SlideShare a Scribd company logo
Project Value Delivery
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Best Practices for
Large Complex
Projects Control
Jeremie Averous
Senior Managing Partner
V0 – March 2015
Contents
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Large Complex Projects
Best Practices
• Introduction: Specifics of Large,
Complex Projects
• Project Team
• Project Control
• Cost
• Schedule
• Risk
• Project Systems
• Summary
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 3
• Be Focused on the right
things – Convergence
Monitoring
• Be in Control while
remaining Agile
• Address Complexity
• Create Space for
Responding to the
Unexpected
Section
1
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
• Introduction: specifics of Large,
Complex Projects
• Project Team
• Project Control
• Cost
• Schedule
• Risk
• Project Systems
• Summary
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 5
What is Complexity?
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 6
Complex System = System with many
independent components and strong
interactions
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 7
Complicated vs Complex
Section
2
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
• Introduction: specifics of Large,
Complex Projects
• Project Team
• Project Control
• Cost
• Schedule
• Risk
• Project Systems
• Summary
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 9
Project Team Best Practices
• Strong Project governance
• Strong Project Manager authority / specialized
disciplines providing resources
• Project Leadership not just Management
• An effective, integrated team with full-time
contributors in a separate open-space
• Effective teambuilding and operating practices
• The Project Execution Plans are developed and
revisited as a group during workshops at project
start-up
• To the extent practical ensure alignment between
individual capabilities and interests and project goals
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 10
Why?
• Diminish complexity
– Improve contributors’ alignment
• Strength of Project Sponsorship & governance
• Familiarization, alignment workshops
• Incentive schemes
– Minimize the number of contributors and
interfaces
• Integrated work package / subcontractors
• Integrated teams
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 11
Integrated teams
• High Authority Level of Project Manager
• Most people are allocated full time to a project
• The project-team is collocated in an open-plan
space to facilitate communication
• They do what it takes for the project
– recognition of need to contribute outside formal role
description for overall success
• A Matrix organization is
implemented within the
project with delivery
responsibility
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 12
Project Governance
• Proper project governance is often lacking on large
projects
– Project sponsor should understand specifics of large
projects,
– Project sponsorship should be strong and present,
– Project execution strategy and decision-making key points
for management should be well defined (gates),
– Utilization of contingency reserves process should be clear,
– Will to invest to prevent future costs or manage risks.
…You need to
build an
effective
integrated
team to find
the solution in
complexity
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 15
A team where blaming starts
=
100% project failure
Section
3
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
• Introduction: specifics of Large,
Complex Projects
• Project Team
• Project Control
• Cost
• Schedule
• Risk
• Project Systems
• Summary
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 17
The Three Fundamental Questions
WHERE ARE WE?
(ARE WE ON COURSE?)
WHERE ARE WE GOING?
WHAT DO WE NEED TO DO TO BE
BACK ON COURSE?
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 18
Project Control Best Practices
• Project Control is implemented as a specific senior role
reporting to the PM – does not exist as such in smaller
projects
• Project Control to ensure consistency between cost,
schedule, risk and contracts at the adequate level of
detail
– Breakdown structures
– Forecasts / Earned Value Management
– Contingency, reserves, allowances
• Project Control sets up the relevant measurement and
reporting processes & systems
• Project Control is not just about compliance - it needs to
be the strategic advisor for the PMT
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 19
Large projects typical organization
Project
managerProject
Control
manager
Package
Manager 1
HSE, Q
Package
Manager 2
Package
Manager 3
Engineering
Manager
Procurement
manager
Construction
manager
Commissioning
Manager
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 20
What is Project Controls?
Project Control is about building
information sensors, and making
sense of the information.
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 21
Project Breakdown detail level
(Cost Model, Schedule)
Breakdown detail
Too little detail
will not allow
to grasp
the project drivers
Too much detail
drowns the team
and removes agility
Effectiveness
Optimal
Cost /
Schedule
Detail
Range
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 22
Too much detail!
= Not enough time for
analysis!
Section
4
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
• Introduction: specifics of Large,
Complex Projects
• Project Team
• Project Control
• Cost
• Schedule
• Risk
• Project Systems
• Summary
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 24
Project Cost Control Best Practices
• Fully distinct from Accounting
• Focus on commitments and Project-end forecast
• Actual Cost (VOWD) is evaluated independently of
invoicing
• Breakdown structures are owned by Project Control and
coordinated with Procurement and Construction
contracting strategies
• A full Project Cost Model is maintained (in source
currency, time-phased, by work package)
• Issues / events are reported immediately in the forecast
• Sensitivities are provided in addition to the (prudent)
forecast
• Data integrity is maintained, all variances remain
traceable
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 25
Common “maturity’ observations
when no strong Cost Management
• Costs for internal resources as actual costs instead
of standard rates
– Extreme complication of cost tracking
• Commitments are not tracked – only invoicing
– Invoicing without commitments
– Poor control on project bottom line because of
invoicing delays
• Poor consistency with project execution strategy
and forecast schedule
• No support to PM in scenario planning
• No sensitivities available
Section
5
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
• Introduction: specifics of Large,
Complex Projects
• Project Team
• Project Control
• Cost
• Schedule
• Risk
• Project Systems
• Summary
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 33
Project Schedule Best Practices
• Limit the detail of the Project Integrated Schedule – use a
proper scheduling hierarchy
• Use the Convergence Planning / monitoring method +
communicate focus to the team
• Float and Buffers are owned by the PM
• Avoid ‘virtual float’ generation by constraining delivery
on fixed dates
• Implement float monitoring / trending (evolution of float
from one update to the next)
• Avoid having different schedules for different
stakeholders
• Prefer to increase the schedule robustness and
resilience instead of minimizing the critical path.
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 35
Best Practice Schedule Vision
Integrated Project Schedule
1,500 – 2,500 activities
Convergence
Plan
~ 100-200
deliverables
MOREDETAILS
MOREFOCUS
Document
List &
detailed
engineering
schedule
SCM
Detailed
Plan
Construction
Sub-
contractor’s
schedules
Commi-
ssioning
Plan /
schedule
Installation
Plan
Simplified Project Schedule
200-400
Activities
(Schedule Risk Analysis)
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 37
Convergence processFor Complex Projects, the focus needs to be on
convergence
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 38
Convergence process
Simple Project Complex Project
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 39
Convergence process
Project Performance Driver
(or, what kills a project)
Simple project Large project
Efficiency Convergence
Potential upside/
downside±10%
+20%
- 30, -50, -100%
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 40
Most
Projects fail
because of a
small piece
missing…
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 41
Convergence
Plan Example
Section
6
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
• Introduction: specifics of Large,
Complex Projects
• Project Team
• Project Control
• Cost
• Schedule
• Risk
• Project Systems
• Summary
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 43
Project Risk Best Practices
• Opportunity and Risks, and ratings to be discussed as a team
• Focused action-taking. Prioritize ruthlessly and focus effort
• The earlier, the better for action-taking
• Use all opportunities of contractual relationships to transfer risk
• Do not confuse allowances, contingency, management
reserves
• Schedule risk analysis focus on improving schedule resilience
• Monte Carlo methods are conventional and their limits must
be understood (e.g. low probability risk, independence
assumptions)
• Most of the project risk is related to schedule slippage & lack
of convergence, and consequential impacts
• Prevention of major accidents is essential – industrial risk
management
• In case of major event, create a separate task-force to
minimize consequential impact on project execution
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 44
Advanced Risk Management
approaches
• Industrial Risk Management
– Specific methods to prevent major catastrophic
events (low probability, high consequences)
• Portfolio risk management
– Manage dependencies between projects
(resources etc) and consequential effects
• Minimize complexity
• Ensure there is a way to escape the project if it goes
bad – contractual T&C
– Limit of liability, termination clause etc
• Proper contingency calculation and Senior
Management ownership
Section
7
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
• Introduction: specifics of Large,
Complex Projects
• Project Team
• Project Control
• Cost
• Schedule
• Risk
• Project Systems
• Summary
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 48
Systems
• Large project = lots of data to control
– Manual systems are overwhelmed, high error rate
• Need to:
– manage inter-office remote work, remote sites
– guarantee data correctness and accurate
reporting
• What minimum systems?
– Document control & Correspondence control
– Cost control (different from accounting)
– Commitments & approvals
• SCM
• Logistics
• Travel, HR
• Timesheets
– Scheduling & convergence planning
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 49
Project Systems Best Practices
• Minimize risks of mistakes by having systems that synchronize or
are shared/ accessible between different sites & worksite (new
trend = in addition, go mobile) and across the full process cycles
(e.g. site commitments)
• Single integrated systems (~ERP) often less effective in terms of
control and efficiency than a suite of specialized systems with
checks at the interface; and in addition longer and more
expensive to set-up
• All action-tracking systems to be coordinated to allow real
prioritization across the board
• Reporting to be as automated as possible to leave space for
actual analysis work (new trend = real time dashboards)
• Leverage systems to create performance indicators and reports
• Ensure shared breakdown structures and consistent references
across the entire contracting levels
Conclusion
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 51
Moving into Larger, more Complex
Projects
• Management by “efficient”
hierarchical departments
• Purely rational approaches
• Following an immutable baseline
plan
(a.k.a the Stalinist approach)
…DON’T WORK!
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 52
So, is your organization is ready for
large projects?
Key indicators:
• Strength of project managers vs department heads
• Project leadership capabilities and effective teams
• Office lay-out – really integrated teams
• Cost mindset vs investment mindset at
management level
• Strength of project governance process
• Strength of IT systems for project data management
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 53
• Be Focused on the right
things – Convergence
Monitoring
• Be in Control while
remaining Agile
• Address Complexity
• Create Space for
Responding to the
Unexpected
LEAD!
© Project Value Delivery, 2016
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 54
This presentation summarizes key best practices for
Large Complex Projects.
More information is available on our White Papers and
other documents on www.ProjectValueDelivery.com
…as well as in our handbooks!
W e E m p o w e r O r g a n i z a t i o n s
T o b e R e l i a b l y S u c c e s s f u l i n
E x e c u t i n g L a r g e , C o m p l e x P r o j e c t s
Discover more on
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Project Value Delivery
Project Soft Power
Unleashing Value
from Your
Large, Complex
Projects
Project Health Check
Project Coaching
Organizational maturity
Team effectivenessIntercultural leadership
Advanced project trainingProject Startup support
Project Recovery
Advanced risk management
Project Control and Reporting
Support systems integration
Convergence planning
Remote sites integration
Leadership development

More Related Content

What's hot

Advanced Work Packaging: Implementation Challenges
Advanced Work Packaging: Implementation ChallengesAdvanced Work Packaging: Implementation Challenges
Advanced Work Packaging: Implementation Challenges
The Advanced Work Packaging Institute
 
Setting up a new PMO - Arpin
Setting up a new PMO - ArpinSetting up a new PMO - Arpin
Setting up a new PMO - Arpin
Arpin Consulting
 
Advanced Work Packaging: Applying Project Controls
Advanced Work Packaging: Applying Project ControlsAdvanced Work Packaging: Applying Project Controls
Advanced Work Packaging: Applying Project Controls
The Advanced Work Packaging Institute
 
How to set up a project management office (PMO)
How to set up a project management office (PMO)How to set up a project management office (PMO)
How to set up a project management office (PMO)
PM Majik
 
Assessing PMO Maturity In Your Organization
Assessing PMO Maturity In Your OrganizationAssessing PMO Maturity In Your Organization
Assessing PMO Maturity In Your Organization
Sasha Lapshina
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve
Satish Yadavalli
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)
Anand Subramaniam
 
Primavera P6 manual
Primavera P6 manual Primavera P6 manual
Primavera P6 manual
Abbas Tahir
 
Advanced Work Packaging (AWP) Presentation
Advanced Work Packaging (AWP) PresentationAdvanced Work Packaging (AWP) Presentation
Advanced Work Packaging (AWP) Presentation
Device Media
 
Organization Chart Roles & Responsibilities Matrix
Organization Chart Roles & Responsibilities MatrixOrganization Chart Roles & Responsibilities Matrix
Organization Chart Roles & Responsibilities MatrixChris Garbett
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
Chris Carson
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
ignitetribes
 
PMO Overview June 2009
PMO Overview June 2009PMO Overview June 2009
PMO Overview June 2009
Chevy Marchosky
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
Rahul Sudame
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
Chris Carson
 
Advanced Work Packaging (AWP): Benefits
Advanced Work Packaging (AWP): BenefitsAdvanced Work Packaging (AWP): Benefits
Advanced Work Packaging (AWP): Benefits
The Advanced Work Packaging Institute
 
DCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdfDCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdf
Karim Ragab
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt
TecnicoItca
 
PMO View Interactive Dashboard
PMO View Interactive DashboardPMO View Interactive Dashboard
PMO View Interactive Dashboard
Matt Angerer
 
PMO Frameworks
PMO FrameworksPMO Frameworks
PMO Frameworks
Michael Kaplan
 

What's hot (20)

Advanced Work Packaging: Implementation Challenges
Advanced Work Packaging: Implementation ChallengesAdvanced Work Packaging: Implementation Challenges
Advanced Work Packaging: Implementation Challenges
 
Setting up a new PMO - Arpin
Setting up a new PMO - ArpinSetting up a new PMO - Arpin
Setting up a new PMO - Arpin
 
Advanced Work Packaging: Applying Project Controls
Advanced Work Packaging: Applying Project ControlsAdvanced Work Packaging: Applying Project Controls
Advanced Work Packaging: Applying Project Controls
 
How to set up a project management office (PMO)
How to set up a project management office (PMO)How to set up a project management office (PMO)
How to set up a project management office (PMO)
 
Assessing PMO Maturity In Your Organization
Assessing PMO Maturity In Your OrganizationAssessing PMO Maturity In Your Organization
Assessing PMO Maturity In Your Organization
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)
 
Primavera P6 manual
Primavera P6 manual Primavera P6 manual
Primavera P6 manual
 
Advanced Work Packaging (AWP) Presentation
Advanced Work Packaging (AWP) PresentationAdvanced Work Packaging (AWP) Presentation
Advanced Work Packaging (AWP) Presentation
 
Organization Chart Roles & Responsibilities Matrix
Organization Chart Roles & Responsibilities MatrixOrganization Chart Roles & Responsibilities Matrix
Organization Chart Roles & Responsibilities Matrix
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
 
PMO Overview June 2009
PMO Overview June 2009PMO Overview June 2009
PMO Overview June 2009
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
Advanced Work Packaging (AWP): Benefits
Advanced Work Packaging (AWP): BenefitsAdvanced Work Packaging (AWP): Benefits
Advanced Work Packaging (AWP): Benefits
 
DCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdfDCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdf
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt
 
PMO View Interactive Dashboard
PMO View Interactive DashboardPMO View Interactive Dashboard
PMO View Interactive Dashboard
 
PMO Frameworks
PMO FrameworksPMO Frameworks
PMO Frameworks
 

Viewers also liked

Project Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsProject Value Delivery methodology and interventions
Project Value Delivery methodology and interventions
Jeremie Averous
 
How Governance Makes or Breaks a Project
How Governance Makes or Breaks a ProjectHow Governance Makes or Breaks a Project
How Governance Makes or Breaks a Project
Jeremie Averous
 
Organizational Transformation Best Practices (Project-Driven Businesses)
Organizational Transformation Best Practices (Project-Driven Businesses)Organizational Transformation Best Practices (Project-Driven Businesses)
Organizational Transformation Best Practices (Project-Driven Businesses)
Jeremie Averous
 
Large Complex Projects (PMI-MY presentation Sept 2012)
Large Complex Projects (PMI-MY presentation Sept 2012)Large Complex Projects (PMI-MY presentation Sept 2012)
Large Complex Projects (PMI-MY presentation Sept 2012)
Jeremie Averous
 
Project Soft Power
Project Soft PowerProject Soft Power
Project Soft Power
Jeremie Averous
 
Specifics of Managing Large, Complex Projects
Specifics of Managing Large, Complex ProjectsSpecifics of Managing Large, Complex Projects
Specifics of Managing Large, Complex Projects
Jeremie Averous
 

Viewers also liked (6)

Project Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsProject Value Delivery methodology and interventions
Project Value Delivery methodology and interventions
 
How Governance Makes or Breaks a Project
How Governance Makes or Breaks a ProjectHow Governance Makes or Breaks a Project
How Governance Makes or Breaks a Project
 
Organizational Transformation Best Practices (Project-Driven Businesses)
Organizational Transformation Best Practices (Project-Driven Businesses)Organizational Transformation Best Practices (Project-Driven Businesses)
Organizational Transformation Best Practices (Project-Driven Businesses)
 
Large Complex Projects (PMI-MY presentation Sept 2012)
Large Complex Projects (PMI-MY presentation Sept 2012)Large Complex Projects (PMI-MY presentation Sept 2012)
Large Complex Projects (PMI-MY presentation Sept 2012)
 
Project Soft Power
Project Soft PowerProject Soft Power
Project Soft Power
 
Specifics of Managing Large, Complex Projects
Specifics of Managing Large, Complex ProjectsSpecifics of Managing Large, Complex Projects
Specifics of Managing Large, Complex Projects
 

Similar to PVD Project Control Best Practices for Large Projects

Advanced project scheduling: proper practices for integrated project schedules
Advanced project scheduling: proper practices for integrated project schedulesAdvanced project scheduling: proper practices for integrated project schedules
Advanced project scheduling: proper practices for integrated project schedules
Jeremie Averous
 
How to Manage the Transition from Small, Simple to Large Complex Projects
How to Manage the Transition from Small, Simple to Large Complex ProjectsHow to Manage the Transition from Small, Simple to Large Complex Projects
How to Manage the Transition from Small, Simple to Large Complex Projects
Jeremie Averous
 
Cost Estimation and Control on Projects: Addressing today's challenges
Cost Estimation and Control on Projects: Addressing today's challengesCost Estimation and Control on Projects: Addressing today's challenges
Cost Estimation and Control on Projects: Addressing today's challenges
Jeremie Averous
 
The Business of Projects
The Business of ProjectsThe Business of Projects
The Business of Projects
Unanet
 
Project Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsProject Value Delivery methodology and interventions
Project Value Delivery methodology and interventions
Jeremie Averous
 
Business Transformation Best Practices-Project Value Delivery.pdf
Business Transformation Best Practices-Project Value Delivery.pdfBusiness Transformation Best Practices-Project Value Delivery.pdf
Business Transformation Best Practices-Project Value Delivery.pdf
hasan752746
 
Large Complex Industrial Projects:Owner specific role and associated requirem...
Large Complex Industrial Projects:Owner specific role and associated requirem...Large Complex Industrial Projects:Owner specific role and associated requirem...
Large Complex Industrial Projects:Owner specific role and associated requirem...
Jeremie Averous
 
PROJECT MANAGEMENT ESSENTIALS.pptx
PROJECT MANAGEMENT ESSENTIALS.pptxPROJECT MANAGEMENT ESSENTIALS.pptx
PROJECT MANAGEMENT ESSENTIALS.pptx
NanthakkumarAppathur1
 
Aconex connected cost webinar - drive project performance
Aconex connected cost webinar - drive project performanceAconex connected cost webinar - drive project performance
Aconex connected cost webinar - drive project performance
Aconex
 
Environmental Engineering.pptx
Environmental Engineering.pptxEnvironmental Engineering.pptx
Environmental Engineering.pptx
BonnelAlos1
 
PRESTO Change Management
PRESTO Change ManagementPRESTO Change Management
PRESTO Change Management
TOPP Tactical Intelligence Ltd
 
project introduction.pdf
project introduction.pdfproject introduction.pdf
project introduction.pdf
RajeevRanjan959412
 
PRESTO Change Management
PRESTO Change ManagementPRESTO Change Management
PRESTO Change Management
TOPP Tactical Intelligence Ltd
 
Support & Consultancy, Robers Hobbs, APM PMO SIG conference 2017
Support & Consultancy, Robers Hobbs, APM PMO SIG conference 2017Support & Consultancy, Robers Hobbs, APM PMO SIG conference 2017
Support & Consultancy, Robers Hobbs, APM PMO SIG conference 2017
Association for Project Management
 
New Techniques to Elevate QA to Program Assurance
New Techniques to Elevate QA to Program AssuranceNew Techniques to Elevate QA to Program Assurance
New Techniques to Elevate QA to Program AssuranceSusan Schanta
 
Pm audit and assessment approach final
Pm audit and assessment approach   finalPm audit and assessment approach   final
Pm audit and assessment approach final
Project Management Solutions
 
Lessons From The Project Front Line - 4th November 2015
Lessons From The Project Front Line - 4th November 2015Lessons From The Project Front Line - 4th November 2015
Lessons From The Project Front Line - 4th November 2015
Association for Project Management
 
Project controls function
Project controls functionProject controls function
Project controls function
Hatem Hegazi
 
Change management made easy with PRESTO Digital Change Manager
Change management made easy with PRESTO Digital Change ManagerChange management made easy with PRESTO Digital Change Manager
Change management made easy with PRESTO Digital Change Manager
TOPP Tactical Intelligence Ltd
 
Project Life Cycle final.pptx
Project Life Cycle final.pptxProject Life Cycle final.pptx
Project Life Cycle final.pptx
PranshiGoyal2
 

Similar to PVD Project Control Best Practices for Large Projects (20)

Advanced project scheduling: proper practices for integrated project schedules
Advanced project scheduling: proper practices for integrated project schedulesAdvanced project scheduling: proper practices for integrated project schedules
Advanced project scheduling: proper practices for integrated project schedules
 
How to Manage the Transition from Small, Simple to Large Complex Projects
How to Manage the Transition from Small, Simple to Large Complex ProjectsHow to Manage the Transition from Small, Simple to Large Complex Projects
How to Manage the Transition from Small, Simple to Large Complex Projects
 
Cost Estimation and Control on Projects: Addressing today's challenges
Cost Estimation and Control on Projects: Addressing today's challengesCost Estimation and Control on Projects: Addressing today's challenges
Cost Estimation and Control on Projects: Addressing today's challenges
 
The Business of Projects
The Business of ProjectsThe Business of Projects
The Business of Projects
 
Project Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsProject Value Delivery methodology and interventions
Project Value Delivery methodology and interventions
 
Business Transformation Best Practices-Project Value Delivery.pdf
Business Transformation Best Practices-Project Value Delivery.pdfBusiness Transformation Best Practices-Project Value Delivery.pdf
Business Transformation Best Practices-Project Value Delivery.pdf
 
Large Complex Industrial Projects:Owner specific role and associated requirem...
Large Complex Industrial Projects:Owner specific role and associated requirem...Large Complex Industrial Projects:Owner specific role and associated requirem...
Large Complex Industrial Projects:Owner specific role and associated requirem...
 
PROJECT MANAGEMENT ESSENTIALS.pptx
PROJECT MANAGEMENT ESSENTIALS.pptxPROJECT MANAGEMENT ESSENTIALS.pptx
PROJECT MANAGEMENT ESSENTIALS.pptx
 
Aconex connected cost webinar - drive project performance
Aconex connected cost webinar - drive project performanceAconex connected cost webinar - drive project performance
Aconex connected cost webinar - drive project performance
 
Environmental Engineering.pptx
Environmental Engineering.pptxEnvironmental Engineering.pptx
Environmental Engineering.pptx
 
PRESTO Change Management
PRESTO Change ManagementPRESTO Change Management
PRESTO Change Management
 
project introduction.pdf
project introduction.pdfproject introduction.pdf
project introduction.pdf
 
PRESTO Change Management
PRESTO Change ManagementPRESTO Change Management
PRESTO Change Management
 
Support & Consultancy, Robers Hobbs, APM PMO SIG conference 2017
Support & Consultancy, Robers Hobbs, APM PMO SIG conference 2017Support & Consultancy, Robers Hobbs, APM PMO SIG conference 2017
Support & Consultancy, Robers Hobbs, APM PMO SIG conference 2017
 
New Techniques to Elevate QA to Program Assurance
New Techniques to Elevate QA to Program AssuranceNew Techniques to Elevate QA to Program Assurance
New Techniques to Elevate QA to Program Assurance
 
Pm audit and assessment approach final
Pm audit and assessment approach   finalPm audit and assessment approach   final
Pm audit and assessment approach final
 
Lessons From The Project Front Line - 4th November 2015
Lessons From The Project Front Line - 4th November 2015Lessons From The Project Front Line - 4th November 2015
Lessons From The Project Front Line - 4th November 2015
 
Project controls function
Project controls functionProject controls function
Project controls function
 
Change management made easy with PRESTO Digital Change Manager
Change management made easy with PRESTO Digital Change ManagerChange management made easy with PRESTO Digital Change Manager
Change management made easy with PRESTO Digital Change Manager
 
Project Life Cycle final.pptx
Project Life Cycle final.pptxProject Life Cycle final.pptx
Project Life Cycle final.pptx
 

More from Jeremie Averous

Dealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration MegaprojectsDealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration Megaprojects
Jeremie Averous
 
Advanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial ProjectsAdvanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial Projects
Jeremie Averous
 
Project Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsProject Value Delivery methodology and interventions
Project Value Delivery methodology and interventions
Jeremie Averous
 
Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...
Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...
Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...
Jeremie Averous
 
Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...
Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...
Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...
Jeremie Averous
 
Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...
Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...
Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...
Jeremie Averous
 

More from Jeremie Averous (6)

Dealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration MegaprojectsDealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration Megaprojects
 
Advanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial ProjectsAdvanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial Projects
 
Project Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsProject Value Delivery methodology and interventions
Project Value Delivery methodology and interventions
 
Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...
Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...
Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...
 
Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...
Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...
Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...
 
Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...
Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...
Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...
 

Recently uploaded

3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
BBPMedia1
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
seri bangash
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
Workforce Group
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
awaisafdar
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
dylandmeas
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Lviv Startup Club
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
HumanResourceDimensi1
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
RajPriye
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
fakeloginn69
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
taqyed
 
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
agatadrynko
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
Erika906060
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
zoyaansari11365
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
usawebmarket
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
marketingjdass
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
DerekIwanaka1
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
dylandmeas
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
Sam H
 

Recently uploaded (20)

3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
 
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
 

PVD Project Control Best Practices for Large Projects

  • 1. Project Value Delivery © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m Best Practices for Large Complex Projects Control Jeremie Averous Senior Managing Partner V0 – March 2015
  • 2. Contents © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m Large Complex Projects Best Practices • Introduction: Specifics of Large, Complex Projects • Project Team • Project Control • Cost • Schedule • Risk • Project Systems • Summary
  • 3. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 3 • Be Focused on the right things – Convergence Monitoring • Be in Control while remaining Agile • Address Complexity • Create Space for Responding to the Unexpected
  • 4. Section 1 © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m • Introduction: specifics of Large, Complex Projects • Project Team • Project Control • Cost • Schedule • Risk • Project Systems • Summary
  • 5. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 5 What is Complexity?
  • 6. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 6 Complex System = System with many independent components and strong interactions
  • 7. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 7 Complicated vs Complex
  • 8. Section 2 © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m • Introduction: specifics of Large, Complex Projects • Project Team • Project Control • Cost • Schedule • Risk • Project Systems • Summary
  • 9. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 9 Project Team Best Practices • Strong Project governance • Strong Project Manager authority / specialized disciplines providing resources • Project Leadership not just Management • An effective, integrated team with full-time contributors in a separate open-space • Effective teambuilding and operating practices • The Project Execution Plans are developed and revisited as a group during workshops at project start-up • To the extent practical ensure alignment between individual capabilities and interests and project goals
  • 10. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 10 Why? • Diminish complexity – Improve contributors’ alignment • Strength of Project Sponsorship & governance • Familiarization, alignment workshops • Incentive schemes – Minimize the number of contributors and interfaces • Integrated work package / subcontractors • Integrated teams
  • 11. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 11 Integrated teams • High Authority Level of Project Manager • Most people are allocated full time to a project • The project-team is collocated in an open-plan space to facilitate communication • They do what it takes for the project – recognition of need to contribute outside formal role description for overall success • A Matrix organization is implemented within the project with delivery responsibility
  • 12. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 12 Project Governance • Proper project governance is often lacking on large projects – Project sponsor should understand specifics of large projects, – Project sponsorship should be strong and present, – Project execution strategy and decision-making key points for management should be well defined (gates), – Utilization of contingency reserves process should be clear, – Will to invest to prevent future costs or manage risks.
  • 13. …You need to build an effective integrated team to find the solution in complexity
  • 14. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 15 A team where blaming starts = 100% project failure
  • 15. Section 3 © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m • Introduction: specifics of Large, Complex Projects • Project Team • Project Control • Cost • Schedule • Risk • Project Systems • Summary
  • 16. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 17 The Three Fundamental Questions WHERE ARE WE? (ARE WE ON COURSE?) WHERE ARE WE GOING? WHAT DO WE NEED TO DO TO BE BACK ON COURSE?
  • 17. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 18 Project Control Best Practices • Project Control is implemented as a specific senior role reporting to the PM – does not exist as such in smaller projects • Project Control to ensure consistency between cost, schedule, risk and contracts at the adequate level of detail – Breakdown structures – Forecasts / Earned Value Management – Contingency, reserves, allowances • Project Control sets up the relevant measurement and reporting processes & systems • Project Control is not just about compliance - it needs to be the strategic advisor for the PMT
  • 18. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 19 Large projects typical organization Project managerProject Control manager Package Manager 1 HSE, Q Package Manager 2 Package Manager 3 Engineering Manager Procurement manager Construction manager Commissioning Manager
  • 19. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 20 What is Project Controls? Project Control is about building information sensors, and making sense of the information.
  • 20. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 21 Project Breakdown detail level (Cost Model, Schedule) Breakdown detail Too little detail will not allow to grasp the project drivers Too much detail drowns the team and removes agility Effectiveness Optimal Cost / Schedule Detail Range
  • 21. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 22 Too much detail! = Not enough time for analysis!
  • 22. Section 4 © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m • Introduction: specifics of Large, Complex Projects • Project Team • Project Control • Cost • Schedule • Risk • Project Systems • Summary
  • 23. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 24 Project Cost Control Best Practices • Fully distinct from Accounting • Focus on commitments and Project-end forecast • Actual Cost (VOWD) is evaluated independently of invoicing • Breakdown structures are owned by Project Control and coordinated with Procurement and Construction contracting strategies • A full Project Cost Model is maintained (in source currency, time-phased, by work package) • Issues / events are reported immediately in the forecast • Sensitivities are provided in addition to the (prudent) forecast • Data integrity is maintained, all variances remain traceable
  • 24. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 25 Common “maturity’ observations when no strong Cost Management • Costs for internal resources as actual costs instead of standard rates – Extreme complication of cost tracking • Commitments are not tracked – only invoicing – Invoicing without commitments – Poor control on project bottom line because of invoicing delays • Poor consistency with project execution strategy and forecast schedule • No support to PM in scenario planning • No sensitivities available
  • 25. Section 5 © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m • Introduction: specifics of Large, Complex Projects • Project Team • Project Control • Cost • Schedule • Risk • Project Systems • Summary
  • 26. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 33 Project Schedule Best Practices • Limit the detail of the Project Integrated Schedule – use a proper scheduling hierarchy • Use the Convergence Planning / monitoring method + communicate focus to the team • Float and Buffers are owned by the PM • Avoid ‘virtual float’ generation by constraining delivery on fixed dates • Implement float monitoring / trending (evolution of float from one update to the next) • Avoid having different schedules for different stakeholders • Prefer to increase the schedule robustness and resilience instead of minimizing the critical path.
  • 27. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 35 Best Practice Schedule Vision Integrated Project Schedule 1,500 – 2,500 activities Convergence Plan ~ 100-200 deliverables MOREDETAILS MOREFOCUS Document List & detailed engineering schedule SCM Detailed Plan Construction Sub- contractor’s schedules Commi- ssioning Plan / schedule Installation Plan Simplified Project Schedule 200-400 Activities (Schedule Risk Analysis)
  • 28. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 37 Convergence processFor Complex Projects, the focus needs to be on convergence
  • 29. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 38 Convergence process Simple Project Complex Project
  • 30. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 39 Convergence process Project Performance Driver (or, what kills a project) Simple project Large project Efficiency Convergence Potential upside/ downside±10% +20% - 30, -50, -100%
  • 31. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 40 Most Projects fail because of a small piece missing…
  • 32. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 41 Convergence Plan Example
  • 33. Section 6 © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m • Introduction: specifics of Large, Complex Projects • Project Team • Project Control • Cost • Schedule • Risk • Project Systems • Summary
  • 34. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 43 Project Risk Best Practices • Opportunity and Risks, and ratings to be discussed as a team • Focused action-taking. Prioritize ruthlessly and focus effort • The earlier, the better for action-taking • Use all opportunities of contractual relationships to transfer risk • Do not confuse allowances, contingency, management reserves • Schedule risk analysis focus on improving schedule resilience • Monte Carlo methods are conventional and their limits must be understood (e.g. low probability risk, independence assumptions) • Most of the project risk is related to schedule slippage & lack of convergence, and consequential impacts • Prevention of major accidents is essential – industrial risk management • In case of major event, create a separate task-force to minimize consequential impact on project execution
  • 35. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 44 Advanced Risk Management approaches • Industrial Risk Management – Specific methods to prevent major catastrophic events (low probability, high consequences) • Portfolio risk management – Manage dependencies between projects (resources etc) and consequential effects • Minimize complexity • Ensure there is a way to escape the project if it goes bad – contractual T&C – Limit of liability, termination clause etc • Proper contingency calculation and Senior Management ownership
  • 36. Section 7 © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m • Introduction: specifics of Large, Complex Projects • Project Team • Project Control • Cost • Schedule • Risk • Project Systems • Summary
  • 37. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 48 Systems • Large project = lots of data to control – Manual systems are overwhelmed, high error rate • Need to: – manage inter-office remote work, remote sites – guarantee data correctness and accurate reporting • What minimum systems? – Document control & Correspondence control – Cost control (different from accounting) – Commitments & approvals • SCM • Logistics • Travel, HR • Timesheets – Scheduling & convergence planning
  • 38. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 49 Project Systems Best Practices • Minimize risks of mistakes by having systems that synchronize or are shared/ accessible between different sites & worksite (new trend = in addition, go mobile) and across the full process cycles (e.g. site commitments) • Single integrated systems (~ERP) often less effective in terms of control and efficiency than a suite of specialized systems with checks at the interface; and in addition longer and more expensive to set-up • All action-tracking systems to be coordinated to allow real prioritization across the board • Reporting to be as automated as possible to leave space for actual analysis work (new trend = real time dashboards) • Leverage systems to create performance indicators and reports • Ensure shared breakdown structures and consistent references across the entire contracting levels
  • 39. Conclusion © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m
  • 40. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 51 Moving into Larger, more Complex Projects • Management by “efficient” hierarchical departments • Purely rational approaches • Following an immutable baseline plan (a.k.a the Stalinist approach) …DON’T WORK!
  • 41. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 52 So, is your organization is ready for large projects? Key indicators: • Strength of project managers vs department heads • Project leadership capabilities and effective teams • Office lay-out – really integrated teams • Cost mindset vs investment mindset at management level • Strength of project governance process • Strength of IT systems for project data management
  • 42. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 53 • Be Focused on the right things – Convergence Monitoring • Be in Control while remaining Agile • Address Complexity • Create Space for Responding to the Unexpected LEAD!
  • 43. © Project Value Delivery, 2016 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 54 This presentation summarizes key best practices for Large Complex Projects. More information is available on our White Papers and other documents on www.ProjectValueDelivery.com …as well as in our handbooks!
  • 44. W e E m p o w e r O r g a n i z a t i o n s T o b e R e l i a b l y S u c c e s s f u l i n E x e c u t i n g L a r g e , C o m p l e x P r o j e c t s Discover more on w w w . P r o j e c t V a l u e D e l i v e r y . c o m Project Value Delivery Project Soft Power Unleashing Value from Your Large, Complex Projects Project Health Check Project Coaching Organizational maturity Team effectivenessIntercultural leadership Advanced project trainingProject Startup support Project Recovery Advanced risk management Project Control and Reporting Support systems integration Convergence planning Remote sites integration Leadership development