2. Credits and Hour
Teaching
Scheme
Theory Practical Total Credit
Hours/
week
3 2 5
4
Marks 100 50 150
Pedagogy
Continuous
Evaluation Syllabus for Test/Exam Marks Equivalent Marks
Unit Test 30 15
Group Activity 3 activity would be given
Related Topic
Construction Equipment &
methodology
15 15
Total Marks = 30
3. Reference books:
“Construction planning, equipment and
methods” by Peurifoy
“Construction engineering and management”
by S. Seetharaman.
“Construction Management and equipments”
by A. S. Kotadia
“Construction Project Management”
by Kumar Neeraj Jha
4. Introduction
“Construction Technology involves study of methods of
construction to carry out planned production safely,
maintaining quality conforming to the specifications,
standards and codes.”
It also includes study of construction equipments, and
temporary works required to facilitate the construction
process.
The modern trend is towards constructing lighter and taller
buildings which is always a big challenge in an era of
financial crunch.
To achieve it successfully, there is a need of have
sophisticated equipments employed in the construction
process.
4
5. Requirement of Construction
Equipments…
In the case of huge construction projects; Proper use of
the appropriate equipment contributes to economy,
quality, safety, speed and timely completion of a project.
Good project management in construction must
vigorously pursue the efficient utilization of labor,
material and equipment.
The use of modern equipment and innovative methods
has made possible wholesale changes in construction
technologies in recent decades.
5
6. The construction equipment is deployed on
the construction projects for various
reasons..
Larger output
Large output can be maintained, even if there
is a shortage of skilled and semi skilled
manpower.
Cost effective implementation
For execution of certain construction work that
cannot be executed through manual operation
Precision of implementation is done by
modern construction equipment equipped with
software controls.
6
7. The selection of the appropriate type and size of
construction equipment often affects the required
amount of time and effort and thus the job-site
productivity of a project.
15-30% of total project cost has been accounted
towards equipment and machinery.
It is therefore important for site managers and
construction planners to be familiar with the
characteristics of the major types of equipment most
commonly used in construction.
7
8. General Consideration for
Selection of Equipment:
Suitability for job condition, soil condition etc.
time constraints
Space constraints
Economic factors: Economic considerations such as the cost of owning
the equipment and operation and fuel costs are some of the most
important factors that play a deciding role in selecting the equipment.
Besides, consideration over resale value is also very important.
Availability of equipment: selection has to be made from the available
equipment held with manufacture or dealers.
Utilization of equipment: Degree of utilization in future projects to be
evaluated. Depreciation is very high in new equipment. Compare it with
use of old equipment which has high operating cost.
8
9. Uniformity in type: Desirable to have minimum number of types.
Common type of engine for different machines.
Size of equipment: Large equipment require large matching
equipment, high operating cost, uneconomical if not utilized to its full
capacity
Use of standard equipment: Commonly manufactured, repair parts are
easily available, minimum resale problems.
Country of origin: Import/Currency problems, availability of spare parts
Versatility – more functions/inter-convertibility
Operating facility: the equipment chosen for project should be such
that trained operators for the machine are available.
9
10. Classification of equipment
based on type of work
Intermittent type:
This type of equipment have the intermittent cycle of work. They
can be operated on series of work cycle and each cycle complete
in itself.
Ex. Dragline, backhoe, power shovel etc.
Continuous flow type:
This type of equipment have Continuous flow of work.
Ex. Belt conveyor, air compressor etc.
Mixed type:
This type of equipment have characteristics of both.
Ex. Bulldozer, scraper
10
11. Classification of equipment
based on function
Excavating Equipments
Hauling Equipments
Placing (dumping & spreading)
Boring or tunneling Equipments
Compacting Equipments
Lifting Equipments
Pile driving equipments
11
12. Classification of equipment
based on availability
Depending upon their availability, commercial
sizes and specifications, the equipment can
be classified into following types:
(i)Standard Equipment
(ii)Special Equipment
12
13. Standard Eqipments:
The standard equipments are commonly manufactured and are
easily available to the prospective purchasers.
They can be used for variety of construction operations without
any difficulty and they are available in standard commercial
sizes. The initial investment is less as compared to a special
equipment.
The delivery of standard equipments is very quick, as it is
readily available in the market.
The repair parts for standard equipment can be obtained more
quickly in short period.
If the contractor no longer needs a unit of standard equipment,
he can usually dispose of it more easily and at a more favorable
13
14. Special Equipments
The special equipments are those which are manufactured for
a specific project or which does not have readily accessible
spare parts.
The selection of special equipments should be made carefully
after proper financial analysis.
The initial investment in case of special equipment is very high
and there is risk of change in design, it cannot be used
economically on the other project.
A special order is to be given to the manufacturer of special
equipments and a special price is to be given and therefore the
delivery of special equipments can be obtained after long period.
Examples of special equipment include tunnel boring machines,
large hauling units and very large shovels, such as a 70 to 80
cubic meter shovel used to strip-mine coal.
14
15. Engineering fundamentals of
construction material(soil & rock)
Soil and rocks are the principal components of
many construction projects.
Required to support structures; to support
pavements for highway; in dam and canal
construction project.
Most of the soils must be excavated,
processed and compacted to meet
engineering requirements of the project.
Thus knowledge of properties, characteristics and
behaviour of different soil and rock is important to
all person involve in construction projects.
16. The Phase Diagram
Solid
Water
Air
Weight --Wt = Ww + Ws
Volume --Vt = Vv + Vs = Va + Vw + Vs
17. Unit Weight (Density)
This is also known as (same thing by different names)
- Bulk Density
- Soil Density
- Unit Weight
- Wet Density
Dry Unit Weight
gd = Wsolids
Vtotal
Basic Relationships for Calculating Phase Diagram
Components
Relation between dry density & bulk den
18. The degree of saturation can range between
zero for a completely dry soil, and 1 for a fully
saturated soil.
Degree of Saturation effects:
strength of soil
compressibility
20. Volumetric measure of soil
1.0
1.25
0.90
1.0 CUBIC
METER IN
NATURAL
CONDITION
1.25 CUBIC
METER AFTER
DIGGING
(LOOSE
VOLUME)
0.90 CUBIC
METER
AFTER
COMPACTED
(COMPACTE
D VOLUME)
In place Compacted
Loose
BCM LCM CCM
21. Bank Cubic Metre (BCM) Bank Cubic Metre
(BCM) - A volumetric term commonly used to
represent in situ volume of soil before it is
processed.
Loose Cubic Meters (LCM): volume occupy
by Material which has been excavated in some
way and swelled as a result of the space that
now exist between its elements.
Compact Cubic Meters (CCM): volume
occupy by Material which has
been compacted and become more dense as
a result.
22. Continue…
For bulk materials, volumetric measure varies
with the material's position in the construction
process.
The same weight of a material will occupy
different volumes as handled on the project.
In planning or estimating of earth work job, the
engineer must use a consistent volumetric
measure in any set of calculation.
The necessary consistency of units is
achieved by use of shrinkage and swell
factors.
23. Machine Power
General Information
Pay load
Required power
Available power
Usable power
24. Power requirement for construction
equipments(Machine Power):
The constructor must select the proper
equipment to relocate and process material
economically.
The analysis procedure for matching the best
possible machine to the project task requires
information of machine’s mechanical
capability.
The engineer must first calculate the power
required to propel the machine and its load.
This power requirements is established by two
factor:
Rolling
resistanc
e
Grade
resistanc
e
25. The decision process for matching the best
possible machine to the project task requires
that the engineer take into account both
Material properties
Mechanical properties of machine
When the engineer considers the material
handling problem of a project, there are three
crucial material considerations:
Total quantity of material
Rate at which it must be moved
Size of individual pieces
The selection of machine in terms of type, size
and number to be employed is depend on
quantity of material, expected weather
condition, time constraints.
26. Payload:
The payload is carrying capacity of construction
excavation and hauling equipment can be expressed
either volumetrically(BCM, LCM, CCM) or
gravimetrically.
• Struck Volume
• Heaped Volume
Volumetric
capacity
The payload capacity of excavation
buckets and hauling unit is often
stated by manufacturer in terms of
volume of loose material, assuming
that the material is heaped in some
specified angle of repose.
A gravimetric capacity represent the
safe operational weight that the axles
27. Struck capacity: The capacity of bucket to the
flat surface at the edges.
The Heaped Capacity is the amount of
material inside the bucket plus the amount
piled on top as per its angle of repose.
28. Machine Performance
Cycle time and payload determine a machine’s
production rate, and machine travel speed directly
affects cycle time.
The three power :
1. Required Power
2. Available Power
3. Usable Power
29. Required Power
Power required is the power needed to overcome
resisting forces and cause machine motion.
The forces resisting the movement of mobile equipment
are:
1. Rolling Resistance
2. Grade Resistance
Therefore, power required is the power necessary to overcome the
total resistance to machine movement, which is the sum of rolling
and grade resistance.
Total Resistance(TR) = Rolling Resistance(RR) + Grade Resistance
30. Rolling Resistance
The resistance of a level surface to constant-velocity motion
across it.
Or
Rolling resistance, sometimes called rolling friction or
rolling drag, is the force resisting the motion when a body
(such as a ball, tire, or wheel) rolls on a level surface.
31. Rolling Resistance
Rolling Resistance Varies with the type & Condition of the
Surface; Soft earth offers a more resistance than hard
surface road.
32. For machines hat move on rubber tyre, the rolling
resistance varies with size of, pressure on, the tread
design of the tyre.
A narrow tread, high pressure tyre gives lower resistance than a
broad tread, low pressure tyre on a hard surfaced road.
If the road surface is soft and tyre tends to sink into earth, a
broad tread, low pressure tyre gives lower resistance than a
narrow tread, high pressure tyre.
Rolling Resistance
33. For crawler tracks, the resistance varies primarily
with type and condition of the road surface.
Rolling Resistance
34. For machine that move on rubber tyres, the
rolling resistance varies with size of,
pressure on and tread design of the tyre.
Narrow tread, high pressure tyre gives lower rolling
resistance than a broad tread, low pressure tyre on
hard surface road.
If the road surface is soft and tyre tend to sink into
earth, a broad tread, low pressure tyre will offer
lower rolling resistance than a narrow tread, high
pressure tyre
The maintenance of low-rolling resistance haul roads is one
of the best financial investments an earthmoving contractor
can make. The cost of having a grader to maintain the haul
road is repaid in increased production.
Rolling Resistance
35. Rolling Resistance
The rolling resistance in kg per gross ton is . . .
R = P (kg)
W (tons)
Where:
R = Rolling resistance factor in kg. per ton
P = Total tension in tow cable in kg
W = Gross weight of mobile vehicle in tons
R.R(kg) = R.R. factor (kg/ton) * Weight of vehicle
36. Rolling Resistance
When tire penetration is known, an approximate
rolling resistance value for a wheeled vehicle can be
calculated . . .
RR = [20 + (6* TP)] * GVW
Where:
RR = Rolling resistance in kg
TP = Tire penetration in cm
GVW = Gross vehicle weight in kg
39. Grade Resistance
The most common method of expressing a slope is by
gradient in percent.
A 1% slope is one where the surface rises or drops 1 m.
vertically in a horizontal distance of 100 m.
If the slope is 5%, the surface rises or drops 5 m. per 100
m of horizontal distance.
If the surface rises, the slope is defined as plus,
whereas if it drops, the slope is defined as minus.
41. Frictionless Slope-Force
Relationships
F = W sin α
N = W cos α
For angles less than 10°, sin α ≈ tan α (the small -angle
assumption); with that substitution:
F = W tan α
tan α = V = G%
H 100
42. Frictionless Slope-Force
Relationships
F (GR)= W * G%
100
If we substitute W = 1000 kg/ton, the formula reduces
to:
GRF(Grade Resistance Factor) = 10 kg/ton * G%
GR(kg) = GRF*W in ton
This formula is valid for a G up to about 10%, that is,
the small angle assumption (sin α ≈ tan α).
43. Total Resistance
Total resistance equals rolling resistance plus grade
resistance or rolling resistance minus grade assistance.
It can also be expressed as an effective grade.
Rolling resistance expressed in lb/ton = G%
20 lb/ton
45. Available Power
Internal combustion engines power most construction
equipment.
Because diesel engines perform better under heavy-
duty applications than gasoline engines, diesel
powered machines are the workhorses of the
construction industry.
Diesel engines have longer service lives and lower fuel
consumption.
Diesel fuel presents less of a fire hazard.
46. Rim pull
Rim pull is a term that is used to designate the tractive
force between the tires of machine’s driving wheels
and the surface on which they travel.
If the coefficient of traction is sufficiently high there
will be no tire slippage, in which case maximum rim
pull is a function of the power of the engine and the
gear ratios between the engine and the driving wheels.
If the driving wheels slip on the supporting surface,
the maximum effective rim pull will be equal to the
total pressure the tires exert on the surface multiplied
by the coefficient of traction.
47. Coefficient of Traction
The factor that determines the maximum possible
tractive force between the powered running gear of a
machine and the surface on which it travels.
48. Rim Pull Equation
Rim Pull = 270 * hp * efficiency
speed (kmph)
The efficiency of most tractors and trucks will range
from 0.80 to 0.85 (use 0.85 if efficiency is not known).
49. Drawbar Pull
The towing force a crawler tractor can exert on a load is
referred to as drawbar pull.
Drawbar pull is typically expressed in pounds.
To determine the drawbar pull available for towing a
load it is necessary to subtract from the total pulling
force available at the engine the force required to
overcome the total resistance imposed by the haul
conditions.
If a crawler tractor tows a load up a slope, its drawbar
pull will be reduced by 20 lb for each ton of weight of
the tractor for each 1% slope.
50. Usable Power
Usable power depends on project conditions:
primarily, haul-road surface condition, altitude, and
temperature.
Usable force = Coefficient of traction * Weight on driving wheel in
powered running gear
51. Effect of Altitude on usable Power
of IC engine
When a manufacture provides a Horsepower
rating, it is based on standard condition(T=60 ͦ
F) and barometric pressure at seal Level(76.99 cm)
For natural operation at altitudes above sea level
will cause significant decrease in available engine
power as the barometric pressure decrease.
air density decrease; affect combustion fuel to air
ratio
Turbocharger supercharger.