PROJECT MANAGEMENT
MSE 1
TOPICS COVERED:
1. Machinery and Equipment
2. Structure and Civil Work
3. Environmental Aspects
4. Project Charts and Layouts
 Machinery & Equipment requirement depends upon the
production technology and plant capacity of the proposed
project.
 Steps to select machinery and equipment for a project:
1. Estimate levels of production over time
2. Define various machining and operations
3. Calculate machine hours required for each type of
operations
4. Select equipment and machinery for each function
1.1.1. Machinery & Equipment
DIKSHA PRAKASH 2
 Types of Machinery and equipment:
1. Plant equipment
2. Mechanical equipment
3. Electrical equipment
4. Instruments
5. Controls and internal transportation system
6. Spare parts & tools
 Things to be considered while selecting machinery and equipment:
1. Availability of power to rum machines
2. Transporting heavy equipment
3. Ease of use
4. Import policies of Govt. if the machines are to be imported from a
foreign country
 Factored affecting the procurement of machinery:
1. Quality of machinery
2. Level of technical sophistication
3. Reputation of supplier
4. Expected delivery schedule
5. Payment terms
6. Performance guarantees
DIKSHA PRAKASH 3
 Size of the job: Larger volumes of excavation will require larger
excavators, or smaller excavators in greater number.
 Activity time constraints: Shortage of time for excavation may force
contractors to increase the size or numbers of equipment for activities
related to excavation.
 Availability of equipment: Productivity of excavation activities will
diminish if the equipment used to perform them is available but not the
most adequate.
 Cost of transportation of equipment: This cost depends on the size of
the job, the distance of transportation, and the means of transportation.
 Type of excavation: Principal types of excavation in building projects are
cut and/or fill, excavation massive, and excavation for the elements of
foundation. The most adequate equipment to perform one of these
activities is not the most adequate to perform the others.
Choice of Machinery
(with the example of an excavation project)
DIKSHA PRAKASH 4
 Soil characteristics: The type and condition of the soil is important when
choosing the most adequate equipment since each piece of equipment
has different outputs for different soils. Moreover, one excavation pit
could have different soils at different stratums.
 Geometric characteristics of elements to be excavated: Functional
characteristics of different types of equipment makes such
considerations necessary.
 Space constraints: The performance of equipment is influenced by the
spatial limitations for the movement of excavators.
 Characteristics of haul units: The size of an excavator will depend on the
haul units if there is a constraint on the size and/or number of these units.
 Location of dumping areas: The distance between the construction site
and dumping areas could be relevant not only for selecting the type and
number of haulers, but also the type of excavators.
 Weather and temperature: Rain, snow and severe temperature
conditions affect the job-site productivity of labour and equipment.DIKSHA PRAKASH 5
 WHY?
For manufacturing a product, more than one
process/technology may be available.
For example, steel can be manufactured either by the
Bessemer process or by the open-hearth process.
Cement can be manufactured either by the wet
process or by the dry process.
1.1.2. Choice of Technology
DIKSHA PRAKASH 6
 Depends on quality and quantity of product.
 If quantity increases then, mass production technique
with relevant technology is required.
 Quality depends upon what use it is meant for. Eg:
(a) Any pharmaceutical grade product should have high
quality and hence demands sophisticated technology.
(b) Any product for commercial use doesn’t need to be of
extra high quality.
Selection of Process/ Technology
DIKSHA PRAKASH 7
 For technology, latest technology should be chosen
provided it has no constraints & proves successful for
large scale production at factory.
 Any technology protected by patent rights can be
purchased outright if the cost of acquisition is
affordable.
 The term ‘appropriate technology’ is the one suitable
for local economic, social and cultural conditions.
DIKSHA PRAKASH 8
Appropriate technology can be identified by asking the
following questions:
1. Does the technology makes use of the locally available
raw material ?
2. Can the technology by implemented and maintained by
the locally available man power ?
3. Is the technology in tune with the local social and
cultural conditions ?
4. Does the technology protects ecological balance etc. ?
Appropriate Technology
DIKSHA PRAKASH 9
 Often, the basic flaw in project planning and design is the
complete neglect or minimal consideration of
environmental and social costs and dependence only on
economic analysis for project preparation and investment.
 A failure to understand and internalize adverse or negative
impacts on environment during project preparation could
lead to several undesirable consequences, which may
ultimately jeopardize the very objectives of growth and
development for which the project was proposed.
1.2. Environmental Aspects
DIKSHA PRAKASH 10
 Environment management reduces the unforeseen
obstacles and bottlenecks that may otherwise
hamper the delivery of project objectives while
helping to improve the environmental performance
of project operations.
 Environmental impact assessment (EIA) study is
suggested as a tool for formulating an environment
management plan
DIKSHA PRAKASH 11
Environmental Impact Analysis
DIKSHA PRAKASH 12
 For Example, a forest ecosystem is a complete
ecosystem which provides food, shelter to a wide
variety of species. It provides firewood, resins,
timber, medicinal herbs, etc.. to us. Therefore forests
are our lifeline. Whenever a project is undertaken
which demands clearing of the forest like
construction of road or a dam, then EIA helps us to
access the impact of that activity on this life line. It
also suggests alternate project sites and alternate
process technologies.
Example:
DIKSHA PRAKASH 13
 Surface water quality ?
 Air quality ?
 Seismology/geology impact?
 Erosion ?
 Land quality ?
 Fisheries ?
 Forests ?
 Terrestrial wildlife ?
 Noise?
 Archaeological/historical significance ?
 Public health ?
FAQ : Environmental aspects
DIKSHA PRAKASH 14
 Site preparation and development ( grading and levelling
of the site, demolition and removal of existing structure,
relocation of existing pipelines, cables, roads, power lines
etc. connection of public network like electric power,
water, communications, transportations etc. )
 Building and Structures ( involves construction of factory
or process building, ancillary buildings, administrative
buildings, residential buildings)
 Outdoor works ( involves the supply and distribution of
utilities, handling and treatment of emission, wastages,
transportation, supervision etc)
1.3. Structures and Civil Works
DIKSHA PRAKASH 15
 Technical Analysis of a project for buildings,
structures and civil works involves the preparation
and development of site which includes
1. Grading and levelling of land
2. Demolition of existing structures
3. Relocation of pipeline, cables, roads
4. Reclamation of sewers and drainage
5. Connections for utilities
6. Arranging for electricity, water etc.
DIKSHA PRAKASH 16
 General functional layout
 Material flow diagram
 Production line diagram
 Transport layout
 Utility consumption layout
 Communication layout
 Organizational layout
 Plant layout
1.4. Project charts and Layout
DIKSHA PRAKASH 17
 General Functional Layout shows the functional relationship between
building, civil works and machines. It facilitates smooth and
economical movement of raw materials, work in progress and
finished products.
 Material flow diagram shows the quantum of flow of materials, work-
in-progress, finished products etc. along with the basic flow of these
items.
 Product Line Diagram shows the production process envisaged for
the project. It also shows the vital information for the main machines
and equipment's (description, location, foundation, space
requirement, power and utilities required, distance between one
centre to another etc.)
 Plant Layout indicates the physical layout of the entire factory. In
case of the process industry, the plant layout depends upon the
production process involved chronologically.
DIKSHA PRAKASH 18
 Utility Consumption Layout shows main points of consumption
of utilities and the qualities and quantities required.
 Transport Layout indicates the distance and means of
transportation outside the production line.
 Communication layout shows how various departments of the
project are connected with the communication system.
 Organization layout indicates the organization structure of the
project, the interrelationship between different departments
and the manpower required for the various departments.
 Plant Layout refers to the arrangement of physical facilities
such as machinery, equipment, furniture etc. with in the factory
building in such a manner so as to have quickest flow of
material at the lowest cost.DIKSHA PRAKASH 19
 “Project Management & Control” : Subhash Chandra Das. ISBN:
8120344502
 http://pmbook.ce.cmu.edu/04_Labor,_Material,_And_Equipment_
Utilization.html
 http://ijiset.com/vol3/v3s5/IJISET_V3_I5_16.pdf
 http://www.bbamantra.com/technical-analysis-of-a-project/
 https://enviroliteracy.org/environment-
society/economics/environmental-impact-analysis/
 http://www.newagepublishers.com/samplechapter/001059.pdf
 www.ef.uns.ac.rs/mis/archive-pdf/2008%20-
%20No1/MIS2008_1_1.pdf
 https://www.slideshare.net/search/slideshow?searchfrom=header
&q=project+management
REFERENCES
DIKSHA PRAKASH 20

More Related Content

Viewers also liked

8086 labmanual
8086 labmanual8086 labmanual
8086 labmanualiravi9
 
The+clay+minerals+2007
The+clay+minerals+2007The+clay+minerals+2007
The+clay+minerals+2007Zakee Kazmee
 
Project Mgmt Fundamentals
Project Mgmt FundamentalsProject Mgmt Fundamentals
Project Mgmt Fundamentals
Chris Miller
 
Project Management - Module 1 Training (Fabio Moioli)
Project Management - Module 1 Training (Fabio Moioli)Project Management - Module 1 Training (Fabio Moioli)
Project Management - Module 1 Training (Fabio Moioli)
Fabio Moioli
 
311 angle modulation
311 angle modulation311 angle modulation
311 angle modulation
Mohammad Bappy
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
Robert Kelly
 
PMI Project Management Framework
PMI Project Management FrameworkPMI Project Management Framework
PMI Project Management FrameworkAarti Dahiya PMP
 
Phase modulation
Phase modulationPhase modulation
Phase modulationavocado1111
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
Marius FAILLOT DEVARRE
 
PMBOK_5th_Project Management Framework
PMBOK_5th_Project Management FrameworkPMBOK_5th_Project Management Framework
PMBOK_5th_Project Management Framework
Hossam Maghrabi
 
Geotechnical Investigation
Geotechnical InvestigationGeotechnical Investigation
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
Rahul Sudame
 
Frequency modulation
Frequency modulationFrequency modulation
Frequency modulation
Akanksha_Seth
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
Wadhwani Foundation
 
An introduction to civil engineering
An introduction  to civil engineeringAn introduction  to civil engineering
An introduction to civil engineeringBhanu Pratap
 
Why Civil Engineering is Best
Why Civil Engineering is BestWhy Civil Engineering is Best
Why Civil Engineering is BestRahul Chavda
 
8086 class notes-Y.N.M
8086 class notes-Y.N.M8086 class notes-Y.N.M
8086 class notes-Y.N.M
Dr.YNM
 

Viewers also liked (20)

8086 labmanual
8086 labmanual8086 labmanual
8086 labmanual
 
Listening
ListeningListening
Listening
 
The+clay+minerals+2007
The+clay+minerals+2007The+clay+minerals+2007
The+clay+minerals+2007
 
Angle modulation
Angle modulationAngle modulation
Angle modulation
 
Project Mgmt Fundamentals
Project Mgmt FundamentalsProject Mgmt Fundamentals
Project Mgmt Fundamentals
 
Project Management - Module 1 Training (Fabio Moioli)
Project Management - Module 1 Training (Fabio Moioli)Project Management - Module 1 Training (Fabio Moioli)
Project Management - Module 1 Training (Fabio Moioli)
 
311 angle modulation
311 angle modulation311 angle modulation
311 angle modulation
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
PMI Project Management Framework
PMI Project Management FrameworkPMI Project Management Framework
PMI Project Management Framework
 
Phase modulation
Phase modulationPhase modulation
Phase modulation
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
PMBOK_5th_Project Management Framework
PMBOK_5th_Project Management FrameworkPMBOK_5th_Project Management Framework
PMBOK_5th_Project Management Framework
 
Geotechnical Investigation
Geotechnical InvestigationGeotechnical Investigation
Geotechnical Investigation
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Frequency modulation
Frequency modulationFrequency modulation
Frequency modulation
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
An introduction to civil engineering
An introduction  to civil engineeringAn introduction  to civil engineering
An introduction to civil engineering
 
Why Civil Engineering is Best
Why Civil Engineering is BestWhy Civil Engineering is Best
Why Civil Engineering is Best
 
8086 class notes-Y.N.M
8086 class notes-Y.N.M8086 class notes-Y.N.M
8086 class notes-Y.N.M
 
Technical analysis
Technical analysisTechnical analysis
Technical analysis
 

Similar to Project Management

1347 notes ii_ppe_304
1347 notes ii_ppe_3041347 notes ii_ppe_304
1347 notes ii_ppe_304kriti201
 
Selection Criteria of Equipment in Construction Project
Selection Criteria of Equipment in Construction ProjectSelection Criteria of Equipment in Construction Project
Selection Criteria of Equipment in Construction Project
IRJET Journal
 
Technical analysis in project.khudshfkwjjjjjjjjjjs
Technical analysis in project.khudshfkwjjjjjjjjjjsTechnical analysis in project.khudshfkwjjjjjjjjjjs
Technical analysis in project.khudshfkwjjjjjjjjjjs
MeghaSingh506383
 
Plant location and layout in any industry
Plant location and layout in any industryPlant location and layout in any industry
Plant location and layout in any industry
Mehran University of Engineering and Technology Jamshoro
 
technical analysis
technical analysistechnical analysis
technical analysisAshish Singh
 
Engineering dictionary
Engineering dictionaryEngineering dictionary
Engineering dictionary
Shivkumar Yadav
 
CL 380_Unit-1 (1).pptx
CL 380_Unit-1 (1).pptxCL 380_Unit-1 (1).pptx
CL 380_Unit-1 (1).pptx
megha desai
 
Job Layout
Job LayoutJob Layout
Job Layout
Bahzad5
 
CL 380_Unit-1.pptx
CL 380_Unit-1.pptxCL 380_Unit-1.pptx
CL 380_Unit-1.pptx
megha desai
 
IRJET- Planning and Selection of Heavy Construction Equipments in Civil En...
IRJET- 	  Planning and Selection of Heavy Construction Equipments in Civil En...IRJET- 	  Planning and Selection of Heavy Construction Equipments in Civil En...
IRJET- Planning and Selection of Heavy Construction Equipments in Civil En...
IRJET Journal
 
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET Journal
 
Chapter 2 Plant Location
Chapter 2 Plant LocationChapter 2 Plant Location
Chapter 2 Plant Location
mustafizulhilmie
 
Technical Analysis & Financial Analysis
Technical Analysis & Financial AnalysisTechnical Analysis & Financial Analysis
Technical Analysis & Financial Analysis
anshagrawal2121
 
Diethyl Ether (DEE): Site Selection and Plant Layout
Diethyl Ether (DEE): Site Selection and Plant LayoutDiethyl Ether (DEE): Site Selection and Plant Layout
Diethyl Ether (DEE): Site Selection and Plant Layout
Pratik Patel
 
Unit 6 A Construction Equipments for civil engineering.pdf
Unit 6 A Construction Equipments for civil engineering.pdfUnit 6 A Construction Equipments for civil engineering.pdf
Unit 6 A Construction Equipments for civil engineering.pdf
D. Y. Patil College of Engineering & Technology, Kolhapur, Maharastra, India
 
Planning and Selection of Heavy Construction Equipment in Civil Engineering
Planning and Selection of Heavy Construction Equipment in Civil EngineeringPlanning and Selection of Heavy Construction Equipment in Civil Engineering
Planning and Selection of Heavy Construction Equipment in Civil Engineering
IJERA Editor
 
Site layout cpm module4
Site layout cpm module4Site layout cpm module4
Site layout cpm module4
ahsanrabbani
 
Ici individual
Ici individualIci individual
Ici individual
Klaus Chiang
 
Diesel Production: Site Location
Diesel Production: Site LocationDiesel Production: Site Location
Diesel Production: Site Location
Pratik Patel
 

Similar to Project Management (20)

1347 notes ii_ppe_304
1347 notes ii_ppe_3041347 notes ii_ppe_304
1347 notes ii_ppe_304
 
Selection Criteria of Equipment in Construction Project
Selection Criteria of Equipment in Construction ProjectSelection Criteria of Equipment in Construction Project
Selection Criteria of Equipment in Construction Project
 
Technical analysis in project.khudshfkwjjjjjjjjjjs
Technical analysis in project.khudshfkwjjjjjjjjjjsTechnical analysis in project.khudshfkwjjjjjjjjjjs
Technical analysis in project.khudshfkwjjjjjjjjjjs
 
Plant location and layout in any industry
Plant location and layout in any industryPlant location and layout in any industry
Plant location and layout in any industry
 
technical analysis
technical analysistechnical analysis
technical analysis
 
Engineering dictionary
Engineering dictionaryEngineering dictionary
Engineering dictionary
 
CL 380_Unit-1 (1).pptx
CL 380_Unit-1 (1).pptxCL 380_Unit-1 (1).pptx
CL 380_Unit-1 (1).pptx
 
Job Layout
Job LayoutJob Layout
Job Layout
 
CL 380_Unit-1.pptx
CL 380_Unit-1.pptxCL 380_Unit-1.pptx
CL 380_Unit-1.pptx
 
IRJET- Planning and Selection of Heavy Construction Equipments in Civil En...
IRJET- 	  Planning and Selection of Heavy Construction Equipments in Civil En...IRJET- 	  Planning and Selection of Heavy Construction Equipments in Civil En...
IRJET- Planning and Selection of Heavy Construction Equipments in Civil En...
 
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
 
Chapter 2 Plant Location
Chapter 2 Plant LocationChapter 2 Plant Location
Chapter 2 Plant Location
 
Technical Analysis & Financial Analysis
Technical Analysis & Financial AnalysisTechnical Analysis & Financial Analysis
Technical Analysis & Financial Analysis
 
Diethyl Ether (DEE): Site Selection and Plant Layout
Diethyl Ether (DEE): Site Selection and Plant LayoutDiethyl Ether (DEE): Site Selection and Plant Layout
Diethyl Ether (DEE): Site Selection and Plant Layout
 
Unit 6 A Construction Equipments for civil engineering.pdf
Unit 6 A Construction Equipments for civil engineering.pdfUnit 6 A Construction Equipments for civil engineering.pdf
Unit 6 A Construction Equipments for civil engineering.pdf
 
Planning and Selection of Heavy Construction Equipment in Civil Engineering
Planning and Selection of Heavy Construction Equipment in Civil EngineeringPlanning and Selection of Heavy Construction Equipment in Civil Engineering
Planning and Selection of Heavy Construction Equipment in Civil Engineering
 
Site layout cpm module4
Site layout cpm module4Site layout cpm module4
Site layout cpm module4
 
Construction Equipment used in construction projects
Construction Equipment used in construction projectsConstruction Equipment used in construction projects
Construction Equipment used in construction projects
 
Ici individual
Ici individualIci individual
Ici individual
 
Diesel Production: Site Location
Diesel Production: Site LocationDiesel Production: Site Location
Diesel Production: Site Location
 

Recently uploaded

De-risk Your Digital Evolution - Hannah Grap
De-risk Your Digital Evolution - Hannah GrapDe-risk Your Digital Evolution - Hannah Grap
AI Driven Emotional Recognition in Digital Ads - Tarun Gupta
AI Driven Emotional Recognition in Digital Ads - Tarun GuptaAI Driven Emotional Recognition in Digital Ads - Tarun Gupta
AI Driven Emotional Recognition in Digital Ads - Tarun Gupta
DigiMarCon - Digital Marketing, Media and Advertising Conferences & Exhibitions
 
Smart Tools, Smarter Business -15 AI Tools to Optimize Your Workflows from Id...
Smart Tools, Smarter Business -15 AI Tools to Optimize Your Workflows from Id...Smart Tools, Smarter Business -15 AI Tools to Optimize Your Workflows from Id...
Smart Tools, Smarter Business -15 AI Tools to Optimize Your Workflows from Id...
DigiMarCon - Digital Marketing, Media and Advertising Conferences & Exhibitions
 
Phil Pallen PPT Biography and Interviews
Phil Pallen PPT Biography and InterviewsPhil Pallen PPT Biography and Interviews
Phil Pallen PPT Biography and Interviews
travisomalana
 
How To Navigate AI - The Future is Yours to Define - Tim Hayden
How To Navigate AI - The Future is Yours to Define - Tim HaydenHow To Navigate AI - The Future is Yours to Define - Tim Hayden
How To Navigate AI - The Future is Yours to Define - Tim Hayden
DigiMarCon - Digital Marketing, Media and Advertising Conferences & Exhibitions
 
Unknown to Unforgettable - The Art and Science to Being Irresistible on Camer...
Unknown to Unforgettable - The Art and Science to Being Irresistible on Camer...Unknown to Unforgettable - The Art and Science to Being Irresistible on Camer...
Unknown to Unforgettable - The Art and Science to Being Irresistible on Camer...
DigiMarCon - Digital Marketing, Media and Advertising Conferences & Exhibitions
 
Podcast, The New Marketing Currency - Ozeal Debastos
Podcast, The New Marketing Currency - Ozeal DebastosPodcast, The New Marketing Currency - Ozeal Debastos
Podcast, The New Marketing Currency - Ozeal Debastos
DigiMarCon - Digital Marketing, Media and Advertising Conferences & Exhibitions
 
Mastering SEO for Google in the AI Era - Dennis Yu
Mastering SEO for Google in the AI Era - Dennis YuMastering SEO for Google in the AI Era - Dennis Yu
Winning local SEO in the Age of AI - Dennis Yu
Winning local SEO in the Age of AI - Dennis YuWinning local SEO in the Age of AI - Dennis Yu
Grow Your Business Online: Introduction to Digital Marketing
Grow Your Business Online: Introduction to Digital MarketingGrow Your Business Online: Introduction to Digital Marketing
Grow Your Business Online: Introduction to Digital Marketing
Digital Discovery Institute
 
Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...
Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...
Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...
DigiMarCon - Digital Marketing, Media and Advertising Conferences & Exhibitions
 
Top digital marketing institutein noida
Top digital marketing institutein noidaTop digital marketing institutein noida
Top digital marketing institutein noida
aditisingh6607
 
Exploring the Top Digital Marketing Company in Canada
Exploring the Top Digital Marketing Company in CanadaExploring the Top Digital Marketing Company in Canada
Exploring the Top Digital Marketing Company in Canada
Solomo Media
 
How to Use AI to Write a High-Quality Article that Ranks
How to Use AI to Write a High-Quality Article that RanksHow to Use AI to Write a High-Quality Article that Ranks
How to Use AI to Write a High-Quality Article that Ranks
minatamang0021
 
Luxury Hanloom Saree Brand ,Capstone Project_Kiran Bansal.pdf
Luxury Hanloom Saree Brand ,Capstone Project_Kiran Bansal.pdfLuxury Hanloom Saree Brand ,Capstone Project_Kiran Bansal.pdf
Luxury Hanloom Saree Brand ,Capstone Project_Kiran Bansal.pdf
KiranRai75
 
Google Ads Vs Social Media Ads-A comparative analysis
Google Ads Vs Social Media Ads-A comparative analysisGoogle Ads Vs Social Media Ads-A comparative analysis
Google Ads Vs Social Media Ads-A comparative analysis
akashrawdot
 
[Google March 2024 Update] How To Thrive: Content, Link Building & SEO
[Google March 2024 Update] How To Thrive: Content, Link Building & SEO[Google March 2024 Update] How To Thrive: Content, Link Building & SEO
[Google March 2024 Update] How To Thrive: Content, Link Building & SEO
Search Engine Journal
 
janani Digital Marketer|Digital Marketing consultant|Marketing Promotion|Coim...
janani Digital Marketer|Digital Marketing consultant|Marketing Promotion|Coim...janani Digital Marketer|Digital Marketing consultant|Marketing Promotion|Coim...
janani Digital Marketer|Digital Marketing consultant|Marketing Promotion|Coim...
janudm24
 
Traditional Store Audits are Outdated: A New Approach to Protecting Your Bran...
Traditional Store Audits are Outdated: A New Approach to Protecting Your Bran...Traditional Store Audits are Outdated: A New Approach to Protecting Your Bran...
Traditional Store Audits are Outdated: A New Approach to Protecting Your Bran...
Auxis Consulting & Outsourcing
 

Recently uploaded (20)

De-risk Your Digital Evolution - Hannah Grap
De-risk Your Digital Evolution - Hannah GrapDe-risk Your Digital Evolution - Hannah Grap
De-risk Your Digital Evolution - Hannah Grap
 
AI Driven Emotional Recognition in Digital Ads - Tarun Gupta
AI Driven Emotional Recognition in Digital Ads - Tarun GuptaAI Driven Emotional Recognition in Digital Ads - Tarun Gupta
AI Driven Emotional Recognition in Digital Ads - Tarun Gupta
 
Smart Tools, Smarter Business -15 AI Tools to Optimize Your Workflows from Id...
Smart Tools, Smarter Business -15 AI Tools to Optimize Your Workflows from Id...Smart Tools, Smarter Business -15 AI Tools to Optimize Your Workflows from Id...
Smart Tools, Smarter Business -15 AI Tools to Optimize Your Workflows from Id...
 
Phil Pallen PPT Biography and Interviews
Phil Pallen PPT Biography and InterviewsPhil Pallen PPT Biography and Interviews
Phil Pallen PPT Biography and Interviews
 
How To Navigate AI - The Future is Yours to Define - Tim Hayden
How To Navigate AI - The Future is Yours to Define - Tim HaydenHow To Navigate AI - The Future is Yours to Define - Tim Hayden
How To Navigate AI - The Future is Yours to Define - Tim Hayden
 
Unknown to Unforgettable - The Art and Science to Being Irresistible on Camer...
Unknown to Unforgettable - The Art and Science to Being Irresistible on Camer...Unknown to Unforgettable - The Art and Science to Being Irresistible on Camer...
Unknown to Unforgettable - The Art and Science to Being Irresistible on Camer...
 
Podcast, The New Marketing Currency - Ozeal Debastos
Podcast, The New Marketing Currency - Ozeal DebastosPodcast, The New Marketing Currency - Ozeal Debastos
Podcast, The New Marketing Currency - Ozeal Debastos
 
Mastering SEO for Google in the AI Era - Dennis Yu
Mastering SEO for Google in the AI Era - Dennis YuMastering SEO for Google in the AI Era - Dennis Yu
Mastering SEO for Google in the AI Era - Dennis Yu
 
Mastering Email Campaign Automation Strategies and Best Practices - Michelle...
Mastering Email Campaign Automation Strategies and Best Practices  - Michelle...Mastering Email Campaign Automation Strategies and Best Practices  - Michelle...
Mastering Email Campaign Automation Strategies and Best Practices - Michelle...
 
Winning local SEO in the Age of AI - Dennis Yu
Winning local SEO in the Age of AI - Dennis YuWinning local SEO in the Age of AI - Dennis Yu
Winning local SEO in the Age of AI - Dennis Yu
 
Grow Your Business Online: Introduction to Digital Marketing
Grow Your Business Online: Introduction to Digital MarketingGrow Your Business Online: Introduction to Digital Marketing
Grow Your Business Online: Introduction to Digital Marketing
 
Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...
Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...
Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...
 
Top digital marketing institutein noida
Top digital marketing institutein noidaTop digital marketing institutein noida
Top digital marketing institutein noida
 
Exploring the Top Digital Marketing Company in Canada
Exploring the Top Digital Marketing Company in CanadaExploring the Top Digital Marketing Company in Canada
Exploring the Top Digital Marketing Company in Canada
 
How to Use AI to Write a High-Quality Article that Ranks
How to Use AI to Write a High-Quality Article that RanksHow to Use AI to Write a High-Quality Article that Ranks
How to Use AI to Write a High-Quality Article that Ranks
 
Luxury Hanloom Saree Brand ,Capstone Project_Kiran Bansal.pdf
Luxury Hanloom Saree Brand ,Capstone Project_Kiran Bansal.pdfLuxury Hanloom Saree Brand ,Capstone Project_Kiran Bansal.pdf
Luxury Hanloom Saree Brand ,Capstone Project_Kiran Bansal.pdf
 
Google Ads Vs Social Media Ads-A comparative analysis
Google Ads Vs Social Media Ads-A comparative analysisGoogle Ads Vs Social Media Ads-A comparative analysis
Google Ads Vs Social Media Ads-A comparative analysis
 
[Google March 2024 Update] How To Thrive: Content, Link Building & SEO
[Google March 2024 Update] How To Thrive: Content, Link Building & SEO[Google March 2024 Update] How To Thrive: Content, Link Building & SEO
[Google March 2024 Update] How To Thrive: Content, Link Building & SEO
 
janani Digital Marketer|Digital Marketing consultant|Marketing Promotion|Coim...
janani Digital Marketer|Digital Marketing consultant|Marketing Promotion|Coim...janani Digital Marketer|Digital Marketing consultant|Marketing Promotion|Coim...
janani Digital Marketer|Digital Marketing consultant|Marketing Promotion|Coim...
 
Traditional Store Audits are Outdated: A New Approach to Protecting Your Bran...
Traditional Store Audits are Outdated: A New Approach to Protecting Your Bran...Traditional Store Audits are Outdated: A New Approach to Protecting Your Bran...
Traditional Store Audits are Outdated: A New Approach to Protecting Your Bran...
 

Project Management

  • 1. PROJECT MANAGEMENT MSE 1 TOPICS COVERED: 1. Machinery and Equipment 2. Structure and Civil Work 3. Environmental Aspects 4. Project Charts and Layouts
  • 2.  Machinery & Equipment requirement depends upon the production technology and plant capacity of the proposed project.  Steps to select machinery and equipment for a project: 1. Estimate levels of production over time 2. Define various machining and operations 3. Calculate machine hours required for each type of operations 4. Select equipment and machinery for each function 1.1.1. Machinery & Equipment DIKSHA PRAKASH 2
  • 3.  Types of Machinery and equipment: 1. Plant equipment 2. Mechanical equipment 3. Electrical equipment 4. Instruments 5. Controls and internal transportation system 6. Spare parts & tools  Things to be considered while selecting machinery and equipment: 1. Availability of power to rum machines 2. Transporting heavy equipment 3. Ease of use 4. Import policies of Govt. if the machines are to be imported from a foreign country  Factored affecting the procurement of machinery: 1. Quality of machinery 2. Level of technical sophistication 3. Reputation of supplier 4. Expected delivery schedule 5. Payment terms 6. Performance guarantees DIKSHA PRAKASH 3
  • 4.  Size of the job: Larger volumes of excavation will require larger excavators, or smaller excavators in greater number.  Activity time constraints: Shortage of time for excavation may force contractors to increase the size or numbers of equipment for activities related to excavation.  Availability of equipment: Productivity of excavation activities will diminish if the equipment used to perform them is available but not the most adequate.  Cost of transportation of equipment: This cost depends on the size of the job, the distance of transportation, and the means of transportation.  Type of excavation: Principal types of excavation in building projects are cut and/or fill, excavation massive, and excavation for the elements of foundation. The most adequate equipment to perform one of these activities is not the most adequate to perform the others. Choice of Machinery (with the example of an excavation project) DIKSHA PRAKASH 4
  • 5.  Soil characteristics: The type and condition of the soil is important when choosing the most adequate equipment since each piece of equipment has different outputs for different soils. Moreover, one excavation pit could have different soils at different stratums.  Geometric characteristics of elements to be excavated: Functional characteristics of different types of equipment makes such considerations necessary.  Space constraints: The performance of equipment is influenced by the spatial limitations for the movement of excavators.  Characteristics of haul units: The size of an excavator will depend on the haul units if there is a constraint on the size and/or number of these units.  Location of dumping areas: The distance between the construction site and dumping areas could be relevant not only for selecting the type and number of haulers, but also the type of excavators.  Weather and temperature: Rain, snow and severe temperature conditions affect the job-site productivity of labour and equipment.DIKSHA PRAKASH 5
  • 6.  WHY? For manufacturing a product, more than one process/technology may be available. For example, steel can be manufactured either by the Bessemer process or by the open-hearth process. Cement can be manufactured either by the wet process or by the dry process. 1.1.2. Choice of Technology DIKSHA PRAKASH 6
  • 7.  Depends on quality and quantity of product.  If quantity increases then, mass production technique with relevant technology is required.  Quality depends upon what use it is meant for. Eg: (a) Any pharmaceutical grade product should have high quality and hence demands sophisticated technology. (b) Any product for commercial use doesn’t need to be of extra high quality. Selection of Process/ Technology DIKSHA PRAKASH 7
  • 8.  For technology, latest technology should be chosen provided it has no constraints & proves successful for large scale production at factory.  Any technology protected by patent rights can be purchased outright if the cost of acquisition is affordable.  The term ‘appropriate technology’ is the one suitable for local economic, social and cultural conditions. DIKSHA PRAKASH 8
  • 9. Appropriate technology can be identified by asking the following questions: 1. Does the technology makes use of the locally available raw material ? 2. Can the technology by implemented and maintained by the locally available man power ? 3. Is the technology in tune with the local social and cultural conditions ? 4. Does the technology protects ecological balance etc. ? Appropriate Technology DIKSHA PRAKASH 9
  • 10.  Often, the basic flaw in project planning and design is the complete neglect or minimal consideration of environmental and social costs and dependence only on economic analysis for project preparation and investment.  A failure to understand and internalize adverse or negative impacts on environment during project preparation could lead to several undesirable consequences, which may ultimately jeopardize the very objectives of growth and development for which the project was proposed. 1.2. Environmental Aspects DIKSHA PRAKASH 10
  • 11.  Environment management reduces the unforeseen obstacles and bottlenecks that may otherwise hamper the delivery of project objectives while helping to improve the environmental performance of project operations.  Environmental impact assessment (EIA) study is suggested as a tool for formulating an environment management plan DIKSHA PRAKASH 11
  • 13.  For Example, a forest ecosystem is a complete ecosystem which provides food, shelter to a wide variety of species. It provides firewood, resins, timber, medicinal herbs, etc.. to us. Therefore forests are our lifeline. Whenever a project is undertaken which demands clearing of the forest like construction of road or a dam, then EIA helps us to access the impact of that activity on this life line. It also suggests alternate project sites and alternate process technologies. Example: DIKSHA PRAKASH 13
  • 14.  Surface water quality ?  Air quality ?  Seismology/geology impact?  Erosion ?  Land quality ?  Fisheries ?  Forests ?  Terrestrial wildlife ?  Noise?  Archaeological/historical significance ?  Public health ? FAQ : Environmental aspects DIKSHA PRAKASH 14
  • 15.  Site preparation and development ( grading and levelling of the site, demolition and removal of existing structure, relocation of existing pipelines, cables, roads, power lines etc. connection of public network like electric power, water, communications, transportations etc. )  Building and Structures ( involves construction of factory or process building, ancillary buildings, administrative buildings, residential buildings)  Outdoor works ( involves the supply and distribution of utilities, handling and treatment of emission, wastages, transportation, supervision etc) 1.3. Structures and Civil Works DIKSHA PRAKASH 15
  • 16.  Technical Analysis of a project for buildings, structures and civil works involves the preparation and development of site which includes 1. Grading and levelling of land 2. Demolition of existing structures 3. Relocation of pipeline, cables, roads 4. Reclamation of sewers and drainage 5. Connections for utilities 6. Arranging for electricity, water etc. DIKSHA PRAKASH 16
  • 17.  General functional layout  Material flow diagram  Production line diagram  Transport layout  Utility consumption layout  Communication layout  Organizational layout  Plant layout 1.4. Project charts and Layout DIKSHA PRAKASH 17
  • 18.  General Functional Layout shows the functional relationship between building, civil works and machines. It facilitates smooth and economical movement of raw materials, work in progress and finished products.  Material flow diagram shows the quantum of flow of materials, work- in-progress, finished products etc. along with the basic flow of these items.  Product Line Diagram shows the production process envisaged for the project. It also shows the vital information for the main machines and equipment's (description, location, foundation, space requirement, power and utilities required, distance between one centre to another etc.)  Plant Layout indicates the physical layout of the entire factory. In case of the process industry, the plant layout depends upon the production process involved chronologically. DIKSHA PRAKASH 18
  • 19.  Utility Consumption Layout shows main points of consumption of utilities and the qualities and quantities required.  Transport Layout indicates the distance and means of transportation outside the production line.  Communication layout shows how various departments of the project are connected with the communication system.  Organization layout indicates the organization structure of the project, the interrelationship between different departments and the manpower required for the various departments.  Plant Layout refers to the arrangement of physical facilities such as machinery, equipment, furniture etc. with in the factory building in such a manner so as to have quickest flow of material at the lowest cost.DIKSHA PRAKASH 19
  • 20.  “Project Management & Control” : Subhash Chandra Das. ISBN: 8120344502  http://pmbook.ce.cmu.edu/04_Labor,_Material,_And_Equipment_ Utilization.html  http://ijiset.com/vol3/v3s5/IJISET_V3_I5_16.pdf  http://www.bbamantra.com/technical-analysis-of-a-project/  https://enviroliteracy.org/environment- society/economics/environmental-impact-analysis/  http://www.newagepublishers.com/samplechapter/001059.pdf  www.ef.uns.ac.rs/mis/archive-pdf/2008%20- %20No1/MIS2008_1_1.pdf  https://www.slideshare.net/search/slideshow?searchfrom=header &q=project+management REFERENCES DIKSHA PRAKASH 20