SlideShare a Scribd company logo
COMMISSIONING STAGE COMPLIANCE CERTIFICATE – CSCC
System Reference / Description:
Discipline Code:
Location:
Certificate of Installation Completion
Verification that Installation Activities are Completed sufficiently for Pre-Functional and Operational Check
Out Procedures to commence.
Certificate of Readiness
Verification that Pre-Functional and Operational Check Out Activities are Completed and prior to the
Functional Testing being commenced.
Certificate of Commissioning Completion
Verification that Functional Testing Activities are Completed and prior to the Integrated Commissioning
being commenced.
Item
Completed
Comment
Signed by
Date
1
QAN’s Reviewed.
Refer to Checklist
2
CTI’s Reviewed.
Refer to Checklist
3
NCR’s
Refer to Checklist
4
Commissioning Issues Log Items reviewed.
5
Construction/Installation Completed.
6
Sub-Contractors works Complete.
7
Pre-Functional Check Out Signed.
8
Operational Check Out Signed.
9
Functional Check Out Signed.
Note: All outstanding issues that can be carried forward and do not prevent commissioning from continuing must be added to the
commissioning issues log.
Signed by:
Signature:
On Behalf of:
Sub-Contractor
Date:
Signed by:
Signature:
On Behalf of:
SOJV Construction
Date:
Signed by:
Signature:
On Behalf of:
SOJV Cx
Date:
Signed by:
Signature:
On Behalf of:
OBI
Date:
Upon sign off of this document, the following procedures / test activities may be conducted.
TABTP/CTP/TPPRef.
A
B
E
F
J
M
P
J
X
COMMISSIONING STAGE COMPLIENCE CERTIFICATE CHECKLIST
SYSTEM/EQUIPMENT REF:
Date:
AREA LOCATION:
WORKS DESCRIPTION:
ITEM
DOCUMENT/DRAWING No
CODE
1. Method Statements
2. Test Procedures
3. Shop Drawings
4. QAN’s
5. NCR’s
6.CTI’s

More Related Content

What's hot

Seismic Supervisor- Position available
Seismic Supervisor- Position availableSeismic Supervisor- Position available
Seismic Supervisor- Position available
Erika Vanessa Rodriguez, M.A
 
Calibration Services
Calibration ServicesCalibration Services
Calibration Services
sigmatest21
 
Warehouse process time reduction project
Warehouse process time  reduction projectWarehouse process time  reduction project
Warehouse process time reduction project
CarlosMoura111
 
OFCCP Compliance Review Steps and Strategies
OFCCP Compliance Review Steps and StrategiesOFCCP Compliance Review Steps and Strategies
OFCCP Compliance Review Steps and StrategiesCarla Irwin
 
PCAPP Update 28 May 2014
PCAPP Update 28 May 2014PCAPP Update 28 May 2014
Code
CodeCode
Sa 230
Sa 230Sa 230
Sa 230
Niket Talwar
 
Alo site coordinator
Alo site coordinatorAlo site coordinator
Alo site coordinatorgergelz
 
Ntp calculo d extintores
Ntp  calculo d extintoresNtp  calculo d extintores
Ntp calculo d extintores
Jesus Silva Silva
 
Sunny Mui_X474.3_Contract Closure
Sunny Mui_X474.3_Contract ClosureSunny Mui_X474.3_Contract Closure
Sunny Mui_X474.3_Contract Closuresunnycmui
 
QMS Calibration Powerpoint
QMS Calibration PowerpointQMS Calibration Powerpoint
QMS Calibration PowerpointDennis J Morgan
 
Standard Assessment Procedure - ATSPACE LTD
Standard Assessment Procedure - ATSPACE LTDStandard Assessment Procedure - ATSPACE LTD
Standard Assessment Procedure - ATSPACE LTD
atspaceltd
 
JOB DISCRIPTION OF WORK
JOB DISCRIPTION OF WORKJOB DISCRIPTION OF WORK
JOB DISCRIPTION OF WORKFeby Gunadi
 
Innovation in Evidential Breath Testing - EASYCAL from Lifeloc Technologies
Innovation in Evidential Breath Testing - EASYCAL from Lifeloc TechnologiesInnovation in Evidential Breath Testing - EASYCAL from Lifeloc Technologies
Innovation in Evidential Breath Testing - EASYCAL from Lifeloc Technologies
Lifeloc Technologies
 
Equity solutions - Our panel
Equity solutions - Our panelEquity solutions - Our panel
Equity solutions - Our panel
Bill Cannova
 

What's hot (20)

ci newsletter
ci newsletterci newsletter
ci newsletter
 
Seismic Supervisor- Position available
Seismic Supervisor- Position availableSeismic Supervisor- Position available
Seismic Supervisor- Position available
 
Calibration
CalibrationCalibration
Calibration
 
Calibration Services
Calibration ServicesCalibration Services
Calibration Services
 
Warehouse process time reduction project
Warehouse process time  reduction projectWarehouse process time  reduction project
Warehouse process time reduction project
 
OFCCP Compliance Review Steps and Strategies
OFCCP Compliance Review Steps and StrategiesOFCCP Compliance Review Steps and Strategies
OFCCP Compliance Review Steps and Strategies
 
PCAPP Update 28 May 2014
PCAPP Update 28 May 2014PCAPP Update 28 May 2014
PCAPP Update 28 May 2014
 
Code
CodeCode
Code
 
Sa 230
Sa 230Sa 230
Sa 230
 
Alo site coordinator
Alo site coordinatorAlo site coordinator
Alo site coordinator
 
Ntp calculo d extintores
Ntp  calculo d extintoresNtp  calculo d extintores
Ntp calculo d extintores
 
Justin Ray Hernandez
Justin Ray HernandezJustin Ray Hernandez
Justin Ray Hernandez
 
Syllabus
SyllabusSyllabus
Syllabus
 
Sunny Mui_X474.3_Contract Closure
Sunny Mui_X474.3_Contract ClosureSunny Mui_X474.3_Contract Closure
Sunny Mui_X474.3_Contract Closure
 
QMS Calibration Powerpoint
QMS Calibration PowerpointQMS Calibration Powerpoint
QMS Calibration Powerpoint
 
CPA Certificates
CPA  CertificatesCPA  Certificates
CPA Certificates
 
Standard Assessment Procedure - ATSPACE LTD
Standard Assessment Procedure - ATSPACE LTDStandard Assessment Procedure - ATSPACE LTD
Standard Assessment Procedure - ATSPACE LTD
 
JOB DISCRIPTION OF WORK
JOB DISCRIPTION OF WORKJOB DISCRIPTION OF WORK
JOB DISCRIPTION OF WORK
 
Innovation in Evidential Breath Testing - EASYCAL from Lifeloc Technologies
Innovation in Evidential Breath Testing - EASYCAL from Lifeloc TechnologiesInnovation in Evidential Breath Testing - EASYCAL from Lifeloc Technologies
Innovation in Evidential Breath Testing - EASYCAL from Lifeloc Technologies
 
Equity solutions - Our panel
Equity solutions - Our panelEquity solutions - Our panel
Equity solutions - Our panel
 

Similar to Commissioning stage compliance certificate

Module 6 qaqc training
Module 6 qaqc trainingModule 6 qaqc training
Module 6 qaqc training
Diaz Susetyo
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completionRonie Chu
 
Mata electric QC PLAN
Mata electric QC PLANMata electric QC PLAN
Mata electric QC PLANTina Sharpe
 
General guidelines for building commissioning ppt.pptx
General guidelines  for building  commissioning ppt.pptxGeneral guidelines  for building  commissioning ppt.pptx
General guidelines for building commissioning ppt.pptx
Dayasagar Govidaraju
 
General guidelines for building commissioning ppt
General guidelines  for building  commissioning pptGeneral guidelines  for building  commissioning ppt
General guidelines for building commissioning ppt
Dayasagar Govidaraju
 
commissioning.pdf
commissioning.pdfcommissioning.pdf
commissioning.pdf
haris348605
 
Quality checking
Quality checkingQuality checking
Quality checking
Arjun kumar
 
Quality application
Quality applicationQuality application
Quality application
Walid AlSarady
 
Spec05 pro-ka-kc151a -contractor_quality_control_dated_10-19-98
Spec05 pro-ka-kc151a -contractor_quality_control_dated_10-19-98Spec05 pro-ka-kc151a -contractor_quality_control_dated_10-19-98
Spec05 pro-ka-kc151a -contractor_quality_control_dated_10-19-98
osers
 
TG-15595- report-and-analysis_powerpointviewer(1).doc
TG-15595- report-and-analysis_powerpointviewer(1).docTG-15595- report-and-analysis_powerpointviewer(1).doc
TG-15595- report-and-analysis_powerpointviewer(1).doc
jennbarroga7
 
1.8.0 SITTNER CONOCO TRAIN HOW TO SURVIVE AN AUDIT
1.8.0 SITTNER CONOCO TRAIN HOW TO SURVIVE AN AUDIT1.8.0 SITTNER CONOCO TRAIN HOW TO SURVIVE AN AUDIT
1.8.0 SITTNER CONOCO TRAIN HOW TO SURVIVE AN AUDITSCOTT SITTNER
 
Updated Umang resume
Updated Umang resumeUpdated Umang resume
Updated Umang resumeUmang Tailor
 
Mechanical Completions
Mechanical CompletionsMechanical Completions
Mechanical Completions
Andy Lang
 
Commissioning Inspections Vs QC inspection
Commissioning Inspections Vs QC inspectionCommissioning Inspections Vs QC inspection
Commissioning Inspections Vs QC inspection
Olivia Wilson
 
Difference Between Quality Control Inspection and Commissioning Inspection
Difference Between Quality Control Inspection and Commissioning InspectionDifference Between Quality Control Inspection and Commissioning Inspection
Difference Between Quality Control Inspection and Commissioning Inspection
Olivia Wilson
 
Cmsc 1215 ensuring a quality order management (3)
Cmsc 1215  ensuring a quality order management  (3)Cmsc 1215  ensuring a quality order management  (3)
Cmsc 1215 ensuring a quality order management (3)Perficient, Inc.
 
Ensuring a Quality Order Management Implementation
Ensuring a Quality Order Management ImplementationEnsuring a Quality Order Management Implementation
Ensuring a Quality Order Management Implementation
Perficient, Inc.
 
250250902-141-ISACA-NACACS-Auditing-IT-Projects-Audit-Program.pdf
250250902-141-ISACA-NACACS-Auditing-IT-Projects-Audit-Program.pdf250250902-141-ISACA-NACACS-Auditing-IT-Projects-Audit-Program.pdf
250250902-141-ISACA-NACACS-Auditing-IT-Projects-Audit-Program.pdf
Addisu15
 
Facility Qualification & Consideration of Validation Aspects
Facility Qualification & Consideration of Validation Aspects Facility Qualification & Consideration of Validation Aspects
Facility Qualification & Consideration of Validation Aspects
Apoorva Bauskar
 

Similar to Commissioning stage compliance certificate (20)

019113
019113019113
019113
 
Module 6 qaqc training
Module 6 qaqc trainingModule 6 qaqc training
Module 6 qaqc training
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completion
 
Mata electric QC PLAN
Mata electric QC PLANMata electric QC PLAN
Mata electric QC PLAN
 
General guidelines for building commissioning ppt.pptx
General guidelines  for building  commissioning ppt.pptxGeneral guidelines  for building  commissioning ppt.pptx
General guidelines for building commissioning ppt.pptx
 
General guidelines for building commissioning ppt
General guidelines  for building  commissioning pptGeneral guidelines  for building  commissioning ppt
General guidelines for building commissioning ppt
 
commissioning.pdf
commissioning.pdfcommissioning.pdf
commissioning.pdf
 
Quality checking
Quality checkingQuality checking
Quality checking
 
Quality application
Quality applicationQuality application
Quality application
 
Spec05 pro-ka-kc151a -contractor_quality_control_dated_10-19-98
Spec05 pro-ka-kc151a -contractor_quality_control_dated_10-19-98Spec05 pro-ka-kc151a -contractor_quality_control_dated_10-19-98
Spec05 pro-ka-kc151a -contractor_quality_control_dated_10-19-98
 
TG-15595- report-and-analysis_powerpointviewer(1).doc
TG-15595- report-and-analysis_powerpointviewer(1).docTG-15595- report-and-analysis_powerpointviewer(1).doc
TG-15595- report-and-analysis_powerpointviewer(1).doc
 
1.8.0 SITTNER CONOCO TRAIN HOW TO SURVIVE AN AUDIT
1.8.0 SITTNER CONOCO TRAIN HOW TO SURVIVE AN AUDIT1.8.0 SITTNER CONOCO TRAIN HOW TO SURVIVE AN AUDIT
1.8.0 SITTNER CONOCO TRAIN HOW TO SURVIVE AN AUDIT
 
Updated Umang resume
Updated Umang resumeUpdated Umang resume
Updated Umang resume
 
Mechanical Completions
Mechanical CompletionsMechanical Completions
Mechanical Completions
 
Commissioning Inspections Vs QC inspection
Commissioning Inspections Vs QC inspectionCommissioning Inspections Vs QC inspection
Commissioning Inspections Vs QC inspection
 
Difference Between Quality Control Inspection and Commissioning Inspection
Difference Between Quality Control Inspection and Commissioning InspectionDifference Between Quality Control Inspection and Commissioning Inspection
Difference Between Quality Control Inspection and Commissioning Inspection
 
Cmsc 1215 ensuring a quality order management (3)
Cmsc 1215  ensuring a quality order management  (3)Cmsc 1215  ensuring a quality order management  (3)
Cmsc 1215 ensuring a quality order management (3)
 
Ensuring a Quality Order Management Implementation
Ensuring a Quality Order Management ImplementationEnsuring a Quality Order Management Implementation
Ensuring a Quality Order Management Implementation
 
250250902-141-ISACA-NACACS-Auditing-IT-Projects-Audit-Program.pdf
250250902-141-ISACA-NACACS-Auditing-IT-Projects-Audit-Program.pdf250250902-141-ISACA-NACACS-Auditing-IT-Projects-Audit-Program.pdf
250250902-141-ISACA-NACACS-Auditing-IT-Projects-Audit-Program.pdf
 
Facility Qualification & Consideration of Validation Aspects
Facility Qualification & Consideration of Validation Aspects Facility Qualification & Consideration of Validation Aspects
Facility Qualification & Consideration of Validation Aspects
 

Recently uploaded

Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Albert Hoitingh
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance
 
zkStudyClub - Reef: Fast Succinct Non-Interactive Zero-Knowledge Regex Proofs
zkStudyClub - Reef: Fast Succinct Non-Interactive Zero-Knowledge Regex ProofszkStudyClub - Reef: Fast Succinct Non-Interactive Zero-Knowledge Regex Proofs
zkStudyClub - Reef: Fast Succinct Non-Interactive Zero-Knowledge Regex Proofs
Alex Pruden
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
DanBrown980551
 
Removing Uninteresting Bytes in Software Fuzzing
Removing Uninteresting Bytes in Software FuzzingRemoving Uninteresting Bytes in Software Fuzzing
Removing Uninteresting Bytes in Software Fuzzing
Aftab Hussain
 
PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)
Ralf Eggert
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
Sri Ambati
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance
 
A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...
sonjaschweigert1
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
UiPathCommunity
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
James Anderson
 
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
James Anderson
 
Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™
Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™
Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™
UiPathCommunity
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
Jemma Hussein Allen
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
DianaGray10
 
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdfObservability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Paige Cruz
 
Pushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 daysPushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 days
Adtran
 
Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
Thijs Feryn
 
Elevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object CalisthenicsElevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object Calisthenics
Dorra BARTAGUIZ
 

Recently uploaded (20)

Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
 
zkStudyClub - Reef: Fast Succinct Non-Interactive Zero-Knowledge Regex Proofs
zkStudyClub - Reef: Fast Succinct Non-Interactive Zero-Knowledge Regex ProofszkStudyClub - Reef: Fast Succinct Non-Interactive Zero-Knowledge Regex Proofs
zkStudyClub - Reef: Fast Succinct Non-Interactive Zero-Knowledge Regex Proofs
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
 
Removing Uninteresting Bytes in Software Fuzzing
Removing Uninteresting Bytes in Software FuzzingRemoving Uninteresting Bytes in Software Fuzzing
Removing Uninteresting Bytes in Software Fuzzing
 
PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 
A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
 
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
 
Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™
Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™
Le nuove frontiere dell'AI nell'RPA con UiPath Autopilot™
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
 
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdfObservability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
 
Pushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 daysPushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 days
 
Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
 
Elevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object CalisthenicsElevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object Calisthenics
 

Commissioning stage compliance certificate

  • 1. COMMISSIONING STAGE COMPLIANCE CERTIFICATE – CSCC System Reference / Description: Discipline Code: Location: Certificate of Installation Completion Verification that Installation Activities are Completed sufficiently for Pre-Functional and Operational Check Out Procedures to commence. Certificate of Readiness Verification that Pre-Functional and Operational Check Out Activities are Completed and prior to the Functional Testing being commenced. Certificate of Commissioning Completion Verification that Functional Testing Activities are Completed and prior to the Integrated Commissioning being commenced. Item Completed Comment Signed by Date 1 QAN’s Reviewed. Refer to Checklist 2 CTI’s Reviewed. Refer to Checklist 3 NCR’s Refer to Checklist 4 Commissioning Issues Log Items reviewed. 5 Construction/Installation Completed. 6 Sub-Contractors works Complete. 7 Pre-Functional Check Out Signed. 8 Operational Check Out Signed. 9 Functional Check Out Signed. Note: All outstanding issues that can be carried forward and do not prevent commissioning from continuing must be added to the commissioning issues log. Signed by: Signature: On Behalf of: Sub-Contractor Date: Signed by: Signature: On Behalf of: SOJV Construction Date: Signed by: Signature: On Behalf of: SOJV Cx Date: Signed by:
  • 2. Signature: On Behalf of: OBI Date: Upon sign off of this document, the following procedures / test activities may be conducted. TABTP/CTP/TPPRef. A B E F J M P J X COMMISSIONING STAGE COMPLIENCE CERTIFICATE CHECKLIST SYSTEM/EQUIPMENT REF: Date: AREA LOCATION: WORKS DESCRIPTION: ITEM DOCUMENT/DRAWING No CODE 1. Method Statements 2. Test Procedures 3. Shop Drawings 4. QAN’s 5. NCR’s 6.CTI’s