PRESENTATION ON
PREPARATION OF SLUM FREE CITY UNDER
RAJIV AWAS YOJANA IN MIRA BHAYANDAR
MUNICIPAL CORPORATION



                            Date: 23/11/2012
RAJIV AWAS YOJANA (RAY)
  The various components of this projects includes:
   Identification of Slum Pockets
   Conduction of Socio-economic and Biometric
    survey of the beneficiaries
   Conduction of Total Station/ Plane table survey
    of the slum area.
   Preparation of Base map using GIS and Satellite
    Images.
   MIS and GIS integration
   Preparation of architectural Layouts of the Slum
    area for its development
   Preparation of DPR
INNOVATION IN RAY REQUIRED
 All the Socio-economic, biometric and total
  station survey data are currently being
  integrated offline which will be later on
  submitted to the governing authority.
 Such data shall be made available to
  WAPCOS field offices by preparing an online
  module of the same.
 This will also ensure that the status on the
  work done by WAPCOS in RAY projects can
  be easily retrieved and produced before the
  clients.
UPDATE ON PREPARATION OF SLUM FREE CITY
  PLAN OF ACTION.
     GIS Mapping: The whole GIS-MIS component
      shall be available on our WAPCOS site. The
      various components of GIS which are completed
      are as follows:
       i.     Preparation of City Base Map.
       ii.    Slum Marking using Satellite Images.
       iii.   Digitization of DP maps, Village/ Cadastral maps
              and their rectification.
       iv.    Road Digitization.
       v.     Marking of important Landmarks.
STATUS ON PREPARATION OF SLUM FREE CITY
                         PLAN OF ACTION
SLUM DETAILS                       SLUMS COVERED

            No. of huts                        No. Of Slums


                           Less than                           Less Than
        2                  100                    1            100
   5                       Between     2                       Between
                15
                           100-500                             100-500
   10                      Between                             Between
                           500-1500                   2        500-1500
                           Above           1                   Above
                           1500                                1500




SLUMS DETAILS (WRT. NO. OF HUTS)
SLUM FREE CITY PLAN OF ACTION
UPDATE ON PREPARATION OF INNOVATIVE PILOT
  PROJECTS.
     Status on Pilot projects prepared
       i.    Pilot Projects for Ambedkar Nagar, Bhola Nagar and
             Gandhinagar Pocket is on the verge of completion.
       ii.   Clearing the reservation of Garden and Cementry
             encroached by Slum, Development of Roads, water
             supply lines & Drainage Lines, provision for
             STP, Primary health care center, Electric Sub-
             Station and school is included in the pilot project.
COMMUNITY MEETING AT SLUM
During community meetings information such as the objective of the
scheme, the contribution of the beneficiaries in the project, the type of
houses to be built if sanctioned, their area etc. are discussed.
CONDUCTION OF TOTAL STATION SURVEY
The total station survey is carried out in order to confirm the no. of huts
present in the slum including tracing their exact location. This data is later on
merged with the satellite images so as to propose a Slum development
scheme
DPR PREPARATION
SLUM LOCATIONS
AMBEDKAR NAGAR SLUM POCKET
DEVELOPMENT PLAN FOR AMBEDKAR NAGAR
            SLUM POCKET




                           Data        Slum Layout
        Total Station
           Survey       Verification
FLOOR PLAN
AMENITIES PROVIDED

 No. of Tenements = 2048
 Plot reserved for cemetery and Garden
  released
 32 Nos. of buildings with 64 tenements each

 Plot allotted for Primary School, Primary
  health center
 92 Beneficiaries from Anna Nagar will be
  relocated in Ambedkar Nagar Pocket.
MIS-GIS INTEGRATION
After completion of the total station and the biometric survey, the data is
integrated with the GIS base map prepared. Thus, the data of each and
every beneficiary can be retrieved as and when required.
Thank you

Ray presentation mbmc (ara@wapcos.gov.in)

  • 1.
    PRESENTATION ON PREPARATION OFSLUM FREE CITY UNDER RAJIV AWAS YOJANA IN MIRA BHAYANDAR MUNICIPAL CORPORATION Date: 23/11/2012
  • 2.
    RAJIV AWAS YOJANA(RAY) The various components of this projects includes:  Identification of Slum Pockets  Conduction of Socio-economic and Biometric survey of the beneficiaries  Conduction of Total Station/ Plane table survey of the slum area.  Preparation of Base map using GIS and Satellite Images.  MIS and GIS integration  Preparation of architectural Layouts of the Slum area for its development  Preparation of DPR
  • 3.
    INNOVATION IN RAYREQUIRED  All the Socio-economic, biometric and total station survey data are currently being integrated offline which will be later on submitted to the governing authority.  Such data shall be made available to WAPCOS field offices by preparing an online module of the same.  This will also ensure that the status on the work done by WAPCOS in RAY projects can be easily retrieved and produced before the clients.
  • 4.
    UPDATE ON PREPARATIONOF SLUM FREE CITY PLAN OF ACTION.  GIS Mapping: The whole GIS-MIS component shall be available on our WAPCOS site. The various components of GIS which are completed are as follows: i. Preparation of City Base Map. ii. Slum Marking using Satellite Images. iii. Digitization of DP maps, Village/ Cadastral maps and their rectification. iv. Road Digitization. v. Marking of important Landmarks.
  • 5.
    STATUS ON PREPARATIONOF SLUM FREE CITY PLAN OF ACTION
  • 6.
    SLUM DETAILS SLUMS COVERED No. of huts No. Of Slums Less than Less Than 2 100 1 100 5 Between 2 Between 15 100-500 100-500 10 Between Between 500-1500 2 500-1500 Above 1 Above 1500 1500 SLUMS DETAILS (WRT. NO. OF HUTS)
  • 7.
    SLUM FREE CITYPLAN OF ACTION
  • 8.
    UPDATE ON PREPARATIONOF INNOVATIVE PILOT PROJECTS.  Status on Pilot projects prepared i. Pilot Projects for Ambedkar Nagar, Bhola Nagar and Gandhinagar Pocket is on the verge of completion. ii. Clearing the reservation of Garden and Cementry encroached by Slum, Development of Roads, water supply lines & Drainage Lines, provision for STP, Primary health care center, Electric Sub- Station and school is included in the pilot project.
  • 9.
    COMMUNITY MEETING ATSLUM During community meetings information such as the objective of the scheme, the contribution of the beneficiaries in the project, the type of houses to be built if sanctioned, their area etc. are discussed.
  • 10.
    CONDUCTION OF TOTALSTATION SURVEY The total station survey is carried out in order to confirm the no. of huts present in the slum including tracing their exact location. This data is later on merged with the satellite images so as to propose a Slum development scheme
  • 11.
  • 12.
  • 13.
  • 14.
    DEVELOPMENT PLAN FORAMBEDKAR NAGAR SLUM POCKET Data Slum Layout Total Station Survey Verification
  • 15.
  • 16.
    AMENITIES PROVIDED  No.of Tenements = 2048  Plot reserved for cemetery and Garden released  32 Nos. of buildings with 64 tenements each  Plot allotted for Primary School, Primary health center  92 Beneficiaries from Anna Nagar will be relocated in Ambedkar Nagar Pocket.
  • 17.
    MIS-GIS INTEGRATION After completionof the total station and the biometric survey, the data is integrated with the GIS base map prepared. Thus, the data of each and every beneficiary can be retrieved as and when required.