SlideShare a Scribd company logo
1
REPORT
ON
Ready to use Cut and Bend
Reinforcement Bars
2
1. INTRODUCTION: -
There has been a long felt need to bring up speed in the field of construction,
which remain a core contributor to the growth of economy, but still suffers from
low productivity, higher costs and wastages. Unsafe working conditions and
resultant pollution are other areas of concern. This calls for modernization of
construction. As Construction is one of the pillars of domestic economy, but
currently suffering sue to Low Profitability & Margins.
The need has been felt mainly due to the following reasons
• Environmental benefits
• Safety & Health
• Improved working conditions
• Cost reduction/ Waste elimination
• Enhanced customer satisfaction
• Improved profitability
Environmental benefits:
Construction sites are prone to producing pollution in the form of dust, noise and
chemicals used for construction. Longer the duration of construction, bigger will
be the impact on the environment and will cause irritation and health related
hazards in the neighborhood.
Safety & Health
As mentioned above, a typical construction site is a hazardous site with dust,
noise and pilfered scrap pieces lying around. Deep holes dug for foundation work
and other material used cause health and safety hazard for the people working at
the site. By speeding up the process and removing even a part of hazardous
material can improve site operating conditions drastically
Improved working conditions
If construction activity is accelerated, the working condition can be improved by
focusing on site management and overall labor productivity can be improved.
Apart from this many construction sites functioning in metro cities do not have
enough space to organize such activity at site and therefore for such projects cut
& bend rebars in ready to use condition is only solution.
Cost reduction/ Waste elimination
This obviously has an impact on the reduction of the cost of project. Longer the
project takes for completion, higher would be the cost. By focusing on the core
construction activity and eliminating wasteful activities the cost can be lowered
and wastage can be reduced considerably
3
Enhanced customer satisfaction
Since the project duration is reduced and the end customer can make use of the
buildings earlier, customer delight and satisfaction is increased and also increases
the probability of getting more business from same customers.
Improved profitability
With reduction in cost, shortening of schedules and overall improvement in
project execution, the obvious benefit is in the improvement in the profitability.
Clients are undiscriminating and still equate price with cost and select designers
and constructors almost exclusively based on lowest tendered price. Thus, in
order to get more business, it is imperative that construction agencies remain
competitive with low cost of project execution.
Projects are widely seen as unpredictable in terms of on time delivery, within
budget and to the standards of quality expected due to on site conditions
resulting in delays, cost over runs and at times compromised quality, and the
need of the hour is to turn around this situation by bringing focus on quality and
deliveries thereby controlling the over all cost
Drivers of change:
Focus on the customer - Activities which do not add value from the customer's
viewpoint are classified as waste and should be eliminated. Clients would become
much more demanding of construction in time to come.
Quality driven agenda - Quality means not only zero defects but right first time,
delivery on time and to budget, innovating for the benefit of the client and
stripping out waste, whether it be in design, materials or construction on site.
Integrating the process and the team around the product- the industry is
typically dealing with the project process as a series of sequential and largely
separate operations undertaken by individual designers, constructors and
suppliers who have no stake in the long-term success of the product and no
commitment to it. Changing this culture is fundamental to increasing efficiency
and quality in construction.
2. Cut & Bend TMT bars for ready use:-
Cut and Bend Process:
TMT bars provide required strength and shape to any RCC structure. However,
TMT bars are available in market in standard lengths of 12 meters and require
further cutting and bending as per the requirements of the project. This requires
considerable time, space & results in generation of scrap, which is estimated to
be around 3-5% apart from pilferage and damage/ obsolesce. Total cost of Rebar
usage is illustrated in the table1 below:
4
Table 1.
Head Value (Rs/ton)
Base price 41,000
Labor cost @9735/ mon, 60 man hours/
ton 2,921
Scrap @ 5% 2,050
Scrap salvage@ 21000/PMT (1,050)
Pilferage/ obsolesce @2% 820
Inventory carrying cost @ 24% PA for 15
days 820
Yard expenses @ 1% 410
Total Additional cost 5,971
Source: Survey done by McKinsey & Company in 2015-16 and applicable taxes
are extra over the values shown.
The challenge is that in majority of the cases, the cutting and bending of the
rebars is manually done by unskilled labors at construction sites. It usually takes
around 60-man hours for cutting, bending and binding one tone of rebars. This
also generates scrap 5-7%, which needs to be stored separately and disposed
periodically causing losses. This being a manual process, the inaccuracy and
inefficiency rates are high. Slow rate of construction pushes up the construction
cost, increases pilferage of material at site and makes site hazardous due to
littering of scrap and cut pieces around the place.
The cut and bend production process Proposed is a comprehensive and technical
one. It aims to provide customized shapes of rebars that are needed at various
construction sites without customer going through hassles as listed above.
The process uses quality TMT bars to produce cut and bend TMT bars. It cuts &
bends them to precise dimensions & required angles in line with the
requirements of the customer, and as deliveries can be times in line with
customer’s production schedules, customers cab work comfortably with Just in
Time concept reducing their capital blocked up in unproductive stock of Rebars at
site. This also removes requirement of steel yard saving in space (which is at
premium in metros), possibility f theft and expenses incurred in maintaining the
stocks.
The Cut and Bend process involves the following machines-
Shear Line, Automatic Double Side Bending, Cutting and Bending machine,
Electronic Sheer, Automatic Double Head Bender, Automatic Stirrups and large
size bender and Bi-directional Bending Machine
3. PROCESS: -
The process uses quality TMT bars to produce cut and bend TMT bars in the
desired shapes as per reinforcement drawings. It cuts & bends them to precise
dimensions & required angles in line with the requirements of the customer.
5
The Cut and Bend process involves various types of machines like-
Shear Line, Automatic Double Side Bending, Cutting and Bending machine,
Electronic Sheer, Automatic Double Head Bender, Automatic Stirrups and large
size bender and Bi-directional Bending Machine
4. Plant requirements: -
1. Cut & Bend Services require the following equipment’s
a. Shearing Equipment
b. Benders
c. Stirrup making machine
d. Couplers
e. Cage Making facility
f. Any other shape & size indicated by customer
It is learnt from the interaction that for the higher capacities, additional
equipment must be installed.
2. For a bending operation of 2500-3000 MT per month, area apparently required is
about 2-3 acres.
3. For doing volume of about 2500-3000 MT per month required inventory is about
1000-1500 MT with regular levels of ordering to replenish the stocks.
4. As understood from the offer received, for 2500-3000 MT per month operation,
the manpower requirement is about 70 (may be outsourced)
• Supervisor 1
• Draftsman for BBS 6
• Skilled Operators 16
• Crane operator 4
• Unskilled labor 43
Apart from above, one sales manager and adequate security staff is also required
5. The differential price for this service, as understood from industry, is about Rs
2500/ MT over the prevailing TMT price
6. The key success factor in this business is timely delivery. Customer gives the BBS
(Bar Bending Schedule) and Producer has to deliver the product in 5-6 days. The
site comes to a complete halt if the timelines are not met.
5. FINANCIAL ASPECTS: -
A. Land & Building-
The plant will need about 20,000 square feet of covered area for plant
machinery installation and another 20,000 square feet area for storing raw
6
material for 15 days inventory. Estimated cost of land will be around 1.00
crore
B. Machinery & Equipment’s: -
In order to produce around 2500 tons per month, following machines will be
needed:
SHEAR LINE: Hydraulic shear line for TMT Rod Cutting with electrical motor
and the following accessories
• 3 Storage type racks on each side
• Feeding conveyor
• Measuring conveyor with both sides’ kickoff
• Roller track (Transfer of Cut bars to bender), double side
• Storage pockets on both sides with chains
• Panel board
DOUBLE BENDER (ROBO MASTER) – 36 mm capacity: Automatic Robo master
with conveyor table
STIRRUP MAKING MACHINE, HIGH SPEED MODEL. ARUNO 12 (6mm to
12mm) – Fully Automatic Stirrup Bending Machine for Straightening, Bending
and Cutting of TMT
Rod with electrical Servo Motor and accessories as follows.
• Panel Board.
• De coiling stand with brake system
MANUAL BENDING MACHINE 42 D (36 mm capacity) with electrical motor
MANUAL BENDING MACHINE 55 D (40 mm capacity) with electrical motor
MANUAL CUTTING MACHINE WITH ELECTRICAL MOTOR ( 40MM capacity)
Estimated cost of all the above machinery will be Rs 2.5 Crs approximately
Shed of 20000 square feet: Estimated cost will be approximately 150 lakhs
2 no’s of EOT cranes of 5-ton capacity 20 meter span: approximately 60 lakhs
One number mobile Hydra crane approximately 15 lakhs (can be rented)
Thus, total capital requirement will be approximately as under
COST OF PROJECT AMOUNT
(Rs. Lakhs)
LAND 100.00
LAND LEVELING & BUILDING SHED 192.50
EQUIPMENTS 315.00
OFFICE BUILDING & OTHERS 10.00
ELECTRIC CONNECTION 10.50
OTHER FIXED ASSETS 2.00
TOTAL COST OF PROJECT 630.00
7
Working Capital Requirement (P.M.)
Assuming average cost of Raw material at Rs 47000/ PMT including GST, and
average inventory of 10 days (Approx. 750 tons) Valued at 3.5 Crs and as the
product is sold on 30-60 days credit. Approx. Value will be 11.5 Crs.
Considering these two aspects, Requirement of capital to keep the plant
functioning will be 15 Crs approx.
Other Contingent Expenses like telephone. Conveyance & travelling,
Stationary, Power and water charges, Stationary postage and other misc.
expenses etc. to be considered as lumpsum approx. Rs 15 lakhs/mon
Since interest on the working capital will be making heavy dent on the
profitability, suitable means of credit control and facilities like bill discounting
are recommended to reduce this burden.
Treatment of wastage and effluents
Since the operation is only cutting and shaping of bars already rolled, no liquid
discharge is envisaged. The process may generate some quantity of steel
scrap, which will be sold to the local scrap market periodically after salvaging
usable bars. Some negligible amount of mill scale and dust may get generated
(around 0.05%), which can be collected, bagged and disposed of to
prospective users. Used Oil and grease will be collected and disposed of to
prospective users who recycle them.
8
Cost impact to the project
Considering a house construction project of Site Size: 30x50 feet site house construction
cost (Ground + 1, 3 BHK) up to 2125 Sq. ft built up area With Concrete Blocks, Total
House cost (Rs. 74.37 lakhs) and material cost is as per table below:
Total cost of house ownership 7,437,500
Materials Required Quantity Unit
Premium
Brand (Rs.)
Matl.
Cost
share
Overall
Cost
share
TMT Steel 7.6 Tonnes 357,200 29% 5%
Cement 930 Bags 337,590 27% 5%
Plastering M Sand 147 Tonnes 205,800 17% 3%
Concrete M Sand 65 Tonnes 61,750 5% 1%
40mm Jelly 513 Cft 12,825 1% 0%
20mm Jelly 2996 Cft 74,900 6% 1%
6" Concrete Block 3120 Blocks 156,000 13% 2%
4" Concrete Block 1040 Blocks 37,440 3% 1%
Total material cost 1,243,505
Traditional bending @
6000/ton
7.98 Tonnes 47,880 0.5% 0.6%
C&B @ 2500/ton 7.6 Tonnes 19,000 0.2% 0.3%
Saving due to C&B Tonnes 28,880 0.3% 0.4%
Source: https://www.materialtree.com/30-50-house-construction-cost/
From above calculations it may be seen while customer pays Rs. 19,000 extra for C&B
charges, actual saving by the customer is Rs. 28,880 and applicable taxes. Thus
customer doesn’t incur any additional expenses in using Cut & Bent Rabars. Added to
this saving are intangible benefits like quality, reduced pollution levels, wastage and
saving on account of shortened project execution time resulting in overall
improvement in project execution
9
Project time line
Week 0 1 2 3 4 5 6 7 8 9 10 11 12
Sigining of
Consultancy
agreement
Preparation
of Project
feasibility
report
Application
for land
Sanctioning
of land &
initial
payment
Bhoomi Pooja &
Civil work
commencement
Shed
erection
Application
for financial
closure
Finalization
of civil
contractor
Application for
electric
connection
Electric
connection
Negotiation
with
equipment
supplier &
Ordering
Work order
for Job work
finalization
Shortlisting
for sales team
Recruitment Training
Order
booking
Servicing
of orders
Contacting prospective customers and presentations
A
c
t
i
v
i
t
y
Sales team candidate
search
Production of machinary at vendor's place and dispatch
Electric wiring
Civil work in progress
Receipt of
equipments
Equipment erection &
Commissioning
Expected duration of the project will be 12 weeks from beginning to
commissioning
Details of financial working
Table 1
Capital requirement and working capital needed
Break Even
1289
Capital cost Rs. Lakhs Rs. Lakhs Rs. Lakhs
Land 100.00 100.00 100.00
Shed+ Land development 150.00 150.00 150.00
Equipments 315.00 315.00 315.00
Electrical connection & Others 13.65 13.65 13.65
Office building & others 10.00 10.00 10.00
Boundary wall 1300 Feet, 8"X9'high @ 1700/ft 22.10 22.10 22.10
Hardfacing of land 5500m
3
, @350/cu Mtr 19.25 19.25 19.25
Total Capital 630.00 6.3 630.00 630.00
Int. on Capital @ 12% 75.60
Working capital Rs. Lakhs Int Rs. Lakhs Int Rs. Lakhs Int
30 days credit on orders serviced 646.43 6.5 752.25 7.5 1253.75 12.5
Stock @10 days, Rs. 40000/ton+ 18% GST 202.80 2.0 236.00 2.4 393.33 3.9
Total Working capital 849.24 8.5 988.25 9.9 1,647.08 16.5
Cut & Bend Project
Production/ Mon
25001500.00
10
Table 2
Projected Working results of Steel center
Break even
1289
Head
Amount
(Rs. Lakhs/
month)
Amount
(Rs. Lakhs/
month)
Amount
(Rs. Lakhs/
month)
Income
From Sale of FG @ 2500/PMT 32.22 37.50 62.50
From sale of Scrap @ 25000/PMT, 1% Scrap 3.22 3.75 6.25
Total Income 35.45 41.25 68.75 a
Expenses
Operating expenses
Labor contract 20.62 24.00 40.00
Losses due to scrap generation @1% 4.90 5.70 9.50
Total Operating expenses 25.52 29.70 49.50 b
Fixed cost
Interest @12% on capital 6.30 6.30 6.30 c
Depreciation @ 10% on Machinary 2.63 2.63 2.63 d
Staff salaries (including security) 1.00 1.00 1.00 e
Total Fixed cost 9.93 9.93 9.93 f
EBIDTA 8.93 10.55 18.25 (a-b-e)
PBT - 1.63 9.33 (a-b-f)
Cut & Bend Project
Production/ Mon
25001500.00

More Related Content

What's hot

Labour Productivity for construction projects
Labour Productivity for construction projectsLabour Productivity for construction projects
Labour Productivity for construction projects
Kapugantikapuganti Gupta
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & Equipments
GAURAV. H .TANDON
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tenders
gayu pandian
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
NAVNEET KUMAR JHA
 
Site engineer duties
Site engineer dutiesSite engineer duties
Site engineer duties
getmar2
 
Specifications, reports and tenders - Estimation, Costing and Valuation Engin...
Specifications, reports and tenders - Estimation, Costing and Valuation Engin...Specifications, reports and tenders - Estimation, Costing and Valuation Engin...
Specifications, reports and tenders - Estimation, Costing and Valuation Engin...
Shanmugasundaram N
 
Tendering presenation
Tendering presenationTendering presenation
Tendering presenation
JIT KUMAR GUPTA
 
Building project presentation
Building project presentationBuilding project presentation
Building project presentation
emdad bhuiyan
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
Manit Agarwal
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
johnkirth1898
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
Anil Kumar(6)
 
Specifications 101
Specifications 101Specifications 101
Specifications 101
Andrej_M
 
Types and forms of contracts
Types and forms of contracts Types and forms of contracts
Types and forms of contracts
fritzlejarso
 
Catalogue moulds for precast concrete Moldtech
Catalogue moulds for precast concrete MoldtechCatalogue moulds for precast concrete Moldtech
Catalogue moulds for precast concrete Moldtech
Moldtech SL
 
Constructability In Construction
Constructability In ConstructionConstructability In Construction
Constructability In Construction
Sunil Manjeri
 
Metal Casting processes including pattern making and mold making,Patterns,Cas...
Metal Casting processes including pattern making and mold making,Patterns,Cas...Metal Casting processes including pattern making and mold making,Patterns,Cas...
Metal Casting processes including pattern making and mold making,Patterns,Cas...
Azlan
 
Industrial flooring by tremix vacuum system
Industrial flooring by tremix vacuum systemIndustrial flooring by tremix vacuum system
Industrial flooring by tremix vacuum system
Hebin Chiriyankandath
 
Shear strengthening of structural members
Shear strengthening of structural membersShear strengthening of structural members
Shear strengthening of structural members
Ashutosh Maurya
 
Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity
SSudhaVelan
 

What's hot (20)

Labour Productivity for construction projects
Labour Productivity for construction projectsLabour Productivity for construction projects
Labour Productivity for construction projects
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & Equipments
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tenders
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
 
Welding process
Welding processWelding process
Welding process
 
Site engineer duties
Site engineer dutiesSite engineer duties
Site engineer duties
 
Specifications, reports and tenders - Estimation, Costing and Valuation Engin...
Specifications, reports and tenders - Estimation, Costing and Valuation Engin...Specifications, reports and tenders - Estimation, Costing and Valuation Engin...
Specifications, reports and tenders - Estimation, Costing and Valuation Engin...
 
Tendering presenation
Tendering presenationTendering presenation
Tendering presenation
 
Building project presentation
Building project presentationBuilding project presentation
Building project presentation
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
 
Specifications 101
Specifications 101Specifications 101
Specifications 101
 
Types and forms of contracts
Types and forms of contracts Types and forms of contracts
Types and forms of contracts
 
Catalogue moulds for precast concrete Moldtech
Catalogue moulds for precast concrete MoldtechCatalogue moulds for precast concrete Moldtech
Catalogue moulds for precast concrete Moldtech
 
Constructability In Construction
Constructability In ConstructionConstructability In Construction
Constructability In Construction
 
Metal Casting processes including pattern making and mold making,Patterns,Cas...
Metal Casting processes including pattern making and mold making,Patterns,Cas...Metal Casting processes including pattern making and mold making,Patterns,Cas...
Metal Casting processes including pattern making and mold making,Patterns,Cas...
 
Industrial flooring by tremix vacuum system
Industrial flooring by tremix vacuum systemIndustrial flooring by tremix vacuum system
Industrial flooring by tremix vacuum system
 
Shear strengthening of structural members
Shear strengthening of structural membersShear strengthening of structural members
Shear strengthening of structural members
 
Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity
 

Similar to Project study report c&b

EPC world magazine oct 2014
EPC world magazine oct 2014EPC world magazine oct 2014
EPC world magazine oct 2014Param Saxena
 
Construction mirror oct2014
Construction mirror oct2014Construction mirror oct2014
Construction mirror oct2014Param Saxena
 
Cut & bend rebars
Cut & bend rebarsCut & bend rebars
Cut & bend rebars
Param Saxena
 
2014 04 (a4) naogp editorial - q&a maats bending machines
2014   04 (a4) naogp editorial - q&a maats bending machines2014   04 (a4) naogp editorial - q&a maats bending machines
2014 04 (a4) naogp editorial - q&a maats bending machines
Maats
 
HARD TURNING....Draft Copy
HARD TURNING....Draft CopyHARD TURNING....Draft Copy
HARD TURNING....Draft Copyvins049
 
Vice Cum Bender Machine
Vice Cum Bender MachineVice Cum Bender Machine
Vice Cum Bender Machine
IRJET Journal
 
Cape east Internship report
Cape east Internship reportCape east Internship report
Cape east Internship report
Tushar Chopra
 
Fine machining lean approach
Fine machining  lean approachFine machining  lean approach
Fine machining lean approachPankaj Chavan
 
IRJET- Experimental Analysis and Geometrical Effect on Mild Steel with Un...
IRJET-  	  Experimental Analysis and Geometrical Effect on Mild Steel with Un...IRJET-  	  Experimental Analysis and Geometrical Effect on Mild Steel with Un...
IRJET- Experimental Analysis and Geometrical Effect on Mild Steel with Un...
IRJET Journal
 
Hard Turning
Hard TurningHard Turning
Hard Turning
vins049
 
Gillam cascade
Gillam cascadeGillam cascade
Gillam cascade
Dave Davidson
 
Industrial training presentation (mechanical engineering)
Industrial training presentation (mechanical engineering)Industrial training presentation (mechanical engineering)
Industrial training presentation (mechanical engineering)
Rahul Banerjee
 
Jk files (india) limited
Jk files (india) limitedJk files (india) limited
Jk files (india) limited
engineeringwatch
 
IRJET- An Investigation of Maintenance Management of Construction Equipment f...
IRJET- An Investigation of Maintenance Management of Construction Equipment f...IRJET- An Investigation of Maintenance Management of Construction Equipment f...
IRJET- An Investigation of Maintenance Management of Construction Equipment f...
IRJET Journal
 
Project report
Project reportProject report
Project reportDolly Roy
 
Abrasive belt grinder capstone report
Abrasive belt grinder   capstone reportAbrasive belt grinder   capstone report
Abrasive belt grinder capstone report
DevenMahajan2
 
Graded unit Civil engineering Presentation
Graded unit Civil engineering PresentationGraded unit Civil engineering Presentation
Graded unit Civil engineering Presentation
Tehmas Saeed
 

Similar to Project study report c&b (20)

EPC world magazine oct 2014
EPC world magazine oct 2014EPC world magazine oct 2014
EPC world magazine oct 2014
 
Construction mirror oct2014
Construction mirror oct2014Construction mirror oct2014
Construction mirror oct2014
 
Cut & bend rebars
Cut & bend rebarsCut & bend rebars
Cut & bend rebars
 
2014 04 (a4) naogp editorial - q&a maats bending machines
2014   04 (a4) naogp editorial - q&a maats bending machines2014   04 (a4) naogp editorial - q&a maats bending machines
2014 04 (a4) naogp editorial - q&a maats bending machines
 
HARD TURNING....Draft Copy
HARD TURNING....Draft CopyHARD TURNING....Draft Copy
HARD TURNING....Draft Copy
 
Vice Cum Bender Machine
Vice Cum Bender MachineVice Cum Bender Machine
Vice Cum Bender Machine
 
Cape east Internship report
Cape east Internship reportCape east Internship report
Cape east Internship report
 
Fine machining lean approach
Fine machining  lean approachFine machining  lean approach
Fine machining lean approach
 
IRJET- Experimental Analysis and Geometrical Effect on Mild Steel with Un...
IRJET-  	  Experimental Analysis and Geometrical Effect on Mild Steel with Un...IRJET-  	  Experimental Analysis and Geometrical Effect on Mild Steel with Un...
IRJET- Experimental Analysis and Geometrical Effect on Mild Steel with Un...
 
Hard Turning
Hard TurningHard Turning
Hard Turning
 
Gillam cascade
Gillam cascadeGillam cascade
Gillam cascade
 
K10672
K10672K10672
K10672
 
Report File
Report FileReport File
Report File
 
Industrial training presentation (mechanical engineering)
Industrial training presentation (mechanical engineering)Industrial training presentation (mechanical engineering)
Industrial training presentation (mechanical engineering)
 
Jk files (india) limited
Jk files (india) limitedJk files (india) limited
Jk files (india) limited
 
IRJET- An Investigation of Maintenance Management of Construction Equipment f...
IRJET- An Investigation of Maintenance Management of Construction Equipment f...IRJET- An Investigation of Maintenance Management of Construction Equipment f...
IRJET- An Investigation of Maintenance Management of Construction Equipment f...
 
updated_resume
updated_resumeupdated_resume
updated_resume
 
Project report
Project reportProject report
Project report
 
Abrasive belt grinder capstone report
Abrasive belt grinder   capstone reportAbrasive belt grinder   capstone report
Abrasive belt grinder capstone report
 
Graded unit Civil engineering Presentation
Graded unit Civil engineering PresentationGraded unit Civil engineering Presentation
Graded unit Civil engineering Presentation
 

Recently uploaded

Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 

Recently uploaded (20)

Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 

Project study report c&b

  • 1. 1 REPORT ON Ready to use Cut and Bend Reinforcement Bars
  • 2. 2 1. INTRODUCTION: - There has been a long felt need to bring up speed in the field of construction, which remain a core contributor to the growth of economy, but still suffers from low productivity, higher costs and wastages. Unsafe working conditions and resultant pollution are other areas of concern. This calls for modernization of construction. As Construction is one of the pillars of domestic economy, but currently suffering sue to Low Profitability & Margins. The need has been felt mainly due to the following reasons • Environmental benefits • Safety & Health • Improved working conditions • Cost reduction/ Waste elimination • Enhanced customer satisfaction • Improved profitability Environmental benefits: Construction sites are prone to producing pollution in the form of dust, noise and chemicals used for construction. Longer the duration of construction, bigger will be the impact on the environment and will cause irritation and health related hazards in the neighborhood. Safety & Health As mentioned above, a typical construction site is a hazardous site with dust, noise and pilfered scrap pieces lying around. Deep holes dug for foundation work and other material used cause health and safety hazard for the people working at the site. By speeding up the process and removing even a part of hazardous material can improve site operating conditions drastically Improved working conditions If construction activity is accelerated, the working condition can be improved by focusing on site management and overall labor productivity can be improved. Apart from this many construction sites functioning in metro cities do not have enough space to organize such activity at site and therefore for such projects cut & bend rebars in ready to use condition is only solution. Cost reduction/ Waste elimination This obviously has an impact on the reduction of the cost of project. Longer the project takes for completion, higher would be the cost. By focusing on the core construction activity and eliminating wasteful activities the cost can be lowered and wastage can be reduced considerably
  • 3. 3 Enhanced customer satisfaction Since the project duration is reduced and the end customer can make use of the buildings earlier, customer delight and satisfaction is increased and also increases the probability of getting more business from same customers. Improved profitability With reduction in cost, shortening of schedules and overall improvement in project execution, the obvious benefit is in the improvement in the profitability. Clients are undiscriminating and still equate price with cost and select designers and constructors almost exclusively based on lowest tendered price. Thus, in order to get more business, it is imperative that construction agencies remain competitive with low cost of project execution. Projects are widely seen as unpredictable in terms of on time delivery, within budget and to the standards of quality expected due to on site conditions resulting in delays, cost over runs and at times compromised quality, and the need of the hour is to turn around this situation by bringing focus on quality and deliveries thereby controlling the over all cost Drivers of change: Focus on the customer - Activities which do not add value from the customer's viewpoint are classified as waste and should be eliminated. Clients would become much more demanding of construction in time to come. Quality driven agenda - Quality means not only zero defects but right first time, delivery on time and to budget, innovating for the benefit of the client and stripping out waste, whether it be in design, materials or construction on site. Integrating the process and the team around the product- the industry is typically dealing with the project process as a series of sequential and largely separate operations undertaken by individual designers, constructors and suppliers who have no stake in the long-term success of the product and no commitment to it. Changing this culture is fundamental to increasing efficiency and quality in construction. 2. Cut & Bend TMT bars for ready use:- Cut and Bend Process: TMT bars provide required strength and shape to any RCC structure. However, TMT bars are available in market in standard lengths of 12 meters and require further cutting and bending as per the requirements of the project. This requires considerable time, space & results in generation of scrap, which is estimated to be around 3-5% apart from pilferage and damage/ obsolesce. Total cost of Rebar usage is illustrated in the table1 below:
  • 4. 4 Table 1. Head Value (Rs/ton) Base price 41,000 Labor cost @9735/ mon, 60 man hours/ ton 2,921 Scrap @ 5% 2,050 Scrap salvage@ 21000/PMT (1,050) Pilferage/ obsolesce @2% 820 Inventory carrying cost @ 24% PA for 15 days 820 Yard expenses @ 1% 410 Total Additional cost 5,971 Source: Survey done by McKinsey & Company in 2015-16 and applicable taxes are extra over the values shown. The challenge is that in majority of the cases, the cutting and bending of the rebars is manually done by unskilled labors at construction sites. It usually takes around 60-man hours for cutting, bending and binding one tone of rebars. This also generates scrap 5-7%, which needs to be stored separately and disposed periodically causing losses. This being a manual process, the inaccuracy and inefficiency rates are high. Slow rate of construction pushes up the construction cost, increases pilferage of material at site and makes site hazardous due to littering of scrap and cut pieces around the place. The cut and bend production process Proposed is a comprehensive and technical one. It aims to provide customized shapes of rebars that are needed at various construction sites without customer going through hassles as listed above. The process uses quality TMT bars to produce cut and bend TMT bars. It cuts & bends them to precise dimensions & required angles in line with the requirements of the customer, and as deliveries can be times in line with customer’s production schedules, customers cab work comfortably with Just in Time concept reducing their capital blocked up in unproductive stock of Rebars at site. This also removes requirement of steel yard saving in space (which is at premium in metros), possibility f theft and expenses incurred in maintaining the stocks. The Cut and Bend process involves the following machines- Shear Line, Automatic Double Side Bending, Cutting and Bending machine, Electronic Sheer, Automatic Double Head Bender, Automatic Stirrups and large size bender and Bi-directional Bending Machine 3. PROCESS: - The process uses quality TMT bars to produce cut and bend TMT bars in the desired shapes as per reinforcement drawings. It cuts & bends them to precise dimensions & required angles in line with the requirements of the customer.
  • 5. 5 The Cut and Bend process involves various types of machines like- Shear Line, Automatic Double Side Bending, Cutting and Bending machine, Electronic Sheer, Automatic Double Head Bender, Automatic Stirrups and large size bender and Bi-directional Bending Machine 4. Plant requirements: - 1. Cut & Bend Services require the following equipment’s a. Shearing Equipment b. Benders c. Stirrup making machine d. Couplers e. Cage Making facility f. Any other shape & size indicated by customer It is learnt from the interaction that for the higher capacities, additional equipment must be installed. 2. For a bending operation of 2500-3000 MT per month, area apparently required is about 2-3 acres. 3. For doing volume of about 2500-3000 MT per month required inventory is about 1000-1500 MT with regular levels of ordering to replenish the stocks. 4. As understood from the offer received, for 2500-3000 MT per month operation, the manpower requirement is about 70 (may be outsourced) • Supervisor 1 • Draftsman for BBS 6 • Skilled Operators 16 • Crane operator 4 • Unskilled labor 43 Apart from above, one sales manager and adequate security staff is also required 5. The differential price for this service, as understood from industry, is about Rs 2500/ MT over the prevailing TMT price 6. The key success factor in this business is timely delivery. Customer gives the BBS (Bar Bending Schedule) and Producer has to deliver the product in 5-6 days. The site comes to a complete halt if the timelines are not met. 5. FINANCIAL ASPECTS: - A. Land & Building- The plant will need about 20,000 square feet of covered area for plant machinery installation and another 20,000 square feet area for storing raw
  • 6. 6 material for 15 days inventory. Estimated cost of land will be around 1.00 crore B. Machinery & Equipment’s: - In order to produce around 2500 tons per month, following machines will be needed: SHEAR LINE: Hydraulic shear line for TMT Rod Cutting with electrical motor and the following accessories • 3 Storage type racks on each side • Feeding conveyor • Measuring conveyor with both sides’ kickoff • Roller track (Transfer of Cut bars to bender), double side • Storage pockets on both sides with chains • Panel board DOUBLE BENDER (ROBO MASTER) – 36 mm capacity: Automatic Robo master with conveyor table STIRRUP MAKING MACHINE, HIGH SPEED MODEL. ARUNO 12 (6mm to 12mm) – Fully Automatic Stirrup Bending Machine for Straightening, Bending and Cutting of TMT Rod with electrical Servo Motor and accessories as follows. • Panel Board. • De coiling stand with brake system MANUAL BENDING MACHINE 42 D (36 mm capacity) with electrical motor MANUAL BENDING MACHINE 55 D (40 mm capacity) with electrical motor MANUAL CUTTING MACHINE WITH ELECTRICAL MOTOR ( 40MM capacity) Estimated cost of all the above machinery will be Rs 2.5 Crs approximately Shed of 20000 square feet: Estimated cost will be approximately 150 lakhs 2 no’s of EOT cranes of 5-ton capacity 20 meter span: approximately 60 lakhs One number mobile Hydra crane approximately 15 lakhs (can be rented) Thus, total capital requirement will be approximately as under COST OF PROJECT AMOUNT (Rs. Lakhs) LAND 100.00 LAND LEVELING & BUILDING SHED 192.50 EQUIPMENTS 315.00 OFFICE BUILDING & OTHERS 10.00 ELECTRIC CONNECTION 10.50 OTHER FIXED ASSETS 2.00 TOTAL COST OF PROJECT 630.00
  • 7. 7 Working Capital Requirement (P.M.) Assuming average cost of Raw material at Rs 47000/ PMT including GST, and average inventory of 10 days (Approx. 750 tons) Valued at 3.5 Crs and as the product is sold on 30-60 days credit. Approx. Value will be 11.5 Crs. Considering these two aspects, Requirement of capital to keep the plant functioning will be 15 Crs approx. Other Contingent Expenses like telephone. Conveyance & travelling, Stationary, Power and water charges, Stationary postage and other misc. expenses etc. to be considered as lumpsum approx. Rs 15 lakhs/mon Since interest on the working capital will be making heavy dent on the profitability, suitable means of credit control and facilities like bill discounting are recommended to reduce this burden. Treatment of wastage and effluents Since the operation is only cutting and shaping of bars already rolled, no liquid discharge is envisaged. The process may generate some quantity of steel scrap, which will be sold to the local scrap market periodically after salvaging usable bars. Some negligible amount of mill scale and dust may get generated (around 0.05%), which can be collected, bagged and disposed of to prospective users. Used Oil and grease will be collected and disposed of to prospective users who recycle them.
  • 8. 8 Cost impact to the project Considering a house construction project of Site Size: 30x50 feet site house construction cost (Ground + 1, 3 BHK) up to 2125 Sq. ft built up area With Concrete Blocks, Total House cost (Rs. 74.37 lakhs) and material cost is as per table below: Total cost of house ownership 7,437,500 Materials Required Quantity Unit Premium Brand (Rs.) Matl. Cost share Overall Cost share TMT Steel 7.6 Tonnes 357,200 29% 5% Cement 930 Bags 337,590 27% 5% Plastering M Sand 147 Tonnes 205,800 17% 3% Concrete M Sand 65 Tonnes 61,750 5% 1% 40mm Jelly 513 Cft 12,825 1% 0% 20mm Jelly 2996 Cft 74,900 6% 1% 6" Concrete Block 3120 Blocks 156,000 13% 2% 4" Concrete Block 1040 Blocks 37,440 3% 1% Total material cost 1,243,505 Traditional bending @ 6000/ton 7.98 Tonnes 47,880 0.5% 0.6% C&B @ 2500/ton 7.6 Tonnes 19,000 0.2% 0.3% Saving due to C&B Tonnes 28,880 0.3% 0.4% Source: https://www.materialtree.com/30-50-house-construction-cost/ From above calculations it may be seen while customer pays Rs. 19,000 extra for C&B charges, actual saving by the customer is Rs. 28,880 and applicable taxes. Thus customer doesn’t incur any additional expenses in using Cut & Bent Rabars. Added to this saving are intangible benefits like quality, reduced pollution levels, wastage and saving on account of shortened project execution time resulting in overall improvement in project execution
  • 9. 9 Project time line Week 0 1 2 3 4 5 6 7 8 9 10 11 12 Sigining of Consultancy agreement Preparation of Project feasibility report Application for land Sanctioning of land & initial payment Bhoomi Pooja & Civil work commencement Shed erection Application for financial closure Finalization of civil contractor Application for electric connection Electric connection Negotiation with equipment supplier & Ordering Work order for Job work finalization Shortlisting for sales team Recruitment Training Order booking Servicing of orders Contacting prospective customers and presentations A c t i v i t y Sales team candidate search Production of machinary at vendor's place and dispatch Electric wiring Civil work in progress Receipt of equipments Equipment erection & Commissioning Expected duration of the project will be 12 weeks from beginning to commissioning Details of financial working Table 1 Capital requirement and working capital needed Break Even 1289 Capital cost Rs. Lakhs Rs. Lakhs Rs. Lakhs Land 100.00 100.00 100.00 Shed+ Land development 150.00 150.00 150.00 Equipments 315.00 315.00 315.00 Electrical connection & Others 13.65 13.65 13.65 Office building & others 10.00 10.00 10.00 Boundary wall 1300 Feet, 8"X9'high @ 1700/ft 22.10 22.10 22.10 Hardfacing of land 5500m 3 , @350/cu Mtr 19.25 19.25 19.25 Total Capital 630.00 6.3 630.00 630.00 Int. on Capital @ 12% 75.60 Working capital Rs. Lakhs Int Rs. Lakhs Int Rs. Lakhs Int 30 days credit on orders serviced 646.43 6.5 752.25 7.5 1253.75 12.5 Stock @10 days, Rs. 40000/ton+ 18% GST 202.80 2.0 236.00 2.4 393.33 3.9 Total Working capital 849.24 8.5 988.25 9.9 1,647.08 16.5 Cut & Bend Project Production/ Mon 25001500.00
  • 10. 10 Table 2 Projected Working results of Steel center Break even 1289 Head Amount (Rs. Lakhs/ month) Amount (Rs. Lakhs/ month) Amount (Rs. Lakhs/ month) Income From Sale of FG @ 2500/PMT 32.22 37.50 62.50 From sale of Scrap @ 25000/PMT, 1% Scrap 3.22 3.75 6.25 Total Income 35.45 41.25 68.75 a Expenses Operating expenses Labor contract 20.62 24.00 40.00 Losses due to scrap generation @1% 4.90 5.70 9.50 Total Operating expenses 25.52 29.70 49.50 b Fixed cost Interest @12% on capital 6.30 6.30 6.30 c Depreciation @ 10% on Machinary 2.63 2.63 2.63 d Staff salaries (including security) 1.00 1.00 1.00 e Total Fixed cost 9.93 9.93 9.93 f EBIDTA 8.93 10.55 18.25 (a-b-e) PBT - 1.63 9.33 (a-b-f) Cut & Bend Project Production/ Mon 25001500.00