SlideShare a Scribd company logo
Head Checks
Head checks on Gauge Face of a Rail
 Reduction in Rail/ Weld Failures

Action on two fronts
Arresting Initiation
& Growth of Flaws

Rail Grinding

Objective Detection
of the Flaws

Vehicular
USFD Testing
 Rail Grinding is an important track maintenance tool
 Rail Grinding is the removal of metal from the surface

of the rail head
 Through the action of a rotating grinding wheel
 Mechanism used in rail grinding is cutting of metal
associated with formation of metal chips (and not
metal deformation)
 Corrective – Removing the defects in

one go
 Preventive Gradual – Removing the
defects in stages
 Preventive – Removing the defects in
nascent stage
 Also known as traditional Rail Grinding
 To correct existing surface defects and the shape of the

head of the rail
 A problem exists and sufficient grinding is done to
correct the problem
 Defect is allowed to develop before taking up the
grinding; so remedial type action taken
Condition

Typical Recommendations

New Rail

At 20 GMT

Corrugations

0.25-1.5 mm

Engine Burns

0.6-0.8 mm

Rail End Batter

0.8 mm

Weld Batter

0.8 mm

Flaking and Shelling

0.8 mm

New Rail requires grinding for removal of mill scale.
Mill scale is a very fine layer on rail head(<0.25MM).
 Also known as profile grinding
 Carried out before problems occurs
 Rail head is ground to specific profile so as to improve

rail wheel contact interface
 Carried out more frequently
 This is periodic maintenance grinding carried out at
frequency decided on the basis of GMT.
 Less aggressive grinding process

 Removes fatigued material, surface cracks & improves

rail wheel interaction
 Eliminates the need for defect correction grinding
 Generally one pass process carried out at higher speed
ranging from 10 to 24 kmph.
 In between corrective and preventive grinding
 The defects in the rail are not removed in one go
 Rails are ground at slow speed - only 1 to 3 passes are

given
 In each round, the defects will taper down
 Ultimately, we shift to preventive grinding
 IR has adopted Preventive Gradual Grinding to start

with
 Grinding cycle – 25 GMT –Ist, 50 GMT-2nd
 One pass on straight and 3 passes in curve (speed 15-18
kmph)
 Metal removal 0.1-0.2 mm (approx.)
After I Cycle
Cracks Partly Removed

R
NO C

ACKS

After II Cycle
(approx. 30 GMT)
More Cracks Removed

After III Cycle
(approx. 60 GMT)
Cracks Fully Removed
 Reshaping Rail Head Profile - favourable Rail

Wheel Interaction reducing contact stresses
 Removal of cracks in initial growth phase avoiding their propagation deeper
 Shifting the contact of the wheels - away from the
damaged zone
 Avoid Dip Formation at Welds - Reduction in
hunting by avoiding contact on misaligned welds
 Increased rail life
 Increased wheel life
 Reduction in fatigue & surface defects
 Less tractive resistance & therefore less fuel

consumption
 Reduced need for rail transposing in curves, thus
saving cost on maintenance
 Improved reliability of USFD testing
 Reduced track geometry deterioration
 Reduced degradation of ballast
 Less noise
 Improved vehicle ride quality
 Reduced derailment proneness
 Fastening (Rubber pad, ERC)
 Life extended 3 times
 Sleepers
 Life extended by 20%
 Tamping Cycle
 Extended by 30%
 Ballast Cleaning Cycle
 Extended by 15%
 Vehicle Maintenance & Wheel turning improved
 Tractive energy
 Reduced by 8 – 10%

 Noise and vibration
 In the human-hearing frequency range noise reduction

of over 10 db can be achieved by grinding of
corrugations
*One Time Activities
*Repetitive Activities
 Establishment of Test Sites
 Obstructions in the track
 Details of Rail – Old/ New, GMT carried
 Measurements
 Rail condition data
22.01.2010

PKG/SPT2/IRICEN
Test Sites -Selection
Why: For establishing
- Appropriate metal removal to control the growth of
RCF cracks
- Target Rail profile
- Grinding cycle requirements

Where:

-High tonnage
- Typical curvature / rail type
- Good access to track
- Rail history / defects
- No planned rail replacement
-Typical traffic & speed
- Away from Weld, Signal, LC etc

How:

Gather data –MiniProf, surface photos, dye penetrate,
weld dips, hunting
Test Sites - MiniProf
How– MiniProf:
• Mark rail location with
paint on field side for all
future measurements
• Record:
- Line
- Curve High, Low
-Tangent right,
Tangent left
- Track –UP, DN
- Date -automatic
- Gauge –automatic
MiniProf
Dye Penetration Testing
Grinding Test Sites:
How –Dye Penetrant:
•cleaner, dye (wait 2 min), Wipe clean,
water wash, Apply Developer (no
overspray)

•Record:
- Location
-Outside (OR) Inside (IR) rail, T
Left, T Right
-Track –UP, DN
-Date
-Gauge
-Direction Traffic
-Crack length
-Rail age and weight
 Turn-outs
 SEJs
 Level Crossings
 Axle counters
 Location – Chainages
 Start & End of Curves
 RH/LH Curve
• Rail surface defects
• Wear of rails
• USFD defects in rails/weld
• Rail/Weld failure details
• Weld dip details
• How it is decided?
• For IR, designed by NRC
• Four Profiles– CPC for DN road straight track & low rail of mild curve
– CPF for UP road and low rail of sharp curve

– HS for high rail of sharp curve
– HM for low rail of Mild curve

• Why two profiles for straight track?
 Arrangement of stones across the rail and along the

grinding train
 Pattern needs to be selected by P. Way supervisor
trained in grinding
 Purpose is to achieve target rail profile from existing
rail profile
 Factors affecting Metal to be removed
Different patterns being fed into HMI of RGM
NRC Recommendation for Preventive Gradual Grinding Edit 6 Sep 6th, 2011
Wrong Direction in GDMS
Patterns
Speed
3 Pass Patterns
First Pass
First Pass
Template
Track
Aggressive
Generic
Kph
Pass 1
Pass 2
Pass 3
HS
UP/Down
14
45
18
14
27
15
HS NEW RAIL UP/Down
2
45
18
2
47
23
HM
UP/Down
10
45
18
10
43
27
HM NEW
2
47
x
RAIL
UP/Down
2
45
18

All Passes
Speed
Kph
18
18
18
18

LS-CPF

UP/Down

20

47

18

20

23

27

18

LS-CPF NEW
RAIL

UP/Down

24

47

18

24

23

23

18

UP/Down
LM-CPC
LM-CPC NEW
UP/Down
RAIL
TCPF
UP

39

39

18

39

42

39

18

17

41

18

39

46

x

18

24

24

15

UP

24

24

15

DN

39

39

15

39

39

15

39

39

15

39

39

18

39

42

39

18

39

39

18

39

42

39

18

TCPF New rail
TCPC

TCPC NEW
DN
RAIL
TCPC 52 Kg
RAIL
UP/Down
LS-CPC 52 Kg
UP/Down
RAIL
LM-CPC 52 Kg
UP/Down
RAIL
• For Straight/ Tangent Track
– DN Road – Template CPC – Pattern 39
– UP Road – Template CPF – Pattern 24

• For Curve Track – Mild Curve (< 1.25 deg)
– High/ Outer Rail – Template HM – Pattern 10

– Low/Inner Rail – Template CPC – Pattern 39

• For Curve Track – Sharp Curve (> 1.25 deg)
– High Rail – Template HS – Pattern 14
– Low Rail – Template CPF – Pattern 10
 Straight Track – same as for old rail
 For Curve Track – Mild Curve (< 1.25 deg)
 High/ Outer Rail – Template HM – Pattern 2
 Low/Inner Rail – Template CPC – Pattern 17

 For Curve Track – Sharp Curve (> 1.25 deg)
 High Rail – Template HS – Pattern 2
 Low Rail – Template CPF – Pattern 24

 For 52 kg Rail – For all conditions - 39
 As suggested by GDMS
 First cycle – 3 passes on both high & low rails
 If GDMS gives 2 Passes – ask for alternative with 3

passes
 What to do if GDMS data has wrong direction of curve
 The Grind Data Management System is an

integrated automatic data acquisition, data viewing
and analysis, quality control, reporting and rail
grinding planning tool.
 The depth of cut w.r.t rail head and area of metal

removal for different patterns is not available with
IR to check the correctness of grinding.
 The use of RCA in deciding the grinding pattern
and grinding depth is not yet established.
 Calculation of metal removal/m is still to be
incorporated in GDMS.
 Filling of Water to be done in night i.e during maintenance shifts.
 The requirement of HSD oil from each RCD shall be arrived based on

the locations of RCD and the track to be ground and suitable
instructions shall be got issued from HQ to the respective RCDs.
 While working of RGM, one track machine operator of the concerned
division having route learning of that section shall be deputed for
working as pilot and to assist in calling the signals.
 When using the aggressive patterns as given by NRC, metal to the
extent of 1.5mm was removed.
 On some occasions it is noted that the pattern entered in HMI are not
as per the grind plan due to operator mistake. This should be taken
care.
 A moped trolley with PA system, arranged to go ahead of RGM to warn the

gatemen, gang men working in section to keep at least 20m away from track
while grinding. The onlookers and vehicles at LC shall be warned to keep a safe
distance.
 From each division, a PWI is nominated as grinding supervisor. His duties shall

be
 To ensure the pattern fed into the HMI is same as suggested by NRC.
 To ensure correct preparation of grind plan
 To cross check the grind plan and grind history after grinding to find any

deviations in the patterns.
 To take pre and post miniprof readings at test locations and to keep the
record as per proforma circulated by RDSO.
 With experience, to check whether grinding is proper or not while
observing the pre and post grind profiles on GDMS and to suggest the
change in the patterns if required while grinding.
 Identify the sections to be ground based on GMT, axle load
 Establish test site locations and fill the RDSO proforma for







these locations.
Identify stabling sidings at 50km apart, if not available
provide ( Provide only RL platform)
Identify the RCDs for HSD filling and make watering
arrangements at stabling sidings.
Issue JPO at HQ level and Divisional level for RGM
operations.
Obtain CRS sanction.
Prepare track database for input to GDMS
 (Direction of curves shall not be w.r.t traffic direction
but w.r.t increasing chainage)
Works to be carried out Before Rail grinding
Knowing the Location/Sec where grinding is to be done.
Type of Rail and sleeper, joint type(LWR,SWR,FP), and
Sectional GMT.
Location of SEJ, Points & X-ing, LC, Axle counter and any
other obstacle which may infringe the grinding.
Finding the location where grinding will not to be done.
Finalizing the Location where grinding Machine will be stabled
(where maintenance can be done).
Preparation of grind plan consisting of locations to be ground
with first pass patterns and depth of cut and details of
obstructions .
Clearing of rail head ballast to prevent damage to grinding
motors
Painting of Curve starting and ending on sleeper with
white/yellow paint conspicuously.
Ensuring sufficient HSD and water for the day
Measurements and condition monitoring before grinding

Measure the rail profile at nominated test locations
with miniprof, Bar gauge, do DPT, take surface photos
and measure hardness.
 while taking miniprof readings, the details such as
LH/RH of rail and TP to be fed otherwise it will not be
possible to identify the pre and post grind profiles.
Just Before the Grinding starts
Availability of complete & sufficient staff with
competency and Pilot with route learning
Moped trolley with PA system to warn Rly. staff and
onlookers and public at LC
Removing of axle counters by S&T staff
Job briefing consisting of
Location of work
Safety precautions to be taken
Head count and complete PPE
Allocation of duties with locations
First aid, Location of nearest hospitals and fire stations along the
work site.
Effective Communication system between crew, crew and station
*ON GROUND
*ON MACHINE
 Real Time Monitoring of Grinding Operation
 on the vehicle
 On the ground

 Monitoring
 Amount of metal removed
 Profile of the rail achieved after each pass
 Efficacy of the grinding motors
 The Grind Data Management System is an integrated

automatic data acquisition, data viewing and analysis,
quality control, reporting and rail grinding planning
tool.
 WATER SPRAY SYSTEM
 BAR GAUGE
 STAR GAUGE
 CONTACT BAND
 SURFACE ROUGHNESS
 RAIL SURFACE FINISH
 FIRE HAZARDS
BAR GAUGE
Taking measurements of rail profile before and grinding with bar-gaug
Star Gauge to check
Crown Radius
Surface Roughness > 12 Microns Poor Finish Stays a Long Time
Quality Control Examples –Straw
Colour and Missed Grind
Poor Finish – Blueing and
Large Facets
Rail ‘blueing”Poor
cutting (low
pressure)

Grinding stoneNot set
correctly. Grinding on
the outside diameter
(OD)
• Sequencing Monitor - Skipping Obstructions
• Safety systems
• Calling Patterns
• Feeding Patterns
• Working of motors
• Water Spray System
• Calling Patterns
• Pre & Post GQI
LORAM RGI MODEL
72 STONE RAIL GRINDER


Self propelled Diesel powered vehicle.



Can work in both directions.



Negotiate cant up to 185 mm.









Traveling speed 80 Kmph when self propelled and 100 Kmph in
train formation.
25 kmph on 1 in 33 Grade
Speed with buggies down – 40kmph
Grinding Speed - 2.4 to 24 kmph
Can grind on a 100 m radius curve
Stopping Distance – 400 m from 80 kmph on a level track
 Self propelled car
 Pilot, Guard and T.I. to be provided by the division in

two shifts for first three months
 Operating speed
 10kmph @ 0.20mm
 15kmph @ 0.13mm

 Speed Cert to be issued and CRS sanction to be

obtained
 Joint monthly prog. at zonal & weekly prog. At Divl








level
4 hours corridor block daily and 6 hours block on
weekends by SL working, trains cancellation/
regulation
Controller to allow RGM in the section following a
train to save time
Goods trains carrying highly inflammable material
like Naptha to be regulated on adjacent line during
block
Obstructions in the track
Passage of trains after the grinding block
 Spark Guards of different designs
 Water Storage – Front Control Car 20000 lit






- Water Tank 55000 lit
Water Pump – One 30hp 945 lit/min
Sleeper Spray – 2 Sets 7.6 lit/min
Ditch Spray – 2 Sets 100 lit/min
Water Cannons – 2 Sets 220 lit/min upto 31m
No. of Fire Extinguishers at different locations in the
car
 Water to be arranged
 Fuel arrangement
 Hydraulic oil
 Grinding stones for 600 hrs of working included with

machine
 RDSO to issue the specs and list of suppliers for
grinding stones
 Zonal Railways to send vetted indents to COS every

year
 Diesel to be provided by RCDs( Railway Consumers
Depots)
 COS to place order on oil Cos.
 Sufficient fuel imprest to be created - 5 lakhs; this will
cater for other unforeseen expenses also
 300m or 2X150m sidings at every 50kms
 Connectivity at both ends
 Lighting, watering, approach road and other facilities

to be provided
 Lodging and Boarding of staff
 Stabling either on unwired sdg or sdg should be with
OHE isolation system
 Dust Collection System
 Laser Based Rail Profile Measurement System on both

ends of the consist
 LORAM’s Software – GDMS
- The software stores the data, analyses and compares
the data and works out the grinding efficiency
 Recommendation of target profile, pattern and speed
in different passes to achieve the target profile
optimally
Thank You

More Related Content

What's hot

IRC Method of Signal Design
IRC Method of Signal DesignIRC Method of Signal Design
IRC Method of Signal Design
Vijai Krishnan V
 
Highway geometric design
Highway geometric designHighway geometric design
Highway geometric design
Shehzadkhan Munshi
 
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
Hossam Shafiq I
 
Highway planning and alignment
Highway planning and alignmentHighway planning and alignment
Basics of Metro Railway Signalling system
Basics of Metro Railway Signalling systemBasics of Metro Railway Signalling system
Basics of Metro Railway Signalling system
Bhaskar Kumar Dan
 
Accident study
Accident studyAccident study
Accident study
Aglaia Connect
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
srinivas2036
 
Traffic engineering
Traffic engineeringTraffic engineering
Traffic engineering
RonakModi34
 
Presentation on railway construction and maintenance
Presentation on railway construction and maintenancePresentation on railway construction and maintenance
Presentation on railway construction and maintenance
Mohd Bakhsh
 
railway failure and its type
railway failure and its typerailway failure and its type
railway failure and its type
Yash Patel
 
Road Safety as a Key Element in Planning & Design
Road Safety as a Key Element in Planning & DesignRoad Safety as a Key Element in Planning & Design
Road Safety as a Key Element in Planning & Design
WRI Ross Center for Sustainable Cities
 
Civil engineering in indian railways spce
Civil engineering in indian railways spceCivil engineering in indian railways spce
Civil engineering in indian railways spce
irkportal
 
turnouts in railways
 turnouts in railways turnouts in railways
turnouts in railways
Srinivasulu Srinu
 
Points and Crossings
Points and Crossings Points and Crossings
Points and Crossings
Abhijeet Salve
 
Railway engg geometric design
Railway engg geometric designRailway engg geometric design
Railway engg geometric design
Vijai Krishnan V
 
What are the Crash Barrier types?
What are the Crash Barrier types?What are the Crash Barrier types?
What are the Crash Barrier types?
Om Wire & Wire
 
Lect 29- traffic rotaries
Lect 29- traffic rotariesLect 29- traffic rotaries
Lect 29- traffic rotaries
HamidullahFarhang
 
GEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAYGEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAY
reemajadwani
 
Different Cross sections of Rail Tracks and Railway Station Layout
Different Cross sections of Rail Tracks and Railway Station LayoutDifferent Cross sections of Rail Tracks and Railway Station Layout
Different Cross sections of Rail Tracks and Railway Station Layout
Sunil Kumar Meena
 
Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptx
BalpreetSingh47890
 

What's hot (20)

IRC Method of Signal Design
IRC Method of Signal DesignIRC Method of Signal Design
IRC Method of Signal Design
 
Highway geometric design
Highway geometric designHighway geometric design
Highway geometric design
 
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
10 Geometric Design of Railway Track [Horizontal Alignment] (Railway Engineer...
 
Highway planning and alignment
Highway planning and alignmentHighway planning and alignment
Highway planning and alignment
 
Basics of Metro Railway Signalling system
Basics of Metro Railway Signalling systemBasics of Metro Railway Signalling system
Basics of Metro Railway Signalling system
 
Accident study
Accident studyAccident study
Accident study
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
 
Traffic engineering
Traffic engineeringTraffic engineering
Traffic engineering
 
Presentation on railway construction and maintenance
Presentation on railway construction and maintenancePresentation on railway construction and maintenance
Presentation on railway construction and maintenance
 
railway failure and its type
railway failure and its typerailway failure and its type
railway failure and its type
 
Road Safety as a Key Element in Planning & Design
Road Safety as a Key Element in Planning & DesignRoad Safety as a Key Element in Planning & Design
Road Safety as a Key Element in Planning & Design
 
Civil engineering in indian railways spce
Civil engineering in indian railways spceCivil engineering in indian railways spce
Civil engineering in indian railways spce
 
turnouts in railways
 turnouts in railways turnouts in railways
turnouts in railways
 
Points and Crossings
Points and Crossings Points and Crossings
Points and Crossings
 
Railway engg geometric design
Railway engg geometric designRailway engg geometric design
Railway engg geometric design
 
What are the Crash Barrier types?
What are the Crash Barrier types?What are the Crash Barrier types?
What are the Crash Barrier types?
 
Lect 29- traffic rotaries
Lect 29- traffic rotariesLect 29- traffic rotaries
Lect 29- traffic rotaries
 
GEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAYGEOMETRIC DESIGN OF HIGHWAY
GEOMETRIC DESIGN OF HIGHWAY
 
Different Cross sections of Rail Tracks and Railway Station Layout
Different Cross sections of Rail Tracks and Railway Station LayoutDifferent Cross sections of Rail Tracks and Railway Station Layout
Different Cross sections of Rail Tracks and Railway Station Layout
 
Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptx
 

Viewers also liked

Grinding machine
Grinding machineGrinding machine
Grinding machine
Sunit Neeli
 
GRINDING WHEEL SPECIFICATIONS
GRINDING WHEEL SPECIFICATIONSGRINDING WHEEL SPECIFICATIONS
GRINDING WHEEL SPECIFICATIONS
Yashraj Patil
 
Single Use Crucible
Single Use CrucibleSingle Use Crucible
Single Use Crucible
Thermitrex
 
Embedded system
Embedded systemEmbedded system
Embedded system
BESTECH SOLUTIONS
 
LVT
LVTLVT
Track Performance
Track PerformanceTrack Performance
Track Performance
Railways and Harbours
 
Mr. jose solorza haramain high speed railway phase 2
Mr. jose solorza  haramain high speed railway phase 2Mr. jose solorza  haramain high speed railway phase 2
Mr. jose solorza haramain high speed railway phase 2
imadhammoud
 
Lining&leveling
Lining&levelingLining&leveling
Lining&leveling
jitendra mandal
 
Grinding machine by- Diparsh Modh
Grinding machine by- Diparsh ModhGrinding machine by- Diparsh Modh
Grinding machine by- Diparsh Modh
Diparsh
 
1.grinding machine
1.grinding machine1.grinding machine

Viewers also liked (10)

Grinding machine
Grinding machineGrinding machine
Grinding machine
 
GRINDING WHEEL SPECIFICATIONS
GRINDING WHEEL SPECIFICATIONSGRINDING WHEEL SPECIFICATIONS
GRINDING WHEEL SPECIFICATIONS
 
Single Use Crucible
Single Use CrucibleSingle Use Crucible
Single Use Crucible
 
Embedded system
Embedded systemEmbedded system
Embedded system
 
LVT
LVTLVT
LVT
 
Track Performance
Track PerformanceTrack Performance
Track Performance
 
Mr. jose solorza haramain high speed railway phase 2
Mr. jose solorza  haramain high speed railway phase 2Mr. jose solorza  haramain high speed railway phase 2
Mr. jose solorza haramain high speed railway phase 2
 
Lining&leveling
Lining&levelingLining&leveling
Lining&leveling
 
Grinding machine by- Diparsh Modh
Grinding machine by- Diparsh ModhGrinding machine by- Diparsh Modh
Grinding machine by- Diparsh Modh
 
1.grinding machine
1.grinding machine1.grinding machine
1.grinding machine
 

Similar to Rail Grinding Machine:A Basic approach

Gang Strenght Formula.ppt
Gang Strenght Formula.pptGang Strenght Formula.ppt
Gang Strenght Formula.ppt
ssuser9cea3f
 
Translamatic robotic reconditioning by aden(pku)
Translamatic robotic reconditioning by aden(pku)Translamatic robotic reconditioning by aden(pku)
Translamatic robotic reconditioning by aden(pku)
Prem Prakash Kumar
 
ENGINEERING PPT BOX PUSHING ON PUNE DIVISION
ENGINEERING PPT BOX PUSHING ON PUNE DIVISIONENGINEERING PPT BOX PUSHING ON PUNE DIVISION
ENGINEERING PPT BOX PUSHING ON PUNE DIVISION
bridgelc
 
Track
TrackTrack
Traffic Control By Brian Kidd
Traffic Control By Brian KiddTraffic Control By Brian Kidd
Traffic Control By Brian Kidd
Engineers Australia
 
ROAD SAFETY AUDIT
ROAD SAFETY AUDITROAD SAFETY AUDIT
ROAD SAFETY AUDIT
lokeshthondamanati
 
SCT an Advanced Pipeline Integrity Solution
SCT an Advanced Pipeline Integrity SolutionSCT an Advanced Pipeline Integrity Solution
SCT an Advanced Pipeline Integrity Solution
Brett Payton
 
Featutes of New Guideline for the Design of Flexible Pavement.pptx
Featutes of New Guideline for the Design of Flexible Pavement.pptxFeatutes of New Guideline for the Design of Flexible Pavement.pptx
Featutes of New Guideline for the Design of Flexible Pavement.pptx
bnraj2
 
Flash butt welding
Flash butt weldingFlash butt welding
Flash butt welding
sabdou
 
Planning track maintenance.ppt
Planning track maintenance.pptPlanning track maintenance.ppt
Planning track maintenance.ppt
AfendiAriff
 
CONCEPT AND WORKING OF WILD (Wheel Impact Load Detector)
CONCEPT AND WORKING OF WILD (Wheel Impact Load Detector)CONCEPT AND WORKING OF WILD (Wheel Impact Load Detector)
CONCEPT AND WORKING OF WILD (Wheel Impact Load Detector)
Vipin Kumar
 
Presentation on track works
Presentation on track  worksPresentation on track  works
Presentation on track works
Vijay Raj
 
Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)
John Latilla
 
Iai rcs3 ct8 c-cj0210-1a-ust-1-0114
Iai rcs3 ct8 c-cj0210-1a-ust-1-0114Iai rcs3 ct8 c-cj0210-1a-ust-1-0114
Iai rcs3 ct8 c-cj0210-1a-ust-1-0114
Electromate
 
Iai rcp2 ra2_c_specsheet
Iai rcp2 ra2_c_specsheetIai rcp2 ra2_c_specsheet
Iai rcp2 ra2_c_specsheet
Electromate
 
Iai rcp2 ss7_c_specsheet
Iai rcp2 ss7_c_specsheetIai rcp2 ss7_c_specsheet
Iai rcp2 ss7_c_specsheet
Electromate
 
Iai rcp3 ra2_bc_specsheet
Iai rcp3 ra2_bc_specsheetIai rcp3 ra2_bc_specsheet
Iai rcp3 ra2_bc_specsheet
Electromate
 
Iai rcp2 ra10_c_specsheet
Iai rcp2 ra10_c_specsheetIai rcp2 ra10_c_specsheet
Iai rcp2 ra10_c_specsheet
Electromate
 
Railway Geometric Design
Railway Geometric DesignRailway Geometric Design
Railway Geometric Design
Umar Karimi
 
Alternative Approach to Permanent way Alignment Design
Alternative Approach to Permanent way Alignment DesignAlternative Approach to Permanent way Alignment Design
Alternative Approach to Permanent way Alignment Design
Constantin Ciobanu
 

Similar to Rail Grinding Machine:A Basic approach (20)

Gang Strenght Formula.ppt
Gang Strenght Formula.pptGang Strenght Formula.ppt
Gang Strenght Formula.ppt
 
Translamatic robotic reconditioning by aden(pku)
Translamatic robotic reconditioning by aden(pku)Translamatic robotic reconditioning by aden(pku)
Translamatic robotic reconditioning by aden(pku)
 
ENGINEERING PPT BOX PUSHING ON PUNE DIVISION
ENGINEERING PPT BOX PUSHING ON PUNE DIVISIONENGINEERING PPT BOX PUSHING ON PUNE DIVISION
ENGINEERING PPT BOX PUSHING ON PUNE DIVISION
 
Track
TrackTrack
Track
 
Traffic Control By Brian Kidd
Traffic Control By Brian KiddTraffic Control By Brian Kidd
Traffic Control By Brian Kidd
 
ROAD SAFETY AUDIT
ROAD SAFETY AUDITROAD SAFETY AUDIT
ROAD SAFETY AUDIT
 
SCT an Advanced Pipeline Integrity Solution
SCT an Advanced Pipeline Integrity SolutionSCT an Advanced Pipeline Integrity Solution
SCT an Advanced Pipeline Integrity Solution
 
Featutes of New Guideline for the Design of Flexible Pavement.pptx
Featutes of New Guideline for the Design of Flexible Pavement.pptxFeatutes of New Guideline for the Design of Flexible Pavement.pptx
Featutes of New Guideline for the Design of Flexible Pavement.pptx
 
Flash butt welding
Flash butt weldingFlash butt welding
Flash butt welding
 
Planning track maintenance.ppt
Planning track maintenance.pptPlanning track maintenance.ppt
Planning track maintenance.ppt
 
CONCEPT AND WORKING OF WILD (Wheel Impact Load Detector)
CONCEPT AND WORKING OF WILD (Wheel Impact Load Detector)CONCEPT AND WORKING OF WILD (Wheel Impact Load Detector)
CONCEPT AND WORKING OF WILD (Wheel Impact Load Detector)
 
Presentation on track works
Presentation on track  worksPresentation on track  works
Presentation on track works
 
Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)
 
Iai rcs3 ct8 c-cj0210-1a-ust-1-0114
Iai rcs3 ct8 c-cj0210-1a-ust-1-0114Iai rcs3 ct8 c-cj0210-1a-ust-1-0114
Iai rcs3 ct8 c-cj0210-1a-ust-1-0114
 
Iai rcp2 ra2_c_specsheet
Iai rcp2 ra2_c_specsheetIai rcp2 ra2_c_specsheet
Iai rcp2 ra2_c_specsheet
 
Iai rcp2 ss7_c_specsheet
Iai rcp2 ss7_c_specsheetIai rcp2 ss7_c_specsheet
Iai rcp2 ss7_c_specsheet
 
Iai rcp3 ra2_bc_specsheet
Iai rcp3 ra2_bc_specsheetIai rcp3 ra2_bc_specsheet
Iai rcp3 ra2_bc_specsheet
 
Iai rcp2 ra10_c_specsheet
Iai rcp2 ra10_c_specsheetIai rcp2 ra10_c_specsheet
Iai rcp2 ra10_c_specsheet
 
Railway Geometric Design
Railway Geometric DesignRailway Geometric Design
Railway Geometric Design
 
Alternative Approach to Permanent way Alignment Design
Alternative Approach to Permanent way Alignment DesignAlternative Approach to Permanent way Alignment Design
Alternative Approach to Permanent way Alignment Design
 

More from Prem Prakash Kumar

Report on insertion of br. approach sleeper to standardised the approach slee...
Report on insertion of br. approach sleeper to standardised the approach slee...Report on insertion of br. approach sleeper to standardised the approach slee...
Report on insertion of br. approach sleeper to standardised the approach slee...
Prem Prakash Kumar
 
Correct method of handling and stacking of rails
Correct method of handling and stacking of railsCorrect method of handling and stacking of rails
Correct method of handling and stacking of rails
Prem Prakash Kumar
 
Noble thoughts
Noble thoughtsNoble thoughts
Noble thoughts
Prem Prakash Kumar
 
Monsoon precaution [aden pku]
Monsoon precaution [aden pku]Monsoon precaution [aden pku]
Monsoon precaution [aden pku]
Prem Prakash Kumar
 
Development dynamics
Development dynamicsDevelopment dynamics
Development dynamics
Prem Prakash Kumar
 
Administrative tribunals
Administrative tribunalsAdministrative tribunals
Administrative tribunals
Prem Prakash Kumar
 

More from Prem Prakash Kumar (6)

Report on insertion of br. approach sleeper to standardised the approach slee...
Report on insertion of br. approach sleeper to standardised the approach slee...Report on insertion of br. approach sleeper to standardised the approach slee...
Report on insertion of br. approach sleeper to standardised the approach slee...
 
Correct method of handling and stacking of rails
Correct method of handling and stacking of railsCorrect method of handling and stacking of rails
Correct method of handling and stacking of rails
 
Noble thoughts
Noble thoughtsNoble thoughts
Noble thoughts
 
Monsoon precaution [aden pku]
Monsoon precaution [aden pku]Monsoon precaution [aden pku]
Monsoon precaution [aden pku]
 
Development dynamics
Development dynamicsDevelopment dynamics
Development dynamics
 
Administrative tribunals
Administrative tribunalsAdministrative tribunals
Administrative tribunals
 

Recently uploaded

Top five deadliest dog breeds in America
Top five deadliest dog breeds in AmericaTop five deadliest dog breeds in America
Top five deadliest dog breeds in America
Bisnar Chase Personal Injury Attorneys
 
The Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collectionThe Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collection
Israel Genealogy Research Association
 
Assessment and Planning in Educational technology.pptx
Assessment and Planning in Educational technology.pptxAssessment and Planning in Educational technology.pptx
Assessment and Planning in Educational technology.pptx
Kavitha Krishnan
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
Priyankaranawat4
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
heathfieldcps1
 
Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
adhitya5119
 
Smart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICTSmart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICT
simonomuemu
 
How to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP ModuleHow to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP Module
Celine George
 
DRUGS AND ITS classification slide share
DRUGS AND ITS classification slide shareDRUGS AND ITS classification slide share
DRUGS AND ITS classification slide share
taiba qazi
 
World environment day ppt For 5 June 2024
World environment day ppt For 5 June 2024World environment day ppt For 5 June 2024
World environment day ppt For 5 June 2024
ak6969907
 
Main Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docxMain Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docx
adhitya5119
 
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
National Information Standards Organization (NISO)
 
writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
Nicholas Montgomery
 
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
RitikBhardwaj56
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
Peter Windle
 
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Akanksha trivedi rama nursing college kanpur.
 
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective UpskillingYour Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Excellence Foundation for South Sudan
 
Pride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School DistrictPride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School District
David Douglas School District
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
Priyankaranawat4
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
Nguyen Thanh Tu Collection
 

Recently uploaded (20)

Top five deadliest dog breeds in America
Top five deadliest dog breeds in AmericaTop five deadliest dog breeds in America
Top five deadliest dog breeds in America
 
The Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collectionThe Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collection
 
Assessment and Planning in Educational technology.pptx
Assessment and Planning in Educational technology.pptxAssessment and Planning in Educational technology.pptx
Assessment and Planning in Educational technology.pptx
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
 
Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
 
Smart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICTSmart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICT
 
How to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP ModuleHow to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP Module
 
DRUGS AND ITS classification slide share
DRUGS AND ITS classification slide shareDRUGS AND ITS classification slide share
DRUGS AND ITS classification slide share
 
World environment day ppt For 5 June 2024
World environment day ppt For 5 June 2024World environment day ppt For 5 June 2024
World environment day ppt For 5 June 2024
 
Main Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docxMain Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docx
 
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
 
writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
 
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
 
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
 
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective UpskillingYour Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective Upskilling
 
Pride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School DistrictPride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School District
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
 

Rail Grinding Machine:A Basic approach

  • 1.
  • 2. Head Checks Head checks on Gauge Face of a Rail
  • 3.  Reduction in Rail/ Weld Failures Action on two fronts Arresting Initiation & Growth of Flaws Rail Grinding Objective Detection of the Flaws Vehicular USFD Testing
  • 4.
  • 5.  Rail Grinding is an important track maintenance tool  Rail Grinding is the removal of metal from the surface of the rail head  Through the action of a rotating grinding wheel  Mechanism used in rail grinding is cutting of metal associated with formation of metal chips (and not metal deformation)
  • 6.
  • 7.  Corrective – Removing the defects in one go  Preventive Gradual – Removing the defects in stages  Preventive – Removing the defects in nascent stage
  • 8.  Also known as traditional Rail Grinding  To correct existing surface defects and the shape of the head of the rail  A problem exists and sufficient grinding is done to correct the problem  Defect is allowed to develop before taking up the grinding; so remedial type action taken
  • 9. Condition Typical Recommendations New Rail At 20 GMT Corrugations 0.25-1.5 mm Engine Burns 0.6-0.8 mm Rail End Batter 0.8 mm Weld Batter 0.8 mm Flaking and Shelling 0.8 mm New Rail requires grinding for removal of mill scale. Mill scale is a very fine layer on rail head(<0.25MM).
  • 10.  Also known as profile grinding  Carried out before problems occurs  Rail head is ground to specific profile so as to improve rail wheel contact interface  Carried out more frequently  This is periodic maintenance grinding carried out at frequency decided on the basis of GMT.
  • 11.  Less aggressive grinding process  Removes fatigued material, surface cracks & improves rail wheel interaction  Eliminates the need for defect correction grinding  Generally one pass process carried out at higher speed ranging from 10 to 24 kmph.
  • 12.  In between corrective and preventive grinding  The defects in the rail are not removed in one go  Rails are ground at slow speed - only 1 to 3 passes are given  In each round, the defects will taper down  Ultimately, we shift to preventive grinding
  • 13.  IR has adopted Preventive Gradual Grinding to start with  Grinding cycle – 25 GMT –Ist, 50 GMT-2nd  One pass on straight and 3 passes in curve (speed 15-18 kmph)  Metal removal 0.1-0.2 mm (approx.)
  • 14. After I Cycle Cracks Partly Removed R NO C ACKS After II Cycle (approx. 30 GMT) More Cracks Removed After III Cycle (approx. 60 GMT) Cracks Fully Removed
  • 15.  Reshaping Rail Head Profile - favourable Rail Wheel Interaction reducing contact stresses  Removal of cracks in initial growth phase avoiding their propagation deeper  Shifting the contact of the wheels - away from the damaged zone  Avoid Dip Formation at Welds - Reduction in hunting by avoiding contact on misaligned welds
  • 16.  Increased rail life  Increased wheel life  Reduction in fatigue & surface defects  Less tractive resistance & therefore less fuel consumption  Reduced need for rail transposing in curves, thus saving cost on maintenance  Improved reliability of USFD testing
  • 17.  Reduced track geometry deterioration  Reduced degradation of ballast  Less noise  Improved vehicle ride quality  Reduced derailment proneness
  • 18.  Fastening (Rubber pad, ERC)  Life extended 3 times  Sleepers  Life extended by 20%  Tamping Cycle  Extended by 30%  Ballast Cleaning Cycle  Extended by 15%  Vehicle Maintenance & Wheel turning improved
  • 19.  Tractive energy  Reduced by 8 – 10%  Noise and vibration  In the human-hearing frequency range noise reduction of over 10 db can be achieved by grinding of corrugations
  • 21.  Establishment of Test Sites  Obstructions in the track  Details of Rail – Old/ New, GMT carried  Measurements  Rail condition data
  • 23. Test Sites -Selection Why: For establishing - Appropriate metal removal to control the growth of RCF cracks - Target Rail profile - Grinding cycle requirements Where: -High tonnage - Typical curvature / rail type - Good access to track - Rail history / defects - No planned rail replacement -Typical traffic & speed - Away from Weld, Signal, LC etc How: Gather data –MiniProf, surface photos, dye penetrate, weld dips, hunting
  • 24. Test Sites - MiniProf How– MiniProf: • Mark rail location with paint on field side for all future measurements • Record: - Line - Curve High, Low -Tangent right, Tangent left - Track –UP, DN - Date -automatic - Gauge –automatic
  • 26.
  • 27. Dye Penetration Testing Grinding Test Sites: How –Dye Penetrant: •cleaner, dye (wait 2 min), Wipe clean, water wash, Apply Developer (no overspray) •Record: - Location -Outside (OR) Inside (IR) rail, T Left, T Right -Track –UP, DN -Date -Gauge -Direction Traffic -Crack length -Rail age and weight
  • 28.  Turn-outs  SEJs  Level Crossings  Axle counters  Location – Chainages  Start & End of Curves  RH/LH Curve
  • 29.
  • 30.
  • 31. • Rail surface defects • Wear of rails • USFD defects in rails/weld • Rail/Weld failure details • Weld dip details
  • 32. • How it is decided? • For IR, designed by NRC • Four Profiles– CPC for DN road straight track & low rail of mild curve – CPF for UP road and low rail of sharp curve – HS for high rail of sharp curve – HM for low rail of Mild curve • Why two profiles for straight track?
  • 33.  Arrangement of stones across the rail and along the grinding train  Pattern needs to be selected by P. Way supervisor trained in grinding  Purpose is to achieve target rail profile from existing rail profile  Factors affecting Metal to be removed
  • 34.
  • 35. Different patterns being fed into HMI of RGM
  • 36.
  • 37. NRC Recommendation for Preventive Gradual Grinding Edit 6 Sep 6th, 2011 Wrong Direction in GDMS Patterns Speed 3 Pass Patterns First Pass First Pass Template Track Aggressive Generic Kph Pass 1 Pass 2 Pass 3 HS UP/Down 14 45 18 14 27 15 HS NEW RAIL UP/Down 2 45 18 2 47 23 HM UP/Down 10 45 18 10 43 27 HM NEW 2 47 x RAIL UP/Down 2 45 18 All Passes Speed Kph 18 18 18 18 LS-CPF UP/Down 20 47 18 20 23 27 18 LS-CPF NEW RAIL UP/Down 24 47 18 24 23 23 18 UP/Down LM-CPC LM-CPC NEW UP/Down RAIL TCPF UP 39 39 18 39 42 39 18 17 41 18 39 46 x 18 24 24 15 UP 24 24 15 DN 39 39 15 39 39 15 39 39 15 39 39 18 39 42 39 18 39 39 18 39 42 39 18 TCPF New rail TCPC TCPC NEW DN RAIL TCPC 52 Kg RAIL UP/Down LS-CPC 52 Kg UP/Down RAIL LM-CPC 52 Kg UP/Down RAIL
  • 38. • For Straight/ Tangent Track – DN Road – Template CPC – Pattern 39 – UP Road – Template CPF – Pattern 24 • For Curve Track – Mild Curve (< 1.25 deg) – High/ Outer Rail – Template HM – Pattern 10 – Low/Inner Rail – Template CPC – Pattern 39 • For Curve Track – Sharp Curve (> 1.25 deg) – High Rail – Template HS – Pattern 14 – Low Rail – Template CPF – Pattern 10
  • 39.  Straight Track – same as for old rail  For Curve Track – Mild Curve (< 1.25 deg)  High/ Outer Rail – Template HM – Pattern 2  Low/Inner Rail – Template CPC – Pattern 17  For Curve Track – Sharp Curve (> 1.25 deg)  High Rail – Template HS – Pattern 2  Low Rail – Template CPF – Pattern 24  For 52 kg Rail – For all conditions - 39
  • 40.  As suggested by GDMS  First cycle – 3 passes on both high & low rails  If GDMS gives 2 Passes – ask for alternative with 3 passes  What to do if GDMS data has wrong direction of curve
  • 41.  The Grind Data Management System is an integrated automatic data acquisition, data viewing and analysis, quality control, reporting and rail grinding planning tool.
  • 42.  The depth of cut w.r.t rail head and area of metal removal for different patterns is not available with IR to check the correctness of grinding.  The use of RCA in deciding the grinding pattern and grinding depth is not yet established.  Calculation of metal removal/m is still to be incorporated in GDMS.
  • 43.  Filling of Water to be done in night i.e during maintenance shifts.  The requirement of HSD oil from each RCD shall be arrived based on the locations of RCD and the track to be ground and suitable instructions shall be got issued from HQ to the respective RCDs.  While working of RGM, one track machine operator of the concerned division having route learning of that section shall be deputed for working as pilot and to assist in calling the signals.  When using the aggressive patterns as given by NRC, metal to the extent of 1.5mm was removed.  On some occasions it is noted that the pattern entered in HMI are not as per the grind plan due to operator mistake. This should be taken care.
  • 44.  A moped trolley with PA system, arranged to go ahead of RGM to warn the gatemen, gang men working in section to keep at least 20m away from track while grinding. The onlookers and vehicles at LC shall be warned to keep a safe distance.  From each division, a PWI is nominated as grinding supervisor. His duties shall be  To ensure the pattern fed into the HMI is same as suggested by NRC.  To ensure correct preparation of grind plan  To cross check the grind plan and grind history after grinding to find any deviations in the patterns.  To take pre and post miniprof readings at test locations and to keep the record as per proforma circulated by RDSO.  With experience, to check whether grinding is proper or not while observing the pre and post grind profiles on GDMS and to suggest the change in the patterns if required while grinding.
  • 45.  Identify the sections to be ground based on GMT, axle load  Establish test site locations and fill the RDSO proforma for      these locations. Identify stabling sidings at 50km apart, if not available provide ( Provide only RL platform) Identify the RCDs for HSD filling and make watering arrangements at stabling sidings. Issue JPO at HQ level and Divisional level for RGM operations. Obtain CRS sanction. Prepare track database for input to GDMS  (Direction of curves shall not be w.r.t traffic direction but w.r.t increasing chainage)
  • 46. Works to be carried out Before Rail grinding Knowing the Location/Sec where grinding is to be done. Type of Rail and sleeper, joint type(LWR,SWR,FP), and Sectional GMT. Location of SEJ, Points & X-ing, LC, Axle counter and any other obstacle which may infringe the grinding. Finding the location where grinding will not to be done. Finalizing the Location where grinding Machine will be stabled (where maintenance can be done). Preparation of grind plan consisting of locations to be ground with first pass patterns and depth of cut and details of obstructions . Clearing of rail head ballast to prevent damage to grinding motors Painting of Curve starting and ending on sleeper with white/yellow paint conspicuously. Ensuring sufficient HSD and water for the day
  • 47. Measurements and condition monitoring before grinding Measure the rail profile at nominated test locations with miniprof, Bar gauge, do DPT, take surface photos and measure hardness.  while taking miniprof readings, the details such as LH/RH of rail and TP to be fed otherwise it will not be possible to identify the pre and post grind profiles.
  • 48. Just Before the Grinding starts Availability of complete & sufficient staff with competency and Pilot with route learning Moped trolley with PA system to warn Rly. staff and onlookers and public at LC Removing of axle counters by S&T staff Job briefing consisting of Location of work Safety precautions to be taken Head count and complete PPE Allocation of duties with locations First aid, Location of nearest hospitals and fire stations along the work site. Effective Communication system between crew, crew and station
  • 50.  Real Time Monitoring of Grinding Operation  on the vehicle  On the ground  Monitoring  Amount of metal removed  Profile of the rail achieved after each pass  Efficacy of the grinding motors
  • 51.
  • 52.  The Grind Data Management System is an integrated automatic data acquisition, data viewing and analysis, quality control, reporting and rail grinding planning tool.
  • 53.  WATER SPRAY SYSTEM  BAR GAUGE  STAR GAUGE  CONTACT BAND  SURFACE ROUGHNESS  RAIL SURFACE FINISH  FIRE HAZARDS
  • 55. Taking measurements of rail profile before and grinding with bar-gaug
  • 56.
  • 57.
  • 58. Star Gauge to check Crown Radius
  • 59.
  • 60. Surface Roughness > 12 Microns Poor Finish Stays a Long Time
  • 61. Quality Control Examples –Straw Colour and Missed Grind
  • 62. Poor Finish – Blueing and Large Facets
  • 63. Rail ‘blueing”Poor cutting (low pressure) Grinding stoneNot set correctly. Grinding on the outside diameter (OD)
  • 64. • Sequencing Monitor - Skipping Obstructions • Safety systems • Calling Patterns • Feeding Patterns • Working of motors • Water Spray System • Calling Patterns • Pre & Post GQI
  • 65. LORAM RGI MODEL 72 STONE RAIL GRINDER
  • 66.  Self propelled Diesel powered vehicle.  Can work in both directions.  Negotiate cant up to 185 mm.       Traveling speed 80 Kmph when self propelled and 100 Kmph in train formation. 25 kmph on 1 in 33 Grade Speed with buggies down – 40kmph Grinding Speed - 2.4 to 24 kmph Can grind on a 100 m radius curve Stopping Distance – 400 m from 80 kmph on a level track
  • 67.
  • 68.  Self propelled car  Pilot, Guard and T.I. to be provided by the division in two shifts for first three months  Operating speed  10kmph @ 0.20mm  15kmph @ 0.13mm  Speed Cert to be issued and CRS sanction to be obtained
  • 69.  Joint monthly prog. at zonal & weekly prog. At Divl      level 4 hours corridor block daily and 6 hours block on weekends by SL working, trains cancellation/ regulation Controller to allow RGM in the section following a train to save time Goods trains carrying highly inflammable material like Naptha to be regulated on adjacent line during block Obstructions in the track Passage of trains after the grinding block
  • 70.  Spark Guards of different designs  Water Storage – Front Control Car 20000 lit      - Water Tank 55000 lit Water Pump – One 30hp 945 lit/min Sleeper Spray – 2 Sets 7.6 lit/min Ditch Spray – 2 Sets 100 lit/min Water Cannons – 2 Sets 220 lit/min upto 31m No. of Fire Extinguishers at different locations in the car
  • 71.  Water to be arranged  Fuel arrangement  Hydraulic oil  Grinding stones for 600 hrs of working included with machine  RDSO to issue the specs and list of suppliers for grinding stones
  • 72.  Zonal Railways to send vetted indents to COS every year  Diesel to be provided by RCDs( Railway Consumers Depots)  COS to place order on oil Cos.  Sufficient fuel imprest to be created - 5 lakhs; this will cater for other unforeseen expenses also
  • 73.  300m or 2X150m sidings at every 50kms  Connectivity at both ends  Lighting, watering, approach road and other facilities to be provided  Lodging and Boarding of staff  Stabling either on unwired sdg or sdg should be with OHE isolation system
  • 74.  Dust Collection System  Laser Based Rail Profile Measurement System on both ends of the consist  LORAM’s Software – GDMS - The software stores the data, analyses and compares the data and works out the grinding efficiency  Recommendation of target profile, pattern and speed in different passes to achieve the target profile optimally

Editor's Notes

  1. Test sites are crucial for establishing the appropriate metal removal, profile and grinding cycle requirements for the railroad. They are used to establish the metal removal rate to control the growth of RCF cracks. Rail samples or non destructive methods are utilized to determine the fatigue-crack growth rates and their internal direction of propagation. The objective is to develop the optimal metal removal rate and the preventive grinding cycles to manage the rail grinding strategy for the changing railroad environment. Test sites are the best way to manage the risks of implementing changes to established preventive grinding cycles. If any serious failure of a new strategy takes place, it will happen in the test site. The data extracted through detailed monitoring of test sites can also be used to calculate the benefits of a modified preventive grinding strategy in controlling RCF, reducing rail wear, reducing grinding effort and cost.
  2. Metal removal depends upon no. of stones, speed of grinding, characterstics of stone, metallurgy of rails and arrangement of stones