LUNAR INTERNATIONAL COLLEGE
School of Business and Economics
Department of Project Management
Thesis Defense
BY Yosef Yirga
Factors causing cost overrun in public building construction projects in Addis Ababa
Addis Ababa, Ethiopia
June 2022
CONTENTS
01
02
03
04
05
INTRODUCTION
Background, statement of problem, research
question, objectives & significance of the study
REVIEW OF RELATED
LITERATURE
General, Theoretical, Empirical & Conceptual
Framework
RESEARCH METHODOLOGY
Research design and approach, sample size,
method of data collection & data analysis
PRESENTATION, ANALYSIS,
DISCUSSION AND INTERPRETATION
OF RESULTS
Response rate, discussion, ranking of causes of
cost overrun, interpretation & triangulation analysis
CONCLUSION AND
RECOMMENDATION
Conclusion and recommendation for future studies
CHAPTER ONE
INTRODUCTION
1.1 Background of the study
• Ethiopia has lately completed magnificent projects such as urban
development projects, bridges, dams, and industrial projects, among
others.
• Cost is one of these performance indicators, particularly for industry
initiatives.
• Building projects, in particular, have issues with construction processes
and administration, as well as budget and time constraints.
• cost overruns in public building construction continue to be a bottleneck
to project completion.
1.2 Research Problem
• The initiation of this research was largely due to personal observation
and the low performance of the construction projects in terms of cost
and time.
• The first motive to undertaking this research was to learn more about
the factors that cause cost overruns during public building
construction projects in Addis Ababa town.
• However, due to the limitations with regard to accessibility of data on
private construction projects, this thesis will focus on public building
construction projects.
1.3 Research Questions
• What are the primary reasons for the cost overrun in public building
construction projects in Addis Ababa?
• Who is the responsible party for the respective causes of cost
overrun?
• What is the extent of cost overrun for different types of public
building construction projects?
• What are the factors that are causes for cost overruns in public
building construction projects?
1.4 Research Objective
1.4.1 General Objective
• To assess the main factors causing project cost overruns on public construction
projects in Addis Ababa and possible mitigation strategies in this industry.
1.4.2 Specific Objectives
• To examine the primary reasons of cost overruns in public building
construction projects in Addis Ababa, as well as their overall effects.
• To identify the related responsible party for the causes of cost overrun.
• To assess the cost overrun rate for different types of public building
construction projects.
• Determine the factors that are causes for cost overruns in public building
construction projects in Addis Ababa.
1.5 Significance of the Study
• describes causes and solutions that contribute to construction time
and cost overruns in public building construction project.
• it enabled researchers to do more in-depth studies on public building
construction projects, and they were able to use this study as a
source of knowledge.
• adds to our understanding of the critical and major factors that
contribute to cost overruns in public-sector construction projects.
• it establishes a foundation for treating the multiple risk factors that
contribute to cost overruns
CHAPTER TWO
REVIEW OF RELATED LITERATURE
2.1 General
A "construction project" is a high-value, time-sensitive, unique
construction mission to develop a facility or service with established
performance targets defined in terms of quality, time, money, and
other limitations.
2.2 Empirical literature
• A lot of studies have been conducted on the variables that cause cost overruns in
building projects in various nations (developed and developing).
• Researchers in the past looked at the elements that influence building costs from
numerous angles.
• Various countries, however, have different cost variables to consider.
• Following the literature review, the researcher discovered the following
information:
 Group of causative factors of cost overrun in construction which are :- material
related factors, equipment related factors, labor factors, contract management
related factors, project related factors, external related factors.
2.3 Conceptual Frame work
CHAPTER THREE
RESEARCH METHODOLOGY
3.1 Research design and approach
• The study has employed survey research design
• The researcher has employed collection of data from the participant
directly through administered questionnaires, interviews & desk
study.
• Stratified sampling was selected because there were different
characteristics among teams of client, contractors and consultant.
3.2 Determining the sample size
• When the population is less than 1000, we can test 30 percent of the
total population. (Gay and Airasian, 2003).
• Currently the Addis Ababa Design and construction bureau has
administered 37 public funded building construction projects and
there are 154 potential respondents.
• n= 154*0.3= 46 for the questionnaire.
• Proportional sampling is used to divide the sub population i.e. client,
consultant and contractors.
3.3 Methods of data collection
• The study has used the data sources to produce the following basic
documents: respondents’ documents and archival documents.
• Questionnaires were prepared in accordance to the objectives of the
research.
• Interview is done to ensure efficient collection of information
• Building projects with contract amount greater than or equal to ten
million birr are surveyed in the desk study.
• Archival documents were mostly from completed projects.
3.4 Methods of Analysis
• Descriptive, Inferential statistics and Data triangulation are employed
in the data analysis.
• In the analysis the “Mean Score” method is adopted to establish the
relative importance of the causes of cost overrun for public building
construction projects in Addis Ababa.
• The Spearman (rho) rank correlation coefficient is used for measuring
the differences in ranking between two groups of respondents scoring
for various factors.
CHAPTER FOUR
PRESENTATION, ANALYSIS, DISCUSSION AND INTERPRETATION OF RESULTS
4.1 Response Rate
The questionnaire was produced and sent in person and by technical means to
three contracting groups, who are currently working on public building construction
sites.
• Forty-six (46) questionnaires were given to the stakeholders after considering the
respondents' participation in the project all were responded accordingly.
56%
33%
11%
Respondents Category
Client Consultant Contractor
4.2 Discussion section
4.2.1 Information of interview
• The interview was conducted using a qualitative standardized interview.
• Fifteen professionals with an interest in public building construction were
available for interviews.
• According to 100% of respondents, cost overruns in public building construction
projects are major concerns that must be addressed soon.
• The most pressing difficulties stated by respondents are financial, commodity
price fluctuations, material scarcities, the Covid 19 epidemic diseases.
• The cost of a project grows as the duration of the project increases.
• The project budget restriction has been established in practice.
4.2.2 Observation at the job site and in the workplace
• Observation and desk study were two of the data gathering
approaches employed in this study.
• The most common causes of cost overrun, according to the desk
study, are supplementary agreements, price fluctuation of
construction materials, change orders or variations, Labor
Productivity.
• Site works, such as fences, site sanitary installations, site electrical
installations, and internal access roads, are frequently overlooked
throughout the design, specification, and/or contract document
preparation process.
• When a project's cost exceeds 10% of the contract amount,
consultants write a "supplementary agreement.“
4.3 Ranking of causes of cost overrun (RII) with High RII score
Relative importance index
Less productivity Inflationary increase of materials price
Unperiodic maintenance cost of machineries Change of consultants for design, supervision and contract management
Late delivery of material management Scarcity of materials
unskilled personnel Failure to identify problems
Poor communication between project team members Dependency on imported material
Low experience of consultants
4.4 Correlation tests on factors of cost overruns
• One of the goals of this thesis is to see if stakeholders in Addis Ababa
agree on the reasons of cost overruns on public building construction
projects.
• The data indicated that there is a strong or clear interaction between
respondents' views in the client and contractor groups,
• whereas the degree of connection between respondents' attitudes in
the contractor and consultant groups is moderate.
• There is no evidence that the two parties are statistically agreeable.
• As a consequence, it was discovered that respondents' opinions of
client and consultant, as well as contractor and consultant, in terms of
how they score the factors, differ significantly.
4.5 Triangulation Analysis
• The results of the literature review and the questionnaire survey,
however, differ in some ways. Delays in payments are tolerated by
local contractors in the Ethiopian construction business, but they are
not tolerated by international contractors working in Ethiopia.
• cost overrun cannot be attributed to a rise in workmen's wages,
contrary to the literature study. If workmen's wages rise owing to
inflation or other difficulties in the country, the contractor will bear
the expense.
• According to the desk research, Most of the time, consultants are
blamed by clients; project owners think that if the designs,
specifications, and contract agreements had been done and prepared
correctly from the start, there would have been no late change orders
and 'unexpected ground conditions’.
Chapter five
Conclusion and recommendation
5.1. Conclusion
• Public building projects investigated in the research suffered cost overrun in their
execution. For these public building construction projects, the actual cost overrun ranges
from 2.78% to 141.36% of the contract amount.
• The contract amount appears to impact the rate of cost overrun. The rate of cost overrun
is found to decrease with increasing contract amount in a regression analysis of data
acquired from a desk research for 35 public building construction projects.
• The overall amount of cost overrun for the various types of public building construction
projects analyzed in this study varies significantly. According to the report, educational
buildings have the lowest cost overrun rate, while recreational structures have the
highest.
Cont.…
• Labor productivity, Inflation or an increase in the cost of construction materials, a change
in the foreign exchange rate (for imported materials), change orders and/or a lack of
control on excessive change orders, and a failure to identify problems and take necessary
and timely actions are the most common causes of cost overrun.
• According to the findings of the study, consultants are most often held accountable for
cost overruns in the construction business, followed by clients.
• Clients that are badly impacted by cost overruns, as determined by this study, are those
who are obliged to seek more funding to complete the building project.
• Cost overruns have several consequences for building sector stakeholders. The most
typical consequences of cost overruns in the construction business include delays,
additional agreements, project owners' budget shortfalls, contentious relationships
among stakeholders, and a loss of reputation for construction professionals, particularly
consultants.
5.2 Recommendations
• Consultants shall have continuous coordination and direct contact will avoid
design conflicts, flaws, and omissions, as well as provide specialists the
opportunity to properly evaluate the contract agreements.
• Provide any necessary details to make interpreting the designs and laying out the
works easier.
• To minimize variations and late adjustments during the building phase, a detailed
and complete site study should be conducted during the design phase.
• Clients shall budget enough time to complete project briefings and other
feasibility assessments.
• Contractors shall collaborate with the customer to order building supplies and
other goods ahead of time.
• All stakeholders in the construction industry should work together to improve the
sector's outputs and ensure that it continues to expand in a healthy manner.
• Institutions and academicians in the construction business must collaborate with
industry practitioners.
• Generally, It will need a collaborative effort from all stakeholders to put the
findings of building research into practice.
THANKS FOR WATCHING!
Any Question?
Suggestion

More Related Content

Similar to project management

journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdf
KarthikeyanP288430
 
2nd Generation Construction procurement Reform -Published at IPPC 2012 at Se...
2nd Generation Construction procurement Reform  -Published at IPPC 2012 at Se...2nd Generation Construction procurement Reform  -Published at IPPC 2012 at Se...
2nd Generation Construction procurement Reform -Published at IPPC 2012 at Se...
Veluppillai Mohan
 
Mba viva slides (scm009432) (1)
Mba viva slides (scm009432) (1)Mba viva slides (scm009432) (1)
Mba viva slides (scm009432) (1)David Goh
 
Ijciet 10 01_088
Ijciet 10 01_088Ijciet 10 01_088
Ijciet 10 01_088
IAEME Publication
 
Jibril muhammad bashir2
Jibril muhammad bashir2Jibril muhammad bashir2
Jibril muhammad bashir2
Jibril Bashir
 
chapter 2.pptx
chapter 2.pptxchapter 2.pptx
chapter 2.pptx
Derashmelaku
 
Irfanullah (Proposal Presentation).pptx
Irfanullah (Proposal Presentation).pptxIrfanullah (Proposal Presentation).pptx
Irfanullah (Proposal Presentation).pptx
namakuBENTO2
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
Dr. Amarjeet Singh
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
IJERA Editor
 
IRJET- Most Efficient Critical Success Factor for Construction
IRJET-  	  Most Efficient Critical Success Factor for ConstructionIRJET-  	  Most Efficient Critical Success Factor for Construction
IRJET- Most Efficient Critical Success Factor for Construction
IRJET Journal
 
An Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in BahrainAn Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in Bahrain
IJRES Journal
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET Journal
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET Journal
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET Journal
 
Attributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewAttributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a review
A Makwana
 
Chapter 4--Project Preparation and Feasibility Analysis.pptx
Chapter 4--Project Preparation and Feasibility Analysis.pptxChapter 4--Project Preparation and Feasibility Analysis.pptx
Chapter 4--Project Preparation and Feasibility Analysis.pptx
AlwanYusuf
 
Factors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction ProjectsFactors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction Projects
ijtsrd
 
Project Management U 1.pptx
Project Management U 1.pptxProject Management U 1.pptx
Project Management U 1.pptx
MADARAUCHIHA278827
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
iosrjce
 
I012646171
I012646171I012646171
I012646171
IOSR Journals
 

Similar to project management (20)

journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdf
 
2nd Generation Construction procurement Reform -Published at IPPC 2012 at Se...
2nd Generation Construction procurement Reform  -Published at IPPC 2012 at Se...2nd Generation Construction procurement Reform  -Published at IPPC 2012 at Se...
2nd Generation Construction procurement Reform -Published at IPPC 2012 at Se...
 
Mba viva slides (scm009432) (1)
Mba viva slides (scm009432) (1)Mba viva slides (scm009432) (1)
Mba viva slides (scm009432) (1)
 
Ijciet 10 01_088
Ijciet 10 01_088Ijciet 10 01_088
Ijciet 10 01_088
 
Jibril muhammad bashir2
Jibril muhammad bashir2Jibril muhammad bashir2
Jibril muhammad bashir2
 
chapter 2.pptx
chapter 2.pptxchapter 2.pptx
chapter 2.pptx
 
Irfanullah (Proposal Presentation).pptx
Irfanullah (Proposal Presentation).pptxIrfanullah (Proposal Presentation).pptx
Irfanullah (Proposal Presentation).pptx
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
 
IRJET- Most Efficient Critical Success Factor for Construction
IRJET-  	  Most Efficient Critical Success Factor for ConstructionIRJET-  	  Most Efficient Critical Success Factor for Construction
IRJET- Most Efficient Critical Success Factor for Construction
 
An Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in BahrainAn Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in Bahrain
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
Attributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewAttributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a review
 
Chapter 4--Project Preparation and Feasibility Analysis.pptx
Chapter 4--Project Preparation and Feasibility Analysis.pptxChapter 4--Project Preparation and Feasibility Analysis.pptx
Chapter 4--Project Preparation and Feasibility Analysis.pptx
 
Factors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction ProjectsFactors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction Projects
 
Project Management U 1.pptx
Project Management U 1.pptxProject Management U 1.pptx
Project Management U 1.pptx
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
I012646171
I012646171I012646171
I012646171
 

More from NetsanetWorkineh

AAI - concept.pptx
AAI - concept.pptxAAI - concept.pptx
AAI - concept.pptx
NetsanetWorkineh
 
multinational corporations
multinational corporationsmultinational corporations
multinational corporations
NetsanetWorkineh
 
financial management
financial managementfinancial management
financial management
NetsanetWorkineh
 
project magement
project magementproject magement
project magement
NetsanetWorkineh
 

More from NetsanetWorkineh (6)

AAI - concept.pptx
AAI - concept.pptxAAI - concept.pptx
AAI - concept.pptx
 
chaspa
chaspachaspa
chaspa
 
alfa
alfaalfa
alfa
 
multinational corporations
multinational corporationsmultinational corporations
multinational corporations
 
financial management
financial managementfinancial management
financial management
 
project magement
project magementproject magement
project magement
 

Recently uploaded

Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
manasideore6
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
dxobcob
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 

Recently uploaded (20)

Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 

project management

  • 1. LUNAR INTERNATIONAL COLLEGE School of Business and Economics Department of Project Management Thesis Defense BY Yosef Yirga Factors causing cost overrun in public building construction projects in Addis Ababa Addis Ababa, Ethiopia June 2022
  • 2. CONTENTS 01 02 03 04 05 INTRODUCTION Background, statement of problem, research question, objectives & significance of the study REVIEW OF RELATED LITERATURE General, Theoretical, Empirical & Conceptual Framework RESEARCH METHODOLOGY Research design and approach, sample size, method of data collection & data analysis PRESENTATION, ANALYSIS, DISCUSSION AND INTERPRETATION OF RESULTS Response rate, discussion, ranking of causes of cost overrun, interpretation & triangulation analysis CONCLUSION AND RECOMMENDATION Conclusion and recommendation for future studies
  • 3. CHAPTER ONE INTRODUCTION 1.1 Background of the study • Ethiopia has lately completed magnificent projects such as urban development projects, bridges, dams, and industrial projects, among others. • Cost is one of these performance indicators, particularly for industry initiatives. • Building projects, in particular, have issues with construction processes and administration, as well as budget and time constraints. • cost overruns in public building construction continue to be a bottleneck to project completion.
  • 4. 1.2 Research Problem • The initiation of this research was largely due to personal observation and the low performance of the construction projects in terms of cost and time. • The first motive to undertaking this research was to learn more about the factors that cause cost overruns during public building construction projects in Addis Ababa town. • However, due to the limitations with regard to accessibility of data on private construction projects, this thesis will focus on public building construction projects.
  • 5. 1.3 Research Questions • What are the primary reasons for the cost overrun in public building construction projects in Addis Ababa? • Who is the responsible party for the respective causes of cost overrun? • What is the extent of cost overrun for different types of public building construction projects? • What are the factors that are causes for cost overruns in public building construction projects?
  • 6. 1.4 Research Objective 1.4.1 General Objective • To assess the main factors causing project cost overruns on public construction projects in Addis Ababa and possible mitigation strategies in this industry. 1.4.2 Specific Objectives • To examine the primary reasons of cost overruns in public building construction projects in Addis Ababa, as well as their overall effects. • To identify the related responsible party for the causes of cost overrun. • To assess the cost overrun rate for different types of public building construction projects. • Determine the factors that are causes for cost overruns in public building construction projects in Addis Ababa.
  • 7. 1.5 Significance of the Study • describes causes and solutions that contribute to construction time and cost overruns in public building construction project. • it enabled researchers to do more in-depth studies on public building construction projects, and they were able to use this study as a source of knowledge. • adds to our understanding of the critical and major factors that contribute to cost overruns in public-sector construction projects. • it establishes a foundation for treating the multiple risk factors that contribute to cost overruns
  • 8. CHAPTER TWO REVIEW OF RELATED LITERATURE 2.1 General A "construction project" is a high-value, time-sensitive, unique construction mission to develop a facility or service with established performance targets defined in terms of quality, time, money, and other limitations.
  • 9. 2.2 Empirical literature • A lot of studies have been conducted on the variables that cause cost overruns in building projects in various nations (developed and developing). • Researchers in the past looked at the elements that influence building costs from numerous angles. • Various countries, however, have different cost variables to consider. • Following the literature review, the researcher discovered the following information:  Group of causative factors of cost overrun in construction which are :- material related factors, equipment related factors, labor factors, contract management related factors, project related factors, external related factors.
  • 11. CHAPTER THREE RESEARCH METHODOLOGY 3.1 Research design and approach • The study has employed survey research design • The researcher has employed collection of data from the participant directly through administered questionnaires, interviews & desk study. • Stratified sampling was selected because there were different characteristics among teams of client, contractors and consultant.
  • 12. 3.2 Determining the sample size • When the population is less than 1000, we can test 30 percent of the total population. (Gay and Airasian, 2003). • Currently the Addis Ababa Design and construction bureau has administered 37 public funded building construction projects and there are 154 potential respondents. • n= 154*0.3= 46 for the questionnaire. • Proportional sampling is used to divide the sub population i.e. client, consultant and contractors.
  • 13. 3.3 Methods of data collection • The study has used the data sources to produce the following basic documents: respondents’ documents and archival documents. • Questionnaires were prepared in accordance to the objectives of the research. • Interview is done to ensure efficient collection of information • Building projects with contract amount greater than or equal to ten million birr are surveyed in the desk study. • Archival documents were mostly from completed projects.
  • 14. 3.4 Methods of Analysis • Descriptive, Inferential statistics and Data triangulation are employed in the data analysis. • In the analysis the “Mean Score” method is adopted to establish the relative importance of the causes of cost overrun for public building construction projects in Addis Ababa. • The Spearman (rho) rank correlation coefficient is used for measuring the differences in ranking between two groups of respondents scoring for various factors.
  • 15. CHAPTER FOUR PRESENTATION, ANALYSIS, DISCUSSION AND INTERPRETATION OF RESULTS 4.1 Response Rate The questionnaire was produced and sent in person and by technical means to three contracting groups, who are currently working on public building construction sites. • Forty-six (46) questionnaires were given to the stakeholders after considering the respondents' participation in the project all were responded accordingly. 56% 33% 11% Respondents Category Client Consultant Contractor
  • 16. 4.2 Discussion section 4.2.1 Information of interview • The interview was conducted using a qualitative standardized interview. • Fifteen professionals with an interest in public building construction were available for interviews. • According to 100% of respondents, cost overruns in public building construction projects are major concerns that must be addressed soon. • The most pressing difficulties stated by respondents are financial, commodity price fluctuations, material scarcities, the Covid 19 epidemic diseases. • The cost of a project grows as the duration of the project increases. • The project budget restriction has been established in practice.
  • 17. 4.2.2 Observation at the job site and in the workplace • Observation and desk study were two of the data gathering approaches employed in this study. • The most common causes of cost overrun, according to the desk study, are supplementary agreements, price fluctuation of construction materials, change orders or variations, Labor Productivity. • Site works, such as fences, site sanitary installations, site electrical installations, and internal access roads, are frequently overlooked throughout the design, specification, and/or contract document preparation process. • When a project's cost exceeds 10% of the contract amount, consultants write a "supplementary agreement.“
  • 18. 4.3 Ranking of causes of cost overrun (RII) with High RII score Relative importance index Less productivity Inflationary increase of materials price Unperiodic maintenance cost of machineries Change of consultants for design, supervision and contract management Late delivery of material management Scarcity of materials unskilled personnel Failure to identify problems Poor communication between project team members Dependency on imported material Low experience of consultants
  • 19. 4.4 Correlation tests on factors of cost overruns • One of the goals of this thesis is to see if stakeholders in Addis Ababa agree on the reasons of cost overruns on public building construction projects. • The data indicated that there is a strong or clear interaction between respondents' views in the client and contractor groups, • whereas the degree of connection between respondents' attitudes in the contractor and consultant groups is moderate. • There is no evidence that the two parties are statistically agreeable. • As a consequence, it was discovered that respondents' opinions of client and consultant, as well as contractor and consultant, in terms of how they score the factors, differ significantly.
  • 20. 4.5 Triangulation Analysis • The results of the literature review and the questionnaire survey, however, differ in some ways. Delays in payments are tolerated by local contractors in the Ethiopian construction business, but they are not tolerated by international contractors working in Ethiopia. • cost overrun cannot be attributed to a rise in workmen's wages, contrary to the literature study. If workmen's wages rise owing to inflation or other difficulties in the country, the contractor will bear the expense. • According to the desk research, Most of the time, consultants are blamed by clients; project owners think that if the designs, specifications, and contract agreements had been done and prepared correctly from the start, there would have been no late change orders and 'unexpected ground conditions’.
  • 21. Chapter five Conclusion and recommendation 5.1. Conclusion • Public building projects investigated in the research suffered cost overrun in their execution. For these public building construction projects, the actual cost overrun ranges from 2.78% to 141.36% of the contract amount. • The contract amount appears to impact the rate of cost overrun. The rate of cost overrun is found to decrease with increasing contract amount in a regression analysis of data acquired from a desk research for 35 public building construction projects. • The overall amount of cost overrun for the various types of public building construction projects analyzed in this study varies significantly. According to the report, educational buildings have the lowest cost overrun rate, while recreational structures have the highest.
  • 22. Cont.… • Labor productivity, Inflation or an increase in the cost of construction materials, a change in the foreign exchange rate (for imported materials), change orders and/or a lack of control on excessive change orders, and a failure to identify problems and take necessary and timely actions are the most common causes of cost overrun. • According to the findings of the study, consultants are most often held accountable for cost overruns in the construction business, followed by clients. • Clients that are badly impacted by cost overruns, as determined by this study, are those who are obliged to seek more funding to complete the building project. • Cost overruns have several consequences for building sector stakeholders. The most typical consequences of cost overruns in the construction business include delays, additional agreements, project owners' budget shortfalls, contentious relationships among stakeholders, and a loss of reputation for construction professionals, particularly consultants.
  • 23. 5.2 Recommendations • Consultants shall have continuous coordination and direct contact will avoid design conflicts, flaws, and omissions, as well as provide specialists the opportunity to properly evaluate the contract agreements. • Provide any necessary details to make interpreting the designs and laying out the works easier. • To minimize variations and late adjustments during the building phase, a detailed and complete site study should be conducted during the design phase. • Clients shall budget enough time to complete project briefings and other feasibility assessments. • Contractors shall collaborate with the customer to order building supplies and other goods ahead of time. • All stakeholders in the construction industry should work together to improve the sector's outputs and ensure that it continues to expand in a healthy manner. • Institutions and academicians in the construction business must collaborate with industry practitioners. • Generally, It will need a collaborative effort from all stakeholders to put the findings of building research into practice.
  • 24. THANKS FOR WATCHING! Any Question? Suggestion

Editor's Notes

  1. As a result, efforts are being made to identify the key causes and consequences of cost overruns in Addis Ababa's public building construction projects
  2. This research is a practical problem developed from the observation of construction projects and the research questions are oriented to investigate the cause of cost overrun.
  3. The sample size was calculated using the statistical formula given below
  4. in which contract documents, project reports, correspondence letters and payment certificates were investigated thoroughly which were very important in identifying the recurrent problems
  5. (i.e. clients versus consultants, clients versus contractors, and consultants versus contractors).
  6. namely contractors, clients, and consultants,
  7. the unit price indicated for these additional items of work will be greater than the original unit price. As a result, Supplementary agreements, in general, drive up construction costs and degrade the consultant's reputation. Unit price valuation is frequently a subject of contention among project partners.
  8. As a result of this discovery, some respondents had differing perspectives on the reasons of cost overruns.
  9. , who request additional payment for the interest rate on delayed payments. These are due to cultural differences between domestic and foreign contractors
  10. Any Question? / Suggestion