including the
Draft/Final Report, will also be provided on CD in pdf format.
The Consultant will provide six hard copies and CD digital versions of draft
document, and six hard copies and CD digital versions of Final document.
All relevant background material referenced during the study shall be listed in a
bibliography to be included in the final report.
(8) Consultation/Meetings
The City’s and VIA’s designated Project Managers will provide direction and day-
to-day administration and management for the study. Project Management
meetings with the Consultant Project Manager/Director will be held on an as
required basis.
A Study team comprised of the City, VIA Rail and Consultant Project Managers
and key City and Consultant staff will be established at the study outset. Regular
Study team meetings will be held to provide direction on issues and monitor the
progress of the work. The Consultant shall be responsible for preparing and
distributing the Study Team meeting agenda and notes in a timely manner with
6
minutes to all meetings distributed within one week after the respective meeting.
At this time no public consultation is envisioned due to the technical nature of the
study. It is however anticipated that the Study Team may seek input from the
National Capital Commission given its immediate ownership of lands to the study
area.

More Related Content

What's hot

Scarborough Subway Extension - June 2015 Public Consultation Report
Scarborough Subway Extension - June 2015 Public Consultation ReportScarborough Subway Extension - June 2015 Public Consultation Report
Scarborough Subway Extension - June 2015 Public Consultation ReportToronto Public Consultation Unit
 
Scarborough Subway Extension Project Assessment - Draft Terms of Reference
Scarborough Subway Extension Project Assessment - Draft Terms of ReferenceScarborough Subway Extension Project Assessment - Draft Terms of Reference
Scarborough Subway Extension Project Assessment - Draft Terms of ReferenceToronto Public Consultation Unit
 
Countywide Transit Network Study: Introductory Public Meeting
Countywide Transit Network Study: Introductory Public MeetingCountywide Transit Network Study: Introductory Public Meeting
Countywide Transit Network Study: Introductory Public MeetingFairfax County
 
Scarborough Subway Extension - Public Meeting Presentation - January/February...
Scarborough Subway Extension - Public Meeting Presentation - January/February...Scarborough Subway Extension - Public Meeting Presentation - January/February...
Scarborough Subway Extension - Public Meeting Presentation - January/February...Toronto Public Consultation Unit
 
Irfp 1819 07 dtx project delivery review services
Irfp 1819 07 dtx project delivery review servicesIrfp 1819 07 dtx project delivery review services
Irfp 1819 07 dtx project delivery review servicesAdina Levin
 
Traffic Access and Impact Study Guidelines & Procedures
Traffic Access and Impact Study Guidelines & ProceduresTraffic Access and Impact Study Guidelines & Procedures
Traffic Access and Impact Study Guidelines & Proceduresgscplanning
 
Resume Bharadwaj
Resume Bharadwaj Resume Bharadwaj
Resume Bharadwaj Bharadwaj B
 
Scarborough Subway Extension - Phase 1 Consultation Report
Scarborough Subway Extension - Phase 1 Consultation ReportScarborough Subway Extension - Phase 1 Consultation Report
Scarborough Subway Extension - Phase 1 Consultation ReportToronto Public Consultation Unit
 
EGK 2011: Construction 03 IRDS
EGK 2011: Construction 03 IRDSEGK 2011: Construction 03 IRDS
EGK 2011: Construction 03 IRDSicebauhaus
 
Resume Bharadwaj
Resume Bharadwaj Resume Bharadwaj
Resume Bharadwaj Bharadwaj B
 
7 ncdot&u senal deladvcurvahor 2010 150p
7   ncdot&u senal deladvcurvahor 2010 150p7   ncdot&u senal deladvcurvahor 2010 150p
7 ncdot&u senal deladvcurvahor 2010 150pSierra Francisco Justo
 
3 Ps Modelling Portfolio 1.002
3  Ps Modelling Portfolio 1.0023  Ps Modelling Portfolio 1.002
3 Ps Modelling Portfolio 1.002paulhstanton
 
North Oakland Community Analysis Final Report
North Oakland Community Analysis Final ReportNorth Oakland Community Analysis Final Report
North Oakland Community Analysis Final ReportSara Barz
 

What's hot (20)

Relief Line Project Assessment Phase 1A Consultation Presentation
Relief Line Project Assessment Phase 1A Consultation PresentationRelief Line Project Assessment Phase 1A Consultation Presentation
Relief Line Project Assessment Phase 1A Consultation Presentation
 
15-03 Relief Line Public Meeting Presentation
15-03 Relief Line Public Meeting Presentation15-03 Relief Line Public Meeting Presentation
15-03 Relief Line Public Meeting Presentation
 
Scarborough Subway Extension - June 2015 Public Consultation Report
Scarborough Subway Extension - June 2015 Public Consultation ReportScarborough Subway Extension - June 2015 Public Consultation Report
Scarborough Subway Extension - June 2015 Public Consultation Report
 
Scarborough Subway Extension Project Assessment - Draft Terms of Reference
Scarborough Subway Extension Project Assessment - Draft Terms of ReferenceScarborough Subway Extension Project Assessment - Draft Terms of Reference
Scarborough Subway Extension Project Assessment - Draft Terms of Reference
 
Relief Line Phase 3 Consultation Report
Relief Line Phase 3 Consultation ReportRelief Line Phase 3 Consultation Report
Relief Line Phase 3 Consultation Report
 
Countywide Transit Network Study: Introductory Public Meeting
Countywide Transit Network Study: Introductory Public MeetingCountywide Transit Network Study: Introductory Public Meeting
Countywide Transit Network Study: Introductory Public Meeting
 
Scarborough Subway Extension - Public Meeting Presentation - January/February...
Scarborough Subway Extension - Public Meeting Presentation - January/February...Scarborough Subway Extension - Public Meeting Presentation - January/February...
Scarborough Subway Extension - Public Meeting Presentation - January/February...
 
Irfp 1819 07 dtx project delivery review services
Irfp 1819 07 dtx project delivery review servicesIrfp 1819 07 dtx project delivery review services
Irfp 1819 07 dtx project delivery review services
 
Traffic Access and Impact Study Guidelines & Procedures
Traffic Access and Impact Study Guidelines & ProceduresTraffic Access and Impact Study Guidelines & Procedures
Traffic Access and Impact Study Guidelines & Procedures
 
Resume Bharadwaj
Resume Bharadwaj Resume Bharadwaj
Resume Bharadwaj
 
Scarborough Subway Extension - Phase 1 Consultation Report
Scarborough Subway Extension - Phase 1 Consultation ReportScarborough Subway Extension - Phase 1 Consultation Report
Scarborough Subway Extension - Phase 1 Consultation Report
 
EGK 2011: Construction 03 IRDS
EGK 2011: Construction 03 IRDSEGK 2011: Construction 03 IRDS
EGK 2011: Construction 03 IRDS
 
Resume Bharadwaj
Resume Bharadwaj Resume Bharadwaj
Resume Bharadwaj
 
7 ncdot&u senal deladvcurvahor 2010 150p
7   ncdot&u senal deladvcurvahor 2010 150p7   ncdot&u senal deladvcurvahor 2010 150p
7 ncdot&u senal deladvcurvahor 2010 150p
 
February Transit Update Presentation
February Transit Update PresentationFebruary Transit Update Presentation
February Transit Update Presentation
 
Nguyen Ngoc An CV
Nguyen Ngoc An CVNguyen Ngoc An CV
Nguyen Ngoc An CV
 
Hector Molina Rivera Resume
Hector Molina Rivera ResumeHector Molina Rivera Resume
Hector Molina Rivera Resume
 
3 Ps Modelling Portfolio 1.002
3  Ps Modelling Portfolio 1.0023  Ps Modelling Portfolio 1.002
3 Ps Modelling Portfolio 1.002
 
Crosstown apwa presentation2016 04-19
Crosstown apwa presentation2016 04-19Crosstown apwa presentation2016 04-19
Crosstown apwa presentation2016 04-19
 
North Oakland Community Analysis Final Report
North Oakland Community Analysis Final ReportNorth Oakland Community Analysis Final Report
North Oakland Community Analysis Final Report
 

Viewers also liked

12 bases del_curriculum
12 bases del_curriculum12 bases del_curriculum
12 bases del_curriculumformaciobcn
 
English assignment- andrew Townsend
English assignment- andrew TownsendEnglish assignment- andrew Townsend
English assignment- andrew Townsendbumbum007
 
Presentacion en la nube
Presentacion en la nubePresentacion en la nube
Presentacion en la nubeGabbs94
 
спецвипуск як і навіщо долучатися до європейського тижня мобільності
спецвипуск  як і навіщо долучатися до європейського тижня мобільностіспецвипуск  як і навіщо долучатися до європейського тижня мобільності
спецвипуск як і навіщо долучатися до європейського тижня мобільностіvelotransport
 
Stem pp for coaches meeting
Stem pp for coaches meetingStem pp for coaches meeting
Stem pp for coaches meetingncmayfield
 
Turning information into insights
Turning information into insightsTurning information into insights
Turning information into insightsIron Mountain
 
2.путевка
2.путевка2.путевка
2.путевкаneznajka_25
 
Dairy Lean Case Study Rory Christie_1607 V3
Dairy Lean Case Study Rory Christie_1607 V3Dairy Lean Case Study Rory Christie_1607 V3
Dairy Lean Case Study Rory Christie_1607 V3Ray McCreadie
 
Layers of the earth
Layers of the earthLayers of the earth
Layers of the earthVinay Parikh
 
L4 Levees And Floodplains
L4 Levees And FloodplainsL4 Levees And Floodplains
L4 Levees And Floodplainstudorgeog
 
Relación de la Tecnologia y el Derecho.
Relación de la Tecnologia y el Derecho.Relación de la Tecnologia y el Derecho.
Relación de la Tecnologia y el Derecho.Arisdelsy
 

Viewers also liked (19)

12 bases del_curriculum
12 bases del_curriculum12 bases del_curriculum
12 bases del_curriculum
 
Normas presentaciones
Normas  presentacionesNormas  presentaciones
Normas presentaciones
 
Aplikācija.
Aplikācija.Aplikācija.
Aplikācija.
 
English assignment- andrew Townsend
English assignment- andrew TownsendEnglish assignment- andrew Townsend
English assignment- andrew Townsend
 
Presentacion en la nube
Presentacion en la nubePresentacion en la nube
Presentacion en la nube
 
спецвипуск як і навіщо долучатися до європейського тижня мобільності
спецвипуск  як і навіщо долучатися до європейського тижня мобільностіспецвипуск  як і навіщо долучатися до європейського тижня мобільності
спецвипуск як і навіщо долучатися до європейського тижня мобільності
 
Power BI preview
Power BI previewPower BI preview
Power BI preview
 
Stem pp for coaches meeting
Stem pp for coaches meetingStem pp for coaches meeting
Stem pp for coaches meeting
 
PRASENJIT SIKDER1
PRASENJIT SIKDER1PRASENJIT SIKDER1
PRASENJIT SIKDER1
 
Iebdinovale
IebdinovaleIebdinovale
Iebdinovale
 
Transcip
TranscipTranscip
Transcip
 
Earthmoon
EarthmoonEarthmoon
Earthmoon
 
Turning information into insights
Turning information into insightsTurning information into insights
Turning information into insights
 
2.путевка
2.путевка2.путевка
2.путевка
 
Dairy Lean Case Study Rory Christie_1607 V3
Dairy Lean Case Study Rory Christie_1607 V3Dairy Lean Case Study Rory Christie_1607 V3
Dairy Lean Case Study Rory Christie_1607 V3
 
Layers of the earth
Layers of the earthLayers of the earth
Layers of the earth
 
Funciones
FuncionesFunciones
Funciones
 
L4 Levees And Floodplains
L4 Levees And FloodplainsL4 Levees And Floodplains
L4 Levees And Floodplains
 
Relación de la Tecnologia y el Derecho.
Relación de la Tecnologia y el Derecho.Relación de la Tecnologia y el Derecho.
Relación de la Tecnologia y el Derecho.
 

Similar to Review of need for grade separations five locations - statement of work

Wynn Transportation Plan
Wynn Transportation PlanWynn Transportation Plan
Wynn Transportation PlanEverettUnited
 
2015 Resume - Private Sector
2015 Resume - Private Sector2015 Resume - Private Sector
2015 Resume - Private SectorBruce L. Wacker
 
Regional Bicycle and Pedestrian Planning Framework
Regional Bicycle and Pedestrian Planning FrameworkRegional Bicycle and Pedestrian Planning Framework
Regional Bicycle and Pedestrian Planning FrameworkRPO America
 
MARTA_Makeover_Exec_Summary_FINAL_072715
MARTA_Makeover_Exec_Summary_FINAL_072715MARTA_Makeover_Exec_Summary_FINAL_072715
MARTA_Makeover_Exec_Summary_FINAL_072715Sarah McColley
 
RFP for Coachella Valley Associated Governments (CVAG)
RFP for Coachella Valley Associated Governments (CVAG)RFP for Coachella Valley Associated Governments (CVAG)
RFP for Coachella Valley Associated Governments (CVAG)apwacoachellavalley
 
Oarc slides c02 assessment workshop
Oarc slides c02 assessment workshop  Oarc slides c02 assessment workshop
Oarc slides c02 assessment workshop pyoungkyova
 
Kings Beach Roundabout Capacity Review
Kings Beach Roundabout Capacity ReviewKings Beach Roundabout Capacity Review
Kings Beach Roundabout Capacity ReviewJerry Dinzes
 
MTC core capacity transit study
MTC core capacity transit studyMTC core capacity transit study
MTC core capacity transit studyAdina Levin
 
Johnson gilmer presentation
Johnson gilmer presentationJohnson gilmer presentation
Johnson gilmer presentationRPO America
 
StevenABert_Project Experience
StevenABert_Project ExperienceStevenABert_Project Experience
StevenABert_Project ExperienceSteven Bert
 
SPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdf
SPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdfSPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdf
SPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdfAdina Levin
 
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...IRJET Journal
 

Similar to Review of need for grade separations five locations - statement of work (20)

Wynn Transportation Plan
Wynn Transportation PlanWynn Transportation Plan
Wynn Transportation Plan
 
2015 Resume - Private Sector
2015 Resume - Private Sector2015 Resume - Private Sector
2015 Resume - Private Sector
 
Regional Bicycle and Pedestrian Planning Framework
Regional Bicycle and Pedestrian Planning FrameworkRegional Bicycle and Pedestrian Planning Framework
Regional Bicycle and Pedestrian Planning Framework
 
MARTA_Makeover_Exec_Summary_FINAL_072715
MARTA_Makeover_Exec_Summary_FINAL_072715MARTA_Makeover_Exec_Summary_FINAL_072715
MARTA_Makeover_Exec_Summary_FINAL_072715
 
RFP for Coachella Valley Associated Governments (CVAG)
RFP for Coachella Valley Associated Governments (CVAG)RFP for Coachella Valley Associated Governments (CVAG)
RFP for Coachella Valley Associated Governments (CVAG)
 
EDC3_Action_Plan_2016-01-01 rev 1
EDC3_Action_Plan_2016-01-01 rev 1EDC3_Action_Plan_2016-01-01 rev 1
EDC3_Action_Plan_2016-01-01 rev 1
 
Oarc slides c02 assessment workshop
Oarc slides c02 assessment workshop  Oarc slides c02 assessment workshop
Oarc slides c02 assessment workshop
 
Scarborough Subway Extension - Phase 2 Presentation
Scarborough Subway Extension - Phase 2 PresentationScarborough Subway Extension - Phase 2 Presentation
Scarborough Subway Extension - Phase 2 Presentation
 
14 04-09 complete streets overview
14 04-09 complete streets overview14 04-09 complete streets overview
14 04-09 complete streets overview
 
Kings Beach Roundabout Capacity Review
Kings Beach Roundabout Capacity ReviewKings Beach Roundabout Capacity Review
Kings Beach Roundabout Capacity Review
 
June Relief Line Update
June Relief Line UpdateJune Relief Line Update
June Relief Line Update
 
Transit Network Plan Update and Financial Strategy
 Transit Network Plan Update and Financial Strategy Transit Network Plan Update and Financial Strategy
Transit Network Plan Update and Financial Strategy
 
MTC core capacity transit study
MTC core capacity transit studyMTC core capacity transit study
MTC core capacity transit study
 
ToR
ToRToR
ToR
 
Johnson gilmer presentation
Johnson gilmer presentationJohnson gilmer presentation
Johnson gilmer presentation
 
Lecture 5.pptx
Lecture 5.pptxLecture 5.pptx
Lecture 5.pptx
 
StevenABert_Project Experience
StevenABert_Project ExperienceStevenABert_Project Experience
StevenABert_Project Experience
 
SPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdf
SPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdfSPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdf
SPUR + TransbayCoalition-Project Delivery Workshop 1 08.31.22.pdf
 
Shahzad Sikandaruk
Shahzad SikandarukShahzad Sikandaruk
Shahzad Sikandaruk
 
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
Traffic Circulation, Diversion, and Management Plan for Ahmedabad- Mumbai Hig...
 

More from StittsvilleCentral.ca

Bill Teron's 2010 lecture to Heritage Ottawa on Beaverbrook
Bill Teron's 2010 lecture to Heritage Ottawa on BeaverbrookBill Teron's 2010 lecture to Heritage Ottawa on Beaverbrook
Bill Teron's 2010 lecture to Heritage Ottawa on BeaverbrookStittsvilleCentral.ca
 
Mayor Jim Watson letter re: RendezVous LeBreton Group negotiations
Mayor Jim Watson letter re: RendezVous LeBreton Group negotiationsMayor Jim Watson letter re: RendezVous LeBreton Group negotiations
Mayor Jim Watson letter re: RendezVous LeBreton Group negotiationsStittsvilleCentral.ca
 
Stantec Johnwoods street closure memo, March 2016
Stantec Johnwoods street closure memo, March 2016Stantec Johnwoods street closure memo, March 2016
Stantec Johnwoods street closure memo, March 2016StittsvilleCentral.ca
 
Public Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove road
Public Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove roadPublic Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove road
Public Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove roadStittsvilleCentral.ca
 
Carp-Hazeldean collision data, 2011-2015
Carp-Hazeldean collision data, 2011-2015Carp-Hazeldean collision data, 2011-2015
Carp-Hazeldean collision data, 2011-2015StittsvilleCentral.ca
 
Memo - 2017 Road Resurfacing Program and Additional Resurfacing Projects
Memo - 2017 Road Resurfacing Program and Additional Resurfacing ProjectsMemo - 2017 Road Resurfacing Program and Additional Resurfacing Projects
Memo - 2017 Road Resurfacing Program and Additional Resurfacing ProjectsStittsvilleCentral.ca
 
Kanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment StudyKanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment StudyStittsvilleCentral.ca
 
Stittsville Fernbank Haliburton Park Concept Plan
Stittsville Fernbank Haliburton Park Concept PlanStittsville Fernbank Haliburton Park Concept Plan
Stittsville Fernbank Haliburton Park Concept PlanStittsvilleCentral.ca
 
Stittsville Fernbank Haliburton Park Concept Images
Stittsville Fernbank Haliburton Park Concept ImagesStittsville Fernbank Haliburton Park Concept Images
Stittsville Fernbank Haliburton Park Concept ImagesStittsvilleCentral.ca
 
Ontario Court of Justice - Appeal Decision April 19, 2017
Ontario Court of Justice - Appeal Decision April 19, 2017Ontario Court of Justice - Appeal Decision April 19, 2017
Ontario Court of Justice - Appeal Decision April 19, 2017StittsvilleCentral.ca
 
March 21 letter from Waste Management to City of Ottawa
March 21 letter from Waste Management to City of OttawaMarch 21 letter from Waste Management to City of Ottawa
March 21 letter from Waste Management to City of OttawaStittsvilleCentral.ca
 
Memo to council about West Carleton Environmental Centre ECA amendment
Memo to council about West Carleton Environmental Centre ECA amendmentMemo to council about West Carleton Environmental Centre ECA amendment
Memo to council about West Carleton Environmental Centre ECA amendmentStittsvilleCentral.ca
 
Cash For Trash 7628 Flewellyn - September 2016 presentation
Cash For Trash 7628 Flewellyn - September 2016 presentationCash For Trash 7628 Flewellyn - September 2016 presentation
Cash For Trash 7628 Flewellyn - September 2016 presentationStittsvilleCentral.ca
 
Potter's Key Community Information Session on January 11, 2017
Potter's Key Community Information Session on January 11, 2017Potter's Key Community Information Session on January 11, 2017
Potter's Key Community Information Session on January 11, 2017StittsvilleCentral.ca
 
Zoning application summary - Farmers' Markets
Zoning application summary - Farmers' MarketsZoning application summary - Farmers' Markets
Zoning application summary - Farmers' MarketsStittsvilleCentral.ca
 
Memo: Acquisition of Urban Natural Features (UNF)
Memo: Acquisition of Urban Natural Features (UNF)Memo: Acquisition of Urban Natural Features (UNF)
Memo: Acquisition of Urban Natural Features (UNF)StittsvilleCentral.ca
 
Official Plan Amendment - Significant Woodland Policy
Official Plan Amendment - Significant Woodland PolicyOfficial Plan Amendment - Significant Woodland Policy
Official Plan Amendment - Significant Woodland PolicyStittsvilleCentral.ca
 

More from StittsvilleCentral.ca (20)

Bill Teron's 2010 lecture to Heritage Ottawa on Beaverbrook
Bill Teron's 2010 lecture to Heritage Ottawa on BeaverbrookBill Teron's 2010 lecture to Heritage Ottawa on Beaverbrook
Bill Teron's 2010 lecture to Heritage Ottawa on Beaverbrook
 
Mayor Jim Watson letter re: RendezVous LeBreton Group negotiations
Mayor Jim Watson letter re: RendezVous LeBreton Group negotiationsMayor Jim Watson letter re: RendezVous LeBreton Group negotiations
Mayor Jim Watson letter re: RendezVous LeBreton Group negotiations
 
Stantec Johnwoods street closure memo, March 2016
Stantec Johnwoods street closure memo, March 2016Stantec Johnwoods street closure memo, March 2016
Stantec Johnwoods street closure memo, March 2016
 
Public Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove road
Public Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove roadPublic Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove road
Public Comments on Zoning Bylaw Amendment - 1620 and 1636 maple grove road
 
Carp-Hazeldean collision data, 2011-2015
Carp-Hazeldean collision data, 2011-2015Carp-Hazeldean collision data, 2011-2015
Carp-Hazeldean collision data, 2011-2015
 
Ottawa BIA overview
Ottawa BIA overviewOttawa BIA overview
Ottawa BIA overview
 
Ontario BIA handbook 2010
Ontario BIA handbook 2010Ontario BIA handbook 2010
Ontario BIA handbook 2010
 
Memo - 2017 Road Resurfacing Program and Additional Resurfacing Projects
Memo - 2017 Road Resurfacing Program and Additional Resurfacing ProjectsMemo - 2017 Road Resurfacing Program and Additional Resurfacing Projects
Memo - 2017 Road Resurfacing Program and Additional Resurfacing Projects
 
Kanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment StudyKanata LRT Planning and Environmental Assessment Study
Kanata LRT Planning and Environmental Assessment Study
 
Stittsville Fernbank Haliburton Park Concept Plan
Stittsville Fernbank Haliburton Park Concept PlanStittsville Fernbank Haliburton Park Concept Plan
Stittsville Fernbank Haliburton Park Concept Plan
 
Stittsville Fernbank Haliburton Park Concept Images
Stittsville Fernbank Haliburton Park Concept ImagesStittsville Fernbank Haliburton Park Concept Images
Stittsville Fernbank Haliburton Park Concept Images
 
City of Ottawa Noise By-Law Review
City of Ottawa Noise By-Law ReviewCity of Ottawa Noise By-Law Review
City of Ottawa Noise By-Law Review
 
Ontario Court of Justice - Appeal Decision April 19, 2017
Ontario Court of Justice - Appeal Decision April 19, 2017Ontario Court of Justice - Appeal Decision April 19, 2017
Ontario Court of Justice - Appeal Decision April 19, 2017
 
March 21 letter from Waste Management to City of Ottawa
March 21 letter from Waste Management to City of OttawaMarch 21 letter from Waste Management to City of Ottawa
March 21 letter from Waste Management to City of Ottawa
 
Memo to council about West Carleton Environmental Centre ECA amendment
Memo to council about West Carleton Environmental Centre ECA amendmentMemo to council about West Carleton Environmental Centre ECA amendment
Memo to council about West Carleton Environmental Centre ECA amendment
 
Cash For Trash 7628 Flewellyn - September 2016 presentation
Cash For Trash 7628 Flewellyn - September 2016 presentationCash For Trash 7628 Flewellyn - September 2016 presentation
Cash For Trash 7628 Flewellyn - September 2016 presentation
 
Potter's Key Community Information Session on January 11, 2017
Potter's Key Community Information Session on January 11, 2017Potter's Key Community Information Session on January 11, 2017
Potter's Key Community Information Session on January 11, 2017
 
Zoning application summary - Farmers' Markets
Zoning application summary - Farmers' MarketsZoning application summary - Farmers' Markets
Zoning application summary - Farmers' Markets
 
Memo: Acquisition of Urban Natural Features (UNF)
Memo: Acquisition of Urban Natural Features (UNF)Memo: Acquisition of Urban Natural Features (UNF)
Memo: Acquisition of Urban Natural Features (UNF)
 
Official Plan Amendment - Significant Woodland Policy
Official Plan Amendment - Significant Woodland PolicyOfficial Plan Amendment - Significant Woodland Policy
Official Plan Amendment - Significant Woodland Policy
 

Recently uploaded

Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...AlexisTorres963861
 
Minto-Morley Reforms 1909 (constitution).pptx
Minto-Morley Reforms 1909 (constitution).pptxMinto-Morley Reforms 1909 (constitution).pptx
Minto-Morley Reforms 1909 (constitution).pptxAwaiskhalid96
 
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docxkfjstone13
 
25042024_First India Newspaper Jaipur.pdf
25042024_First India Newspaper Jaipur.pdf25042024_First India Newspaper Jaipur.pdf
25042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Manipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkManipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkbhavenpr
 
Referendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoReferendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoSABC News
 
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptxKAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptxjohnandrewcarlos
 
26042024_First India Newspaper Jaipur.pdf
26042024_First India Newspaper Jaipur.pdf26042024_First India Newspaper Jaipur.pdf
26042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
College Call Girls Kolhapur Aanya 8617697112 Independent Escort Service Kolhapur
College Call Girls Kolhapur Aanya 8617697112 Independent Escort Service KolhapurCollege Call Girls Kolhapur Aanya 8617697112 Independent Escort Service Kolhapur
College Call Girls Kolhapur Aanya 8617697112 Independent Escort Service KolhapurCall girls in Ahmedabad High profile
 
How Europe Underdeveloped Africa_walter.pdf
How Europe Underdeveloped Africa_walter.pdfHow Europe Underdeveloped Africa_walter.pdf
How Europe Underdeveloped Africa_walter.pdfLorenzo Lemes
 
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docxkfjstone13
 
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...narsireddynannuri1
 
Roberts Rules Cheat Sheet for LD4 Precinct Commiteemen
Roberts Rules Cheat Sheet for LD4 Precinct CommiteemenRoberts Rules Cheat Sheet for LD4 Precinct Commiteemen
Roberts Rules Cheat Sheet for LD4 Precinct Commiteemenkfjstone13
 
Israel Palestine Conflict, The issue and historical context!
Israel Palestine Conflict, The issue and historical context!Israel Palestine Conflict, The issue and historical context!
Israel Palestine Conflict, The issue and historical context!Krish109503
 
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...Ismail Fahmi
 
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...Axel Bruns
 
Different Frontiers of Social Media War in Indonesia Elections 2024
Different Frontiers of Social Media War in Indonesia Elections 2024Different Frontiers of Social Media War in Indonesia Elections 2024
Different Frontiers of Social Media War in Indonesia Elections 2024Ismail Fahmi
 
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep VictoryAP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victoryanjanibaddipudi1
 
Lorenzo D'Emidio_Lavoro sullaNorth Korea .pptx
Lorenzo D'Emidio_Lavoro sullaNorth Korea .pptxLorenzo D'Emidio_Lavoro sullaNorth Korea .pptx
Lorenzo D'Emidio_Lavoro sullaNorth Korea .pptxlorenzodemidio01
 
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...Pooja Nehwal
 

Recently uploaded (20)

Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
 
Minto-Morley Reforms 1909 (constitution).pptx
Minto-Morley Reforms 1909 (constitution).pptxMinto-Morley Reforms 1909 (constitution).pptx
Minto-Morley Reforms 1909 (constitution).pptx
 
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
 
25042024_First India Newspaper Jaipur.pdf
25042024_First India Newspaper Jaipur.pdf25042024_First India Newspaper Jaipur.pdf
25042024_First India Newspaper Jaipur.pdf
 
Manipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkManipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpk
 
Referendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoReferendum Party 2024 Election Manifesto
Referendum Party 2024 Election Manifesto
 
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptxKAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
 
26042024_First India Newspaper Jaipur.pdf
26042024_First India Newspaper Jaipur.pdf26042024_First India Newspaper Jaipur.pdf
26042024_First India Newspaper Jaipur.pdf
 
College Call Girls Kolhapur Aanya 8617697112 Independent Escort Service Kolhapur
College Call Girls Kolhapur Aanya 8617697112 Independent Escort Service KolhapurCollege Call Girls Kolhapur Aanya 8617697112 Independent Escort Service Kolhapur
College Call Girls Kolhapur Aanya 8617697112 Independent Escort Service Kolhapur
 
How Europe Underdeveloped Africa_walter.pdf
How Europe Underdeveloped Africa_walter.pdfHow Europe Underdeveloped Africa_walter.pdf
How Europe Underdeveloped Africa_walter.pdf
 
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
 
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
 
Roberts Rules Cheat Sheet for LD4 Precinct Commiteemen
Roberts Rules Cheat Sheet for LD4 Precinct CommiteemenRoberts Rules Cheat Sheet for LD4 Precinct Commiteemen
Roberts Rules Cheat Sheet for LD4 Precinct Commiteemen
 
Israel Palestine Conflict, The issue and historical context!
Israel Palestine Conflict, The issue and historical context!Israel Palestine Conflict, The issue and historical context!
Israel Palestine Conflict, The issue and historical context!
 
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
HARNESSING AI FOR ENHANCED MEDIA ANALYSIS A CASE STUDY ON CHATGPT AT DRONE EM...
 
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
Dynamics of Destructive Polarisation in Mainstream and Social Media: The Case...
 
Different Frontiers of Social Media War in Indonesia Elections 2024
Different Frontiers of Social Media War in Indonesia Elections 2024Different Frontiers of Social Media War in Indonesia Elections 2024
Different Frontiers of Social Media War in Indonesia Elections 2024
 
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep VictoryAP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
 
Lorenzo D'Emidio_Lavoro sullaNorth Korea .pptx
Lorenzo D'Emidio_Lavoro sullaNorth Korea .pptxLorenzo D'Emidio_Lavoro sullaNorth Korea .pptx
Lorenzo D'Emidio_Lavoro sullaNorth Korea .pptx
 
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...
 

Review of need for grade separations five locations - statement of work

  • 1. 1 Review of Need for Grade-Separations Five Locations Statement of Work Background: On the morning of September 18, 2013, a VIA rail train and an OC Transpo double-decker bus collided at the Transitway rail crossing just north of the Fallowfield transit station. Six people sustained fatal injuries from the accident. On December 2, 2015, the Transportation Safety Board made a series of recommendations following its investigation into the accident, one of which is as follows:  TSB Recommendation R15-05: The Board recommends that the City of Ottawa reconsider the need for grade separation at the Woodroffe Avenue, Transitway and Fallowfield Road level crossings. In the Barrhaven portion of the VIA Rail Smiths Falls Subdivision there exist seven level crossings (Figure 1):  Merivale Road (Mile 1.63)  Woodroffe Avenue (Mile 3.28)  Southwest Transitway (3.30)  Fallowfield Road (Mile 3.88)  Greenbank Road (Mile 5.1)  Jockvale Road (Mile 5.73)  Strandherd Drive (Mile 6.81)
  • 2. 2 Figure 1: At-Grade Crossing Locations Of these seven level crossings, construction is underway at Greenbank Road for a grade separation and along Strandherd Drive design has partially been completed for a grade separation which is identified in the City’s Transportation Master Plan (TMP) and tentatively planned to be constructed between 2020 and 2025. Therefore the focus of this study will be on the remaining five locations, none of which are slated for modifications prior to 2031 as per the TMP roads growth program. Environmental Assessments have been completed at four of the five locations, the exception being Jockvale Road. A detailed safety assessment was completed on behalf of VIA Rail Canada and the City of Ottawa in 2014. The report, entitled “Detailed Safety Assessment Report” and dated December 2014, is available and shall serve as a background document for this assignment.
  • 3. 3 Scope of Assignment: Study Budget: $250K Duration of Study: 10 months from award of contract to a consulting engineering firm to undertake the work. Objectives:  To address the TSB’s recommendation regarding grade separation  To review grade separation scenarios at Merivale and Jockvale Roads Tasks: (1) Information Review and Analysis  Review and compile information for each of these crossing based on previous City studies including EAs and preliminary design work, National Capital Commission Greenbelt Master Plan, VIA safety audits, the TSB report, and current and future VIA Rail service plans  Where EAs exist summarize what were the identified issues, impacts, benefits and risks associated with underpasses and overpasses at each location. For Jockvale (where no EA exists), make best efforts to identify issues, impacts, benefits and risks for underpass and overpass options.  Research best practices and legislations in North America regarding railway-roadway crossings to understand the triggers used to decide to provide for grade separated crossings. Create a framework for such triggers that could be used here in Ottawa. Identify what are the possible applicable outcomes from current CTA rules and policies. (2) Traffic Analysis  Using updated City and VIA traffic data, assess the cross-product and occupant product at each location. This is to include a presentation of similarly produced analysis from the past (e.g. last 15 years) and new projections for the future (e.g. next 15 years).  Incorporate as part of this traffic analysis a review component that examines the safety of all who cross at these locations including walking, cycling, transit, automobile and truck (3) Geotechnical Analysis  Gather available geotechnical information  If borehole and geotechnical information is lacking, particularly for the Jockvale location, identify the need for such. [This additional field work would be done by a separate party outside this study budget.]
  • 4. 4  Identify and assess geotechnical issues that may be of concern for the construction of grade-separations at the five locations. (4) Grade-Separation Analysis  Based on the research, information collected and analysis done for tasks 1, 2 and 3, review and reconfirm the previous recommended grade separation options for the four locations  For the Jockvale location, develop a conceptual grade separation  Identify and reconfirm costing estimates (include all planning and design efforts, property requirements, mitigation, traffic management, detouring requirements, and appropriate contingencies) for these grade crossing projects. The estimates shall allow the authorities to seek funding assistance from senior levels of government. (5) At-Grade Option  Identify if there are any additional measures that might be done to improve safety in the current condition. (6) Go Forward Plan  Identify the next steps for the City to move forward with grade-separations, including any additional studies to address legislative requirements. (7) Documentation/Deliverables Monthly progress report identifying work performed, next month anticipated work, any issue pending, updated schedule. Draft and Final Study Reports will be prepared to document the entire study process including the recommended option plans, costing, implementation and staging plan, and commitments to future action, including external approvals known to be required. The Consultant shall assist the City Project Manager in the preparation of a Staff report and a Microsoft PowerPoint presentation to relevant City Standing Committees at the completion of the study. The report shall be formatted in accordance with City guidelines and accessibility policies.
  • 5. 5 The deliverables for this study include:  Draft and Final Study Report;  Project Recommended Plan incorporating concept design drawings of the preferred design, and other information as identified elsewhere in this document;  Project Cost Estimate Report that will allow authorities to seek funding assistance from senior levels of government for the grade- separated crossings;  Geotechnical Analysis Report;  Maps for recommended cycling and pedestrian facilities shall identify tie-in to existing and/or possible future network connections. Digital version of all maps and plans must be in appropriate format conforming to City CADD and GeoOttawa standards; The Consultant will be responsible for preparing and distributing the agenda for any meetings in connection with this Study at least two days before the meeting date and prepare and distribute minutes of meetings within one week after the meeting date. All documentation produced during the course of the Study will be available to the City both in hard copy and digital formats. Digital copies of written material will be in MS Word and pdf format. Plans and maps for incorporation into the Report and Study notices will be provided in jpg and/or pdf format. Conceptual/ functional design drawings will be provided in MicroStation dgn format in accordance with City CADD standards. All final documents, including the Draft/Final Report, will also be provided on CD in pdf format. The Consultant will provide six hard copies and CD digital versions of draft document, and six hard copies and CD digital versions of Final document. All relevant background material referenced during the study shall be listed in a bibliography to be included in the final report. (8) Consultation/Meetings The City’s and VIA’s designated Project Managers will provide direction and day- to-day administration and management for the study. Project Management meetings with the Consultant Project Manager/Director will be held on an as required basis. A Study team comprised of the City, VIA Rail and Consultant Project Managers and key City and Consultant staff will be established at the study outset. Regular Study team meetings will be held to provide direction on issues and monitor the progress of the work. The Consultant shall be responsible for preparing and distributing the Study Team meeting agenda and notes in a timely manner with
  • 6. 6 minutes to all meetings distributed within one week after the respective meeting. At this time no public consultation is envisioned due to the technical nature of the study. It is however anticipated that the Study Team may seek input from the National Capital Commission given its immediate ownership of lands to the study area.