SlideShare a Scribd company logo
1 of 33
Download to read offline
Chapter 8:
Scheduling Resources and Costs
A Report in Project Research and
Development
By Mr. Cristan A. Marquez
The Resource Problem
• Resources and Priorities
– Project network times are not a schedule until
resources have been assigned.
• The implicit assumption is that resources will be available in the
required amounts when needed.
• Adding new projects requires making realistic judgments of
resource availability and project durations.
• Resource leveling (or smoothing)
– involves attempting to even out demands on
resources by using slack (delaying non-critical
activities) to manage resource utilization.
• Resource-Constrained Scheduling
– Involves delaying some activities if the resources
are enough to meet peak demand
Types of Project Constraints
• Technical or Logic Constraints
– Constraints related to the networked sequence in which
project activities must occur
• Physical constraints
• Resource Constraints
– The absence, shortage, or unique interrelationship and
interaction characteristics of resources that require a
particular sequencing of project activities
– Types of resource constraints
• People
• Materials
• Equipment
• Working Capital
Constraint Examples
FIGURE 8.1
Classification of a Scheduling Problem
• Classification of Problem
– Using a priority matrix will help determine if the project is time
or resource constrained
• Time Constrained Project
– A project that must be completed by an imposed date
• Time is fixed, resources are flexible: additional resources are
required to ensure project meets schedule.
• Resource Constrained Project
– A project in which the level of resources available cannot be
exceeded
• Resources are fixed, time is flexible: inadequate resources will delay
the project.
Resource Allocation Methods
• Limiting Assumptions
– Splitting activities is not allowed—once an activity is
start, it is carried to completion.
– Level of resource used for an activity cannot be
changed.
– Activities with the most slack pose the least risk.
– Reduction of flexibility does not increase risk.
– The nature of an activity (easy, complex) doesn’t
increase risk.
Resource Allocation Methods (cont’d)
• Time-Constrained Projects
– Projects that must be completed by an imposed date
– Require the use of leveling techniques that focus on balancing
or smoothing resource demands by using positive slack
(delaying noncritical activities) to manage resource utilization
over the duration of the project
• Peak resource demands are reduced.
• Resources over the life of the project are reduced.
• Fluctuation in resource demand is minimized.
Botanical Garden
FIGURE 8.2
A
B
C
D
E
F
G
Botanical Garden (cont’d)
FIGURE 8.2 (cont’d)
Resource Allocation Methods (cont’d)
• Resource Demand Leveling Techniques for Time-Constrained
Projects
– Advantages
• Peak resource demands are reduced.
• Resources over the life of the project are reduced.
• Fluctuation in resource demand is minimized.
– Disadvantages
• Loss of flexibility that occurs from reducing slack
• Increases in the criticality of all activities
• Resource-Constrained Projects
– Projects that involve resources that are limited in quantity or by
their availability
– Scheduling of activities requires the use of heuristics (rules-of-
thumb) that focus on:
1. Minimum slack
2. Smallest (least) duration
3. Lowest activity identification number
– The parallel method is used to apply heuristics.
• An iterative process that starts at the first time period of the project
and schedules period-by-period any activities scheduled to start using
the three priority rules
Resource Allocation Methods (cont’d)
The Parallel Method
Resource-Constrained Schedule through Period 2–3
FIGURE 8.3
Resource-Constrained Schedule through Period 2–3
FIGURE 8.3 (cont’d)
ES resource load chart
Resource-Constrained Schedule through Period 2–3
FIGURE 8.3 (cont’d)
Resource-constrained schedule through period 2–3
Resource-Constrained Schedule through Period 5–6
FIGURE 8.4
Resource-constrained schedule through period 5–6
Resource-Constrained Schedule through Period 5–6
FIGURE 8.4 (cont’d)
Final resource-constrained schedule
Resource-Constrained Schedule through Period 5–6
FIGURE 8.4 (cont’d)
New, resource-constrained network
The Impacts of Resource-Constrained Scheduling
• Reduces delay but reduces flexibility
• Increases sensitivity of the network
• Increases scheduling complexity
• May make traditional critical path no longer meaningful
• Can break sequence of events
• May cause parallel activities to become sequential and
critical activities with slack to become noncritical
Splitting/Multitasking
• A scheduling technique use to get a better
project schedule and/or increase resource
utilization
– Involves interrupting work on an activity to employ
the resource on another activity, then returning the
resource to finish the interrupted work
– Is feasible when startup and shutdown costs are
low
– Is considered the major reason why projects fail to
meet schedule
Splitting/Multitasking
FIGURE 8.10
Assigning Project Work
• Factors to Consider in Assigning Work:
– Don’t always pick the same people for the toughest
assignments.
– Choose people with an eye to fostering their development
through participation on the project.
– Pick people with compatible work habits and personalities but
who complement each other.
– Team-up veterans with new hires to share experience and
socialize newcomers into the organization.
– Select people who may need to learn work together on later
stages of the project or other projects.
Multiproject Resource Schedules
• Multiproject Scheduling Problems
– Overall project slippage
• Delay on one project creates delays for other projects.
– Inefficient resource application
• The peaks and valleys of resource demands create
scheduling problems and delays for projects.
– Resource bottlenecks
• Shortages of critical resources required for multiple projects
cause delays and schedule extensions.
Multiproject Resource Schedules
• Managing Multiproject Scheduling
– Create project offices or departments to oversee the
scheduling of resources across projects.
– Use a project priority queuing system: first come, first
served for resources.
– Centralize project management: treat all projects as a
part of a “megaproject.”
– Outsource projects to reduce the number of projects
handled internally.
Creating a Time-Phased Budget
Creating a Time-Phased Budget (cont’d)
Creating a Time-Phased Budget (cont’d)
Creating a Time-Phased Budget (cont’d)
Creating a Time-Phased Budget (cont’d)
Monthly Cash Flow Statement
Resource Usage Table

More Related Content

Similar to Scheduling resources and costs is a crucial aspect of project management that involves effectively allocating and managing the resources needed to complete a project within the allocated budget and timeline.

Network diagrams
Network diagramsNetwork diagrams
Network diagramsLii Van
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertRaj J Das
 
Techniques of OR.pptx
Techniques of OR.pptxTechniques of OR.pptx
Techniques of OR.pptxArdraSabu
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)ShudipPal
 
Time management pressent
Time management pressentTime management pressent
Time management pressentiklil fairuz
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.pptTecnicoItca
 
Chapter EightScheduling Resources and Costs© 2021 McGraw-H
Chapter EightScheduling Resources and Costs© 2021 McGraw-HChapter EightScheduling Resources and Costs© 2021 McGraw-H
Chapter EightScheduling Resources and Costs© 2021 McGraw-HJinElias52
 
Project Management Notes 3
Project Management Notes 3Project Management Notes 3
Project Management Notes 3Golam Bitonsir
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system projecta23ccb
 
projectmanagement-123765482.pdf
projectmanagement-123765482.pdfprojectmanagement-123765482.pdf
projectmanagement-123765482.pdfAmarDeo7
 
Project management
Project managementProject management
Project managementtwilight89
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system projectalpha1unity
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPSagar Kaptan
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagementDhamo daran
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5Hisham Ali,PMP
 

Similar to Scheduling resources and costs is a crucial aspect of project management that involves effectively allocating and managing the resources needed to complete a project within the allocated budget and timeline. (20)

Allocating resources
Allocating resourcesAllocating resources
Allocating resources
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
 
Techniques of OR.pptx
Techniques of OR.pptxTechniques of OR.pptx
Techniques of OR.pptx
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
 
Time management pressent
Time management pressentTime management pressent
Time management pressent
 
ch09s.ppt
ch09s.pptch09s.ppt
ch09s.ppt
 
Time management
Time managementTime management
Time management
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
Chapter EightScheduling Resources and Costs© 2021 McGraw-H
Chapter EightScheduling Resources and Costs© 2021 McGraw-HChapter EightScheduling Resources and Costs© 2021 McGraw-H
Chapter EightScheduling Resources and Costs© 2021 McGraw-H
 
Project Management Notes 3
Project Management Notes 3Project Management Notes 3
Project Management Notes 3
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system project
 
EpM
EpMEpM
EpM
 
projectmanagement-123765482.pdf
projectmanagement-123765482.pdfprojectmanagement-123765482.pdf
projectmanagement-123765482.pdf
 
Project management
Project managementProject management
Project management
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system project
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagement
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 

Recently uploaded

The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
PSYCHIATRIC History collection FORMAT.pptx
PSYCHIATRIC   History collection FORMAT.pptxPSYCHIATRIC   History collection FORMAT.pptx
PSYCHIATRIC History collection FORMAT.pptxPoojaSen20
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Micromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersMicromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersChitralekhaTherkar
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 

Recently uploaded (20)

The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
PSYCHIATRIC History collection FORMAT.pptx
PSYCHIATRIC   History collection FORMAT.pptxPSYCHIATRIC   History collection FORMAT.pptx
PSYCHIATRIC History collection FORMAT.pptx
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Micromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersMicromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of Powders
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 

Scheduling resources and costs is a crucial aspect of project management that involves effectively allocating and managing the resources needed to complete a project within the allocated budget and timeline.

  • 1. Chapter 8: Scheduling Resources and Costs A Report in Project Research and Development By Mr. Cristan A. Marquez
  • 2.
  • 3. The Resource Problem • Resources and Priorities – Project network times are not a schedule until resources have been assigned. • The implicit assumption is that resources will be available in the required amounts when needed. • Adding new projects requires making realistic judgments of resource availability and project durations. • Resource leveling (or smoothing) – involves attempting to even out demands on resources by using slack (delaying non-critical activities) to manage resource utilization. • Resource-Constrained Scheduling – Involves delaying some activities if the resources are enough to meet peak demand
  • 4. Types of Project Constraints • Technical or Logic Constraints – Constraints related to the networked sequence in which project activities must occur • Physical constraints • Resource Constraints – The absence, shortage, or unique interrelationship and interaction characteristics of resources that require a particular sequencing of project activities – Types of resource constraints • People • Materials • Equipment • Working Capital
  • 6. Classification of a Scheduling Problem • Classification of Problem – Using a priority matrix will help determine if the project is time or resource constrained • Time Constrained Project – A project that must be completed by an imposed date • Time is fixed, resources are flexible: additional resources are required to ensure project meets schedule. • Resource Constrained Project – A project in which the level of resources available cannot be exceeded • Resources are fixed, time is flexible: inadequate resources will delay the project.
  • 7. Resource Allocation Methods • Limiting Assumptions – Splitting activities is not allowed—once an activity is start, it is carried to completion. – Level of resource used for an activity cannot be changed. – Activities with the most slack pose the least risk. – Reduction of flexibility does not increase risk. – The nature of an activity (easy, complex) doesn’t increase risk.
  • 8. Resource Allocation Methods (cont’d) • Time-Constrained Projects – Projects that must be completed by an imposed date – Require the use of leveling techniques that focus on balancing or smoothing resource demands by using positive slack (delaying noncritical activities) to manage resource utilization over the duration of the project • Peak resource demands are reduced. • Resources over the life of the project are reduced. • Fluctuation in resource demand is minimized.
  • 11. Resource Allocation Methods (cont’d) • Resource Demand Leveling Techniques for Time-Constrained Projects – Advantages • Peak resource demands are reduced. • Resources over the life of the project are reduced. • Fluctuation in resource demand is minimized. – Disadvantages • Loss of flexibility that occurs from reducing slack • Increases in the criticality of all activities
  • 12. • Resource-Constrained Projects – Projects that involve resources that are limited in quantity or by their availability – Scheduling of activities requires the use of heuristics (rules-of- thumb) that focus on: 1. Minimum slack 2. Smallest (least) duration 3. Lowest activity identification number – The parallel method is used to apply heuristics. • An iterative process that starts at the first time period of the project and schedules period-by-period any activities scheduled to start using the three priority rules Resource Allocation Methods (cont’d)
  • 14. Resource-Constrained Schedule through Period 2–3 FIGURE 8.3
  • 15. Resource-Constrained Schedule through Period 2–3 FIGURE 8.3 (cont’d) ES resource load chart
  • 16. Resource-Constrained Schedule through Period 2–3 FIGURE 8.3 (cont’d) Resource-constrained schedule through period 2–3
  • 17.
  • 18. Resource-Constrained Schedule through Period 5–6 FIGURE 8.4 Resource-constrained schedule through period 5–6
  • 19. Resource-Constrained Schedule through Period 5–6 FIGURE 8.4 (cont’d) Final resource-constrained schedule
  • 20. Resource-Constrained Schedule through Period 5–6 FIGURE 8.4 (cont’d) New, resource-constrained network
  • 21. The Impacts of Resource-Constrained Scheduling • Reduces delay but reduces flexibility • Increases sensitivity of the network • Increases scheduling complexity • May make traditional critical path no longer meaningful • Can break sequence of events • May cause parallel activities to become sequential and critical activities with slack to become noncritical
  • 22. Splitting/Multitasking • A scheduling technique use to get a better project schedule and/or increase resource utilization – Involves interrupting work on an activity to employ the resource on another activity, then returning the resource to finish the interrupted work – Is feasible when startup and shutdown costs are low – Is considered the major reason why projects fail to meet schedule
  • 24. Assigning Project Work • Factors to Consider in Assigning Work: – Don’t always pick the same people for the toughest assignments. – Choose people with an eye to fostering their development through participation on the project. – Pick people with compatible work habits and personalities but who complement each other. – Team-up veterans with new hires to share experience and socialize newcomers into the organization. – Select people who may need to learn work together on later stages of the project or other projects.
  • 25. Multiproject Resource Schedules • Multiproject Scheduling Problems – Overall project slippage • Delay on one project creates delays for other projects. – Inefficient resource application • The peaks and valleys of resource demands create scheduling problems and delays for projects. – Resource bottlenecks • Shortages of critical resources required for multiple projects cause delays and schedule extensions.
  • 26. Multiproject Resource Schedules • Managing Multiproject Scheduling – Create project offices or departments to oversee the scheduling of resources across projects. – Use a project priority queuing system: first come, first served for resources. – Centralize project management: treat all projects as a part of a “megaproject.” – Outsource projects to reduce the number of projects handled internally.
  • 28. Creating a Time-Phased Budget (cont’d)
  • 29. Creating a Time-Phased Budget (cont’d)
  • 30. Creating a Time-Phased Budget (cont’d)
  • 31. Creating a Time-Phased Budget (cont’d)
  • 32. Monthly Cash Flow Statement